Cabinet of Ministers Regulations No. 866 Riga 2010 September (14. No 47 34 §) rules on "operational programme infrastructure and services" Appendix 3.2.1.5. activity "public transport outside of Riga" issued under the European Union's structural and cohesion funds act 18 paragraph 10 of article i. General questions 1. determines: 1.1. procedures for implementing the action programme ' infrastructure and services ' Appendix 3.2. Priority Areas and the availability of "reach" UR3.2.1.pas "contributes to accessibility and transport systems development" activity "public 3.2.1.5. transport outside Riga" (hereinafter referred to as the activity);
1.2 project submission evaluation criteria;
1.3. the requirements of the project the applicant (hereinafter referred to as project applicant);
1.4. the responsible authority.
2. The purpose of the activity is to promote the development of public transport outside Riga as an alternative to private car use.
3. the activity exercised limited project application selection.
4. within the framework of the project the applicant activity is national and local corporations, providing public transport services.
5. the project will be implemented up to august 31, 2015. This period must be completed for all project activities and for all payments made within the project.
II. Activity and one project available for the European Regional Development Fund funding and permitted aid rate. activities implemented in the framework of 6 projects co-financed by the European regional development fund. Activity within the available public funds are the European regional development fund funds 14 056 080 lats. Private funding within the framework of the activity of not less than 2 480 485 lats.
7. Private funding by project. The project funding of the applicant not less than 15 percent of the project's total eligible costs.
8. maximum European regional development fund co-financing amount per project from the project total eligible costs are 7 028 040 dollars. European regional development fund shall not exceed 85 percent of the project's total eligible costs.
III. The responsible authority 9. functions performed by the responsible authority of the Ministry of transportation. Responsible authority: 9.1 implement its functions and competence ensure appropriate, not to be exceeded this rule 6, paragraph activities available for the implementation of the European regional development fund;
9.2. provide activities and project monitoring and control, including the Council of 11 July 2006, Regulation (EC) No 1083/2006 laying down general provisions on the European regional development fund, the European Social Fund and the Cohesion Fund and repealing Regulation (EC) No 1260/1999, article 93 1 and 2 of the principle referred to in the performance of the activities and project level, controlling the project financing plan.
IV. eligible and non eligible project activities eligible and non-eligible costs of the project assisted in 10 steps is a tram line reconstruction and construction, renewal of rolling stock.
11. the eligible costs of the project are: 11.1. building project development costs;
11.2. the cost-benefit analysis development costs;
11.3. construction site preparation, maintenance and harvesting costs;
11.4. the cost of the works;
11.5. the underground communications rebuilding costs no more than five percent of the project total eligible costs if they are directly linked to the implementation of the project and the construction process in the public service for the provision of the necessary infrastructure at risk of deterioration: 11.5.1. public service infrastructure (water, sewage, heating) rebuilding costs;
11.5.2. gas, electricity and telephony communications infrastructure rebuilding costs, not changing their specifications;
11.6. building costs;
7.3. the costs of autoruzraudzīb;
11.8. the rolling stock acquisition costs;
7.4. the rolling stock reconstruction costs;
11.10. environmental compliance costs;
11.11. with fire safety and other requirements of the security-related costs;
11.12. publicity activities, in so far as it provides for the European Union structural funds and the cohesion fund management regulatory laws, not more than 0.1% of the project total eligible costs;
11.13. the value added tax, which is directly related to the project, if a project applicant cannot recover it according to the laws and tax policy;
11.14. land acquisition costs up to 10 percent of the project total eligible costs if they are necessary for the implementation of the project;
11.15. expenditure for contingencies this provision, 11.5, 11.8 11.4 and 11.9. referred to cover not more than five percent of the eligible costs of the project, not including these provisions in 11.13 and 11.12 11.15., referred to.
12. This rule 11.1, 11.2, 11.6 and 11.7. the costs referred to in subparagraph apply no more than 10 percent of the project's total eligible costs.
13. not eligible costs of the project are: 13.1. costs incurred prior to the entry into force of these rules, except that rule 11.1. costs referred to in (a);
13.2. costs not justified by relevant source documents;
13.3. the underground communications conversion costs if their crew capacity by transfer or conversion is increased;
13.4. in paragraph 11 of these rules, the costs, if they occur, making the relationship work.
