Advanced Search

Executive Order On The Grid Connection Of Wind Turbines And Wind Turbine Produced Electricity For Surcharges, Etc.

Original Language Title: Bekendtgørelse om nettilslutning af vindmøller og pristillæg for vindmølleproduceret elektricitet m.v.

Subscribe to a Global-Regulation Premium Membership Today!

Key Benefits:

Subscribe Now for only USD$40 per month.
Table of Contents
Chapter 1 Scope, definitions and common conditions
Chapter 2 Cost allocation for network connection and so on
Chapter 3 Definition of existing windmills
Chapter 4 Land turnips for windmills
Chapter 5 Household mills
Chapter 6 Move wind turbines
Chapter 7 Detapotions of price allowance
Chapter 8 Information to be confidential
Chapter 9 Decisions
Chapter 10 The completion of full cargo hours for existing windmills per 1. April 2001
Chapter 11 Appeal access
Chapter 12 Penalty provisions
Chapter 13 Entry into force

Completion on network connection of windmills and price corps for wind turbine electricity and so on 1)

In accordance with section 30, section 39, paragraph 1. 8, section 42, paragraph. 8, section 43, paragraph. 2 and 3, section 53 (3). One, section 57, paragraph. 1, Section 61, section 65 (5). 3, section 68 and section 73 (3). 1, in the area of the promotion of renewable energy, cf. Law Order no. 122 of 6. February 2015, as amended by law no. 744 of 1. June 2015, and section 85 a of the electricity supply law, cf. Law Order no. 1329 of 25. November 2013, and after submission of the Energy, Forsying and the Climate Committee, to be authorised according to section 4, in fact. 1, in the notice. 436 of 11. May 2012 on the tasks and powers of the Energy Management :

Chapter 1

Scope, definitions and common conditions

§ 1. The announcement shall apply to electricity-producing wind turbines on land and at sea, which are to be connected to the collective power supply network.

Paragraph 2. For the purposes of this notice :

1) '-shall mean measurement of measurements to be used to register the electricity generation or power consumption of wind farms.

2) Household mills : a windmill that produces electricity delivered to the power supply network from a windmill with an installed effect of 25 kW or less, and which is connected in its own consumption installation, cf. Section 41 of the promotion of renewable energy.

3) Sea windmill : a windmill that has been laid down on the sea territory or in the exclusive economic zone and where the foundations of windmills are not visible by normal water.

4) Installed power : the nominal effect of the windmilling windmiller, as specified in the windmill's certificate, cf. technical certification scheme for windmills, or in the technical specification of wind farms.

5) Internally Collecting Network : The internal interconnection network between the windmills of a wind-wind turbine or wind turbines drawn up by group or parks in the country up to the point of connection.

6) Collective collection networks : the collective power supply network from the point of connection to the point of supply.

7) Delivery point : The point of the collective electricity supply network where the collective Capture ceases and where electricity consumers can be connected.

8) Originating production : Elproduction, which is calculated or calculated for the operation of wind turbines, since the original connection.

9) Originating end : a wind turbine's first endorsement of the collective electricity supply network in Denmark or abroad.

10) Manufacturing costs : Cost of buying a windmill, installation and network connection.

11) Large companies : businesses that are not an SME subject to the definition in the Commission's recommendation of 6. May 2003 on the definition of micro-enterprises, small and medium-sized enterprises, (EU-Official Journal 2003, nr. 124 of 20. May 2003, s. 36)

12) The closing point : The point where one or more wind turbines are to be connected to the collective power grid.

13) Designated wind turbine area : an area designated by the State or by the municipality of a municipality plan specifically, for the setting up of one or more windmills, cf. the planning and authorization for the opening of windmills.

§ 2. A windmill may only be connected to the collective power supply network where it is established in accordance with the provisions in force in the law on the promotion of renewable energy, the law on electricity, the planning and the building code and rules issued by : home meal of the said laws.

Paragraph 2. If the conditions of network connection are fulfilled, network and transmission operations have a duty to connect the windmill to the collective power supply network.

Chapter 2

Cost allocation for network connection and so on

§ 3. The network connection shall at the nearest point of the collective power supply network where the electricity from the new windmill can be taken in accordance with the network, where the electricity from the new windmill can be taken in accordance with the network, at the request of a country. However, section 4. The network company determines the voltage level.

