Circulars to determine and manage the cost of construction _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ pursuant to the law No. 50/2014/QH13 on 18/6/2014;

Pursuant to Decree No. 62/2013/ND-CP dated 25/6/2013 of government functions, tasks, powers and organizational structure of the Ministry of construction;

Pursuant to Decree No. 32/2015/ND-CP on 25/3/2015 of the Government on the management of construction cost;                                                                                                                    

According to the recommendation of the Minister of economy of construction, economic Director of the building;

Minister of Ministry of construction issued circulars to determine and manage the cost of construction.

Chapter I GENERAL PROVISIONS article 1. Scope this circular detailed guidance on the content and methods of identifying and managing the cost of construction including the total investment in construction, total investment in construction, construction estimating, estimation of package building, construction norms, price construction , construction price index, price ca machines and construction equipment.

Article 2. Application object 1.    The agencies, organizations, individuals related to determine and manage the investment costs of building construction investment projects using rihà water budget, foreign capital budget according to the provisions in clause 1 article 2 of Decree 32/2015/ND-CP on 25/3/2015 of the Government on the management of the cost of construction (Decree No. 32/2015/ ND-CP) and construction projects in the form of public private partnership (PPP).

2. Encourage the project to build using other capital use, apply the provisions of this circular.

Chapter II the TOTAL INVESTMENT construction of article 3. Content total investment to build 1. Content total investment of construction as defined in paragraph 4 Article 4 of Decree 32/2015/ND-CP, in that the cost of project management, consultancy costs. construction and other costs are specified as follows: a) project management costs include the costs according to the provisions in clause 2 Article 23 of Decree 32/2015/ND-CP is the expenses needed to implement the work of project management from project preparation phase , project implementation and end the construction put on the project's work exploited using as follows:-set the feasibility research report of construction investment (if any), the report proposes investment undertakings (if any), feasibility study report construction or economic reports-technical construction;

-Set the task of building survey, surveying, survey monitoring construction;

-examination, selection of architecture design scheme selection or construction architectural design works;

-perform compensation, assistance and relocation are the responsibility of the owner;

-evaluation of feasibility study report construction or economic reports-technical construction;

-creation, appraisal, assessment, approval of the design, engineering, construction drawing design, construction estimation;

-selection of contractors in construction activities;

-quality management, volume, tempo, construction costs, construction contract;

-implementation of management information systems, public works;

-labour safety and sanitation of buildings;

-Establish new or adjust the norm of construction works;

-determine the construction cost, construction price index;

-quality control of the construction of the bodies of State administration when trials completed;

-check the quality of materials, construction products, constructions, equipment installation in the works;

-quality control of parts of works, projects, the whole works and construction methods as required;

-control the cost of construction;

-Exchange of capital construction after completing trials, handing put to use;

-collecting, billing, settlement contract; payments, capital construction investment;

-monitoring, evaluation of investment projects in construction;

-trials, Commission;

-commencement, inauguration (if any), advertising propaganda;

-define, update, appraisal, financing package for construction;

-implement the management work of the competent State body (if any);

-perform other management tasks.

b) investment costs include the costs of construction as defined in clause 2 article 25 of Decree 32/2015/ND-CP is the costs necessary to make the investment work from project preparation phase, project implementation and end the construction put on the project's work exploited using the following :-set the task of building survey, surveying, survey monitoring construction;

-establishment of feasibility research report of construction investment (if any), the report proposes investment undertakings (if any), newspaper Guo feasibility study of construction or economic reports-technical construction;

-Basic design verification, design technology of the project;

-examination, tuyểư select the architecture design of construction works;

-building design;

-Verify the total investment building, construction design, construction estimation;


-Establish, verify documents of interest, selected documents, tender, records requests and reviews resumes of interest, job applications, tenders, records suggested to choose a contractor in construction activities;

-Verify contractor selection result in construction activities;

-construction supervision, monitoring equipment installation;

-reporting of environmental impact assessment;

-Establish, verify construction norms, price construction, construction price index;

-Verify the work to ensure traffic safety;

-application information system works;

-control the cost of construction works;

-cost management consulting includes preliminary construction investment total investment (if any), total investment in construction, construction estimating, construction package price, price construction contract, construction norms and construction prices, payment and settlement construction contract, payment and settlement of capital construction and other work;

