 The CIRCULAR regulates operation of competitive power markets _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ pursuant to Decree No. 189/2007/ND-CP on December 27, 2007 of the Government functions, tasks, powers and organizational structure of the Ministry of industry and trade;
Pursuant to the law on electricity of 3 December 2004; 
Pursuant to decision No. 26/2006/QD-TTg on January 26, 2006 by the Prime Minister on the approval of the roadmap, the conditions of formation and development of the electricity market level in Vietnam;
Industry regulations operate competitive power markets as follows: chapter I GENERAL PROVISIONS article 1. Scope this circular regulates the operation of a competitive electricity market and the responsibilities of the unit participated in the mobile market.
Article 2. The object that applies to this circular applies to the unit participated in competitive electricity markets: 1. buy wholesale units only.
2. The unit generator.
3. electrical system operators and market power.
4. power transmission unit.
5. data management unit for measuring electric energy counting.
Article 3. Explanation of terms In this circular, the terms below are interpreted as follows: 1. A bid is a Hi-power electricity market up sale by air, to be submitted to the bid unit operated power systems and electrical markets form price specified in this circular.
2. A bid price is scheduled to be operated by electricity market and power system acceptable to schedule the next day, the next hour mobilization.
3. billing statement is the calculation of payments for power plants on the market are operated by electricity market and power system set up for each of the transaction and for each billing cycle.
4. Intervention in the electricity market is the Act of changing the normal operating mode of the power market that operated the electric power market and the system must be applied to handle the situations defined in Article 55 paragraph 1 of this circular.
5. team pricing is the pricing mechanism as a representative unit made the bid for the whole group of terraced hydropower.
6. fully loaded cost is the cost of the generator change when operated in full load, calculated by Dong/kWh.
7. transaction cycle is the cycle calculates the price of electricity on the electricity market in the period of one (1) hour from the first minute of each hour.
8. Billing cycle is the cycle created the vouchers, invoices for transactions on the mobile market in the period of one (1) month from the date of June a month.
9. Capacity announced is the largest available capacity level of the generator is the unit price or unit operating the electricity market and power system and generator Unit contracted ancillary service providers announced according to schedule.
10. The capacity of the capacity of the generator power system operators and the mobile market actual mobilization in the trading cycle. 
11. The capacity to mobilize now to be a level of the generator is expected to be mobilized for the first time in the history of time to mobilize.
12. The capacity to mobilize the next day is a level of the generator is expected to be mobilized for the period in the history of transactions on mobilization to be considering limiting the ability of the transmission grid.
13. the increased power is the power disparity between performance and capacity are arranged in the calendar counted the market value of the generator. 
14. payment capacity is the level of air capacity located in the hourly capacity schedule and paid the price the market capacity.
15. the auxiliary services is the service frequency adjustment dial backup, backup, backup, fast cold boot, operate the security constraints due to the electrical system, adjust the voltage and black boots.
16. the broadcasting power increased as the power play of the generator due to be mobilized corresponds with increased power.
17. The unit price is the unit directly submitted a bid in the market power, including the power unit or power direct bidding registration, purchase units only trade when bids instead of the BOT and factory units representing the group pricing hydro power ladder.
18. the only merchant purchase unit is the unit of purchasing power in the electricity market, has bought the entire functionality of electric power through the electric power market and through power purchase contracts.
19. power unit is the unit that owns one or more power plants and electricity market participants sign the power purchase agreement for this power plant with a single merchant purchase unit.
20. indirect power unit is the unit of transaction generators power plants not bid directly on the power market, including the hydroelectric multi strategy objectives and the power plant has a contract to provide auxiliary services.
21. direct power unit is the unit of transaction generator power plant offered directly on the mobile market.
22. data management unit for measuring electric energy counting is the provider of installation, management, operation of the system of collecting, processing, storing data, Countdown power measurement and transmission line network information service of the mobile market.
23. power transmission unit is the unit of electrical power are active licenses in the field of power transmission, is responsible for the management, operation of the national transmission grid.
24. electrical system operators and the mobile market is the command unit controls the process of power generation, power transmission, power distribution in the national power system, operating the power market trading.
25. the market Price is the price for a unit of power, the effects identified for each transaction cycle, applied to calculate payment capacity for the power unit in the mobile market.
26. a floor Price is the lowest price that units be allowed to bid Hello to a generator in a bid the next day.
27. the electricity market Price is the price for a unit of electricity determined for each transaction cycle, applied to calculate payments for units of electricity generator in the electricity market.
28. The market price of electricity is the sum total of electricity market price and the price the market power of each transaction cycle.
29. a ceiling Price is the highest price that the unit is allowed to bid Hello to a generator in a bid the next day.
30. electricity market ceiling Price is the price the highest market power is identified for each year.
31. The value of water is the marginal price expectations calculated for the amount of water in the hydro when used to replace alternator for electric heat sources in the future, the rules change for a power unit.
32. the coefficient of performance is the performance indicators of the generator over time.
33. the average load factor, or is the ratio between the total power output in a year or a month, and that of total capacity set total hours in a year or a month.
34. the electricity market information system is the system and the database management service, exchange market information unit by operating the electricity market and power system management.
35. The contract provides ancillary services is a contract to provide backup service backup is fast, cold boot and operate security constraints due to the electrical system was signed between the power unit and the unit operating the electricity market and power system form issued by the Ministry of industry and trade.
36. power purchase contract is a written agreement for the sale of electricity between single trade and purchase unit the unit generator or exporter, imports of electricity.
37. power purchase contracts other false form is power purchase contract signed between the only merchant to buy unit with the unit generator direct transactions form issued by the Ministry of industry and trade.
38. the default interest rate is the interest rate is calculated by using the interest period of Vietnam on the interbank market at the time of payment.
39. Schedule that bind is the sort order to mobilize the generator according to the optimal method to cost generators considering the binding technique in power system including transmission capacity limits, ancillary services and other constraints.
40. To schedule non-binding is the sort order to mobilize the generator according to the method of optimal cost generator does not consider the limited transmission and transmission losses in the power system.
41. capacity Calendar is the calendar due to the electrical system operators and power market after the operation to determine the amount of the payment capacity of each transaction cycle.
42. the next hour mobilization Schedules is the schedule of planned mobilization air to generate power and provide ancillary services for the next trading cycle and three adjacent trading cycle after that.
43. on mobilization Schedule to calendar is expected to mobilize the air to generate power and provide ancillary services for the trading cycle of the next trading day.
44. The calendar to calculate the electricity market is operated by the calendar system of electric power market and established after the current transaction to determine the electricity market price for each transaction cycle.
45. the electricity market simulation model system is the simulation software to mobilize the generators and electricity market prices are operated by electricity market and power system used in the operation of the planning year, month, and week.
46. The model calculates the value of the water system is the optimal hydrothermal power software to calculate the value of water power system operators and market electricity use in the operation of the planning year, month, and week.
47. Water level limit is the water level upstream of the reservoir last hydro per month in the last year or each week in the month due to operation of the unit and the electric power market system calculated and published.
48. The year N is the current year operating the electric market, calculated according to the calendar year.
49. On D is the current trading day.
50. Trading days is the day of the power market trading activity, from 0:00 to 24:00 daily.

51. BOT power plant is the power plant was built in the form of investment-business-delivered through contracts between foreign investors and authorized State agencies.
52. best new power plants is the new thermal power plant put into operation the average power price calculations for next year and lowest power purchase contract price agreed according to the swinging standard power generator by the Industry. Best new power plants are chosen annually for use in the calculation of the capacity of the market price.
53. Hydro power multi strategy target is the large hydropower plants have the important role of social-economic, defense, security by the State monopoly to build and operate.
54. terraced hydropower Group is a collection of plants, in which the amount of water discharged from reservoirs of hydroelectric plants on the ladder to occupy the whole or a large part of the water reservoirs of hydroelectric plants on the stairs below and between the two did not have the power to regulate large water reservoir more than a week.
55. the scheduling software mobilization is software system was operated by electric power market and the system used to schedule the next day and hour to mobilize for the generator in the electricity market.
56. the system load is the total power output of the entire power system computer exchange about the extreme head of generators in a transaction cycle.
57. the measured output power measurement is counting to count of the power plant at the measuring location count.
58. the contract is now output power output is allocated from the output, contracts for each transaction cycle and be paid according to the power purchase contracts other false shape.
59. The production contract in power output is committed annually in the wrong format power purchase contracts.
60. The production contract, as the power output is allocated from the output of the contract year for each month.
61. The output of the plan is the power output of the power plant is expected to be mobilized in the coming year.
62. the planned output, is the power output of the power plant is expected to be mobilized the months of the year.
63. the thermal power is the amount of thermal energy consumption of aggregates or power plants to produce one unit of power when operating at full load, the mode is determined for each type of electric heat technology.
64. the binding generator payment is a payment that is received for the generator unit power play increased.
65. the electricity market participants is the unit involved in the transaction or provide the services on the mobile market, as defined in article 2 of this circular.
66. the electricity market is a competitive electricity market is formed and developed under the provisions of article 18 of law electric power.
67. The lack of capacity is the situation when the total capacity of all generator units is under extra system load demand forecasts in a transaction cycle.
68. the security information is the confidential information as provided by law or by agreement between the parties.
69. Market information is the entire data and information related to the operation of the electricity market.
70. The time of the termination of the bid is the time after which the power unit is not allowed to change a bid the next day, except for the special cases set forth in this circular. In the mobile market, the time of the termination of the bid is 10 p.m. of the day D-1.
71. the mobilization order is to sort the results in a power strip under the scheduled rule is not binding.
72. Excess capacity is the situation when the total volume capacity is offered in floor price and capacity announced by the hydro power multi strategy targets due to electrical system operators and market published in the larger transaction cycle load forecasting system.
73. the aggregates run top is the only generator was mobilized into the peak hours of extra power system load chart.
74. the aggregates is back running the generator was the peak and the normal hours of extra power system load chart.
75. the aggregates run as background generator was mobilized into the rush hour, normal hours and hours of extra load chart low-power system.
76. the slow startup is the aggregates generators do not have the ability to boot and the peace of the grid in time is under 30 minutes.
Chapter II REGISTRATION article 4 ELECTRICITY MARKET PARTICIPANTS. Power market participant responsibilities 1. The power plant has a license to operate in the field of electricity generators, have the capacity to put larger than 30 MW connected to national electricity system, except the power plant as defined in paragraph 2 of this article, must participate in a competitive electricity market.
2. Power not power market participants include: a) BOT power plant;
b) wind power and geothermal power plants;
c) power plants in the industrial area just sell part of the production is up to the national electricity system and failed to determine long-term power sales plan. Vietnam electricity Corporation is responsible for establishing a list of power plants and electricity regulatory Agency approval.