Paragraph 2. The costs of the building and reinforcement of the collective power supply network at the networks of a wine mill shall be borne by the network.

Paragraph 3. In the event of the approval of a windmill in its own consumption installation, the possible extraction and reinforcement of the windmill owner shall be responsible for the development of the windmill

Paragraph 4. In the windmill at transmission level, paragraph shall be found. 1 and 2 accordingly applicable to the transmission company.

§ 4. In the case of the establishment of one or more wind turbines in a designated wind turbine area, the undertaking shall be obliged to carry out the collective power supply network up to a point in wind turbine area when there is sufficient certainty that there is sufficient security ; windmills with a combined effect of at least 1,5 MW. Adequate security may be a bank guarantee or equivalent security. The network company determines the voltage level.

Paragraph 2. In the windmill at transmission level, paragraph shall be found. 1 corresponding use shall apply to the transmission company.

Paragraph 3. The windmill owner is obligated to dimension the internal connection network between the connection point and the point of departure (the meter) after Energinet.dk's guidelines. The guidelines have been published on the Energinet dk's website www.energinet.dk.

§ 5. In the case of network connectivity of marine windmills which are established in accordance with the invitation to tender, cf. Section 23, paragraph 1. 1, cf. Section 22 (2). 3, no. 1, in the Promotion of renewable energy (large sea breewwinks), the transmission undertaking which owns the electricity supply network to which the wind turbines are to be connected shall bear the cost of setting up the wiring for the purpose of setting up the pipeline ; The point of extraction at the internal interconnection network of the port wind turbines.

Paragraph 2. The transmission company concerned shall determine the level of voltage.

§ 6. In the context of network connection of marine windmills which are not covered in section 5, the costs of establishing the internal assembly net of the port windmill assembly network shall be borne by the wind turbine owner. From this point of connection, the costs of the building and reinforcement of the collective power supply network, including transformation, the network or transmission undertaking, which owns the collective power supply network, shall be borne by the public sector.

Paragraph 2. The network or transmission company shall fix the voltage at the point of connection at one of the following voltage levels :

1) 10-20 KV.

2) 33 kV.

3) 50-60 KV.

4) 132-150 kV.

Paragraph 3. The windmill owner is responsible for finding the geographic location of the connector point. In the case of the windmill owner, the windmill owner shall bear the cost of construction of the installation project and cover the cost of the network or transmissions undertaking for the construction of a plant to be included in the construction site. area of network connection, including the site of construction.

Paragraph 4. For the purposes of land, the island or mainland where the network or transmission company can establish a delivery point that does not necessitates the establishment of electricity networks in the sea territory.

§ 7. If net connection of windmills as referred to in section 3-6 also necessitates the need for reinforcements of the collective power supply network with tensions up to 100 kW owned by other networks and transmission undertakings, the costs shall be borne by a part of the costs incurred by these undertakings for the network connection.

Paragraph 2. Where electricity from windmills covered by section 3-5 is provided to a network or transmission operation by means of a wiring which is not connected to consumers or non-windmills, the cost of net losses shall be borne in : this wiring from the reicer as part of the net or transmission company ' s cost of windmills is connected to the collective power supply network.

Paragraph 3. If net connection of windmills in accordance with section 6 is provided to a network or transmission operation by means of a wiring which is not connected to consumers or other power producers other than windmills, the cost of net losses shall be borne in this wires from the connection point as part of network or transmission costs by windmills into the collective power supply network.

§ 8. The costs of a wind turbine network up to the connecting point referred to in section 3-6 shall be held by the windmill owner, cf. paragraph Two and three.

Paragraph 2. Network connection costs for the opening of a windmill comprises costs for the installation, low-voltage and low-voltage, and the establishment of settlement gauges, meter transforms and local transformer plug-in ; collective power supply networks and connectivity to the collective power supply network, including phase compensation. Cost of phase compensation for non-supplied reactive power shall be borne by the network or transmission company. Costs for the processing of the collective power supply undertaking shall be the responsibility of the windmill owner.

Paragraph 3. Afreing meters and gauge transforges are owned by network or transmission company.