-consulting and project management (consulting rental cases);

-specialized laboratory construction;

-check the quality of materials, construction products, constructions, equipment installation on the work at the request of the owner (if any);

-quality control of parts of works, projects, entire works;

-monitoring, evaluation of investment projects in construction (case hired consultant);

-consultation and monitoring environmental monitoring;

-Exchange of capital construction after completing trials, handing put to use;

-perform other consulting work.

c other costs) to perform the work include:-demining, explosive objects;

-insurance of works during construction;

-Register of international quality, the deformation observation of works;

-audit, assessment, approval of investment capital;

-check the work experience in the construction process and when trials completed projects, the work of the governing body of the competent State;

-Science and technology studies related to the project; working capital for the initial construction investment project aimed at business, interest during construction; the cost for the test run does not load and the load according to the technological processes before delivery (excluding the value of product recovered);

-resource taxes, fees and charges as prescribed;                                   ..

-General category include the cost of items at the point of a clause 5 article 7 of this circular;

-the costs of performing the work.

2. in case of request determines the total investment to build the preliminary content total investment of construction as defined in clause 2 article 4 of Decree 32/2015/ND-CP.

3. For projects only require reporting of technical-economic construction content total investment, construction of the provisions in paragraph 3 article 4 of Decree 32/2015/ND-CP.                                 

4. With regard to the project, using official development capital (ODA), in addition to the content has been calculated in the total investment was still swollen ừên said the cost of other essential items to suit the particularities, the nature of the investment project to build using this capital according to the provisions of the relevant existing legislation , ensure the correct calculation principles, computer enough fit specific conditions and using the market price of construction area.

Article 4. Method of determining the total cost of building 1.   The total cost of construction is determined by one of the methods prescribed in clause 2 article 5 of Decree 32/2015/NĐ-CP dated as follows: a) determined from the mass calculated according to the building design and the other necessary requirements of the project.   .

b) determined by the productivity of capital construction c) determined from data on the cost of similar works have been or are done.

d) combine the method specified in point a, b, c Paragraph 1 of this article.

2. The total investment of construction is determined by the provisions of article 5 paragraph 1 of Decree 32/2015/ND-CP of cases not yet eligible to determine the scale, capacity or the capacity to serve as the preliminary design of the project or have identified but not yet have data capacity of construction investment was announced the preliminary total investment, build determined on the basis of cost data of similar projects on the type, level, scale, capacity or capacity have been performed and adjustments, supplements the other necessary expenses.

3. A number of cost items in the content project management costs, costs of construction investment, other costs of the project if it is not specified or not yet counted are added immediately and planned to take on the total cost of the construction.

4. Method of determining the total cost of construction, the total investment of building instructions in Appendix 1 of this circular.

Article 5. Evaluation, testing and approval of investment to build 1.  Content evaluation, appraisal and approval authority total investment of construction as defined in article 6 of Decree 32/2015/ND-CP.

2. evaluation results report Form, verify that the total cost to build under the guidance in Appendix 8 of this circular.

Article 6. Adjust the total investment building


1. Total investment approved construction are adjusted for the case prescribed in clause 1 article 7 of Decree 32/2015/ND-CP.

2. The additional cost of redundancy due to the sliding elements specified in clause 4 Article 7 of Decree 32/2015/ND-CP by the owner organization determine when building price index on average of the complete building price index by the competent State agencies announced from the time of project implementation to adjust building cost index greater used in total investment approved the construction.

3. for works not yet in the category building price index announced by the Department of building and construction works by going through the area of several provinces and cities under central Page, as specified in paragraph 4 Article 22 of Decree 32/2015/ND-CP, the construction price index averaged in paragraph 2 of this Article is determined to base the construction price index from the project time to time adjusted on the basis of the method of determining the construction price index as defined in article 21 of this circular.

4. the total investment value to build the additional cost of redundant tầeo prescribed in clause 2 and clause 3 This includes value increases due to the increased level of construction price index for volume has made time to adjust and the increased value due to the level of construction price index changes (including the level of expected volatility on the market) for the remaining volume is done.

5. The assessment, appraisal and approval of investment to build the thing chỉrửi made according to the provisions in clause 1 and 2 article 7 of the Decree, no. 32/2015/ND-CP.