3. Power plant specified in clause 1 of this article are responsible for investment, improve the system of equipment to connect to the electricity markets information system, SCADA/EMS system and counting system of electric power to meet the requirements of the electricity market.
Article 5. Application of electricity market participants 1. Generator unit that owns the power plant as defined in article 4 of this circular are responsible for submission of registered market participants for each power plant.
2. Registration documents to join the electric market include: a) A register of electric market, which specify the name, address of unit generators, power plant;
b) copy license to operate in the field of electricity generators;
c) material testing system put into operation the equipment to connect to the electricity markets information system, SCADA/EMS system and counting system of electric power;
d) other necessary information required by the electricity system operators and market power.
Article 6. The order approval sign market participants 1. Within ten (10) working days from receipt of valid records, power system operators and the mobile market is responsible for the evaluation and the electricity regulatory Bureau to allow the power plant to join the mobile market.
2. In the case of invalid records, within a period of five (5) working days from the date of the application, the electrical system operators and market power must have a written request additional generator units, complete the profile.
3. within five (5) working days of receipt of the text of the unit operating the power system and electricity markets, electricity regulatory Agency is responsible for issuing the decision to allow the power plant to join the market power and notified in writing to the unit operating the power system and electricity markets to bring power plants on the list of market participants the electric field.
4. within five (5) working days since the power plant is allowed to join the market power, generator units are responsible for registering with the unit operating the power system and the market power of the subject bid on electricity markets (electricity or power plants).
Article 7. Membership information, entering the market of electricity 1. Power transmission unit, the unit bought the only merchant and data management unit for measuring electric energy counting is responsible for registering the General information about the unit for power system operators and market power.
2. electrical system operators and market power have a responsibility to store registration information, update the changes to the registration information of the members participate in the mobile market.
3. the electricity market participants are responsible for notifying the unit operating the power system and electricity market when there is a change in the registered information.
4. electrical system operators and market power have a responsibility to publish registration information of the electricity market participants and registration information has changed.
Article 8. Suspend and restore the right to participate in the market of electric power plants 1. The power plant is suspended the right to participate in the mobile market in the following scene: a) does not fulfill the provisions of article 4 of this circular;
b) Have the following behavior:-do not provide information or provide incorrect information for the planning of power market operation and the mobilization of the aggregates in the electric system;
-Agreement with the electric system operators and market electricity or other power units in the bid to mobilize non-scheduled rules;
-Direct or indirect agreement with other units in the announced capacity and bid on the market power to raise prices of electric power market and affect the security of electricity supply;
-The other violations that cause serious consequences on power system security or financially for the other units in the mobile market.
2. electricity regulatory Bureau reserves the right to participate in the market of electric power plant had violations of the provisions of paragraph 1 of this article. The sequence and procedures for suspension of the right to participate in the market of power plants are specified in article 108 of this circular.
3. During the power plant suspended the right to join the market power: a) power unit or power plants are not bid directly on the mobile market but must comply with the provisions of this circular;
b) unit purchase only merchant is responsible for bid instead of power plants;
c) power plant has the responsibility to provide information to the unit purchase wholesale only to bid instead.
4. the suspended power restore the right to participate in the mobile market when it meets the following conditions: a When the right suspension period) to join the mobile market expire;
b) has fulfilled the obligations stipulated in the decision on sanctions.
5. When did meet the conditions specified in paragraph 4 of this article, the power plant is responsible for sending the text suggested restoring the right to participate in the mobile market accompanied by the documents operational unit to the electrical system and the electrical market. Power systems operators and market power have a responsibility to check and to allow the power plant to be market participants.

6. In the case of the time limit for the suspension of the right to participate in the mobile market ended but the power plant has not yet meet all the conditions specified in point b of paragraph 4 of this article, the mobile system operators and market power have a responsibility to report the electricity regulatory Bureau to review the process.
Article 9. Termination of market participants 1. Termination of power plant electric power market participant in the following cases: a) as proposed by the unit in the following cases:-the unit's power generator stop or stop generator national power system;
-The unit's power generator is not maintained and is not likely to restore capacity set greater than 30 MW.
b) license to operate in the field of electricity generators of the power plant is revoked or expired.
2. In the case provided for in point a of this paragraph 1, unit generator is responsible for filing the proposal ended up electricity market electricity regulatory Bureau at least thirty (30) days before the time of wanting to end the electricity market participants.
3. electrical system operators and market power are responsible to update an archive subscription information and disclosure of information about termination of power of market participants.
4. In the case of the power plant had violations prior to the termination of market participants, the power generators that power plant owners have the responsibility to continue the implementation of the provisions on testing, verification and processing the violation under the provisions of this circular.
Chapter III the PRINCIPLE of OPERATION of the ELECTRICITY MARKET article 10. Limit bid 1. The price of the generator on the market competitive power is limited from a floor price to a ceiling price.
2. a ceiling price of thermal power is determined annually, adjusted monthly and is calculated based on the following factors: a) the thermal power of the generator;
b) coefficient of performance according to the operating time of the generator;
c) fuel prices;
d) startup costs.
3. floor Price of thermal power is 1/kWh.
4. Limit the bid of hydropower is determined according to the value of the water every week and is prescribed in article 37 of this circular.
Article 11. The value of water 1. The value of water is used for the planning of the operation next year, next month, next week and determine the price limit Hi of hydropower in electricity market.
2. electrical system operators and the mobile market is responsible for the calculation and publication of the value of water according to the timeline of the market specified in annex 1 of this circular.
Article 12. The total market value of full market value for the transaction cycle is calculated by the sum of the two (2) the following components: 1. The price of electric power market.
2. market power Prices.
Article 13. Electricity market price 1. Electricity market price is the price for the entire system, which is used to calculate payment power on power market for each transaction cycle.
2. market power Prices due to electrical system operators and power market after the operation time calculation based on the scheduling method not binding.
3. The price of electric energy market does not exceed the ceiling price of the market due to the electrical system operators and market electricity regulatory Bureau and the computational power of approval each year.
4. The determination of market power prices are stipulated in article 63 and article 65 of this circular.
Article 14. Market capacity price 1. Market power prices for each transaction cycle was operated by electric systems and power computing market in the process of planning for operation next year and no change in the applicable year.
2. market power Prices are calculated on the principle of ensuring the best new power plants sufficient recovery of fixed and variable costs.
3. The determination of market power prices are stipulated in article 25 and 26 of this circular.
Article 15. Power purchase contracts other false shape 1. Generator unit dealing directly and purchase unique wholesale unit is responsible for signing the wrong form power purchase contract under model by other Industry.
2. The output of the contract year is operated power systems and electrical markets calculated based on the output of the plan and yield rate of payment under the contract price specified in paragraph 5 of this Article. The output of the plan was the electrical system operators and market power calculation in the process of planning for operation next year under article 27 of this circular.
3. The output of the contract, to be operated by power system and electricity markets identified in the operational planning process next year based on the allocation of contract production in the month under article 28 of this circular.
4. Production contracts now are operated by electricity market and power system identified in the process of planning the next operation based on the allocation of the production contract, on the hour, according to article 35 of this circular.
5. electricity regulatory Bureau is responsible for determining and announcing the rate of payment under the production contract price of unit generators every year according to the following principles: a) ensure harmonised objectives:-gradually reduce power output rate of payment under the contract price;
-Stable sales of generator unit;
-Average electricity price stability, in line with the regulations on the construction schedule of the retail price of electricity.
b) power output rate of payment under the contract price in electricity market operation start no higher than 95%, and a gradual decline in the next year but not lower than 60%.
Article 16. The principle of payment of electricity market 1. Power unit to be paid under the contract and paid the market price of electricity.
2. power unit are paid according to the following type of contract: a) power purchase contracts other false form for the unit to directly power transactions;
b) power purchase contracts for hydro power multi strategy objectives;
c) ancillary services contract for the power unit provided supporting services.
3. Payments under market value applies only to the direct power generation units and transactions are calculated based on the following factors: a) the price of electric power market;
b) Reviews the capacity of the market;
c) power output and capacity be mobilized.
4. The payment is made according to the provisions in chapter VI to this circular.
Chapter IV PLANS to OPERATE the ELECTRIC MARKET section 1 PLANS article 17 NEXT YEAR. Plans to operate next year 1. Power systems operators and the mobile market is responsible for planning the operation next year, including the following: a) the choice of the best new power plants;
b) calculate the price the market capacity;
c) calculated the value of water and limited water level of the reservoirs of hydroelectric power;
d) calculated a price limit of power;
DD) determine the price ceiling market;
e) presided, in collaboration with the only merchant to buy units of calculation of output plans, contract-year production and distribution contract production in the month of the year of the transaction generator unit directly.
2. electrical system operators and market power are responsible for using market simulation models to calculate the content specified in paragraph 1 of this article. The price of a salute used in the simulation of market power by a ceiling price determined in paragraph 1 to article 21 of this circular, of the value of water hydroelectric calculations for next year.
3. electrical system operators and the mobile market is responsible for the Vietnam electricity Corporation evaluation and the electricity regulatory Bureau approved plans to operate next year according to the timeline of the market rules in annex 1 of this circular. The records include calculation results, the input data and calculation.
Article 18. Classification of hydroelectric plants 1. The hydropower plants in electricity market are classified as follows: a) hydro power multi strategy objectives;
b) groups of terraced hydropower;
c) other hydropower plants.
2. Every year, the electricity system operators and the mobile market is responsible for updating the list of terraced hydropower group.
3. electricity regulatory Bureau responsible created list of hydro power multi strategy targeted to Industry the Prime Minister for approval.
Article 19. Extra load forecasting for planning next year's operating units operating the power system and the mobile market is responsible for load forecasts to serve operational planning next year according to the method prescribed in the electrical transmission systems regulated by the Ministry of industry and trade. The figures forecasted load planning service operate next year include: 1. The total system load demand and load each of the Northern, Central, southern for the whole year and each month of the year.
2. extra chart on downloads the typical of the Northern, Central, Southern and the entire system of the months of the year.
3. maximum capacity, minimum of load system in each month.
Article 20. Supporting services for planning next year 1. Power systems operators and the mobile market is responsible for determining the needs of the service type for the coming year according to the provisions stipulated by the transmission power systems Industry.
2. electrical system operators and the mobile market is responsible for the choice of the power plant and ancillary service providers contracted to provide ancillary services to unit generators form issued by the Ministry of industry and trade.
Article 21. Classification of aggregates to run in the background, running back and run the Summit next year 1. Power systems operators and the mobile market is responsible for classifying the aggregates run in the background, running backs and running top as defined in the classification process aggregates and computes a ceiling price of thermal power plants.