Paragraph 4. The network connection of wind turbines shall cover documented expenditure and shall be provided by invoice, which shall be furnired to the windmill owner within three months after the wind power of wind power.

Paragraph 5. Costs for the maintenance or replacement of resettlement gauges and meter transforges, calibration and reading of the meters and the settlement of electricity shall be incumbable to the windmill owner. The costs must cover real documented costs relating to the individual windmill. The net or transmission company shall specify the composition of the windmill in accordance with the windmill, cf. 1. pkt., on submission of invoice. The net or transmission shall be documented by the windmill owner on the windmill owner ' s request.

Paragraph 6. If the network or transmission company has not submitted the invoice, cf. paragraph 4, or can document the cost of invoice, cf. paragraph 5, the wind turbine owner may issue the case for the energy supervision, which may impose on the net or transmission company to produce invoice or documentation of expenditure.

Paragraph 7. The cost of setting up the wire, which is the responsibility of the transmission company after paragraph 5, shall be charged as costs through the individual company's tariffs.

Paragraph 8. Net management costs and by means of a windmill being connected to the windmill, which is not referred to in paragraph 1. In the case of a single undertaking, 2, 3 and 5 shall be charged as the cost of the individual company. Section 8 (8) of the power supply. However, this does not apply to the operating costs of wiring, as referred to in Section 7 (2). 2 and 3, and which are part of the collective collection network.

§ 9. Windls, like after the 20th. May 2003 shall be connected to the collective power grid or to a consumer installation from which the electricity can be delivered to the collective power supply network, must have its own conversion measures which comply with Energinet.dk's power measurement requirements. The recipes have been published on Energinet. dk's website www.energinet.dk.

Paragraph 2. Wenvirons, which are netsigned at the latest 20. In May 2003 and drawn up in groups or parks, they shall have their own conversion measures, as referred to in paragraph 1. 1, where the electricity from each wind mills is subject to a different price allowance.

Paragraph 3. Where the production of wind turbines is not measured on an hourly basis, production will be distributed on an Hourly basis by Energinet.dk in accordance with the provisions of paragraph 1. 1 that is said.

Paragraph 4. Wine mills at 25 kW or less connected to a consumer installation are exempt from the requirement for the own conversion measures in accordance with paragraph 1. 1.

Paragraph 5. Minor windmills are exempt from the requirement for the own conversion measures in accordance with paragraph 1. 1. This does not apply to testing mills.

§ 10. The Net and transmission company has a duty to give an owner of the windmill, requesting network connection, all necessary information, including :

1) a detailed estimate, which includes all expenses, whether or not the connectivity will cost,

2) a reasonable and precise timetable for receipt and processing of the application for network connection and

3) a reasonable indicative schedule for the network connection.

Chapter 3

Definition of existing windmills

§ 11. Existing wind turbines on land and on the sea shall be defined as windmills ;

1) by 31. December 1999 has been purchased by binding, unconditional contract, cf. however, paragraph 1 3,

2) by 31. December 1999 has been notified in accordance with the notice. 1518 of 14. December 2006 on the noise of windmills, and

3) for which no later than 31. In August 2000, the request for connection to the collective power supply network, together with proof of fulfilment of the conditions of connection, shall be endorsed.

Paragraph 2. Existing wind turbines shall at the latest date of 31. December 1999 was notified to the municipality in accordance with the structure of the building code and either :

1) by 31. In December 1999, a final approved local plan has been established, where the opening of windmills is expressly permitted, or

2) by 31. In December 1999, a farmer ' s authorization has been granted, including, where appropriate, the necessary derogations for the construction of the building.

Paragraph 3. The one in paragraph 1. 1, no. The contract may be subject to the necessary regulatory authorisations for the opening of the windmill at the latest by 31 of the said contract. December 1999, and that the conditions for network connection are met by 31 December. August 2000.

Paragraph 4. If a local plane is repealed by the Natural Board due to the relationship associated with the processing of the case, windmills covered by the local plan shall be considered as existing if the municipal management board within six months from ; The termination of the local plan of nature shall definitively adopt a local plan in its unaltered form after public submission and re-examination of the municipal management board.