Chapter III section 1 CONSTRUCTION ESTIMATION estimating construction article 7. Content construction estimation 1. Construction estimation according to the provisions in clause 2 article 8 of Decree 32/2015/ND-CP was defined for the work, projects, ancillary, temporary works construction service. In particular, construction costs include direct costs, general costs, income taxes, value added tax.

-direct costs include the cost of materials (including materials due the investor level), labor costs, costs of construction machines and equipment.

-General costs include the management costs of the business, the operating cost of production in the market, the costs of service workers, the cost of construction at the service of the University and some of the cost of service for the management of the business.

-the taxable income calculated trưởc is the account of profits of the business building was planned in the estimation of construction works.

-value added Tax according to the provisions of the State.

2. The cost of the equipment works, projects include items fee as specified in point b of paragraph 2 article 8 of Decree 32/2015/ND-CP.

3. project management costs include cost items as defined in point a of article 3 paragraph 1 of this circular.

4. the costs of construction investment include items fee as specified in point b of paragraph 1 of article 3 of this circular. With respect to the project are nliiều-works investment costs of building construction estimation does not include the costs of construction investment is related to the whole project.

5. other costs in the estimation of building works include items fee as specified in point c of paragraph 1 of article 3 of this circular. Among them: a) General items costs include:-the cost of the temporary home where to stay and what works;

-The cost of labour safety and environmental protection for construction workers and the surrounding environment;

-cost of materials laboratory of the contractor;

-the cost of labour force migration in the internal market;

-the cost of pumping water, occasional mud suits;

-the cost of moving machinery, special equipment and labour force (skilled in management of business, long-term labor contract business) to and from the school;

-the cost of ensuring safety construction service (if available);

-costs reimbursed by the infrastructure is affected when the construction works (if any);

-construction costs cover air, Foundation, electrical, pneumatic supply systems, water supply and drainage system at the scene, installation, dismantling some of the type (such as cement concrete mixing plant, asphalt mixing plant, the cranes migrate on Rails, tower crane, some kind of air, other construction equipment have similar nature);

b) no interest in construction estimating construction. For construction projects with the other costs of construction estimation does not include the cost of demining, explosive objects; audit costs; verified, approved capital investment; costs of research science and technology related to the project; the initial capital for investment projects aimed at building the glass; the cost for the test run does not load and the load according to the technological processes before delivery (excluding the value of product recovered); charges, fees and other costs were charged to the project.

6. preventive expenses include costs for elements of the workload incurred and costs for sliding elements during construction.

Article 8. Estimation method of determining construction tumble 1. Determine the cost of building


Construction costs can identify each content costs or the costs of content aggregated by one of the methods referred to in points a and b below.

a) calculated according to the volume and the price of construction-the cost of materials, labor, machinery and construction equipment in direct costs are determined by the volume and the price of construction. The volume of the building is determined from the technical design drawings or construction drawing design, technical instructions, work requirements to the execution of works, projects and construction prices are regulated in article 18 and article 19 of this circular. To sync with the price package estimation to estimate building can be constructed in full.

-General costs are calculated by the percentage (%) on the direct costs or labor costs in the estimation of construction for each type works as a guide in Table 3.7 and 3.8 of Appendix 3 of this circular. for works using ODA for international bidding, the General cost is determined by the norm in percentage (%) under the provisions of this circular and the additional costs required at the request of the international tender package, ensure the correct calculation principles, computer enough.

-taxable income calculated in advance is calculated by the percentage (%) on the direct costs and general costs as guidance in Table 3.9 annexes 3 of this circular.

-value added Tax according to the provisions of the State.

b) Computer, by mass attrition costs of materials, labour, construction machinery and equipment and the corresponding prices.

-the cost of materials, labor, machinery and construction equipment in direct costs identified by mass attrition costs of materials, labour, construction machinery and equipment and the corresponding prices. The total volume of wear and yật types, costs, construction machines and equipment is determined on the basis of free labor, material wear, construction machines and equipment for each volume of building works of the works projects.

Determining the price of materials and construction workers, as defined in article 19 of this circular.