2. electrical system operators and market power are responsible for using market simulation models to determine the average load factor of the generator.
3. the average load factor of base year from simulation results, the aggregates are classified into the following groups: three (3) a) Group aggregates background including running the generator has the average load factor greater than or equal to 60%;
b) Group aggregates run backs include the gensets have average annual load factor is greater than 25% and less than 60%;

c) Group aggregates run top include the gensets have average annual load factor is less than or equal to 25%.
Article 22. Define bid of power 1. Determining the ceiling price of a thermal power) Price ceiling price of thermal power is determined according to the following formula: in which: a ceiling price of thermal (VND/kWh);
KKD: coefficient of startup costs of thermal power. For the thermal background KKD = 0; nest run thermal power backs KKD = 5%; nest run thermal power Summit KKD = 25%;
f: extra cost coefficient, calculated by the percentage of the total fuel cost and maintenance operating costs versus variable costs the main fuel;
PNL: price of fuel thermal power (Dong/BTU);
: The thermal power of the heat (BTU/kWh).
b) fuel prices used to calculate the ceiling a fuel price is expected for the year N by buying unique merchant offers for power system operators and market power. Fuel prices are calculated to fence conversion power plants;
c) heat of electric power is determined by the thermal power was agreed in the contract or in the record of negotiating power purchase contracts by buying wholesale unit provides unique and are calibrated according to the coefficient of performance.
The case of the nest thermal thermal power figures in the contract or in contract negotiations for the sale of electricity, thermal power plant's power which is determined by the thermal electric power plant's standard of the same group according to technology and capacity. Power systems operators and the mobile market is responsible for the calculation of the heat consumption of the standard power plant.
Case no thermal power figures in the contract or in the record of negotiating power purchase contracts and do not have the same standard power plant group match, power system operators and market power heat power calculations based on past operating figures because the generator units provided.
d) coefficient of performance of thermal power is determined by the coefficient of performance of the contract or in the record of negotiating power purchase contracts by buying wholesale unit supplied.
Case no thermal power system metrics of performance of the contract or in the record of negotiating power purchase contracts, the applicable coefficient of performance of standard power plant of the same group with the power plant operated by the power system and electricity markets identified;
extra cost multiplier) of thermal power are the only merchant to buy units determined based on data in your purchase contract or record contract negotiations for the sale of electricity and provide power system operators and market power.
2. The price floor of the thermal power is regulated in article 10 paragraph 3 of this circular.
3. electrical system operators and market power have a responsibility to publish limited bids was approved of by thermal power market timetable in annex 1 of this circular.
Article 23. Limited bids for BOT power plant 1. A ceiling price of BOT power plant by power component prices in the power purchase contracts of BOT.
2. a floor Price of BOT power plant by 1/kWh.
Article 24. Choose the best new power plants 1. Best new power plants for year N is the power plant electricity market participants meet the following criteria: a) started commercial operation and the entire power generator set in the year N-1;
b) Is the power plant running in the background, are classified according to the criteria in paragraph 3 article 21 of this circular;
c) thermal technology uses charcoal or gas turbine cycle the mixture;
d) full generator costs on average for 1 kWh is the lowest.
2. buy only wholesale unit is responsible for establishing a list of power plants that meet the criteria in point a and point c of paragraph 1 of this article and provide the metrics of power purchase contracts this power plants for power system operators and power markets to identify the best new power plants. The figures include: a) the price for the transforms in N;
b) fixed price for year N;
c) power output agreement to calculate the price of the contract.
3. In the case of no power plants that meet the criteria specified in the points a, b and c of paragraph 1 of this article, the unit operating the power system and electricity market using the new plant has the best selection for the year N-1 and requested the unit to buy unique wholesale update again, the figures prescribed in clause 2 of this Thing to calculate for the year N. 4. Power systems operators and the mobile market is responsible for calculating the cost of the average full power for 1 kWh for power plants that meet the criteria specified in the points a, b and c of paragraph 1 of this article according to the following formula: total power: cost on average for 1 kWh in year N of power stations (VND/kWh);
: fixed price for year N power purchase contract under the wrong form of the power plant (VND/kWh);
the price for the transforms in: N power purchase contract under the wrong form of the power plant (VND/kWh);
power output: agreement to contract prices for the year N of the power plant (kWh);
: power output expected in year N of power plants identified from the simulation model in the market according to the scheduling methods that bind (kWh).
5. new power plants to the best option for year N is the power plant has cost the average full power for 1 kWh lowest according to results calculated in paragraph 4 of this Article.
Article 25. The principle of determining market capacity price 1. To ensure the best new power plants sufficient recovery power generation costs as market participants.
2. Do not apply market power prices for the peak night, the peak of which night is the hours counted from 0:00 to 4:00 and from 16:00 to 24:00.
3. price the market capacity is proportional to the load forecasting system for transaction cycle.
Article 26. The order determines the price of power market operator system of electric power market and is responsible for determining market capacity according to the following sequence: 1. Determine the cost of lack of new power plants good for a) determine the expected turnover in the market of new power plants in year N according to the following formula : where: RTTĐ: revenue expected over the price of electric power plant's new power market best in years N (copper);
I: cycle of transactions i in year N;
I: the total number of transaction in the year N cycle;
SMPi: electricity price market proposed transaction cycle i in year N are determined from the power market simulation model according to the scheduling method not binding (VND/kWh);
: output is expected of new power plants in the trading cycle i in year N determined from market simulation model according to the scheduling methods that bind (kWh).
b) determine the total cost of electricity in the power plant's best new according to the following formula: where: TCBNE: the cost of electricity in the new power plant's best in years N (copper);
PBNE: full power cost on average for 1 kWh of power plants the best defined in new paragraph 4 to article 24 of this circular (VND/kWh);
: output is expected of new power plants in the trading cycle i in year N determined from market simulation model according to the scheduling methods that bind (kWh);
I: cycle of transactions I in year N;
I: the total number of transactions in the year cycle N. c) deficiency in cost of best new power plants is determined by the following formula: in which: AS: costs of lack of new power plants in year N (copper);
TCBNE: the total cost of electricity in the new power plant's best in years N determined in point b of this Clause (copper);
 revenue expected over the price of electric power plant's new power market best in years N defined in point a of this paragraph (copper).
2. Determine costs, shortage, shortfall costs of new power plants are best determined by allocating the cost shortfall in the month of the year N by the following formula: where: t:, t in year N;
MS: costs, lack of new power plants t best (copper);
As the cost of lack of new power plants in year N (copper);
load capacity: Summit in April t (MW).
3. Determine the capacity of the market price for the transaction cycle a) determine the capacity available to the average of the year best new power plants according to the following formula: in which: QBNE: available capacity on average in the year of the new power plant N best (kW);
I: the total number of transaction in the year N cycle, except for the peak night;
I: transaction cycle in which new power plants are expected to mobilize the best except the peak night;
: capacity mobilization expected of the best new power plants in the trading cycle i of year N followed the power market simulation model according to the scheduling methods that bind (kW).
b) determine market power prices for each transaction cycle next year according to the following formula: in which: I: the total number of transactions in the cycle, t, except the peak night;
I: i in the transaction cycle, t, except the peak night;
the capacity of the market price in transaction cycle i (Dong/kW);
QBNE: available capacity on average in the year of the new power plant N best (kW);
MS: costs, lack of new power plants t best (copper);
: load prediction system of transaction cycle i followed the diagram on load forecasting of typical, t are stipulated in article 19 of this circular (MW);
: load State for forecasting system, t (MW).
Article 27. Determine the output of the contract in the contract production of power plants are determined during the planning for operation next year, includes the following steps: 1. Using market simulation models to determine the expected output of the power plant had scheduling method binding.
2. calculate the output of the plan of power plant according to the following formula: If if if in it:: the output of the plan of the power plant (kWh);
expected output: the years of power plant N determined from market simulation model according to the scheduling method, there's bound to be converted on the measuring position count (kWh);
: power output in N's agreement to calculate the power purchase contract (kWh);

a, b: five output correction coefficient, in which a = 0.9; b = 1.1. 
3. calculate the output of the power plant contract according to the following formula: in which: Qc: production contract in N (kWh);
: production planning in N of the power plant (kWh);
: output rate of payment under the contract price applicable to the year N (%). Article 28. Determine the output, contract, contract production of power plants are determined during the planning for operation next year, includes the following steps: 1. Using market simulation models to determine the expected output each month of power plants.
2. Determine the output of the contract, according to the following formula: in which:: output, contract t of the power plant (kWh);
QC: the output of the power plant contract (kWh);
: output is expected in the month t's determined from market simulation model according to the scheduling methods that bind (kWh).
Article 29. Responsible for identifying and signing of contract production in April and 1. Power systems operators and the mobile market is responsible for: a.) calculate the output of the contract year, the month of the generator unit as defined in article 27 and article 28 of this circular;
b) Send calculation results yield a contract for the purchase of single trade unit and unit generators directly to check transactions;
2. buy only wholesale unit and generator units directly responsible for transaction: a) provided the figures for power system operators and market power to calculate the output of the contract year, month;
b) check and coordinate with units operating the power system and electricity markets to handle discrepancies in calculation results;
c) Supplement Addendum of August contract output on power purchase contracts other false shape according to calculation results.
Article 30. Determining the ceiling price of the market 1. Power systems operators and the mobile market is responsible for calculating the ceiling price in the market, including market ceiling rate, average electricity price for year N and the rate of change of the average electricity price in comparison to the year N-1. The number of price ceiling approach to market a minimum of three (3) options.
2. The price ceiling, the market for the year N does not exceed 115% of the ceiling price of a greeting of the most expensive thermal power running backs.
3. the average annual electricity Prices are calculated according to the following formula: where: j: j generator of unit generators directly to transactions;
J: the total number of power generator units directly dealing;
PPDTB: the average power price system in year N (VND/kWh);
: full market prices by an average of five N prescribed in clause 4 of this (VND/kWh);
: the total power output of the system N year (kWh);
: total power output in N of the direct power units (kWh);
: the total power output of the power purchase contracts other false shape in N j power (kWh);
power purchase contract price in the wrong format to another year of N j power (kWh);
: the total cost of buying electricity from the power plant in BOT N (copper);
: the total cost of buying electricity from the hydroelectric multi strategy objectives in the year N (copper);
CDVPT: total cost buy ancillary services in the year N (copper).