14. the project cost does not include administrative costs of the project.
15. the project can include only 11 and 13 of these regulations, paragraph.
16. in the implementation of Projects not eligible costs incurred or costs in excess of the contract for the implementation of a project for the attributable costs, shall be borne by the beneficiaries of their own funds in accordance with the agreement on the implementation of the project.
V. project application form and annexes 17. submission of project financial calculation in LCY.
18. the project applicant project application shall be accompanied by the original of the accompanying document or law in the order certified copies.
19. the project application shall be accompanied by the following supporting documents:

19.1. the decision of the Board of Directors of the Corporation, the Corporation is prepared to implement the project. Draft decision the applicant shall indicate the amount of private financing, which it will invest in project implementation;
19.2. a copy of the contract for the provision of public transport services in the municipality;
19.3. a certificate attesting that the applicant has not been declared bankrupt, is being wound up and the economic activity it is not paused or stopped, and it is not in any analogous situation similar to procedure defined by the law of the Republic of Latvia;
19.4. such specialist dzīvesgait descriptions (curriculum vitae): 19.4.1. civil engineer with at least three years of experience in the construction of transport infrastructure;
19.4.2. Project Manager with at least three years of experience in the management of transport infrastructure projects;
19.4.3. accountant financiers with at least three years experience in financial accounting;
19.5. the projects in accordance with the laws and regulations on environmental impact assessment is not necessary for environmental impact assessment, add one of the following documents: 19.5.1. regional environmental management issued a copy of the technical regulation;
19.5.2. regional environmental management issued a copy of the certificate that the technical provisions are not required;
12.2. the local government issued assurances that the project planned activities comply with the municipal territory planning (if the project is a tram line reconstruction and construction);
19.7. the cost-benefit analysis a copy of the calculation. Applicant project analyzes the costs and benefits and the European regional development fund contribution calculations pursuant to annex 1 of these rules. Project applicant if the financial analysis, planning to implement the project from which derive revenue according to the Council on 11 July 2006, Regulation (EC) No 1083/2006 laying down general provisions on the European regional development fund, the European Social Fund and the Cohesion Fund and repealing Regulation (EC) No 1260/1999, article 55;
19.8. the report on the implementation of the project alternatives with a detailed assessment of each variant, which indicates a project solution that in the long term (at least 20 years) provide much of the flow of passengers shift from private vehicles to public;
12.4. documents certifying the degree of readiness of the project (if the project is a tram line reconstruction and construction): planning and architectural 19.9.1. copy of a task, if not designed for construction;
19.9.2. sketch a copy of the project under construction in the area of regulatory legislation (the sketch project matching būvvald);
19.9.3. a copy of the construction according to the construction of laws and regulatory requirements (construction of coherent and accepted būvvald);
19.10. signing of formal rights of the person who signed the application for the project;
19.11. real estate in which to make investments, ownership or possession of the documents or a statement by the applicant that the investment made by the owner of the property will be closed or agreed under article 3 of the law on construction;
19.12. If the project is intended for the provision referred to in paragraph 11.5.1. investments: 19.12.1. certified civil engineer examination of the opinion, which found that the project planned investments in certain areas, it is not possible to avoid this provision 11.5.1. infrastructure referred to transmission or damage;
19.12.2. a copy of the contract for the public service that meets the business supports the control law 21.1 the requirements set out in article;
19.13. If the project is for the rules referred to in point 11.5.2. investments-certified civil engineer examination of the opinion, which found that the project planned investments in certain areas, it is not possible to avoid this provision as referred to in point 11.5.2. transmission or damage to infrastructure;
19.14. the project application to the electronic version of the media (at the ievietojamo documents formatted in MS Word, MS Excel format). Project application electronic version may not include this rule 19.1, 19.2, 19.3, 19.4, 19.5, 19.6.,.,., 12.4 19.8 19.10 19.11 19.12.,., and 19.13. the documents referred to in point (where the application is submitted in the form of a paper document).
