Advanced Search

A Documentation Of Buildings

Original Language Title: o dokumentaci staveb

Subscribe to a Global-Regulation Premium Membership Today!

Key Benefits:

Subscribe Now for only USD$40 per month.
499/2006 Sb.



DECREE



of 10 June 1999. November 2006



a documentation of buildings



Change: 62/Sb.



Ministry for regional development shall determine pursuant to section 193 of the Act No. 183/2006

Coll., on zoning and the building code (the building Act):



§ 1



the title launched



(1) this Ordinance shall determine the scope and content of the



and) documentation for a decision on the location of the building or facility,



(b) documentation for the issue) the decision to change land use,



(c) documentation for the issue) the decision to change the impact of the use of the building on

territory,



d) common documentation common area decision and

a building permit,



e) project documentation for construction of the notification referred to in § 104 paragraph. 1

(a). a) to (e)) of the building code or design documentation for issuance of the

a building permit,



(f)) for the implementation of construction and documentation



g) documentation of the actual construction.



(2) this Decree also provides for requirements documentation demolition,

the content requirements for the building of the journal, a simple record of the structure and

the way their leadership.



(3) this Ordinance shall not apply to the project documentation for construction

air, railway and construction on the runway, including equipment on the runway, buildings

highways, roads, local roads and public purpose

communications pursuant to section 194 (a). (c)) to the building Act.



§ 1a



Documentation for the issuance of the decision on the location of the building or facility



(§ 86 para. 7 of the building Act)



The scope and content of the dossier for the issuance of the decision on the location of the building or

the device is set out in annex 1 to this notice.



section 1b



Documentation for the decision about the change of land use



(§ 86 para. 7 of the building Act)



The scope and content of the documentation for the decision about the change of land use

is set out in annex 2 to this Decree.



§ 1 c



Documentation for the issuance of the decision to change the influence of the use of the construction works on the territory of the



(§ 86 para. 7 of the building Act)



The scope and content of the documents for the issuance of the decision to change the influence of the use of

construction in the territories is set out in annex 3 to this notice.



§ 1 d



Common documentation for issuance of zoning and planning decision and joint

a building permit



(Section 94a 7 construction law)



The scope and content of a joint common spatial documentation

decision and building permit is set out in annex 4 to this

the Decree.



§ 2



Project documentation



(§ 105 para. 8 and section 110 (5) of the building Act)



The scope and content of the project documentation for construction of the Declaration referred to in §

paragraph 104. 1 (b). a) to (e)) of the building Act or building

authorization is set out in annex 5 to this Decree.



§ 3



Documentation for the execution of the project



(§ 134 para. 6 of the construction Act)



The scope and content of the project documentation for implementation of construction is determined by the

in annex 6 to this Ordinance.



§ 4



Documentation of the actual construction



(§ 125 (6) for the building of the Act)



(1) the scope and content of the documentation of the actual construction is determined by the

in Appendix 7 to this Decree.



(2) documentation of the actual construction can consist of copies of certified

project documentation, supplemented by drawings of the derogations, provided that this does not prejudice the

clarity and readability of the documentation.



§ 5



Demolition documentation



(Section 128 paragraph 8 for the building of the Act)



Demolition documentation requirements set out in annex 8 to this

the Decree.



§ 6



Construction journal, and a simple record of the construction



(To § 157 (4) of the building Act)



The content requirements for the building of the journal and a simple record of the construction

and the way their guidance set out in annex 9 to this Decree.



Transitional and final provisions



§ 7



This Ordinance shall not apply to the documentation referred to in § 2, 3, or section 5,

assessed after 1. January 2007, if they have been processed, mostly before the date

entry into force of this Decree.



§ 8



This Decree shall enter into force on 1 January 2000. January 1, 2007.



Minister:



Mgr. Gandalovič in r.



Č. 1



The scope and content of the dossier for the issuance of the decision on the location of the building or

device



The documentation contains sections:



And the accompanying message



(B) a summary technical report



(C) the Situational drawings



(D) drawing documentation



E Book part



The documentation must always include parts A to E, with the scope and content of

the various parts will be adapted to the nature and size of the construction or

equipment (hereinafter referred to as "building") and the conditions in the territory.