4. the average total market value is determined by the following formula: in which: i: cycle of transactions i in year N;
I: general trading cycle of year N;
: full market price average in N (VND/kWh);
: expected output in the market of all the power plants market participants in the transaction cycle i determined from market simulation models are bound to convey (kWh);
electricity price in the market expected the transaction cycle i determined from the electricity market simulation models are not bound to transmit (VND/kWh);
the capacity of the market price in transaction cycle i (Dong/kW).
Section 2 OPERATIONAL PLAN, to article 31. Extra load forecasting for planning the next operation the unit operating the power system and the mobile market is responsible for load forecasts to serve operational planning next month according to the method prescribed in the electrical transmission systems regulated by the Ministry of industry and trade. The extra load forecasting metrics serve to plan operations, to include: 1. The total system load demand and load each of the Northern, Central, Southern, and each week for the entire month.
2. extra chart on downloads the typical of the Northern, Central, Southern and the whole system for a week in May.
Article 32. Calculate the value of the water power system operators and the mobile market is responsible for calculating the value of water for the week in the coming months. The results of calculation of the value of water is used to plan operations, to include: 1. the expected output of the hydropower multi strategy objectives.
2. The value of water hydroelectric plants in terraced hydropower group.
3. The value of other hydroelectric water.
4. Water level limit the downloads in the month of hydro-electric reservoirs.
Article 33. Classification of aggregates to run in the background, running back and run the Summit next month 1. Power systems operators and the mobile market is responsible for classifying the aggregates run in the background, running backs and running top in next month according to the classification process aggregates and calculate a monthly ceiling of thermal power plants.
2. electrical system operators and market power are responsible for using market simulation models to determine the average load factor of the generator in the coming months.
3. the average load factor of base, from simulation results, the aggregates are classified into the following groups: three (3) a) Group aggregates background including running the generator there, average load factor greater than or equal to 70%;
b) Group aggregates run backs include the gensets have average load factor, greater than 25% smaller and 70%;
c) Group aggregates run top include the gensets have average load factor, or smaller by 25%.
Article 34. A ceiling price adjustment of thermal power 1.  Power systems operators and the mobile market is responsible for calculating and adjusting the price ceiling a the thermal power in coming months by the method prescribed in article 22 and results categorized aggregates defined in article 33 of this circular.
2. electrical system operators and market power have a responsibility to publish the price ceiling, a salute of thermal power in the coming months according to the timeline of the market specified in annex 1 of this circular.
Article 35. Determine the output of the contract hours power system operators and the mobile market is responsible for determining the time contract production in the coming months for power plants according to the following steps: 1. Using market simulation models to determine the expected output each hour during the month of power plants.
2. Determine the time contract output according to the following formula: in which: i: first transaction cycle in December;
I: total month cycle;
: the output of the power plant contracts in the transaction cycle i (kWh);
the expected output of transmitter: power plants in the trading cycle i determined from market simulation model according to the scheduling methods that bind (kWh);
: output, contract of power plants are determined according to article 28 of this circular (kWh);
3. electrical system operators and market power have a responsibility to send the results to calculate the production contract for the purchase of single trade unit and unit generators directly to transactions under electric market timeline specified in annex 1 of this circular.
4. purchase units only wholesale and direct power unit transactions are responsible to sign the contract now yields according to the results of calculation of power system operators and market power.
Section 3 PLANS to OPERATE NEXT WEEK Article 36. The value of water to 1 week. Power systems operators and the mobile market is responsible for updating the data load forecasting, hydrological and other related data to calculate the value in the country next week.
2. electrical system operators and the mobile market is responsible for updating information, recalculated the value of water for the coming weeks and announced the following results: a) the value of water and the expected hourly production of hydro power multi strategy objectives;
b) value of terraced hydropower group;
c) water value hydropower;
d) limited water level of the hydroelectric reservoir.
Article 37. The limit price of hydropower plants the limit price of hydro power is determined according to the value of the water next week of the plant which are published according to the provisions in clause 2 Article 36 of this circular, the following particulars: 1. in case the water values greater than 0/kWh : a) Price ceiling of hydroelectric power by 110% of the value of water;
b) Price floor of hydroelectric power by 80% of the value of water.
2. where the value of water is less than or equal to 0/kWh floor price and ceiling price of hydro power by 0/kWh.

Chapter V OPERATE ELECTRICITY MARKETS Item 1 on ELECTRICITY MARKET OPERATORS to the Article 38. Information to operate the electric market next day Before 9 pm on D-1, electrical system operators and the mobile market is responsible for determining, calculating and published the following information: 1. The diagram on load forecasting system-wide and individual D of the North, Central, South.
2. Power output for export or import expects in each day's transaction cycle D. Power output, export and import due to the unique merchant purchase units provided according to the provisions of article 58 and article 59 of this circular.
3. The results of the reviews of short term system security for day D as defined in regulation power transmission system by the Ministry of industry and trade.
Article 39. A bid A bid must comply with the following principles: 1. Have maximum of 5 pairs Hi price (VND/kWh) and capacity (MW) for aggregates for each day's transaction cycle D. 2. The capacity of a bid is the capacity at the top of the pole generator.
3. step Hello minimum of 3 MW.
4. the information on the specifications of the machine, includes: a) capacity announced by the aggregates for d-day;
b) lowest stable development of aggregates;
c) speed increase and reduction of the maximum capacity of the machine.

5. publication of the capacity in a salute on D not lower level announced in the day D-2 security assessment process, power system short term specified in the electrical transmission system regulations except in the case of unforeseen technical problems.
6. Hi power strips, first in a bid to equal the lowest stable development of aggregates. Welcome to ultimate power by power publication.
7. vessel units as per kWh, with decimal number as low as 0.1.
8. Bid from floor to ceiling price bid of aggregates and not falling in the increase of capacity.
Price patterns are specified in annex 3 to this circular.
Article 40. Bid terraced hydropower Group 1. Terraced hydropower group is responsible for bids under a general price group and the compliance with the limit bid specified in article 37 of this circular.
2. Power plants in terraced hydropower group is responsible for the agreement and specify the representative unit bid. Representative unit bids for terraced hydropower group is responsible for filing the registration text enclose text agreement between the groups in power plants for power system operators and market power.
3. in the case of non-registered units represent bids for groups of terraced hydropower, electricity system operators and market power have a responsibility to bid rather for plants in this group according to the true value of water group.
4. Unit pricing representatives are responsible for compliance with the provisions on bid for all of the power plants in terraced hydropower group.
5. water value of terraced hydropower group is the value of the country's largest hydroelectric Lake in the ladder. Power systems operators and market power have a responsibility to identify indoor hydro used to calculate the value of water for hydropower group steps together with the classification of the hydroelectric provisions in article 18 of this circular.
6. In the case of groups of terraced hydropower has hydro power multi strategy goal: a) power system operators and market power have a responsibility to publish the output time delivery next week of each power plant in groups of terraced hydropower as specified in paragraph 2 to article 36 of this circular;
b) As publication output of the hydropower in the target group maximum adjusted according to the provisions of article 51 of this circular, the electrical system operators and market power have a responsibility to regulate the output of the power plants in the ladder below accordingly.
Article 41. Bid other hydroelectric and thermoelectric BOT 1. The other hydroelectric reservoirs to regulate on one (1) week of the bid on the market and limited compliance reviews touted the provisions of article 37 of this circular.
2. The other hydroelectric reservoir regulating under one (1) week announced release of hourly output on D for power system operators and the mobile market before 10:00 on the D-1 to schedule the mobilization.
3. the only merchant to buy unit responsible for bid instead of the BOT power plant.
Article 42. Submit a bid of 1. Before 10:00 on D-1, the unit responsible for bids submitted a bid on D. 2. The unit bid submitted a bid through market information system. In the event of disruptions may not use the market information system, the unit responsible for pricing consistency with units operating the power system and electricity markets on the other modalities for the submission of a bid according to the following order of priority: a) by electronic mail to the e-mail address by the electricity system operators and market regulation;
b) by fax under fax number due to electrical system operators and market regulation;
c) Filed a bye directly at the headquarters unit of the electrical system and the electrical market.
43 things. Check the validity of a bid of 1. Thirty (30) minutes before the time of the termination of the bid, the electrical system operators and market power are responsible for checking the validity of a bid is received from the unit bid according to the provisions of article 39 of this circular. The case of the unit bid sent many a bid shall only consider a bid received at last.
2. In the case of a bid invalid, power system operators and market power have a responsibility to notify the unit submitted a bid and ask the unit to resubmit a bid for the last time before the termination of the bid.
3. after receiving the notice of the unit operating the power system and the market power of a bid that is not valid, the unit responsible for the revised bid and resubmit a bid before the time of the termination of the bid. 
Article 44. A bid to schedule 1. After the time of cessation of bidding, electrical system operators and market power are responsible for checking the validity of the price received in the end according to the provisions of article 39 of this circular. A valid final bid is used as a pricing schedule for work on mobilization to scheduling.
2. In the case of the unit operating the power system and electricity market does not get a bid or the last price of the unit bid invalid, power system operators and power markets use a default bid of unit generators which make a bid schedule.
3. the default price of the power plant is determined as follows: a) for thermal power plants, a default bid is the nearest valid bid or price of an equivalent generator unit by operating the power system and electricity markets identified;
b) for hydroelectric and hydraulic plants group ladder, a default bid is a bid by water values are week was announced.
Article 45. Data used for schedule on mobilization to power system operators and market power have a responsibility to use the figures below to schedule on mobilization to: 1. The diagram on load of the whole system and each region in North, Central, South.
2. The price schedule of the unit bid.
3. Output publication of the hydroelectric provisions in clause 2 Article 36, paragraph 6 Article 40 and Article 41 clause 2 of this circular.
4. Power output, export and import regulation in Articles 58 and 59 of this circular.
5. the capacity of the power plants providing ancillary services.  
6. backup capacity requirements and frequency thing.
7. Maintenance Schedule transmission grid and generator power system operators and approved by the electrical market.
8. The results of the reviews of short term system security for day D as defined in regulation power transmission system by the Ministry of industry and trade.
9. Updated information about the availability of the transmission grid and generator from the SCADA system or due to the transport unit and the power supply unit.
Article 46. Schedule on mobilization to power system operators and market power have a responsibility to schedule next day mobilization. On mobilization schedules to include: 1. The calendar of mobilizing non-binding, include: a) market power Prices expected in each of the next day's trading cycle;
b) the mobilization order generator in each cycle the next day's trading.
2. mobilizing the binding Schedule, including: a) the chart is expected to mobilize each of aggregates in each of the next day's trading cycle;
b) Schedule stop, start and the expected grid connection status of individual aggregates in coming days;
c) method of operation, the wiring diagram of the electrical system is expected in the next day's trading cycle;
d) warning information (if available).