Paragraph 5. Rae the windmill after the 1. In April 2001, the installed power is the effect that is apparent from the binding contract, cf. paragraph 1, no. 1.

Chapter 4

Land turnips for windmills

Windler degrading in the period from 3. March 1999 to the 31 st. December 2003

§ 12. A wind turbine owner may obtain the scrapping proof of a windmill of 150 kW or less during the period from the third. March 1999 to and with the 31 st. In December 2003, under those referred to in paragraph 1, 2 or 3 conditions mentioned.

Paragraph 2. The turnip certificate for windmills which have been reduced in the period from 1. April 2001 to and with the 31. In December 2003, if this is shown by one of the windmill owner, the farmer ' s principal declaration of windmills shall be obtained from the windmills. Furthermore, the declaration made by one of the network undertaking issued a declaration that the wind turbine has been set up has been in operation and has had a capacity of less than 100 kW or between 100 and 150 kW (both power values inclusive).

Paragraph 3. In the case of windmills which have been reduced in the period from 3. March 1999 to and with the 31 st. In March 2001, the scrapping certificate may be obtained if a statement signed by both the network operator and by the owner of the windmill has been signed. The declaration must indicate that the wind turbine has been in operation, has had a capacity of less than 100 kW or between 100 and 150 kW (both power levels, including) and the time when the windmill has been decommissioned and removed.

Paragraph 4. The certificate shall allow the owner to receive price allowance in accordance with section 42 (2). 2, on the promotion of renewable energy for the reduced power of the windmill, if this had an installed power of less than 100 kW, the installed power of three (2).

Paragraph 5. The certificate shall allow the owner to receive price allowance in accordance with section 42 (2). 2, in the Prompting of renewable energy for twice the installed power of the windmill, if this had an effective power of between 100 kW and 150 kW (both power values inclusive) and if it was located at a maximum of five kilometres, from a windmill that had an installed power of less than 100 kW, which has itself obtained a scrap of scrap.

Windler depreciated during the period from the 15th. December 2004 to the 15th. December 2011

§ 13. A scrap of scrap metal as referred to in paragraph 1. 2 gives the owner the right to receive price allowance as referred to in section 42 (2). 5, in the promotion of renewable energy for electricity produced in a factory new windmill, from the 1. 1 January 2005 to 31. December 2011.

Paragraph 2. A wind turbine owner may under the windmills of paragraph 1. the conditions referred to in paragraph 3, 4 and 6, and subject to the conditions laid down in paragraph 1 3 the pool shall obtain the scrapping proof of a windmill having an effect of 450 kW or below for the period from the 15th. December 2004s and at the latest and with the 15th. December 2011. A scrapping certificate can be divided into up to 10 independent scrapping evidence.

Paragraph 3. The certificate of casing may be issued only within a pool that corresponds to a total effect of 175 MW in windmills, with an impact of 450 kW and below which has been removed from the 15th. December 2004 to and with the 15th. December 2011.

Paragraph 4. The proof of the certificate shall also be subject to the existence of :

1) a declaration signed by the network undertaking concerned by the fact that the wind turbine has been in operation and has had an effect of 450 kW or there, as well as the time when the wind turbine is detached from the collective ; the electricity supply network ; and

2) a statement signed by the windmill owner that the windmill has been reduced.

Paragraph 5. The network shall deliver the one in paragraph 1. 4, no. 1, the declaration of the windmiller owner no later than eight days after receiving a request for this.

Paragraph 6. Request for scrap heap shall be submitted to Energinet.dk at the latest by 15. December 2011.

§ 14. A wind turbine owner may ask Energinet.dk to give a written advance notice that a scrap of scrap metal may be issued for the collection of a windmill after Article 13. The insurance network cannot be translated. Energinet.dk provides the prehenchness if the company considers it in section 13 (3). 3, the maximum of 175 MW is not exceeded as a result.

Paragraph 2. A forfeit legend gives the windmill owner the right to receive a scrapping certificate, provided that the conditions for receiving a scrapping certificate have been fulfilled and the windmill owner ;

1) within 8 days of the receipt of the handover network, the network is requesting to disconnect the windmill as soon as possible from the collective power supply network ; and

2) within 40 days from the date of receipt of the case of the forehand, cf. however, the one in section 13 (1). The time limit referred to in paragraph 6 shall be submitted by 6, to the request for scrap certificate to Energinet.dk, with proof of the facts referred to in paragraph 1. Paragraph 1 and paragraph 13 (1). 4.