Volume pricing and attrition costs of material, labour, construction machines and equipment are defined according to the guidelines in table 3.4 and 3.5 of Appendix 3 of this circular.

-General costs, income taxes, value added taxes as instructed in point a, paragraph 1 of this article.

2. Determine the cost of the device a) device costs are determined by weight, quantity, type of equipment from the technology design, construction, and the purchase price of the respective device. The purchase price of the equipment according to the quotation of the supplier, manufacturer or according to the market price at the time of calculation, the whore or the works have similar equipment (capacity, technology, origin) have been made.

For the production, the processing costs are determined on the basis of volume, the quantity of equipment needed for production, processing and manufacturing, processing unit price accordingly with the nature and type of equipment under contract manufacturing, outsourcing has been signed or based on the price of the product machining manufacturer is the owner of options or price production, similar equipment machining of the work has been done.

b) costs of training and technology transfer were determined by estimating depending on the specific requirements of the work.

c) the cost of equipment installation, testing, and other related costs are determined by estimating as for estimating construction costs.

3. Determine the cost of project management project management costs are determined on the basis of norms in percentage (%) by the Ministry of construction announced used in calculating total investment to build or by estimating.

4. Determine the cost of investment to build a) costs of consultancy in construction estimation is determined on the basis of percentage rates (địnli%) by the Ministry of construction announced or by estimating. The case of the construction investment made before determining the construction estimation shall be determined by the value of consulting contracts signed in line with the provisions of the State.

b) cases to hire foreign consultants, the consulting fee was determined by estimating fit requires the use of consultants, the regulations of the authority and international practices. Methods of determining the cost of hiring foreign consultants according to the tutorial of the Ministry of construction.

5. other costs are determined on the basis of norms in percentage (%) according to the instructions of the competent authority or by estimating the contract value or the signed accord with the provisions of the law.

For some specialized building construction have specific cost factors, the process of using ODA, if also the other relevant costs, the addition of this cost, ensure the correct calculation principles, computer enough costs, in accordance with the specific conditions of the works and using the market price where the building works.

6. Determine the cost of a backup) backup costs for elements of the workload generated by the percentage (%) on the total construction cost, cost of equipment, project management costs, the costs of construction and investment advisory fees.


b) costs for the sliding factor prices are determined on the basis of construction time (calculated by month, quarter, year), the layout plan of capital construction price index and match types of construction works taking into account the possibility of fluctuating prices in the country.

7. Method of determining construction cost, cost of equipment, project management costs, costs of construction investment, other costs, the costs of redundancy specified in paragraphs 1, 2, 3, 4, 5, 6 of which are specific guidelines in annex 2 of this circular.

Article 9. Appraisal, assessment and approval of the construction project tọán 1. Content evaluation, competence assessment, approval of construction estimation carried out according to the provisions of article 10 of Decree 32/2015/ND-CP.

2. evaluation results report Form, verify construction estimation according to the instructions in Appendix 8 of this circular.

Article 10. Adjust the construction estimation 1. Construction estimation has to be approved by regulators in the case prescribed in clause 1, 4 and the authority to identify, assess and approve the construction estimation to adjust according to the provisions in clause 3, 5 article 11 of Decree 32/2015/ND-CP.

 2. Method of determining the construction estimation to adjust guidance in annex III Part 2 of this circular.

Section 2 estimate of package build article 11. Estimating the construction bid packages 1. The content and method of determining the financing package of the construction according to the provisions of article 13 of Decree 32/2015/ND-CP.

2. in case of construction estimation has approved is determined on the basis of the unit cost of building more of the work is not complete, when determining the financing package for the construction of needed sum according to unit price construction details of the full works correspond to the volume of construction work needs done of tenders as specified in point b of paragraph 2 Article 13 of Decree 32/2015/ND-CP unit price construction details of incomplete work and unit price construction details of the full work prescribed in clause 1 Article 18 of this circular.

3. The cost of the General category of the construction bid packages include one, some or all of the costs identified in the estimation of construction works in accordance with approved scope of work, requirements, technical instruction and package are determined by the level of costs by the competent authorities or by estimating. The total cost of the General category of the construction bid packages not exceeding the cost of the General category in the estimation of construction works were approved.