20. the responsible authority regulations in accordance with the procedure laid down by the request of the State revenue service information certifying that the applicant is not the project for tax and the State social insurance compulsory contribution to the debt. Project applicant project application may be accompanied by the information mentioned in this paragraph of the supporting documents. In this case, the certificate must be issued no earlier than 90 days prior to the application of the project.
21. This rule 19.2. the contract referred to in subparagraph must include information on: 21.1. the public transport service to be provided;
21.2. requirements of the public transport service provider to maintain and restore the necessary technical equipment for the service or services that could be provided according to the specific service requirements;
21.3. the duration of the contract;
21.4. the provision of public transport services;
13.4. public transport service provider assigned exclusive or special rights;
21.6. opportunities to receive compensation (compensation) payments, investment in public services, infrastructure and conditions of remuneration (compensation) payment calculation, control and review, as well as compensation (compensation) payment and repayment of the overpayment.
Vi. application and submission of the draft selection 22. Responsible Authority application round project is implemented on all activity in the funding available.
23. If the project application selection round all available funds are not learned, the responsible authority may organise a second round of project submissions for the remainder of the funding.
24. Each project within the framework of the activity, the applicant may submit only one project submission. Project applicants who do not submit the project application to the responsible authorities within the time specified in the invitation, or which project application in the previous round rejected, the competent authority may invite to participate in the next round of project submissions.

25. the responsible authority shall, not later than three months after the entry into force of these rules, send a letter to invite the applicant to submit these draft regulations under the draft submission.
26. the applicant shall submit a project application to the responsible body within a time limit which it shall specify, for not less than 30 days from the date of dispatch of the invitation.
27. project submissions prepared according to the project application form (annex 1).
28. the project application submitted in person, by post or by electronic means.
29. the project submission in paper form shall be submitted in triplicate (one original and one copy).
30. the project submission in electronic form submitted in accordance with the legislation on electronic document design. Project application with secure electronic signature, certified by the stamp of the time before the draft submission closing date and sent to the electronic mail address (investicijas@sam.gov.lv).
VII. submission of Project evaluation procedures and criteria for assessment 31. activities within the project submitted submissions judged responsible authorities established a project application to the Evaluation Commission (hereinafter the Commission). Panelists include the Ministry of transport and representatives of the responsible authority. The composition of the Commission, approved by the responsible authorities. The representatives of the managing authority is the power to participate in the meetings of the Commission as observers without voting rights.
32. the Commission is governed by a Statute approved by the responsible authority.
33. the project submission compliance is assessed on the basis of this provision listed in annex 2 of the draft application evaluation criteria.
34. the project submission's compliance with this provision of the annex 2 section 1 and 2, the assessment criteria listed in is valued at "Yes" () or "no" (no matches). The project's compliance with this provision application annex 2 referred to in section 3 of the evaluation criteria evaluated by giving a certain number of points.
35. in order to determine the total number of points in the annex 2 of this rule 3. title in the criteria mentioned in, showing the significance of the criteria, criteria for the number of points earned are multiplied by the percentage of the proportion of the corresponding criteria.
36. the project submission's compliance with this provision in annex 2 section 4 of the evaluation criteria evaluated with "Yes" () or "no" (no matches).
VIII. Decision-making and reporting results of responsible authority 37. project application is approved if it meets all the rules referred to in annex 2 of the assessment criteria.
38. the project's responsible authority approves the application, if the application does not need to specify the corresponding to one of the provisions of annex 2 section 1 and 2, the assessment criteria listed in, which allows the application of the project approval with conditions.
39. the responsible authority shall reject the application for the project if it does not match any of the rules referred to in annex 2 of the evaluation criteria, which do not allow for the approval of the application, the project on condition.
40. Where the application does not comply with any of the rules referred to in annex 2 of the evaluation criteria, which do not allow the application to the approval of the project, the responsible authority for the project assessment of the application terminated.
41. the decision on the approval of the project application, approval or rejection provided the determining authority within five working days after the decision has been forwarded to the project applicant.
42. the decision on the application for the approval of the project provided the conditions contained in the project applicant 15 working days of notification of the decision.