Paragraph 3. Energinet.dk publishes on-going information on electronic media on the size of the power for which scrapping evidence and processing lore have been issued.

Paragraph 4. Energinet.dk is preparing the application material for the issue and processing of scrapping certificates and forcandal folklore.

Common provisions governing the two scrapping schemes

§ 15. In order to make use of a piece of scrap certificate issued under Clause 12 or 13, the proof must be delivered to and endorsed by the company at the latest at the time of the network connection of the new windmill. The endorsement shall indicate the new windmill in which the proof is used. The form of the certificate shall then not be used in other windmills.

Paragraph 2. If a scrap of scrap is not fully utilized in one new windmill, the excess shall lapse.

Paragraph 3. The owner of a scrap certificate which has not been used for the payment of price allowance in accordance with section 42 (5). 2 and 5, in the promotion of renewable energy, can pass this on to others.

Paragraph 4. A windmill which has triggered scrap-scaling evidence in accordance with sections 12 or 13 cannot be reconnected to the collective power grid or to a consumer installation from which the electricity can be delivered to the collective power supply network.

Chapter 5

Household mills

§ 16. The price paper for windmills covered by section 41 (s). Amendment No 2, on the promotion of renewable energy, to be determined in such a way as to ensure that the price supplement and the provisions of Article 51 (1) of the law are applied. 2, no. 1, the market price for which the market is fixed shall be 60 cents per kWh, this is 12 years from the network connection. If the power connection has occurred before 1. However, as of January 2003, the period for prices shall be counted as from 1. January 2003.

§ 17. Application for an undertaking on price corps for wind turds attached to the 1. of January 2016 or later after section 41 (1). 4, cf. § 41, paragraph. 3, in the Promotion of Renewable Energy, will be sent to Energinet.dk. An application schema has to be applied drawn up by Energinet.dk.

Paragraph 2. A windmill that meets the conditions laid down in section 7 (2). 5, Law No. No. 744 of 1. In June 2015, no pledges shall apply for price allowance pursuant to paragraph 1. 1, but shall apply for price allowance in accordance with section 26 (s). 1, no. 1, in this notice.

Paragraph 3. Search schema is available when approached to Energinet.dk or on the Home page www.energinet.dk .

Paragraph 4. The application schema can be completed electronically on the www.energinet.dk home page or sent to Energinet.dk.

Paragraph 5. Application for an undertaking on price allowance as referred to in section 41 (1). 4, cf. § 41, paragraph. 3, in the promotion of renewable energy, must at least contain the following information :

1) Name and address of the wind turbine owner.

2) CPR No, CVR no. or other identification number of the wind turbine owner.

3) The windmill owner of the windmill.

4) The address of its own usage installation.

5) Phone number or email address for the windmill owner.

6) The installed power of the windmills measured in kW.

7) Achile certificate for wind turbine.

8) Expected time for network connection of the wind turbine.

9) Written documentation for agreement on the purchase of the windmill, cf. however, paragraph 1 6.

10) A confirmation from the wind turbine owner to the wind turbine has not been set and that the windmill will not be set up if there is no commitment to price allowance.

11) A confirmation from the wind turbine owner that the wind turbine owner has not received or will receive other support for the windmill.

12) Buy price for wind turbine.

13) Installation costs.

14) Net reg; of wind turbine.

15) Indication of the types of elf the wind turbine owner pays.

16) Documentation of the drawing-up rule of legal persons.

Paragraph 6. The Agreement pursuant to paragraph 1 5, no. 9 must be conditional upon obtaining an undertaking on price allowance.

Paragraph 7. Large undertakings shall provide evidence that the windmill will not be set up if no pledges are made on price allowance.

Paragraph 8. Applications that have not been confirmed in accordance with paragraph 1 shall be : 4, no. 10 and 11, brawl.

§ 18. Energinet.dk shall decide on price allowance pursuant to section 41 (1). 4, cf. § 41, paragraph. Three, in the promotion of renewable energy.