And the accompanying message



A.1 identification data



A.1.1 information about construction



and the name of the building),



(b)) instead of (address, numbers, cadastral, land

the numbers of the land),



(c)) the subject of documentation.



A.1.2. Information on the applicant



and) name, surname and place of residence (individual) or



(b)) the full name, business name, registration number, if assigned, place

business (natural person-entrepreneur) or



(c) the business name or name), registration number, if assigned, registered address

(legal person).



And 1.3 information about the processor documentation



and) the full name, business name, registration number, if assigned, place

business (natural person-entrepreneur) or business name, or the name,

CORPORATE ID, if allocated, the address of the registered office (legal entity),



(b) main) name and surname of the designer, including the number, under which the

registered in the register of authorized people led by Czech architects

or the Czech Chamber of authorised engineers and technicians active in

construction, with the declared scope or specialization of its authorization,



(c)) first and last names of designers of different parts, including documentation

numbers under which are entered in a register kept by the authorized persons

The Czech Chamber of architects or the Czech Chamber of authorised engineers and

technicians in the construction, with the declared scope, where appropriate,

a specialization of their authorization.



And 2 a list of input documents



And 3 information on the territory



and the solution to the range of the territory;) built-up/undeveloped territory,



(b) the present use and built-up areas) of the territory,



(c) information on the protection of the territory) under other legislation (^ 1) Memorial

reservations, heritage zone, the specially protected territories, floodplain

etc.),



d) details of the runoff ratios



e) data on the line with the spatial planning documentation, with the objectives and tasks of the

town and country planning,



(f) General) information on the requirements for the use of the territory,



g) data on the meet the requirements of the bodies concerned,



h) exception list, and úlevových solutions



I) list of related and underlying investments



j) list of land and buildings affected by the location of buildings (according to the cadastre

real estate).



And 4 information about construction



and new construction) or change the finished structure,



(b) the purpose of use of construction works,)



c) permanent or temporary building,



(d) protection of data on buildings) under other legislation (^ 1) cultural

Monument etc.),



(e) compliance with) the data on technical requirements for the construction and General

belonging to the barrier-free use of the technical requirements of buildings,



f) data on compliance with the requirements of the concerned bodies and the requirements

from other legislation ^ 2)



g) exception list, and úlevových solutions



(h) the proposed capacity building) (built-up area, built-up area,

floor area, number of functional units and their sizes, the number of

users/workers, etc.),



I) basic balance construction (needs and consumption of media and materials,

management of rainwater, the total produced quantity and types of

waste and emissions, etc.),



j) basic assumptions of the construction (the time data on the implementation of the construction work,

breakdown on stage),



indicative costs of the building).



And 5 the breakdown of the construction on the objects and the technical and technological equipment



(B) a summary technical report



(B) a description of the territory of construction 1



and characteristics of building land,)



(b)) and the conclusions of the surveys carried out by the enumeration and analysis (geological survey,

hydrogeological survey, architectural and historical survey, etc.),



(c)) the current protection and safety zones,



(d)) position relative to the záplavovému territory poddolovanému territory, etc.



(e) the construction of the surrounding) the effects of construction and land protection area, the influence of the construction

the flow conditions in the territory,



f) requirements for sanitation, demolition, cutting down trees,



g) requirements for the maximum land agricultural land resources or

the land intended for the performance of the functions of the forest (temporary/permanent),



h) territorial technical conditions (in particular, the possibility of connection to the existing

transport and technical infrastructure),



I) accruals binding construction, contingent upon, developed, related

investment.



(B) a general description of the construction of the 2.



(B) the purpose of use of construction works 2.1, the basic capacity of the functional units



(B). 2.2 the overall urban planning and architectural design



and urban-territorial control), composition space,



(b)) architectural design-composition shape, material and solutions

the color of the solution.



(B) 2.3 Disposition and operational solutions, production technology



(B) the use of the buildings accessible to the disabled.



(B) 2.5 safety during the use of the building



B. technical description Basic construction 2.6



B. 2.7 technical and technological equipment



Equipment solutions, policy needs and consumption of decisive media.