Article 47. Published on mobilization schedules Prior to 15 h daily, power system operators and market power have a responsibility to publish the information in the schedule the next day mobilization, specifically as follows: 1. The capacity to mobilize expected (including the capacity and frequency of backup rotation thing) of the aggregates in each cycle the next day's trading.
2. The price of electric power market scheduled for each day's transaction cycle to come.
3. List of aggregates is expected to increase or decrease capacity in each of the next day's trading cycle.
4. Information about the lack of warning capacity in coming days (if available), including: a) The projected transaction cycle lack of capacity;
b) the amount of the capacity shortage;
c) system security constraints are violated.
5. Information about excess capacity alert (if any) in the coming days, including: a) The projected transaction cycle excess capacity;
b) aggregates are expected to stop the generator.
Article 48. Grid Republic hosted the generator 1. For slow startup aggregates, units of electricity are responsible prepared to reconcile this calendar aggregates NET mobilized to do the electrical system operators and electricity market announced. The case of the startup time of the aggregates is greater than 24 hours, the unit responsible for power generation grid Republic aggregates based on the results of reviews by the short term system security units operating the electricity market and power system announced.
2. for aggregates is not slow startup, power generation units are responsible for preparing ready to reconcile this calendar aggregates mesh mobilize now to do power system operators and electricity market announced.
Article 49. When handling measures have warned the lack of capacity of 1. Modify a bid a) units bid be allowed to modify and resubmit a bid the next day or for the rest of the trading cycle on D for power system operators and market power for at least 60 minutes before operating the change a bid;
b) price of modifications and changes bid than a salute to the unit's bid;
c) electrical system operators and market power are responsible for checking the validity of the revised price and used as a pricing schedule to schedule the time to mobilize and the market price of electricity.
2. Modify the capacity announced by the hydro power multi strategy targets the unit operating the power system and power markets are allowed to modify the capacity announced by the hydro power multi strategy objectives as defined in paragraph 2 Article 51 of this circular.
Section 2 OPERATING the ELECTRIC MARKET HOURS to article 50. Scheduling data to mobilize now to

Power systems operators and market power have a responsibility to use the figures below to schedule a time to mobilize: 1. load chart of the entire system and each region in North, Central, South predictions for the coming hours and three (3) hours.
2. The price schedule of the unit bid.
3. inclusion of the grid plan your launch scheduled on mobilization to delay was announced.
4. The output of the hydropower most targets.
5. Power frequency thing, backup, backup, backup quick start cool and operate due to power system security constraints for the next hour.
6. Availability of the transmission grid and generator from the SCADA system or due to unit power transmission and power supply units.
7. other constraints on system security.
Article 51. Adjust the output of hydro power multi strategy objectives 1. Before the scheduled time to mobilize, power system operators and market power are allowed to adjust the time output of hydro power multi strategy target has been published according to the provisions in clause 2 of this circular 36 Articles in the following cases: a) Have abnormal fluctuations of Hydrogeology;
b) Have warned the lack of scheduled capacity to mobilize the next day;
c) Has the decision of State administration authority on reservoir of the hydro power multi strategy the goal of serving the purpose of flood prevention, irrigation.
2. Scope the production of hydro power multi-targeting strategies in cases specified in point a and point b of paragraph 1 of this Article due to the electricity regulatory Bureau annual regulations according to the recommendation of the unit operating the power system and electricity markets on the basis of reviews results operate electrical systems and electrical markets in the years ahead. In its first year of operation of the electricity market, the adjustment range is ± 5%.
Article 52. Schedule time to mobilise 1. Power systems operators and the mobile market is responsible for scheduling the time to mobilize for the generator according to the scheduling methods are bound.
2. Schedule a time to mobilize in the event of a power shortage) unit operating the power system and electricity market scheduled to mobilize the aggregates in the following order:-according to the price schedule;
-The hydro power multi strategy targeting performance tuning;
-The air backup service provides quick start, air cooled backup service providers according to the schedule the next day mobilization;
-The service provider operating the machine must play by power system security constraints;
-Reserve capacity spinning;
-Reduce the frequency thing redundant capacity down to lowest level allows.
b) power system operators and the mobile market check, determine the amount of the expected capacity need laid to ensure system security.
3. Schedule a time to mobilize in the case surplus capacity of the electrical system operators and market power have a responsibility to adjust the calendar to mobilize now to adopt the measures in the following order: a) Stop the aggregates voluntarily stop generator;
b) minimize development of air spinning reserve service providers;
c) minimize development of air provide service frequency thing;
d) Stop the air not start slowly with a price from high to low;
DD) diminishing the capacity of the air start slow on a level playing in the lowest stable;
e) Stop the slow booting machine in the following order:-Has the shortest startup time;
-Startup cost from low to high. Startup costs by buying the only merchant agreement with generator unit and give the unit operating the power system and electricity market;
-Has the lowest capacity level sufficient to solve excess capacity situation.
Article 53. Mobilization schedule announced now to power system operators and market power have a responsibility to publish calendars to mobilize now to fifteen (15) minutes before the operation, including the following: 1. extra time to load forecasting of the whole system and the North, Central, South. 
2. mobilizing the Calendar in the coming hours and three (3) hour next was established according to the provisions of article 52 of this circular.
3. Measures for the handling of the unit operating the power system and electrical markets in case of lack or excess of capacity.
4. The information on the adjustment of capacity announced by hydro power multi strategy objectives as stipulated in article 51 of this circular.
5. the extra load expected dismissal Schedule (if any).
Section 3 OPERATION REAL TIME Article 54. Of real time power system 1. Power systems operators and the mobile market is responsible for operating the power system in real time to base the next hour mobilization schedule has been announced and comply with regulations on operating the power system real time in electrical transmission systems regulated by the Ministry of industry and trade.
2. power unit are responsible for compliance with the order of things by power system operators and market power.
Article 55. Intervention in the market of electricity 1. Cases of interference in the market electric power system operators and market power are allowed to intervene in the electricity market in the following cases: a) the system is operated in emergency mode are specified in the regulation of electricity transmission system by the Ministry of industry and trade;
b) cannot give mobilization schedule hours to fifteen (15) minutes before the hour.
2. The intervention measures on the market of electric power system operators and market power to mobilize the power generators in the following order: a) according to a salute of the unit price for that transaction cycle;
b) in the case of the unit bid does not have a valid for that transaction cycle:-apply floor prices for the output of the contract;
-Apply a ceiling price for the remaining output.
c) in the case could not be made the measures specified in point a and point b of this Clause, the power system operators and market power are responsible for mobilizing the aggregates to ensure the objectives according to the following order of priority:-ensure the balance of power and load;
-Meet the requirements of the backup frequency thing;
-Meet the requirements of the spinning reserve;
-Meet the requirements on quality of voltage.
3. Disclosure of information about a market intervention) When intervening in the market of electricity, power system operators and power markets are announced the following:-The reasons to intervene the market;
-The transaction cycle is expected to intervene in the electricity market.
b) within 24 hours from the conclusion of the intervention in the electricity market, the electricity system operators and market power have a responsibility to publish the following:-The reason to intervene in the electricity market;
-Transaction cycles intervene in electricity markets;
-The measures taken by the electrical system operators and market electricity applied to intervene in the electricity market.
Article 56. Stop electricity market 1. Electricity market operation stops when it happens to one of the following cases: a) due to emergency situations of natural disaster or security guard on defense;
b) due to the power system operators and the mobile market mobile market stop suggested in the case of:-power system operate in extreme emergency mode are specified in transmission system regulations by the Ministry of industry and trade;
-Does not guarantee the operation of the electricity market, constantly.
c) results operating the electric market does not achieve these goals.
2. electricity regulatory Bureau is responsible for the review, the decision to stop the power market in the cases specified in paragraph 1 of this article and inform the unit operating the power system and electrical markets.
3. electrical system operators and market power have a responsibility to inform the members about the electricity market participants decided to stop the electric market of electricity regulatory Bureau.
4. Operate the system in time to stop the electricity market: a) power system operators and the mobile market is responsible for moderation, the electrical system according to the following principles:-ensure the safe operation of the system, stable, reliable, with the cost of buying electricity for the lowest system;
-Ensure implementation of the agreement on the production of the export contract, import electricity, power purchase contracts of BOT power plant and the power purchase agreement has committed to the production of other power plants;
b) power units, power transmission units and other relevant units have the responsibility to comply with the command level of units operating the power system and electrical markets.
Article 57. Restoring electricity market 1. The mobile market is restored when ensuring the following conditions: a) causes the led to stop electricity market have been overcome;
b) unit operating the power system and electricity markets confirms the possibility of operating the electricity market again.
2. electricity regulatory Bureau is responsible for the review, the decision to restore the market and notify the electrical system operators and market power.
3. electrical system operators and market power have a responsibility to inform the members about the electricity market participants decided to restore the electricity market electricity regulatory Bureau.
Section 4 export, IMPORT of ELECTRICITY in ELECTRICITY MARKET OPERATION Article 58. Handle export power in mobilizing scheduling 1. Before 16 hours on D-2, the unit bought the only merchant is responsible for notifying the unit operating the electricity market and power system power output for export is expected in each day's transaction cycle D. 2. Power output for export was calculated as the load at the point of export and are used to calculate the extra load forecasting system on mobilizing the scheduling service and hours.
Article 59. Handle the import of electricity in scheduled mobilization 1. Before 16 hours on D-2, the unit bought the only merchant is responsible for notifying the unit operating the electricity market and power system power output for each import transaction cycle on D. 2. Power output is calculated as import source placed at the point of importation to the bid by 0/kWh in mobilizing to scheduling and hours.
Article 60. Payment for electricity exports and imports

Power export and import are paid under a contract for the sale of electricity by buying single merchant.
Chapter VI MARKET ELECTRICITY PRICE CALCULATION and PAYMENT of ELECTRICITY MARKET section 1 Power COUNTING MEASURES 61. Provide measures to count 1. Before 15:00 on D + 1, data management unit for measuring electric energy counting is responsible for providing electricity system operators and market electric power counting metrics of each day's trading cycle D. 2. Before the eighth working day (8) after the end of the billing cycle, the unit of counting data management power have a responsibility to provide for power system operators and market electric power counting data in billing cycle as specified in circular No. 27/2009/TT-BCT on September 25, 2009 by the Minister of industry and trade regulation measuring cell count in a competitive electricity market.
Article 62. Archive of data counting power system operators and the mobile market is responsible for storing the count measures of electric power and related records within a period of at least five years.