Paragraph 2. When Energinet.dk receives an application after Section 17, Energinet.dk will check whether the price post in section 41, paragraph, is checked. 4, cf. § 41, paragraph. 3, in the promotion of renewable energy, has an incentive effect. It is checked by checking to see whether the total cost of applications for a windmill, cf. Section 19 (1). 1, greater than the costs of the applicant for the purchase of electricity from the collective electricity supply grid, cf. Section 19 (1). 2.

Paragraph 3. The information and standard values that are used for the control of the incentive effect in accordance with paragraph 1. On the basis of the date on which the application is complete, the application shall be adopted.

Paragraph 4. If a windmill that has been pledged for the award of energy from Energinet.dk shall not be connected within two years from the time of the date of the submission of the defendant, the indictator shall be suspended.

Paragraph 5. Energinet.dk may decide on a derogation from paragraph 1. 4 if the windmill does not reach network connection within two years from the date of submission of the defendant, and the ratio cannot be attributed to the wind turbine owner.

§ 19. The total estimated costs of the applicant to a windmill shall be calculated as the sum of :

1) Manufacturing costs were converted into an annual annuity allowance during the acceptance of a 20-year depreciation period and with a call rate calculated as the long debt-bonding + 5% score.

2) Revenue from the sale of surplus electricity production from the windmill.

3) Annual operating costs for the general maintenance of a windmill.

4) Any call for on-call time.

5) Annual payment for the purchase of electricity.

6) Annual payment of the tax.

7) Annual payment of the net caricature.

8) Annual payment of a subscription.

9) Annual payment of public obligations.

Paragraph 2. The applicant ' s cost to the purchase of electricity from the collective electricity supply network, which the applicant will have if the applicant does not set the windmill, shall be calculated as the sum of :

1) Annual payment for the purchase of electricity.

2) Annual payment of the tax.

3) Annual payment of the net caricature.

4) Annual subscription payment.

5) Annual payment of public obligations.

Paragraph 3. If Energinet.dk's control in accordance with section 18 (2), 2, shows that the price supplement does not have incentive effect shall be rejected by the application.

20. Decision on the pledges of price allowance shall be tied to the address of its own consumer installation, which is provided for in section 17 (3). 5, no. 4. The case may not be transferable to others.

Paragraph 2. Paragraph 2. Energinet.dk may decide on a derogation from paragraph 1. ONE, TWO. pkton, if there are special circumstances. In exceptional circumstances, if the defendant is part of a transfer, the defendant shall be subject to the provisions of the Member of the Commission.

Chapter 6

Move wind turbines

§ 21. In the case of relocation and new networks of windmills, the result obtained shall be subject to the individual windmill, cf. however, paragraph 1 2.

Paragraph 2. In the case of wind turbines connected to its own consumption installation, which has an installed effect of 25 kW or thereunder, cf. Section 41 of the promotion of renewable energy (1) shall apply to paragraph 1. 1 only if the wind turbine is again connected in its own consumption installation. Moves the windmill so that this is no longer connected to its own consumption installation, the price supplement shall lapsed, as the conditions for which it is no longer fulfilled, shall be suspended. Section 41 of the promotion of renewable energy.

Chapter 7

Detapotions of price allowance

§ 22. A wind turbine owner may deselect the receipt of price allowance and other services by section 35A42 in the Promotes of Renewable Energy Act. In addition, the wind turbine owner may reopen the receipt of the said price allowance and other benefits. The right to resumption does not include owners of sea windmills established in accordance with the supply.

Paragraph 2. Dissenting and re-opening after paragraph 1 shall take effect from the first day of a month and with prior notice of at least one month if there is a VU certificate or price allowance for the electricity following the provisions of section 35A42 in the Promovation of renewable energy.

Paragraph 3. In the case of the calculation of original production for the calculation of full hours pursuant to this notice and section 35A42 in the promotion of renewable energy, production shall also be included in the opt-out referred to in paragraph 1. 1.

Paragraph 4. Necessary administrative costs of the opt-out and the resumption of the network or transmission activity and Energinet.dk shall be paid by the wind turbine owner on the basis of inventory of these costs.