4. Costs in estimating the construction bid packages include: a) the cost of backup for volume of work elements arise is calculated by the percentage (%) of the cost of construction and cost categories of the construction package.

b) costs for the sliding factor prices are determined on the basis of the time of the construction bid packages and construct price index fit this kind of construction works taking into account the possibility of fluctuations in the price of local and international ữong.

c) level in percentage (%) using defined backup costs according to point a, b of this clause does not exceed the percentage% of costs in the estimation of construction works have been approved.

5. Estimation of package constructions are determined according to the instructions in section 1 of part II of Appendix 2 to this circular.

Article 12. Estimation of package stores supplies, equipment for installation in buildings 1. The content and method of determining the estimate of package stores of supplies, equipment and installation in the works under the provisions in article 14 of Decree 32/2015/ND-CP.

2. the cost of installation, calibration, test equipment includes items such as cost estimation of package construction and is determined by setting the estimation by the method of determining construction cost specified in clause 1 article 8 of this circular.

3. the costs in the estimation of package stores of supplies, equipment and installation in the works include: a) the cost of backup for volume of work elements arise is calculated by the percentage (%) of the costs of purchasing the equipment; the cost of training and technology transfer (if any); installation costs , experiments, edit; transportation costs, insurance; taxes and fees.

b) costs for the sliding factor prices are determined on the basis of the duration of the bid packages and construct price index fit this kind of construction works taking into account the likely movements in the country.

c) level in percentage (%) using defined backup costs according to point a, b of this clause does not exceed the percentage (%) of backup cost corresponding to each of the elements of the construction estimation has been approved.

4. Estimation of package stores supplies, equipment for installation in buildings which are determined according to the instructions in section 2 of part II of Appendix 2 to this circular.

Article 13. Estimating package construction 1. The content and method of determining the estimated investment package built under the provisions of article 15 of Decree 32/2015/ND-CP.

2. professional fees, management costs, other expenses, taxable income, taxes and the cost of redundancy is determined under the guidance of the Ministry of construction.

3. The cost of specialized testing build is determined by estimate according to the instructions as to the method of determining the cost of construction.


4. Costs in the estimation package included construction costs for elements of the workload incurred and costs for sliding elements price is calculated by the percentage (%) under the guidance of the Ministry of construction, but the total percentage (%) of backup cost does not exceed the percentage% of backup cost corresponding to each of the weak estimation of construction was approved.

5. The cost of professional liability insurance of investment advice for the construction work on the building of the construction works from the level II or above are defined in the other costs of the package. For package building survey of the buildings from the level II or higher, the cost of buying insurance professional liability construction investment is own cost items estimated bid packages.

6. Estimate the investment package build is determined according to the instructions in section 3 of part II of Appendix 2 to this circular.

Article 14. Estimation of mixed package of 1. Estimation of package design and construction (EC) include estimating jobs according to the provisions of article 13 and article 11 of this circular.

2. Estimation of package stores of supplies, equipment and building construction (PC) includes the estimation of the work according to the provisions of article 12 and article 11 of this circular.

3. Estimation of package design-shop supplies, equipment-construction (EPC) and project-package design-shop supplies, equipment-construction (turnkey) as specified in clause 3 and clause 4 Article 16 of Decree 32/2015/ND-CP.

Article 15. Authority to identify, verify, assess and approve the package for estimation of building 1. The Organization of the identification, assessment, evaluation and approval of tenders estimation of construction made under the provisions of paragraph 3 and paragraph 4 Article 12 of Decree 32/2015/ND-CP.        .

2. Estimation of package has been approved but not yet organized the selection of the contractor, the owner held updated by price or price index and the other relevant policies, approving instead the price bid packages were tendered before browsing approximately 28 days.

3. where the financing package for the construction exceeded the construction estimation has been approved, the owner must report the investment decision to review the decision.

Chapter IV NORMS BUILD, price and CONSTRUCTION CONSTRUCTION PRICE INDEX section 1 article 16 building norms. System and method for establishing norms to build 1. Norm construction consists of technical-economic norms and norms costs are specified, in article 17 and article 18 of Decree 32/2015/ND-CP.

2. Methods of establishing norms construction estimation: a) norm construction estimates are established according to the following sequence:-set the directory of the work, the work or construction of works demonstrating the technical and technological requirements, conditions of construction, construction measure and determine the unit suited.