Section 2 CALCULATE the PRICE of ELECTRIC ENERGY MARKET and the PAYMENT CAPACITY of 63 Articles. Determine the price of electricity market 1. After the transaction date D, power system operators and the mobile market is responsible for the scheduling of electricity market price calculation for each transaction cycle on D the following sequence: a) calculate the load system in transaction cycle by measuring output conversion counts toward the top of the pole generators;
b) arrange the power strip in the price schedule of unit generator and the output of the hydropower multi strategy targeting the scheduling method is not binding until the total capacity reached arranged load system.
2. The price of electric power market by bid final capacity of strip in computer power market prices. In case the price of the last power strip in the computer market of electricity price is higher than the ceiling price, the market price for electricity is calculated by market price market ceiling.
3. Before 9 p.m. on D + 2, power system operators and market power have a responsibility to publish the price of electric power market of each transaction in the cycle on D. Article 64. Determine the capacity of payment 1. After the transaction date D, power system operators and the mobile market is responsible for the scheduling of capacity for each day's transaction cycle D the following sequence: a) calculate the load calibration in the transaction cycle with load plus system the following components:-rotating backup capacity for trading cycles;
-Capacity frequency thing for transaction cycle;
-Power components encourage (in 3% load system of the trading cycle).
b) arrange the power strip in the price schedule of unit generator and the output of the hydropower multi strategy goals for that transaction cycle according to the scheduling method is not binding until the total capacity reached arranged load adjustment. The amount of capacity and frequency regulator dial backup for the trading cycle of the machine are arranged with the bid by 0/kWh.
2. The amount of the payment capacity of aggregates in the transaction cycle in the amount of capacity of aggregates that are arranged in calendar capacity.
3. Before 9 p.m. on D + 2, power system operators and market power have a responsibility to publish the amount of the payment capacity of each of the aggregates in the trading cycle on D. Article 65. Determine the price of electric energy market and the payment capacity when intervening in the market of electricity 1. In the case of market intervention time less than 24 hours: a) power system operators and power market using a valid bid is to determine the price of electric power market according to the provisions of article 63 and the amount of payment capacity as specified in article 64 of this circular;
b) in the case of aggregates do not have a valid bid, power system operators and power markets use the floor price for the output of the contract now and a ceiling price for production contracts to schedule to calculate the electricity market and the capacity for that transaction cycle.
2. In the case of market intervention time is greater than or equal to 24 hours, the electricity system operators and market power have no responsibility taken for electricity market price calculation and payment capacity for the period market intervention.
3 entries for PAYMENT TRANSACTION GENERATOR UNITS DIRECTLY to article 66. Power output serves the mobile market in payment 1. Power systems operators and the mobile market is responsible for calculating the component power output of the power plant in the transaction cycle payment service in the mobile market, including: a) power output payments according to bid for thermal power plants have a higher ceiling price bid market (Qbp);
b) increased transmitter power output (Qcon);
c) power output of payment according to the price of electric power market (Qsmp).
2. Power output payments according to bid for thermal power plants have bigger ceiling price bid in market transaction cycle is determined as follows: a) determine the aggregates have a higher ceiling price bid the market scheduled computer market value for the transaction cycle i and location of counting of aggregates;
b) calculate the power output of the payment according to bid in each position monitored defined in point a of this Paragraph according to the following formula: If if in it: i: first transaction cycle;
j: counting points Wednesday, j of thermal power plants, defined in point a of this paragraph;
: power output of payment according to the bid at the counting position j in the trading cycle i (kWh);
: power output measured at the measuring location count count the j in the transaction cycle i (kWh);
: power output corresponding to the amount of capacity is priced lower than the ceiling price or say hello to the market in the trading cycle i of the aggregates have connect to the counting position j and exchange about the location of the measurement that counts (kWh);
: power output corresponding to the amount of capacity have a higher ceiling price bid market and was ranked in the computer market price in the transaction cycle i of the aggregates have connect to the counting position j and exchange about the location of the measurement that counts (kWh).
c) power output calculation of payments under the bid for power plants according to the following formula: where: j: points counting something of thermal power plants, defined in point a of this paragraph;
J: the total number of points counting of the power plant has a higher ceiling price welcome aggregates market and scheduled computer market price;
: power output of payment according to the price of power plants in the trading cycle i (kWh);
: power output of payment according to the bid at the counting position j in the trading cycle i (kWh).
3. increased transmitter power output of the power plant in the transaction cycle is determined according to the following sequence: a) determined the additional transmitter transmission constraints or other constraints in the transaction cycle;
b) calculate the increased transmitter power output in the transaction cycle at the beginning of aggregates according to the following formula: – where aggregates are not bound to the scheduled broadcast time to mobilise and increase the capacity of the command in the transaction cycle:-cases aggregates were bound to the scheduled broadcast time to mobilize : where:: power output increased release of the computer at the top of the pole in the transaction cycle i (kWh);
: development of air under the command of the unit's electrical system and the power market in the trading cycle i (kW);
 : the capacity of the machine is placed in charge of electric power market in the trading cycle i (kW);
: the capacity of the machine according to the calendar time to mobilize in the transaction cycle i (kW);
: about time machine to increase orders in the trading cycle i (minutes).
c) identified increased transmitter power output in the trading cycle of the machine, by convert the output from the first pole position of the measuring position count aggregates.
d) calculate the power output increased release of power plants in the trading cycle i according to the following formula: in which: total production increased release of power plants in the trading cycle i (kWh);
g: increase of the transmitter power plants in the trading cycle i;
G: the total number of nests increased transmitter of power plants in the trading cycle i;
increase of the transmitter output: aggregates g in the transaction cycle i (kWh).
4. Power output of payment according to the price of electric power in power market trading cycle i is determined by the following formula: in which:: power output of payment according to the price of electric power in power market trading cycle i (kWh);
: power output measured counts of power plants in the trading cycle i (kWh);
: output power are paid according to the price in the trading cycle to salute i for thermal power plants have a higher ceiling price bid market (kWh);
: power output increased release of power plants in the trading cycle i (kWh).
Article 67. Electricity market payment 1. Power systems operators and the mobile market is responsible for the calculation of the payments market power of power plants in the billing cycle according to the following formula: where: Rg: total payments of electric power market in the billing cycle (the Council);
Rsmp: payments for the production section are paid according to the price of electric power market in the billing cycle (the Council);
RBP's: payments for the production section are paid according to the bid for the thermal power plants have bigger ceiling price bid market in the billing cycle (the Council);
: payment for the increased transmitter power output in the billing cycle (copper).
2. Payments for the output to be paid according to the price of electric power market of power plants in the billing cycle are determined according to the following sequence: a) calculation for each transaction cycle according to the following formula: in which:: payments for the output to be paid according to the price of electric power market of the power plant's cycle of transactions i in the billing cycle (the Council);

SMPi: reviews of market electricity trading cycle i in the billing cycle (VND/kWh);
: power output to be paid according to the price of electric power market of the trading cycle i in the billing cycle (kWh).
b) calculation for billing cycle according to the following formula: in which:: payments for the output to be paid according to the price of electric power market of power plants in the billing cycle (the Council);
I: first transaction cycle in the billing cycle;
I: the total number of transaction cycle billing cycle;
: payments for the output to be paid according to the price of electric power market of the power plant of the trading cycle i (bronze).
3. Payment for the output to be paid according to the bid for thermal power plants have bigger ceiling price bid market in payment cycle is determined according to the following sequence: a) calculation for each transaction cycle according to the following formula: – where the power output of the plant cell count measurement is greater than or equal to the power output of the payment under the contract price : where:: payments for the power part Hi higher ceiling of power plants in the trading cycle i (bronze);
j: Hello Strip something in a bid of the aggregates in the thermal power plants have a higher ceiling price bid market and are arranged in calendar to calculate the electricity market;
J: total Strip Hi in a bid of thermal power plants have a higher ceiling price bid market and are arranged in calendar to calculate the electricity market;
: Hello Hello strips with corresponding price j in a salute of the aggregates of the thermal power g in the transaction cycle i (VND/kWh);
the highest bid rate: the Hi range are arranged in calendar to calculate the market power of thermal power plants in the trading cycle i (VND/kWh);
: total capacity is offered at the price of a greeting of thermal power are mobilized in the transaction cycle i and converted about counting position (kWh);
: total power output has higher ceiling price bid the market of thermal power plants in the trading cycle i (kWh).
-Power output measured case count of smaller power plants power output of payment under the contract price: where:: payments for the power part Hi higher ceiling of power plants in the trading cycle i (bronze);
SMPi: electricity market price in the transaction cycle i (VND/kWh);
: total power output has higher ceiling price bid the market of thermal power plants in the trading cycle i (kWh).
b) calculation for billing cycle according to the following formula: in which:: payments for the power part Hi higher ceiling of the power plant in the billing cycle (the Council);
I: i in the transaction cycle that power plants be mobilized with a higher ceiling price bid levels;
I: the total number of transaction cycle in which the cell factory be mobilized with a higher ceiling price bid levels;
: payments for the electricity price is higher than the ceiling of the Hi power plants in the trading cycle i (bronze).
4. Payment for the increased transmitter power output of the power plant in the transaction cycle is determined according to the following sequence: a) calculation for each transaction cycle according to the following formula: in which:: payments for increased transmitter power output in the transaction cycle i (bronze);
g: increase of the transmitter power plants in the trading cycle i;
G: the total number of nests increased transmitter of power plants in the trading cycle i;
increased transmitter power: of the air g in the trading cycle i, (kWh);
: bid corresponds with increased power range of the air g in the trading cycle i (VND/kWh).
b) calculation for billing cycle according to the following formula: in which:: payments for increased transmitter power output in the billing cycle (the Council);
i: ith trading cycle of the billing cycle in which thermal power plants must increase by order of release;
I: the total number of trading cycle of the billing cycle in which thermal power plants must increase by order of release;
: payments for increased transmitter power output in the transaction cycle i (bronze).
Article 68. The payment capacity of the market units operate electrical systems and electrical market is responsible for calculating the payment capacity of the market for power plants in the billing cycle in the following sequence: 1. Calculation for each transaction cycle according to the following formula: in which:: payment capacity for power plants in the trading cycle i (bronze);
g: aggregates of the power plant is paid according to the rates of capacity;
G: total number of aggregates of the power plant is paid according to the rates of capacity;
market power: the price in the transaction cycle i (Dong/kW);
: the amount of the payment capacity of the air g in the transaction cycle i (kW).
2. calculate for the billing cycle according to the following formula: in which:: payment capacity for the power plant in the billing cycle (the Council);
I: first transaction cycle in the billing cycle;
I: the total number of transactions in cycle billing cycle;
: payment capacity for power plants in the trading cycle i (bronze).