B. 2.8 fire safety solutions



Assessment of technical conditions of fire protection:



calculation and assessment) and odstupových distance and the definition of fire


the danger zone,



(b) ensure the necessary quantity of fire) of water or other extinguishing media,



(c) the estimated construction equipment) dedicated fire-safety

devices, including determination of the requirements for the construction,



(d) evaluation of the access roads) boarding areas for fire

technology including the ability to perform intervention units of fire protection.



B. 2.9 Energy Management Policy



Heat-technical evaluation criteria.



B. 2.10 health requirements for building work and

municipal environment



Resolution policy parameters of the building (ventilation, heating, lighting,

water supply, waste, etc.) and resolution policy construction

around (vibration, noise, dust, etc.).



(B) Protection Policy 2.11 construction before the negative effects of the external environment



The penetration of radon from the ground, wandering streams, seizmicita, noise,

flood protection measures, etc.



(B) 3 connection to the technical infrastructure



and the adjacent places) technical infrastructure, relocation,



b) connecting dimensions, power capacity and length.



B 4 transport solutions



and a description of the transport solutions)



(b)) to the existing territory, transport infrastructure,



(c)) to the right still.



B. related 5 solve vegetation and landscaping



(B) 6 Description of the effects of construction on the environment and its protection



and) impact on the environment-the air, noise, water, waste and soil



b) influence on nature and landscape protection (tree species, protection of protected trees,

protection of plants and animals, etc.), preserving the ecological functions and

linkages in the landscape,



c) influence on the system of protected areas Natura 2000,



(d) taking into account the conditions of) proposal for the conclusion of the fact-finding procedure, or

the opinions of the EIA,



(e)), the proposed conservation and safety zones, the scope of restrictions and conditions

protection under other legislation.



(B) the protection of the population of 7.



Meet the essential requirements in terms of performance of the tasks of the protection

of the population.



(B) 8 principles of organization of construction



and the construction site on) existing transport and technical

infrastructure,



(b) around the construction site and protection) requirements related to the remediation of,

demolition, cutting down trees,



(c) the maximum land for construction site) (temporary/permanent),



(d)) of earthwork, the requirements for the supply or the repository of Earth.



(C) the Situational drawings



C (1) block plan of the wider relations



a) scale 1:1 000 and 1:50 000,



(b) building on the transport) and the technical infrastructure,



c) existing and proposed safeguards and safety zones,



(d) the designation of the boundaries of the territory).



(C) 2 Total block plan



and) scale of 1:200 to 1:1 000, for large buildings 1:2000 or 1:

5 000,



(b) existing buildings, transport) and technical infrastructure,



c) boundaries,



(d)) the boundaries of the territory being tackled,



e) base and positioning, altimetry



(f)), designed the building,



g) determination of altitude 1. floor in buildings (+-0, 00) and

the height of the modified terrain; the maximum height of buildings,



h) communications and paved areas,



I) areas of vegetation.



C. 3 Coordinating block plan



and) scale of 1:200 to 1:1 000, for large buildings 1:2000 or 1:

5 000 for changes to the building, which is a listed building, in the building in the historic

reservation or in the zone at a scale of 1:200,



(b) existing buildings, transport) and technical infrastructure,



(c) the boundaries of the land parcel) number,



(d)) the boundaries of the territory being tackled,



e) existing altimetry and positioning,



f) represent each designed and of buildings and

the technical infrastructure,



g) determination of altitude 1. floor in buildings (+-0, 00) and

the height of the modified terrain; the maximum height of buildings,



(h)) to the proposed communication and paved area, connection to public transport

infrastructure,



I) solution of vegetation,



j) dimensioned spacing of buildings,



the plot of the new technical infrastructure), the connection of the constructions of the technical

infrastructure,



l) existing and proposed safeguards and safety zones, conservation

reservations, zone, etc.



m) maximum land (temporary/permanent),



n) geodetic data, specify the coordinates of the layout of the network



o) distances including the definition of fire hazardous areas,

access communications and boarding areas for fire equipment and resources

fire water.



(C). 4 the cadastral block plan



and according to the scale used) the cadastral maps,



(b)) the plot of building land, the desired location of the building,



(c)) the designation of the links and impacts on the surrounding area.