-Determine the composition of the work from when preparation to the completion of the work, the work or construction of buildings.

-Calculate the cost of materials, hao determined workers, machines and construction equipment.

-Establish the norms on the basis of the aggregate of the cost of materials, wear,, construction machines.            .

b) norm-setting method of construction estimation according to the guidelines in annex 5 of this circular.

3. Level of costs identified under the guidance of the Ministry of construction.

Article 17. Management of construction norms 1. The Ministry of construction announced construction norms according to article 34 of Decree 32/2015/ND-CP of the Roman Empire the agencies, organizations, individuals are related to use, apply, refer to the identification and management of construction cost.

2. Ministry of construction management majors and the provincial people's Committee based on the method of determining the level of đựih estimation of construction according to the guidelines in annex 5 of this circular construction organization, consistent with The construction of the norm estimation for construction jobs have characteristics typical of the majors own industry and local, is not yet in the system, the level of financing of construction, or already have the list but the new technology as specified in paragraph 1 of this article for publication for specialization, and send the norm estimation of construction has announced about The built to track management, as defined in clause 2 article 19 of Decree 32/2015/ND-CP.

3. Owner use, apply, refer to the system level estimation of construction with the same technology and conditions apply was announced or manipulate the norm estimation with the same terms and conditions that apply technology in the works have been done as a basis for determining the total cost of construction estimation, build and manage the cost of construction. For the construction work already in the system level estimation of construction was announced but not yet match the technical requirements, the conditions of construction, construction measures of concrete works or not in the quota system to build estimates were announced, the owner held the additional level of adjustment and estimation of construction as defined in clause 4 and clause 5 article 19 of Decree 32/2015/ND-CP as the basis to calculate the cost of construction works.


4. estimating consultants contractors build according to the designations of public works is responsible for recommending norm estimation of construction for the new building or norms need to adjust, Supplement to estimating and ensuring the adequacy of records documenting the report owner.

Section 2 Reviews construction of Article 18. The content and methods of construction price-setting 1. The price includes the construction unit price construction details of the construction and General construction prices are prescribed in clause 1 article 20 of Decree 32/2015/ND-Cp.

a) unit price construction details for the construction of public buildings including the unit price construction details of the works (including the cost of materials, labor costs, the cost of the machine and construction equipment) and unit price construction details of the works (including the full cost of the material , labor costs, costs of construction machines and equipment, general expenses and taxable income computed), as a basis for determining the construction estimation and estimation of construction bid packages.

b) General construction Price is calculated for a group, type of construction, structural units or parts of works and was escorted from the building unit price details of works in point a of this paragraph includes reviews of incomplete general construction (including the cost of materials, labor costs Record your expenses, and construction equipment) and General construction full price (including costs of materials, labor costs, costs of construction machines and equipment, general expenses and taxable income computed), as a basis for determining construction estimates, the total cost of the construction.

2. Method of setting the price of construction according to the guidelines in annex 4 of this circular.

Article 19. Construction cost management 1. The provincial people's Committee building Facility host, delivered in collaboration with the relevant agencies to identify and publish the price of building materials, construction worker unit price, price ca machines and construction equipment, construction price index and price as the basis of construction cost management in construction according to the provisions in clause 2 Article 36 of Decree 32/2015/ ND-CP.

2. The prices of building materials have to be published periodically by month, quarter; to ensure updated enough materials are commonly used. The price of building materials was announced must correspond to the standard of quality, origin and in accordance with the market price at the time of publication (specify located shipping). As for the geographical border between the central cities, then the building Department need to exchange information before publication to avoid the difference is too big.

3. Unit price construction worker is determined and announced on the basis of the instructions of the Ministry of construction; to be consistent with the level of skilled labor in the hierarchical system of norm estimation of construction works; fit the side by rửiân price the construction labour market trến of each locality; match meeting with characteristics, nature of work of construction workers; meet some klioản costs are the responsibility of the employee to pay according to the rules (social insurance, medical insurance, unemployment insurance and a number of other accounts payable).

4. Unit price ca machines and construction equipment are determined and announced on the basis of the instructions of the Ministry of construction and fit using the local market price at the time of publication.