Article 69. Payments under the power purchase contracts other false shape based on the price of electric power market and power market prices due to the electrical system operators and market electric power generation units, is responsible for the calculation of payments under the power purchase contract form other false billing cycle in the following sequence : 1. Calculation for each transaction cycle according to the following formula: in which: other false payments in the transaction cycle i (bronze);
: power output of payment under the contract price in the transaction cycle i (kWh);
PC power purchase contract price in the wrong format (VND/kWh);
SMPi: electricity market price in the transaction cycle i (VND/kWh);
CANi: market power prices in the trading cycle i (VND/kWh).
2. calculate for the billing cycle according to the following formula: in which: Rc: other false payment in the billing cycle (the Council);
i: ith trading cycle of the billing cycle;
I: the total number of transaction cycle billing cycle;
: other false payments in the transaction cycle i (bronze).
Article 70. Payment when intervening in the market of electricity 1. The case of market intervention time is under 24 hours of generator unit, received the payments specified in Articles 67, 68 and 69 Thing Thing, with the price of electric energy market and the amount of payment capacity determined in article 65 of this circular.
2. in case of market intervention time is greater than or equal to 24 hours, power generation units are paid according to the contract price for the entire power output measured counts.
Article 71. Stop payments when the market power In electricity market, stop time unit generators are paid according to the contract price for the entire power output measured counts.
Section 4 PAYMENT of ANCILLARY SERVICES and PAYMENT Article 72. The payment of the opportunity for preventive service dial 1. Power systems operators and market power have a responsibility to calculate opportunity cost payments for power unit provides dial backup service billing cycle in the following sequence: a) calculation for each transaction cycle according to the following formula: in which:: opportunity cost payments for power generation units in the transaction cycle i (bronze);
g: aggregates provide dial backup service of generator units in the transaction cycle i;
G: total aggregates provide dial backup service of generator units in the transaction cycle i;
capacity: schedule backup service provides rotation of aggregates g in schedule i transaction cycle mobilized hours (kWh);
: opportunity cost in the trading cycle i of the aggregates (g/kWh). Opportunity cost is calculated as follows: where:: the price of electric power market in the trading cycle i of the day D (VND/kWh);
: the largest vessel of the touted price corresponds to the power strip provides dial backup service (VND/kWh).
b) calculation for billing cycle according to the following formula: in which:: payments opportunity cost in the billing cycle (the Council);
I: first transaction cycle in that billing cycle generator Unit provide dial backup;
I: total cycle transactions in the payment cycle generator unit that provides dial backup;
: opportunity cost payment in the transaction cycle i (bronze).
2. Opportunity cost is only paid for the power supply redundancy.
Article 73. Payment for quick launch of backup services, preventive services are cool, service operated by security constraints to the system power units provide preventive services start fast, cold backup service, operating services to do your system security constraints be paid under contract to provide auxiliary services signed with the system operators electricity and electrical markets.
Article 74. Payment for hydro power multi strategy target payments for hydro power multi strategy objectives are to follow the signed power purchase contracts to purchase unique wholesale unit.
Article 75. Other payment 1. Unit generators that power generators release serves to adjust the voltage to be paid for electricity from the grid to power play: a) according to the electricity market price for aggregates has bid on power market;
b) Under power purchase contracts for aggregates do not bid on the electricity market.
2. thermal power Nest was forced to stop as defined in point d and point e in paragraph 3 Article 52 of this circular was to pay the cost level launch agreement between merchant and only buy units of unit generators.
3. where the measuring output power may count by counting data management provided as prescribed in clause 2 Article 61 have wrong other than the total electric energy counting the days in the month due to the measured data management unit count to provide according to the provisions in clause 1 of this circular 61 Articles the power section, the difference is paid according to the price of your purchase contract signed between merchant and only buy units of unit generators.
Section 5 order and PAYMENT PROCEDURES Article 76. Metrics serve electricity market payment calculations

Before 9 h 00 on D + 2, power system operators and the mobile market is responsible for General and provides for the purchase of single trade unit and generator metric units serving the payment calculation for each power plant as defined in annex 6 of this circular.
Article 77. Electricity market payment statement for the transaction 1. Previously on D + 4, power system operators and market power have a responsibility to prepare and send to the unit a unique merchant and buy the unit generator lists preliminary market payment for the transaction according to the form prescribed in annex 3 to this circular.
2. Before the date of D + 6, direct power unit transactions and purchase unique wholesale unit has the responsibility to report back for power system operators and the market power of the errors in the billing statement preliminary power market (if any).
3. On D + 7, power system operators and market power have a responsibility to prepare and send to the unit a unique merchant and buy the unit generator electricity market payment statement complete for d-day. Article 78. Electricity market payment statement for the billing cycle 1. Power systems operators and market power are responsible for General billing data for all trading days in the billing cycle and test, against a general power output by the unit of counting data management power supply.
2. within ten (10) working days from the date of the last transaction of the payment cycle, power system operators and market power have a responsibility to establish and release electricity market payment statement for the billing cycle.
3. electricity market payment statement for the billing cycle including the payment statement for each transaction and the aggregate table according to the form prescribed in annex 5 of this circular and the minutes confirmed only the number of counters and power output.
Article 79. Electricity billing profile 1. Power unit directly and send transactions to the payment voucher electric market for wholesale purchases only unit based on power market payment statement for the billing cycle.
2. set generator unit and send the payment voucher for the purchase of single trade units according to the provisions of the signed power purchase contract between merchant and only buy units of unit generators.
3. Before July 20 monthly, set generator unit and send an invoice for the purchase of single trade units. Invoice includes the payment of the electricity market and contract payment in the billing cycle.
Article 80. The billing records for the contract to provide auxiliary services power generation unit is responsible for making the payment of ancillary services under contract to provide auxiliary services between units of electricity and electrical system operators and market power.
Article 81. Edit Bill of 1. In the case of erroneous bills, generator unit or units purchased the only merchant has the right to propose bills to edit within a period of one (1) month from the date of issue. The parties concerned have the responsibility to coordinate and unify the payments adjust.
2. power unit are responsible for additional payment adjustments to the Bill of the next billing cycle.
Article 82. The payment of 1. The latest on the last day of every month, the only merchant to buy units and electrical system operators and market power have a responsibility to make payments under the Bill of unit generators.
2. power unit and buy unique wholesale unit is responsible for uniform payment method in electricity market consistent with the provisions of this circular and the relevant regulations.
Article 83. Handling errors in payment where there is excess or lack of payment compared to the Bill, the relevant units to handle this error as specified in your purchase contract or contract to provide auxiliary services.

Chapter VII SOFTWARE for the OPERATION of the ELECTRICITY MARKET Article 84. Software for the operation of the electricity market 1. The software for the operation of the electricity market, including: a) market simulation models;
b) value calculation model of water;
c) mobilized scheduling software and moderation;
d) software serving the payment calculations;
DD) other software serves the electric market activities.
2. electrical system operators and market power have a responsibility to build, develop and operate the software serves the electrical market.
Article 85. Software requirements for the operation of the electricity market 1. Ensure the accuracy, reliability, confidentiality and meet the criteria due to electrical system operators and power market construction.
2. There is full of technical guidelines, operational procedures attached.
Article 86. The construction and development of the software for the operation of the electricity market 1. The software for the mobile market activity must be built, developed to support the implementation of the calculation and the transactions specified in this circular and the operating procedures of the power market.
2. electrical system operators and market power have a responsibility) to build on the standards for the software for the operation of the electricity market;
b) appraising, testing the ability of the software to meet the criteria defined in point a of this Paragraph before applying;
c) announced the list, the algorithm and process using the software for the operation of the electricity market.
Article 87. Software audit 1. The software serves the market must be audited in the following cases: a) before the official operation of the electricity market;
b) before bringing new software to use;
c) after the edit, upgrade that affects the calculation;
d) periodic audits.
2. software audit by independent audit unit performs. Power systems operators and the mobile market is responsible for recommending independent auditor, the electricity regulatory Agency approval.
Chapter VIII ELECTRICITY MARKET INFORMATION SYSTEM and INFORMATION DISCLOSURE REGULATIONS Items 1 ELECTRIC MARKET INFORMATION SYSTEM Article 88. The structure of electricity market information system information system of electric market consists of the following basic components: 1. hardware and software system of service management and market information exchange.
2. database systems and storage.
3. electronic portal serves electric market, including internal electronic information and electronic public information page.
Article 89. Management and operation of the electricity market information system 1. Power systems operators and the mobile market is responsible for construction, management and operation of the electricity market information system.
2. The electricity market participants have a responsibility to invest in the equipment management scope meets the technical requirements due to the electrical system operators and power markets, ensure the connection to the electricity market information system.
3. data management unit for measuring electric energy counting is responsible for developing, managing and operating the transmission line network connection between market information system of electric power system operators and the mobile market with the equipment of the electric market participants.
4. electrical system operators and power market only to be put into operation or change market information system of electricity we have after complete testing and regulatory power through the Bureau.
5. electrical system operators and market power are responsible for backup equipment for market information systems to ensure can collect, transmit and publish market information in case the electricity market information system was the problem or is unable to operate.
Section 2 MANAGEMENT and INFORMATION DISCLOSURE of ELECTRIC MARKET Article 90. Provision and disclosure of electricity market 1. Generator unit, the unit bought the only merchant, power transmission units and data management unit for measuring electric energy counting is responsible for providing electricity system operators and market data, information serves operational planning, mobilizing and scheduling calculations of payments under the provisions of this circular via the electronic portal of the system electricity market information.
2. electrical system operators and market power have a responsibility to provide and publish information, data, and other market operators report generator for the electricity market participants as prescribed in this circular via the electronic portal of electricity market information system.
3. Level of information access permission is determined by the function of the unit and are defined in the process of operating the electricity market information system and information disclosure.
4. electrical system operators and market power have a responsibility to publicize on public electronic information page the following information: a) information on the electricity market participants;
b) data about system load;
c) statistics about the market price;
d) The information specified in the process of operating the electricity market information system and information disclosure.
Article 91. Responsible for ensuring the accuracy of the information market of electricity 1. Market participants have a responsibility to ensure the accuracy and completeness of information power market at the time of the supply.
2. in case of the detection of information already provided, incorrect disclosure and full members, market participants are responsible for major improvements and provide accurate information for the relevant unit.
Article 92. Information security of electricity market 1. Power systems operators and electricity market not revealed the information because the electricity market participants to provide, include: a) information on power purchase contracts;
b) price of unit generators before the end of the trading day;
c) other information in addition to the authority.
2. the electricity market participants not to disclose the information outside the scope of the permissions provided and published.