C. 5 Special block plan



Drawings, drawn up as appropriate situational awareness in an appropriate scale

showing the special requirements of objects, technological equipment,

technical networks, infrastructure or related engineering

measures.



(D) drawing documentation



D. 1 Distinctive floor plans



D. 2 Characteristic slices



(including the sections documenting the maintenance of existing buildings, in particular with

given the depth of the Foundation of the proposed buildings and structures of existing)



D. 3 views



(including views of documenting the integration of the building into the existing development

or landscape)



E Book part



This section contains evidence of compliance with the requirements under other

the legislation issued by the competent administrative authorities or the relevant

persons and documentation processed by persons authorised under other

legislation.



E. 1 Binding opinions, opinions, decisions, opinions of the concerned

authorities



E.2. The opinions of the owners of public transport and technical infrastructure



E.2.1 the opinions of the owners of public transport and technical infrastructure

the possibility and the way of connection, for example, drawing on the situation noted



E.2.2 the opinion of the owner or operator to the conditions for the establishment of a

construction, execution of works and activities in the trade and

security zones under other legislation



E. 3 Document under special legislation ^ 3) to demonstrate the conformity of the

characteristics of a product that performs the function of the building, with construction requirements

pursuant to section 156 of the Act for the building or the technical dossier of the manufacturer or

the importer or any other document from which it is possible to verify compliance with the

requirements for the construction



E. 4 Geodetic basis for project activities handled by other

legislation ^ 4)



E. 5 other opinions, observations, opinions, and the results of the negotiations conducted

during the processing of the dossier



Č. 2



The scope and content of the documentation for the decision about the change of land use



The documentation contains sections:



And the accompanying message



(B) a summary technical report



(C) the Situational drawings



(D) drawing documentation



E Book part



The documentation must always include parts A to E, with the scope and content of

the various parts will be adapted to the conditions in the territory and nature

the proposed changes.



And the accompanying message



A.1 identification data



A.1.1. Information on the territory



and a proposed change to land use),



(b)) instead of (cadastral area, parcel numbers land),



(c)) the subject of documentation.



A.1.2. Information on the applicant



and) name, surname and place of residence (individual) or



(b)) the full name, business name, registration number, if assigned, place

business (natural person-entrepreneur) or



(c) the business name or name), registration number, if assigned, registered address

(legal person).



And 1.3 information about the processor documentation



and) the full name, business name, registration number, if assigned, place

business (natural person-entrepreneur) or business name, or the name,

CORPORATE ID, if allocated, the address of the registered office (legal entity),



(b) main) name and surname of the designer, including the number, under which the

registered in the register of authorized people led by Czech architects

or the Czech Chamber of authorised engineers and technicians active in

construction, with the declared scope or specialization of its authorization,



(c)) first and last names of designers of different parts, including documentation

numbers under which are entered in a register kept by the authorized persons

The Czech Chamber of architects or the Czech Chamber of authorised engineers and

technicians in the construction, with the declared scope, where appropriate,

a specialization of their authorization.



And 2 a list of input documents



And 3 information on the territory



and the solution to the range of the territory;) built-up/undeveloped,



(b) the present use and built-up areas) of the territory,



(c) the characteristics of the territory) land and buildings on them,



(d) information on the protection of the territory) under other legislation (^ 1) Memorial

reservations, heritage zone, the specially protected territories, floodplain

etc.),



e) data on runoff ratios



f) data on compliance with the spatial planning documentation, with the objectives and tasks of the

town and country planning,



g) data on compliance with the General requirements on the use of the territory,



h) details of the meet the requirements of the bodies concerned,



I) exception list, and úlevových solutions



j) list of related and underlying investments



to) a list of land and buildings affected by a change in land use (according to the

the land registry).



And 4 Information on changing land use



and the total area of the territory concerned),



(b) data on runoff ratios),



(c) transport capacity requirements) and the technical infrastructure,



(d) the estimated period of implementation changes) land use.