5. Responsible for the management reviews construction of owner, organization management consulting investment costs of building and construction contractor a) owner made identifying and managing construction according to the provisions of article 21 and article 31 of Decree 32/2015/ND-CP.

b) management consulting organization construction costs made up, verify construction cost and construction cost management under the provisions of clause 2 Article 21và Article 32 of Decree 32/2015/ND-CP.

c) building contractor performs construction cost management under the provisions of article 33 of Decree 32/2015/ND-CP.

Item 3 article 20 construction price index. General provisions define the construction price index 1. Construction price index announced by type works, according to the cost structure (including the fake parts index construction, equipment price index, cost price index), the cost elements include construction materials price index, index construction labour, machinery and equipment price index construction are determined on the basis of category and number of works represented to calculation.

2. the construction price index is calculated on average in the period chosen, do not include the costs of compensation, resettlement and assistance, interest during construction, the initial working capital for production business (if any). Unit price index build is percent (%).

3. The structure of the costs used to calculate the construction price index must accord with the prescribed fee structure of cost management in construction, was the meeting of the statistical data and is used to when there is a change to the original point. Index structure for payment of the contract price is determined on the basis of the structure of the financing package.

Article 21. Construction price index classification 1. The building price index is determined by the type of construction works, including: a) the index price according to the cost elements include:-material price index construction are indicators that reflect the level of fluctuations in the price of building materials.


-Construction workers are the targets reflect the degree of fluctuating price construction worker.

-Machinery and equipment price index construction works is the target reflects the level of price fluctuations and devices for the construction of building construction.

b) CPI according to the fee structure are:-joint price index is ehỉ goal reflects the level of volatility in the price of construction section.

-The device is part of the target reflects the level of volatility of the price of the device part works.

-Other costs as part of the target reflects the level of fluctuations in the price of some types of costs such as project management, investment consulting co., ừìrứi construction and other costs of the works.

c) construction price index by category of works is the only goal reflects the level of volatility in the price of each type of construction works.

 2. the construction price index to be announced include the index type as defined in points a, b and c of paragraph 1 of this article.

 3. for works, construction-specific package, the entire calculation or some other indicator of the price referred to in paragraph 1 of this article the base purpose, requirements of the management costs and cost structure of financing packages.

Article 22. The method of determining the construction price index 1. Construction price index for publication is determined according to the following sequence: a) to determine the calculation includes the original point, the point of comparison.

 b) Created the category should specify price index, choose the input element.

 c) collect, process, metrics, data calculation.

 d) define the construction price index consists of determining the cost structure, the price index is calculated for each type of input element, according to the cost factor, as the cost structure and construction price index.

 2. the price index for construction works is determined on the basis of the progress made and the conditions of work to choose from the original point and the point of comparison for matching. Fee structure determines the CPI to adjust estimation is estimation of the structure works. Fee structure determined price index to adjust the contract price is the cost structure of the package price.

 3. the construction price index is determined according to the instructions in Appendix 7 of this circular.

Article 23. Manage the construction price index 1. The provincial people's Committee arranged the annual budget sources of traffic to local construction organizations performed some work: a) presiding, in cooperation with the relevant units pursuant to the instructions of this circular and the situation changes in the price of local construction organizations determine the Roman Empire published timely construction price index in accordance in clause 2 Article 36 of Decree 32/2015/ND-CP.

 b) updated, regularly hosting price information supplies, building materials, construction worker, price ca machines and construction equipment on the local construction market and posted on The monthly construction.

