Law for the Development of Energy Lines (Energy Management Act-EnLAG)

Unofficial table of contents

EnLAG

Date of completion: 21.08.2009

Full quote:

" Energy Management Act of 21 August 2009 (BGBl. 2870), as last amended by Article 3 of the Law of 23 July 2013 (BGBl). 2543).

Status: Last amended by Art. 3 G v. 23.7.2013 I 2543

For more details, please refer to the menu under Notes

Footnote

(+ + + Text evidence from: 26.8.2009 + + +) 

The G was decided by the Bundestag as Art. 1 of the G v. 21.8.2009 I 2870. It's gem. Article 7 of this Act entered into force on 26 August 2009. Unofficial table of contents

§ 1

(1) For projects in accordance with § 43, first sentence, of the Energy Economic Law in the field of maximum voltage networks with a nominal voltage of 380 kilovolts or more, which are the adaptation, development and expansion of transmission networks for the integration of electricity from renewable energy sources, to the interoperability of electricity networks within the European Union, to the connection of new power stations or to the prevention of structural bottlenecks in the transmission system, and for which therefore a priority If there is a need, a demand plan is attached to this law. (2) The Projects included in the plan correspond to the objectives of § 1 of the German Energy Economic Law. For these projects, the need for energy and the need for urgent action are thus firmly established. These findings are binding for the planning and planning approval in accordance with § § 43 to 43d of the Energiewirtschaftsgesetz. (3) For the projects included in the demand plan, § 50 (1) no. 6 of the Administrative Court order applies. (4) The projects also include the facilities necessary for the operation of power lines and the necessary changes to the network links. (5) Energy lines start and end at the network link points at which they are connected with the network. the existing transmission network. Unofficial table of contents

§ 2

(1) In order to test the use of underground cables at the maximum voltage level in the transmission system as a pilot project, the following lines, as referred to in paragraph 2, may be constructed and operated as a ground cable in accordance with the provisions of paragraph 2; or change:
1.
Section Ganderkesee-St. Hülfe of the line Ganderkesee-Wehrendorf,
2.
Line Diele-Niederrhein,
3.
Line Wahle-Mecklar,
4.
Section Altenfeld-Redwitz of the line Lauchstädt-Redwitz.
In the case of the new building, at the request of the authority responsible for the approval of the project, in the case of the projects referred to in paragraph 1, a maximum voltage line shall be set up on a technically and economically efficient subsection as a ground cable and shall be operate or change if the line
1.
shall be constructed at a distance of less than 400 metres from the residential buildings covered by a construction plan or in the unplanned interior area within the meaning of Article 34 of the Civil Code, in the event that these areas are mainly used for housing, or
2.
shall be constructed at a distance of less than 200 metres from the residential buildings situated in the external area within the meaning of Section 35 of the Construction Code.
In addition, at the request of the authority responsible for the approval of the project, in the case of paragraph 1, no. 4, in the Thuringian Forest Nature Park (Regulation on the Thuringian Forest Nature Park of 27 June 2001, GVBl for the Free State of Thuringia, p. 300), to construct and operate a maximum voltage line on a technically and economically efficient part of the race as a ground cable, or to modify it. (3) For the projects referred to in paragraph 1, in addition to § 43, first sentence, no. 1 of the Energy Economy Act a planning procedure also for the establishment and the (4) The transmission system operators shall determine the additional costs for the establishment, operation and modification of underground cables as defined in the Paragraph 1, which shall be incurred in the transmission network of the respective transmission system operator in a calendar year. The additional costs shall be determined on a flat-rate basis on the basis of standard cost estimates as compared to a free line on the same route. The additional costs of all transmission system operators, as determined in accordance with the first and second sentences, shall be added to the extent to which they correspond to an efficient network operation. The total cost of underground cables thus determined shall be calculated on a pro rata basis to all transmission system operators. The share of the total costs, which is to be borne by the individual transmission system operator, is determined in accordance with § 9 (3) of the Kraft-Heat-Coupling Act. In so far as the actual additional costs of a transmission system operator for the establishment, operation and modification of underground cables within the meaning of paragraph 1 exceed its calculated share of the total cost, that difference shall be financial to balance. The obligation to pay shall be made by the transmission system operators whose actual costs are less than the share of the total cost accounting for them, but only up to the level of the proportion of the total cost of the transmission system to which they are calculated. Total cost. Transmission system operators shall determine the balance by 30 November of a calendar year. Unofficial table of contents