(B) a summary technical report



B.1. Description and assessment of the territory



and the characteristics of the territory)



(b)) and the conclusions of the surveys carried out by the enumeration and analysis,



(c)) the current protection and safety zones,



(d)) position relative to the záplavovému territory poddolovanému territory, etc.



e) territorial technical conditions (in particular, the possibility of connection to the existing

transport and technical infrastructure),



(f)) accruals binding, contingent upon, developed, related investments.



(B). 2 description of the proposed changes to land use



basic characteristics of changes) land use,



(b) the justification for the changes) due to the current use of

territory,



(c) ensure the technical conditions) the principles of fire protection in the

territory from the perspective of the presumed mode of land use,



(d) the principle of the protection of the territory) from the negative effects of the external

environment (floods, floods, erosion and landslides, undermining,

seizmicita, radon, noise, emissions, waste, etc.).



(B) 3 connection to the technical infrastructure



B 4 transport solutions



Vegetation b 5 Solutions



(B) a description of the impact of a proposed 6 method of land use on the environment and

its protection



and) impact on the environment-the air, noise, water, waste and soil



b) influence on nature and landscape protection (tree species, protection of protected trees,

protection of plants and animals, etc.), preserving the ecological functions and

linkages in the landscape,



c) influence on the system of protected areas Natura 2000,



(d) taking into account the conditions of) proposal for the conclusion of the fact-finding procedure, or

the opinions of the EIA,



(e)), the proposed conservation and safety zones, the scope of restrictions and conditions

protection under other legislation.



(C) the Situational drawings



C (1) block plan of the wider relations



(e)), scale 1:1 000 and 1:50 000,



(f)) indicate a relationship of the territory to the urban structure of the territory and the

the location of the headquarters.



(C) 2 Total block plan by changing the question



a) scale 1:500 or 1:1, 000, for large plans 1:2 000, or 1

: 5 000,



(b) existing buildings and) technical infrastructure,



(c) the boundaries of the land parcel) number,



(d)) the boundaries of the territory being tackled,



(e)) the existing and proposed altimetry and positioning,



(f) a designation of a connection to transport) and the technical infrastructure,



g) existing and proposed safeguards and safety zones, conservation

reservations, zone, etc.



C. 3 Cadastral block plan



and according to the scale used) the cadastral maps,



(b) the designation of the boundaries of the territory), new uses



(c)) the designation of the links and impacts on the surrounding area.



(D) drawing documentation



Drawings showing the change in land use (drawings in a sufficiently

a clear scale, documenting the overall town planning and

architectural design of the proposed changes to land use; Basic vertical

cuts, documenting the proposed landscaping, the level of existing and

a modified terrain with an indication of the levels of ground water; the plot of the solution

drainage of the territory in the event of changes in runoff ratios, etc.).



E Book part



This section contains evidence of compliance with the requirements under other

the legislation issued by the competent administrative authorities or the relevant

persons and documentation processed by persons authorised under other

legislation.



E. 1 Binding opinions, opinions, decisions, opinions of the concerned

authorities



E.2. The opinions of the owners of public transport and technical infrastructure to

conditions of protection and the safety zones, marked

for example, drawing on the situation



E.3. Geodetic basis for project activities handled by other

legislation ^ 4)



E. 4 Other opinions, observations, opinions, and the results of the negotiations conducted

during the processing of the dossier



Č. 3



The scope and content of the documents for the issuance of the decision to change the influence of the use of

construction on the territory of the



The documentation contains sections:



And the accompanying message



(B) a summary technical report



(C) the Situational drawings



(D) drawing documentation



E Book part



The documentation must always include parts A to E, with the scope and content of

the various parts will be adapted to the conditions in the territory and nature

the proposed changes to the impact of the use of the construction works on the territory.



And the accompanying message



A.1 identification data



A.1.1 information about construction



and the name of the building),



(b)) instead of (address, numbers, cadastral, land

the numbers of the land),



(c)) the subject of documentation.



A.1.2. Information on the applicant



and) name, surname and place of residence (individual) or



(b)) the full name, business name, registration number, if assigned, place

business (natural person-entrepreneur) or



(c) the business name or name), registration number, if assigned, registered address

(legal person).