Paragraph 5. Energinet.dk prepasts application material for the selection of the price allowance.

Chapter 8

Information to be confidential

-23. The owner of a windmill shall be obliged to make such information, including accounts and similar documentation, to be the owner of a windmill, including accounts and similar documentation for the purposes of this Regulation ; the implementation of the notification provisions relating to network connection and price allowance.

Paragraph 2. It shall be incumbated to the owner of a windmill to notify the net company, transmission company and Energinet.dk for ownership change, previous network connections, and the changing circumstances, in accordance with the conditions laid down in compliance with the conditions ; for network connection and for the receipt of price allowance for the supplied electricity.

Paragraph 3. The information must be carried out immediately at the time when the recipient of the price allowance has become aware that the relationship has been made or that the relationship is in place.

Chapter 9

Decisions

§ 24. The network undertaking which has or has applied for the granting of the supply area shall take a decision on network connection, including the fulfilment of the conditions for the approval of the supply. In addition, the undertaking shall decide on the allocation of costs, as mentioned in Section 8.

Paragraph 2. In the case of windmills directly to a transmission network, the transmission company shall decide on network connection, including whether the conditions for connection are met. In addition, the transmission undertaking shall decide on the allocation of costs, as mentioned in Section 8.

Paragraph 3. The network shall decide as to whether a windmill on land meets the conditions laid down in the definition of existing windmills in accordance with section 11, cf. however, paragraph 1 5.

Paragraph 4. Energinet.dk takes a decision whether a sea windmill meets the conditions of the definition of existing windmills after paragraph 11, cf. however, paragraph 1 5.

Paragraph 5. The DEA will decide whether a windmill satisfies the conditions laid down in the definition in accordance with section 11 of existing windmills in all cases where a new windmill has been purchased for the period from the third. March 1999 to and with the 31 st. December 1999.

Paragraph 6. Decision on the completion of full cargo hours for windmills in accordance with section 35a-42 of the promotion of renewable energy shall be taken by the net company. If the wind turbine is directly intended for a transmission network, the transmission company shall decide on this.

§ 25. Notwithstanding the provisions of section 19 (1). 1-3 and 6, a network or transmission operation may ask Energinet.dk to take a decision in accordance with the said provisions on behalf of the network or transmission company. Energinet.dk may, in such a case, require the net or transmission company to reimburse the costs incurred by such a request to intake Energinet.dk.

SECTION 26. Energinet.dk shall decide on the following :

1) Priviations and other services to electricity from windmills in accordance with section 35a-40, section 41 (1). 2, section 41, paragraph. 3, and section 42, in the promotion of renewable energy.

2) Issue of scrapping certificate, as referred to in Chapter 4 of this notice, including the fulfilment of the conditions for obtaining the proof.

3) The deselection and reopening of the payment of the price allowance and other services in accordance with section 16 of this notice.

4) The completion of full cargo hours for windmills in accordance with section 39 of the Promotion of Renewable Energy.

5) Payment of price allowance on the basis of pledges for price allowance in accordance with section 41 (1). 4, cf. § 41, paragraph. 3, in the Promintion of Renewable Energy and section 16-20 of this notice.

6) The grant of a transfer of pledges in accordance with paragraph 20 (3). Two, in this procladilation.

§ 27. Energinet.dk shall take a decision on the payment of price allowance on the basis of pledges for price cores for windmills covered by section 41 (1). 4, cf. § 41, paragraph. 3, in the promotion of renewable energy, and this notice on application.

Paragraph 2. The application is completed electronically on www.energinet.dk or sent to Energinet.dk, with proof that the windmill satisfies the requirements for the payment of price allowance in accordance with section 41 (1). 4, cf. § 41, paragraph. 3, in the area of the promotion of renewable energy, at the time of the network connection.

Paragraph 3. Energinet.dk shall lay down the detailed requirements for the documentation referred to in paragraph 2.

Paragraph 4. Payment of price allowance in accordance with paragraph 1. 1, is conditional on,

1) the windmill shall be notified to the register referred to in section 85 (a) (1). 2, no. 2, in the power of electricity (StamData Register),

2) the wind turbine is connected to its own consumption installation at the address as provided for in Article 17 (3). 5, no. 4, cf. however, section 20. 2,

3) the network connection has been made on 1. January 2016 or later,

4) the installed power of wind power shall be as provided for in Article 17 (3). 5, no. 6, and

5) the net payment shall be made in the group as provided for in Article 17 (3). 5, no. 13.