§ 3

At the end of three years, the Federal Ministry of Economics and Technology, in agreement with the Federal Ministry for the Environment, Nature Conservation and Nuclear Safety, and the Federal Ministry for Transport, Building and Urban Development, shall examine whether: the demand plan for the development of electricity supply is to be adapted and submits a report to the German Bundestag, for the first time to the 1. October 2012. Taking into account the objectives according to § 1 of the German Energy Act (Energiewirtschaftsgesetz), it is also necessary to consider necessary optimization measures. This report shall also present the experience gained with the use of underground cables in accordance with § 2. Unofficial table of contents

Annex

(Fundstelle: BGBl. I 2009, 2872; individual changes, see Footnote) Projects in accordance with Article 1 (1), for which there is a need for urgent necessity: Nr.Projects
1 New construction maximum voltage line Kassø (DK)-Hamburg Nord-Dollern, nominal voltage 380 kV
2 New construction maximum voltage line Ganderkesee-Wehrendorf, rated voltage 380 kV
3 New construction high voltage line Neuenhagen-Bertikow/Vierraden-Krajnik (PL), rated voltage 380 kV
4 New construction of the Lauchstädt-Redwitz high-voltage line (as part of the Halle/Saale-Schweinfurt link), nominal voltage 380 kV
5 New construction high voltage line Diele-Niederrhein, rated voltage 380 kV
6 New construction Maximum Voltage Line Wahle-Mecklar, rated voltage 380 kV
7 Disposal Maximum voltage line Bergkamen-Gersteinwerk, rated voltage 380 kV
8 Rectification maximum voltage line Kriftel-Eschborn, rated voltage 380 kV
9 New construction maximum voltage line Hamburg/Krümmel-Schwerin, rated voltage 380 kV
10 Conversion of the maximum voltage line Redwitz-Grafenrheinfeld from 220 kV to 380 kV (as part of the connection Halle/Saale-Schweinfurt)
11 New construction maximum voltage line Neuenhagen-Wustermark (as 1st part of the Berliner Ring), nominal voltage 380 kV
12 New building Interconnector Eisenhüttenstadt-Baczyna (PL), rated voltage 380 kV
13 Construction of new high-voltage line Niederrhein/Wesel-border NL (direction Doetinchem), nominal voltage 380 kV
14 New construction maximum voltage line Niederrhein-Utfort-Osterath, rated voltage 380 kV
15 New construction Maximum voltage line Osterath-Weißenthurm, rated voltage 380 kV
16 New construction maximum voltage line Wehrendorf-Gütersloh, rated voltage 380 kV
17 New construction maximum voltage line Gütersloh-Bechterdissen, rated voltage 380 kV
18 New construction maximum voltage line Lüstringen-Westerkappeln, rated voltage 380 kV
19 New construction of the maximum voltage line Kruckel-Permanent Mountain, rated voltage 380 kV
20 New construction Maximum voltage line continuous-wave-Hünfelden, rated voltage 380 kV
21 New construction maximum voltage line Marxheim-Kelsterbach, rated voltage 380 kV
22 (dropped)
23 Conversion of the maximum voltage line Neckarwestheim-Mühlhausen from rated voltage 220 kV to nominal voltage 380 kV
24 New construction of high-voltage power line-Lindach, rated voltage 380 kV, and conversion of the high-voltage line Lindach-Goldshöfe from rated voltage 110 kV to nominal voltage 380 kV