And 1.3 information about the processor documentation



and) the full name, business name, registration number, if assigned, place

business (natural person-entrepreneur) or business name, or the name,

CORPORATE ID, if allocated, the address of the registered office (legal entity),



(b) main) name and surname of the designer, including the number, under which the

registered in the register of authorized people led by Czech architects

or the Czech Chamber of authorised engineers and technicians active in

construction, with the declared scope or specialization of its authorization,



(c)) first and last names of designers of different parts, including documentation

numbers under which are entered in a register kept by the authorized persons

The Czech Chamber of architects or the Czech Chamber of authorised engineers and

technicians in the construction, with the declared scope, where appropriate,

a specialization of their authorization.



And 2 a list of input documents



And 3 information on the territory and on changing the impact of the use of the construction works on the territory of



and the solution to the range of the territory;) built-up/undeveloped,



(b) the present use and built-up areas) of the territory,



(c) information on the protection of the territory) under other legislation (^ 1) Memorial

reservations, heritage zone, the specially protected territories, floodplain

etc.),



d) details of the runoff ratios



e) data on the line with the spatial planning documentation, with the objectives and tasks of the

town and country planning,



(f) General) information on the requirements for the use of the territory,



g) data on the meet the requirements of the bodies concerned,



h) exception list, and úlevových solutions



I) list of related and underlying investments, the requirements for

other decisions or measures,



j) list of land and buildings affected by a change in the impact of the use of the building on

territory (according to the land registry).



And 4 information about construction and change in use of the building



the purpose of use of construction works) (existing and proposed)



(b) permanent or temporary building),



(c) data on the protection of the building) under other legislation (^ 1) cultural

Monument etc.),



(d) compliance with) the data on technical requirements for the construction and General

belonging to the barrier-free use of the technical requirements of buildings,



e) details of the authorities concerned, and compliance requirements

from other legislation ^ 2)



f) exception list, and úlevových solutions



(g)) the proposed amendment to the capacity of the buildings (floor area, number of function

units and their sizes, the number of users/workers, etc.),



(h) the balance of the construction () of the underlying needs and consumption of media and materials, the total

the produced quantities and types of waste and emissions, energy

performance of buildings, etc.),



I) basic assumptions.



And 5 the influence of changes of use the building's justification in the territory



(B) a summary technical report



(B) 1 description of the territory



and the characteristics of the territory)



(b)) and the conclusions of the surveys carried out by the enumeration and analysis,



(c)) the current protection and safety zones,



(d)) position relative to the záplavovému territory poddolovanému territory, etc.



e) territorial technical conditions (in particular, the possibility of connection to the existing

transport and technical infrastructure),



(f)) accruals binding, contingent upon, developed, related investments.



(B). 2 description of the proposed changes to the impact of the use of the construction works on the territory of the



existing and proposed) purpose of use of construction works,



(b)) the principle of protection against negative effects caused by territory, by changing the influence

the use of the building,



(c) assessment of technical conditions) of fire protection in the territory of the

the perspective of the changes in the use of the building.



(B) 3 new demands on the technical infrastructure



and the adjacent places) technical infrastructure, relocation,



b) connecting dimensions, power capacity and length.



(B) 4 new demands for transport infrastructure



and a description of the transport solutions)



(b)) to the existing territory, transport infrastructure,



(c)) to the right still.



B. 5 landscaping and vegetation in the context of the solution by modifying the impact of

the use of the construction works on the territory of the



Data on induced noise control measures-ramparts,

acoustic walls, etc.



(B) a description of the changes to 6 effect of use of the construction on the environment and its

the protection of the



and) impact on the environment-the air, noise, water, waste and soil



b) influence on nature and landscape protection (tree species, protection of protected trees,

protection of plants and animals, etc.), preserving the ecological functions and

linkages in the landscape,



c) influence on the system of protected areas Natura 2000,



(d) taking into account the conditions of) proposal for the conclusion of the fact-finding procedure, or

the opinions of the EIA,



(e)), the proposed conservation and safety zones, the scope of restrictions and conditions

protection under other legislation.




(B) a description of the changes to 7 the impact of use of the construction on the barrier-free use of the building



(C) the Situational drawings



C (1) block plan of the wider relations



a) scale 1:1 000 and 1:50 000,



(b) the designation of the connection of the constructions of the) transport and technical infrastructure,



c) existing and proposed safeguards and safety zones,



(d) the designation of the boundaries of the territory).