 c) announced the construction price index by month, quarter, year and posted on the Ministry of construction to the track, management.
2. The investor base method of determining construction price index following the instructions in Appendix 7 of this circular organization determine the construction price index as defined in paragraph 4 of Decree 32/22, 2015/ND-CP use cases above mentioned building price index to adjust the price of the construction contract, the owner reported the decision the investment decision to apply. The Prime project investment decision shall report the Minister provincial PEOPLE'S COMMITTEE Chairman, or President of the Corporation, the Corporation decided to apply to the State.
Article 24. Announce construction price index 1. Construction price indexes published include: a) national building price index are the Ministry of construction announced by quarter and by year.
b) The type of construction price index as defined in clause 1 article 21 of this circular was published construction by month, quarter and year according to the schedule, and 7.4 7.3 7.2, 7.1 of part II of Appendix 7 of this circular.
2. Time of publication a) for the construction price index published by month, the announcement was made on the second week of next month.
b) for the construction price index is published quarterly, the announcement was made on the second week of the first month of the next quarter.
c) for the construction price index to be announced by year, the announcement was made simultaneously with the fourth quarter of the year the price index.
Chapter V REVIEWS CA MACHINES and EQUIPMENT for the construction of article 25. General provisions on determining ca machines and equipment for the construction of 1. Price ca machines and construction equipment to build the average cost level is determined for a ca to work according to the rules of the air and the construction equipment.
2. The price of American machinery and equipment construction are determined on the basis of requirements management using machines and construction equipment, the level of attrition charges to calculate the ca machine and equipment construction and using of local prices.
3. price ca and devices for the construction of specific works to be determined consistent with construction organization design, organizational measures, building construction, building construction (or expected) used for construction works, construction progress and the construction by price in the area of building construction.
Article 26. Content costs in the price of American machinery and equipment construction

1. The price of American machinery and equipment construction includes the whole or some cost items such as depreciation, repair costs, the cost of fuel, energy, labor costs and other cost controls of the machine.
2. The price of American machinery and equipment construction has not included the cost of building the House covering machine, machine foundations, power supply systems, compressed air, water supply and drainage system at the scene, installation, dismantling some of the type (such as cement concrete mixing plant, asphalt mixing plant, the cranes migrate on Rails tower cranes, and some sort of air, other construction equipment have similar properties).
Article 27. Method of determining the price of American machinery and equipment construction 1. Price ca machines and construction equipment are determined in accordance with the type of technology, which has the same origin, the predominant specification and according to the following sequence: a) Established the category of construction machines and equipment building;
b) determined the level of attrition charges to calculate the ca building machinery and equipment;
c) calculates the price of American machinery and equipment construction.
2. Method of determining the price of American machinery and equipment construction instructions in Appendix 6 of this circular.
Article 28. Manage reviews American machinery and equipment construction 1. The provincial people's Committee delivered to the Department of construction based on the method of determining the price of American machinery and equipment construction according to the guidelines in annex 6 of this circular defined organization and publication reviews ca and devices for the construction of the province the city, under the provisions of clause 2 Article 36 of Decree 32/2015/ND-CP as a basis of reference, used when determining the price building and gửỉ of the Ministry of construction to the track, management.                                                                                                                                         
2. Owner use, manipulate, reference reviews American machinery and equipment construction has been announced as a basis for determining the price of construction. The case and the construction equipment not included in the published or was there but not consistent with the requirements and conditions of use of the construction works, the owner of construction organization reviews ca machines and construction equipment of works according to the instructions in Appendix 6 of this circular.
3. estimating consultant contractor built according to the design of construction works are responsible for recommending the price American machinery and equipment construction has not been announced as specified in paragraph 1 of this article or have announced but not yet consistent with the requirements and conditions of use of the construction works to estimating and ensuring the adequacy of your profile Investor report material.
Chapter VI ORGANIZATION of the IMPLEMENTATION of Article 29. Responsible for the governance of investment costs of building responsible governance of investment costs of building of the Ministry of construction, Ministry of finance, the Ministry and the provincial people's Committee made under the provisions of Articles 34, 35 and 36 of Decree 32/2015/ND-CP. Article 30. Handle transition a) the implementation of the identification and management of construction cost in the transitional period specified in paragraph 1 and 2 Article 37 of Decree 32/2015/ND-CP.
  b) for projects approved before the effective date of this circular nliưng chưạ conduct battles, when adjusting the project made under the provisions of Decree No. 32/2015/ND-CP and this circular.            .
Article 31. Effect 1. This circular is effective from 01/05/2016 and replaced the circular No. 03/2009/TT-BXD dated 26/5/2010 guide created and govern the investment cost, construction, circular No. 12/2009/TT-BXD dated 26/5/2010 Guide and method of determining the price of American machinery and equipment construction and circular No. 2/2011/TT-BXD dated 22/02/2011 Guide to determine and construction price index announced by the Ministry of construction.
2. During the implementation process if there are obstacles, agencies, organizations and individuals submitted comments on The building for research, resolve.