43. Within five working days after the conditions for receipt of the supporting documents, the Commission shall evaluate compliance with the conditions contained in the decision and the responsible authority shall draw up the opinion.
44. Where the applicant has complied with the decision on the application for the approval of the project provided the conditions contained in the project application is considered and approved by the responsible authority within five working days after that rule 43. the expiry of the period referred to in paragraph 1 shall send to the applicant, project a positive opinion on the conditions contained in the decision.
45. If the decision contains the conditions are not met or are not met this rule 42 time limit referred to in paragraph or of these rules, paragraph 43 of the responsible authority opinion is negative, the responsible authority in the five working days following that rule 43. the expiry of the period referred to in paragraph 1 shall send to the applicant a negative draft opinion.
46. the responsible authority shall publish information on the projects approved by the Ministry of transport on application home page on the internet (URwww.sam.gov.lv).
IX. conditions for the implementation of the project. the project applicant, 47 submitted to and implementation of the project, the partnership is not.
48. The beneficiary first advertised the procurement procedure not later than within three months after the conclusion of the contract.
49. The beneficiary in accordance with the signed agreement for the implementation of a project to the responsible authority provides full information about the implementation of the project (including project progress reports and yearly – project implementation reports (pēcprojekt reports)).
50. The beneficiary in its homepage on the internet (if available) is placed up to date information on the progress of the implementation of the project, if the project's total cost exceeds 350 000 lats.
51. following the agreement on the conclusion of the project the responsible authority, if it is available in the State budget, provides funding for the requested advance payment according to the regulations on the procedures foreseen in the State budget to fund the European Union co-financed the project implementation, as well as make payments and preparation of declarations of expenditure.
52. If the project is a violation of the regulations on control of business support, the responsible authority shall assess the violations and decide on project funding granted to the reduction in proportion to the seriousness of the infringement.
53. the provisions of this decision referred to in paragraph 52, the responsible authority shall notify the beneficiary within five working days after the decision.
54. the responsible authority five years after completion of the project, but no later than the operational programme ' infrastructure and services ' closing provides the revenue generated by the project, including the withholding of revenue recovery or that were not taken into account in the calculation of project available in the European regional development fund.
Prime Minister v. dombrovsky traffic Minister k. Gerhards submitted by the Ministry of transport of the

1. the annex to Cabinet of Ministers of 14 September 2010 regulations No 866 traffic Minister k. Gerhard annex 2 Cabinet 2010 September 14, Regulation No 866 Project submission evaluation criteria 1. Administrative criteria evaluation system Criteria the impact on decision making (P1, N2) Yes/No (1). the project applicant is invited to submit a project application to the N 2. project proposal is submitted to the responsible authorities within the set N 3. project proposal is prepared into P 4. Project application is made in the Latvian language N 5. Project submission complies with the legal document laid down the requirements for the preparation and presentation of the project application to the 6 P is fully completed, and then attached to the Cabinet of Ministers regulations on the implementation of the activities set out in annex P 7. Project application has been drawn up according to the provisions of the Cabinet of Ministers on the implementation of specific activities for the project submission form for the submission of draft N 8 financial plan and budget summary does not mean error of P 9. project application is signed by the project paraksttiesīg of the applicant party or its authorized person (is connected to the power card) N 10. Requested the European regional development Fund co-financing and national funding amount is calculated in the arithmetic properly P 2. Eligibility 2.1. PROJECT eligibility criteria applicant ranking system Yes/No 11. Notes the project applicant is a municipal corporation that provides public transport services in the municipalities (excluding Riga) N 12. the average number of people in a city where the project applicant provides public transport services in 2008, according to Central Statistical Bureau data is at least 80 000 N 13. Project applicant has been declared insolvent, the , being wound up, and the economic activity it is not paused or stopped, and it is not in any analogous situation similar to procedure defined by the Republic of Latvia Law N 14. Project applicant is not in the tax and the State social insurance compulsory contribution shows N 15. Project applicant has sufficient and stable financial resources to ensure national financing for the project N 16. in case of increase of the cost of the project, the applicant is committed to providing financing from