(C) 2 Total block plan by changing the question



a) scale 1:500 or 1:1, 000, for large buildings 1:2 000, or 1

: 5 000,



(b) the boundaries of the territory being tackled)



(c) the boundaries of the land parcel) number,



(d) the designation of the connection of the constructions of the) transport and technical infrastructure,



e) existing and proposed safeguards and safety zones, conservation

reservations, zone, etc.



C. 3 Cadastral block plan



and according to the scale used) the cadastral maps,



(b) the designation of the new building) the purpose of use,



(c)) the designation of the links and impacts on the surrounding area.



(D) drawing documentation



Drawings showing the change in the use of the building (floor plans with an indication of

the existing and the proposed manner of use of the individual rooms and the

areas, sections, perspectives).



E Book part



This section contains evidence of compliance with the requirements under other

the legislation issued by the competent administrative authorities or the relevant

persons.



E. 1 Binding opinions, opinions, decisions, opinions of the concerned

authorities



E.2. The opinions of the owners of public transport and technical infrastructure to

conditions of protection and the safety zones, marked

for example, drawing on the situation



E. 3 other opinions, observations, opinions, and the results of the negotiations conducted

during the processing of the dossier



Č. 4



The scope and content of a joint common spatial documentation

decision and building permit



Common documentation contains sections:



And the accompanying message



(B) a summary technical report



(C) the Situational drawings



(D) Documentation of the objects and technical and technological equipment



E Book part



Common documentation must always include parts A to E, with the range

and the content of the various parts will be adapted to the nature and size of the building,

conditions in the territory, construction and technical design, purpose, usage, impact

on the environment and the duration of the construction.



And the accompanying message



A.1 identification data



A.1.1 information about construction



and the name of the building),



(b)) instead of (address, numbers, cadastral, land

the numbers of the land),



(c)) the subject of documentation.



A.1.2. Information on the applicant/client



and) name, surname and place of residence (individual) or



(b)) the full name, business name, registration number, if assigned, place

business (natural person-entrepreneur) or



(c) the business name or name), registration number, if assigned, registered address

(legal person).



And 1.3 information about the processors of the common documentation



and) the full name, business name, registration number, if assigned, place

business (natural person-entrepreneur) or business name, or the name,

CORPORATE ID, if allocated, the address of the registered office (legal entity),



(b) main) name and surname of the designer, including the number, under which the

registered in the register of authorized people led by Czech architects

or the Czech Chamber of authorised engineers and technicians active in

construction, with the declared scope or specialization of its authorization,



(c)) first and last names of designers of different parts of the common documentation

including the number under which you are enrolled in the register of authorized persons

led by Czech architects or the Czech Chamber of authorized

engineers and technicians active in construction, with the declared scope, where appropriate,

a specialization of their authorization.



And 2 a list of input documents



And 3 information on the territory



and the solution to the range of the territory;) built-up/undeveloped territory,



(b) the present use and built-up areas) of the territory,



(c) information on the protection of the territory) under other legislation (^ 1) Memorial

reservations, heritage zone, the specially protected territories, floodplain

etc.),



d) details of the runoff ratios



e) data on the line with the spatial planning documentation, with the objectives and tasks of the

town and country planning,



(f) General) information on the requirements for the use of the territory,



g) data on the meet the requirements of the bodies concerned,



h) exception list, and úlevových solutions



I) list of related and underlying investments



j) list of land and buildings affected by the location and execution of a project

(according to the land registry).



And 4 information about construction



and new construction) or change the finished structure,



(b) the purpose of use of construction works,)



c) permanent or temporary building,



(d) protection of data on buildings) under other legislation (^ 1) cultural

Monument etc.),



(e) compliance with) the data on technical requirements for the construction and General

belonging to the barrier-free use of the technical requirements of buildings,



f) data on compliance with the requirements of the concerned bodies and the requirements

from other legislation ^ 2)



g) exception list, and úlevových solutions



(h) the proposed capacity building) (built-up area, built-up area,

floor area, number of functional units and their sizes, the number of

users/workers, etc.),



I) basic balance construction (needs and consumption of media and materials,

management of rainwater, the total produced quantity and types of

waste and emissions, energy performance of buildings, etc.),



j) basic assumptions of the construction (the time data on the implementation of the construction work,

breakdown on stage),



indicative costs of the building).