Article 93. The exclusion information security 1. Provide the information required by the Department to regulate the electricity or competent authority under the provisions of the law.
2. General order information, analysis from the information published on the electricity market, not by the members join other electric market offer wrong specified in article 92 of this circular.

Article 94. Store information power market operator system of electric power market and are responsible for complete information exchange activities is done through market information system. Information storage period of at least five (5) years.
Section 3 OPERATION of the ELECTRIC MARKET REPORT Article 95. Publication information operating the power market operator system of electric power market and is responsible for establishing and periodically publish information operating the electric market is regulated in the process of operating the electricity market information system tools that are as follows: 1. Before 15:00 daily , created and published the report operated electric market the previous day.
2. Before Thursday, establishment and operation of report power market last week.
3. Before July 10 monthly, founded and published the report maximum power market goods last month.
4. Before 31 January each year, the establishment and operation of report power market years ago.
Article 96. Report mode operating the electric market 1. Before November 10 monthly, electrical system operators and market power have a responsibility to send the electricity regulatory Bureau reports power system and electricity market of the month form due to electricity regulatory Bureau regulations.
2. Before 31 January each year, the mobile system operators and market power have a responsibility to send the electricity regulatory Bureau reports power system and electricity markets last year form due to the electricity regulatory Bureau regulations.
3. within 24 hours since the end of the mobile market intervention, electricity system operators and market power have a responsibility to regulate the electricity Bureau report on the electricity market intervention.
4. electrical system operators and market power are responsible for irregular report about operating the power system, power market according to the requirements of the electricity regulatory Bureau.
Article 97. Data audit and compliance in the mobile market 1. Periodic audits before 31 March each year, the mobile system operators and market power have a responsibility to implement and complete the data audit and compliance in the mobile market of the year before. Content of the annual audit include: a auditing) figures, the calculation of power system operators and market power in electricity markets, including:-data for calculation process in the electricity market;
-The steps of calculation;
-Calculation results.
b) audit compliance power system operators and market power with respect to the sequence, the procedure specified in this circular.
2. unscheduled audits electricity regulatory Bureau has the right to request electrical system operators and market your organization perform unscheduled audits according to the content and scope of the specific audits in the following cases: a) When detecting any unusual signs in electricity market operation;
b) as proposed by the electricity market participants. The order of execution is as follows:-market members electrical textual proposals submitted for electricity regulatory Bureau stating the contents and reasons of audit recommendations;
-Within 30 days of receiving the proposed text, the electricity regulatory Bureau is responsible for the review and has written approval or disapproval of the audit recommendations, which clearly states that the content and scope of the audited or the reason for disapproval.
3. electrical system operators and market power are responsible for recommending independent audit unit capable of performing the audit contents electrical market process through electricity regulatory Bureau.
4. The electricity market participants have a responsibility to fully cooperate in the implementation of the audit market.
5. cost audit: a) due to the power system operators and market your pay in the case of audits prescribed in clause 1 and clause 2 of this point a;
b) due to the audit recommendation unit paid in the case of Auditors specified in point b of paragraph 2 of this Article.
6. within 10 days of the end of the audit, the electrical system operators and market power have a responsibility to submit audit reports to the electricity regulatory Bureau and related units.
Chapter IX SETTLEMENT of DISPUTES and HANDLE INFRINGEMENT DISPUTE RESOLUTION section 1 Article 98. The dispute resolution process in the electricity market 1. The dispute arose in the power market are resolved according to the rules of order and dispute resolution procedures in the operation due to the power Industry.
2. Prior dispute resolution as specified in paragraph 1 of this article, the parties have the responsibility to conduct negotiations to resolve the (reconciliation) within a period of sixty (60) days in one of the following forms: a) Auto reconciliation;
b) reconciliation through mediators. The parties may invite experts having expertise or electricity regulatory Bureau proposed the election of officers to do mediation.
Article 99. The responsibilities of the parties during the conciliation 1. Unification of forms of mediation, the time and the place to conduct negotiations.
2. Provide complete, truthful, accurate information, the necessary documentation related to the content dispute.
3. Give legal evidence to protect the rights and legitimate interests.
4. Participate in the negotiation process with the spirit of goodwill and cooperation.
5. In the process of reconciliation, if the dispute had detected signs of electricity market rules violations, the discovered party is responsible for notifying the other party know to stop reconciliation and electricity regulatory Bureau report. 
Article 100. The notice of dispute and negotiation preparation 1. When disputes arise, the complaining parties have the responsibility to notify in writing the parties complained about the litigation and dispute resolution requirements and submit an electricity regulatory Bureau (1) a to the report.
2. Within 15 days of receiving the notification, the responsible party is unified with each other on the form of mediation, content should resolve, time and place for negotiations. The case selection form reconciliation through mediators, the parties have the responsibility to unite the who brokered reconciliation. The parties have the right to change the agreement mediation before the time expected reconciliation agreed.
Article 101. Mediation organizations 1. Mediation the parties themselves are responsible for the Exchange, the agreement about the content should solve.
2. Reconciliation through intermediate a) the parties have the responsibility to choose the mediators and the responsibility of the mediation;
b) the parties have the responsibility to give the mediation dispute the content, information, documents related to the incident and dispute resolution requirements of each party;
c) the parties may agree with the option of settling the mediation; ask the mediators to modify, complement that resolution schemes or deals to new settlement projects.
Article 102. Report on the conciliation 1. After the end of mediation or expiry of mediation, the parties to the dispute have the responsibility to establish a reconciliation include the following: a) the time and location to reconcile;
b) the name, address of the parties to the mediation;
c) summarizes the content dispute;
d) contents of request of the parties;
DD) The content has been agreed by the parties;
e) The content of the non-party agreement was and the reason no agreement was.
2. within five (5) days from the date of establishment of the conciliation proceedings, the parties have the responsibility to submit an electricity regulatory Bureau (1) a to the report.
Article 103. Dispute resolution in the Department regulate electrical power 1. The parties have the right to process the incident up electricity regulatory Bureau to resolve disputes in the following cases: a) the expiry of conciliation prescribed in clause 2 Article 98 this circular that incidents reconcile disputes did not or could not organize reconciliation was due to a non-participating parties to conciliation;
b) one party does not make the content was agreed upon in mediation proceedings.
2. After receiving the proposed dispute resolution Unit (single event), the electricity regulatory Agency is responsible for resolving disputes under the procedures prescribed in the rules of order and dispute resolution procedures in the operation due to the power Industry.
Category 2 PROCESSING of breach of article 104. Detect and report violation 1. The violations in the mobile market was discovered to be electricity regulatory Bureau report in writing.
2. report content violations include: a) the name, address, the Unit reports;
b) unit name, address violations;
c) violations;
d) date, time, violations occur;
DD) reason detected violations.
Article 105. Check, verify violations 1. Within a period of five (5) days of receiving the reports of violations of the electricity regulatory Bureau, is responsible for inspecting, verifying.
2. in the process of conducting inspection, verify violations, electricity regulatory Bureau has the right to: a) requires the unit show signs of violations, the unit concerned to provide the necessary documents, information service for inspection and verification process;
b) require unit signs violate the award;
c) referendum, take expert opinion or the opinion of the Agency, the unit concerned;
d) summon offending signs units, the units affected by violations to get comments on solutions and remedy violations.
3. In the course of inspection, verification, electricity regulatory Bureau is responsible for maintaining the confidentiality of the information and documents are provided under the provisions on the confidentiality provisions of this circular.
Article 106.  Establish a violation of the law 1. Within thirty (30) days from the date of testing, verification, electricity regulatory Bureau is responsible for the end to check, verify and report on the violation of the law for violations of electricity market operation rules. The case got more complicated, the time limit for check, verify may be extended but not more than sixty (60) days from the date of inspection and verification organization.
2. A violation of the law are established according to the provisions on sanction breaking the law in the field of electric power.

3. in case of the test results, verify the device behavior shows no violation of market operation of electricity, electricity regulatory Bureau stop check, verify and inform organizations and individuals, report.
Article 107. The form processing violation 1.  The unit suffered a breach in the form, the level of fines for each violation under the regulation on sanction breaking the law in the field of electric power.
2. for the power plant had violations of the provisions of article 8 paragraph 1 of this circular, also sanctioned by the provisions in clause 1 of this article also suspended the right to participate in the mobile market. The time limit for the suspension of the right to participate in electric power market depending on the nature and extent of the violation, not to exceed six (6) months.
Article 108. Order and procedure for suspension of the right to participate in the electricity market 1. The case of the power plant had violations of the provisions of article 8 paragraph 1 of this circular, within five (5) days from the date the minutes breaking the law was established, the electricity regulatory Bureau review, a decision to suspend the right to participate in the market of electric power plant had violations and sent for power plants and power systems operators and electricity markets.
2. Within a period of one (1) days from the date of the decision to suspend the right to participate in the electricity markets, electricity system operators and market power have a responsibility to announce the suspension of the right to participate in the mobile market with regard to offending power.
3. Most of the time limit specified in paragraph 2 to article 107 of this circular, the power plant has yet to fix the violation, the electricity regulatory Bureau has the right to a decision to extend the suspension of the right to participate in the mobile market. Grace period not to exceed six (6) months from the date of the expiration of the suspension of the right to participate in the mobile market.
Chapter X IMPLEMENTATION Article 109. Implementation 1. Electricity regulatory Bureau is responsible for popular, tutorial, check and supervise the implementation of this circular.
2. Vietnam electricity Corporation is responsible for directing the electrical system operators and market power: a) build the technical process the electricity regulatory Bureau issued within six (6) months from the date of this circular effect, include:-the planning processes operate in , and next week;
-The process of choosing the best new plants and calculated capacity of the market;
-Power market simulation process;
-The process of calculating the value of water;
-The process of classifying aggregates and a ceiling price calculation of the thermal power plants;
-Scheduling process to mobilize the power generators;
-The process of operating the market information system and information disclosure.
b) investment, building, installing and upgrading information systems in power market and power market serving software consistent with the requirements specified in this circular.
3. The Unit participated in the mobile market is responsible for perfecting the equipment information consistent with your market information system according to the provisions of this circular.
4. The generator unit electric market participants are responsible to sign power purchase agreement form issued by the Ministry of industry and trade to apply for the competitive power market.
5. During the implementation of this circular, if there are problems and obstacles, the units concerned have the responsibility to report to regulatory Research Bureau, suggested, the Industry revised, additional circulars for compliance.
Article 110. Effect 1. This circular effect since 25 June 2010.
2. electricity regulatory Bureau Chief, Chief of the Ministry, the Chief Inspector, the Director, the Director concerned in The relevant units, and members of the mobile market is responsible for the implementation of this circular.