Chapter 10

The completion of full cargo hours for existing windmills per 1. April 2001

§ 28. The network shall draw up an inventory of the amount of full cargo hours per day ; 1. April 2001. The statement will be updated at each payment of the price allowance.

Paragraph 2. The inventory shall be based on the production of electricity produced. If the conversion data does not exist back from the original concoction of the windmill, the missing production data is calculated. The recalculation shall be calculated by means of a windage average calculation on the available billing data. This will only be corrected for the whole year. The production of the year in which a windmill net connects for the first time is calculated proportionally, whereby a month ' s production is regarded as 1/12 of a year's production.

Paragraph 3. The average calculation for the calculation of the production data recalculation shall not be included as a year in which the wind-corrected production is deviated by 25%. or more from the end of the year. To the extent that the resettlement data is longer than five years in the network or Energinet.dk, these must be included in the calculation. If the wind turbine owner can document electricity conversion data longer than five years, this is used instead of a calculated figure.

Paragraph 4. If several windmills are connected to the same gauge, the production shall be divided between the windmills based on the wine-corrected annual production of vines. kW.

Paragraph 5. In the case of windmills which are connected to its own consumption installation and which have an installed effect of more than 25 kW, the production of production shall be calculated on the basis of an annual production of 2 200 full-last hours.

Chapter 11

Appeal access

§ 29. Decisions as referred to in section 24 (2). 1, 2 and 6, and section 26 (4). 1, no. 1-4 and section 25 may be charged to the Energy Agency.

Paragraph 2. Complaguing shall be submitted in writing within 4 weeks of the fact that they are in accordance with paragraph 1. 1 above decisions have been announced. Complained to the network, transmission company or Energinet.dk, which shall be forwarded within four weeks of its receipt, the review of the Energy supervision of a statement and the information which has been given to the decision.

-$30. Decisions as referred to in section 24 (2). 3 and 4 can be claimed for the Agency for Energy Management.

k. 2 The decisions of energy management cannot be complained to the climate and energy minister.

§ 31. Decisions taken pursuant to section 24 (2). 5, section 26, paragraph. 1 no. 5 and 6, sections 29 and 30 may be imparted to the Energy Board of Energy.

§ 32. Decisions taken pursuant to section 18, section 20 (8). 2, and section 27 may be imprted to the Energy Board Board.

§ 33. Clail at section 18, section 20, section 20. 2, section 27, section 30, and section 31 must be submitted in writing within 4 weeks of notification of the decisions.

Chapter 12

Penalty provisions

§ 34. Unless higher penalties have been inflished on any other law, the penalty shall be penalised by the penalty which :

1) provide untimely information in connection with the request for network connection and receipt of price allowance and other services for electricity ; or

2) omits to submit notification of changes in the meaning of network connectivity and pricing and other services for electricity or which provide inaccurate information in such notification.

Paragraph 2. Companies can be imposed on companies, etc. (legal persons) punishable by the rules of the penal code 5. Chapter.

Chapter 13

Entry into force

$35. The announcement will enter into force on the 23rd. September 2015.

Paragraph 2. Publication no. 1063 of 7. September 2010, on network connection, of wind turbines and the price of wind for wind turbine electricity, etc. shall be repealed.

The DEA, the 18. September 2015

Morten Creek

/ Jane Glindu Kristensen

Official notes

1) The announcement contains provisions which implement parts of Directive 2009 /28/EC of the European Parliament and of the Council of 23. April 2009, on the promotion of the use of renewable energy sources and amending and subsequent repealing of Directive 2001 /77/EC and 2003 /30/EC, EU-Official Journal 2009, nr. In 140, page 16, as amended by Council Directive 2013 /18/EU of 13. May 2013 on the adaptation of Directive 2009 /28/EC of the European Parliament and of the Council on the promotion of energy use from renewable energy sources due to the accession of the Republic of Croatia, the EU-Official Journal, nr. L158, page 230.