its own resources P 17. Project application describes the implementation of the project required resources (in step the number of staff, skills, responsibilities and facilities) N 18. Real Estate in which to make an investment, the project is located in the applicant's possession or possession of or the applicant has stated that the investment at the time with the owner of the property will be closed or agreed under article 3 of the law on construction P 19. Infrastructure (including rolling stock), which is intended to make an investment, are the property of the applicant of the project P 20. applicant activity within the project has submitted one application for the project N 2.2 project eligibility criteria ranking system notes Yes/ 21. the project applicant, no activity required under the European regional development fund co-financing does not exceed LVL N 7 028 040 22. project application describes the project management, implementation and monitoring of the scheme N 23. Project management personnel have adequate experience and project management capacity, professional and technical expertise, project management and supervision will be employed: 1) one civil engineer with at least three years of experience in transport infrastructure construction area , 2) one project manager with at least three years of experience in the management of transport infrastructure projects, 3) one accountant, financier with at least three years of experience in financial accounting P 24. Project has been cost-benefit analysis has been carried out 25 N different choices offered to the analysis and solution of the project, which in the long term (at least 20 years) provide much of the flow of passengers shift from private vehicles to public N 26. project cost-benefit analysis is used in the social discount rate – 5.5 percent N 27. costs and benefits of the project the analysis is used in real financial discount rate five percent N 28. project economic net present value (ENPV) is greater than zero N 29th. the project economic rate of return (ERR) rate is more than 5.5 percent N 30 project planned publicity and visual identity measures comply with the laws and regulations of the European Union fund publicity and visual identity assurance requirements the requirements of P 31. The project will be completed by 31 august 2015 N 32. Project activities meet the objective to promote the development of public transport outside Riga as an alternative to private car use N 33. Project planned investments in public transport infrastructure development account for at least 50 percent of the total investment volume N 34. Project to take the existing tramway infrastructure reconstruction, renovation or construction of a tram line or extension or branch, the construction or renovation of rolling stock N 35. project planned in the application monitoring indicators are clearly defined and measurable N 36. Project budget includes expenditure corresponds to average market prices of the project in the year of application and results of the project are required to achieve the planned 37. the implementation of the action Project is not P and not been financed or co-financed from other Union financial sources as well as State and local budgets, and the project planned activities do not overlap with the activities financed by other European Union co-financed the activities of the funds and other financial instruments within N 38. Ensuring the sustainability of the results of the project for at least five years after completion of the project N 39. project cost specified in the application to the positions meet the Cabinet regulations on the implementation of the activity and cost around P
3. Criteria of quality evaluation system of Criteria With points 40. economic rate of return of the project norm ERR note. Points are awarded according to ERR. For example, if ERR = 6, the project that this criterion will receive 6 points points = ERR ERR

 
90% 41. Project implementation time 3 10% less than 1 year 1 to 2 years more than 2 years ago 2 1 3.1. Quality criteria for horizontal priorities evaluation system with points 42. developing projects, will be taken into account in the construction of the regulatory laws and requirements, and the project includes specific additional measures for promoting environmental accessibility for people with functional disabilities in developing projects of 1 , will be taken into account in the construction of the regulatory legislation, but the project is not intended for specific measures for the promotion of accessibility for people with functional disabilities 0 43. Implementation of the project, will prevent or reduce negative impacts on the quality of the environment directly, not indirectly 1 2 0 4. the criterion for the award of the FINANCING system for rating notes Yes/No 44.
If the application complies with the 1, 2, 4, 7, 9, 11, 12, 13, 14, 15, 17, 20, 21, 22, 24, 25, 26, 27, 28, 29, 31, 32, 33, 34, 35, 37 and 38. evaluation criteria, as well as 40, 41, 42 and 43 in the evaluation criteria received a total of at least 505 points, then the project submissions, listing in descending order, beginning with the most number of points gained in the project application the project application, insufficient activity of N labels available funding.
1. P-if the evaluation is negative, it shall take a decision on project approval with conditions (project applicant must ensure compliance with the criteria laid down in the decision deadline).
2. N-if the assessment is negative, the project submission is rejected.
Traffic Minister k. Gerhard