And 5 the breakdown of the construction on the objects and the technical and technological equipment



(B) a summary technical report



(B) a description of the territory of construction 1



and characteristics of building land,)



(b)) and the conclusions of the surveys carried out by the enumeration and analysis (geological survey,

hydrogeological survey, architectural and historical survey, etc.),



(c)) the current protection and safety zones,



(d)) position relative to the záplavovému territory poddolovanému territory, etc.



(e) the construction of the surrounding) the effects of construction and land protection area, the influence of the construction

the flow conditions in the territory,



f) requirements for sanitation, demolition, cutting down trees,



g) requirements for the maximum land agricultural land resources or

the land intended for the performance of the functions of the forest (temporary/permanent),



h) territorial technical conditions (in particular, the possibility of connection to the existing

transport and technical infrastructure),



I) accruals binding construction, contingent upon, developed, related

investment.



(B) a general description of the construction of the 2.



(B) the purpose of use of construction works 2.1, the basic capacity of the functional units



(B). 2.2 the overall urban planning and architectural design



and urban-territorial control), composition space,



(b)) architectural design-composition shape, material and solutions

the color of the solution.



(B) 2.3 Overall operational solutions, production technology



(B) the use of the buildings accessible to the disabled.



(B) 2.5 safety during the use of the building



B. basic characteristics of objects 2.6



and building solutions)



(b) structural and material solutions),



c) mechanical resistance and stability.



B. basic characteristics of technical and 2.7 of the technological equipment



and the technical solution)



b) enumeration of technical and technological equipment.



B. 2.8 fire safety solutions



and the Division of buildings and objects) into the fire sections,



(b)) the calculation of the fire risks and determine the degree of fire safety,



(c) the assessment of the proposed structures) and construction products

including the requirements to increase the fire resistance of building structures,



(d) evacuation of persons including) an assessment evaluation of the escape routes,



(e) the assessment distance and odstupových) definition of fire-hazardous

space,



(f) ensure the necessary quantity of fire) of water or other extinguishing media,

including the deployment of internal and external consumption points,



(g)) the appreciation of the design possibilities (firefighting access

communications, emergency trip),



h) an assessment of technical and technological equipment of buildings (distribution

pipes, air handling units),



I) assessment of the security requirements of the building fire safety

devices,



(j)), the scope and the deployment of warning and safety signs and

tables.



B. 2.9 Energy Management Policy



and heat-technical evaluation criteria),



(b) assessment of the use of alternative sources of) energy.



B. 2.10 health requirements for building work and

municipal environment



Resolution policy parameters of the building (ventilation, heating, lighting,

water supply, waste, etc.) and resolution policy construction

around (vibration, noise, dust, etc.).



(B) Protection of construction before 2.11 negative effects of the external environment



and protection against the penetration of radon) from the ground,



b) protection against stray currents,



(c) technical protection seizmicitou),



(d)), noise protection



e) flood control,



(f)) other effects (effect of undermining, the occurrence of methane, etc.).



(B) 3 connection to the technical infrastructure



and the technical infrastructure of the adjacent places),



b) connecting dimensions, power capacity and length.



B 4 transport solutions



and a description of the transport solutions)



(b)) to the existing territory, transport infrastructure,



(c)) the right in a calm,



(d)) walking and cycling trails.




B. related 5 solve vegetation and landscaping



a) landscaping,



(b)) used the vegetation elements



c) biotechnical measures.



(B) 6 Description of the effects of construction on the environment and its protection



and) impact on the environment-the air, noise, water, waste and soil



b) influence on nature and landscape protection (tree species, protection of protected trees,

protection of plants and animals, etc.), preserving the ecological functions and

linkages in the landscape,



c) influence on the system of protected areas Natura 2000,



(d) taking into account the conditions of) proposal for the conclusion of the fact-finding procedure, or

the opinions of the EIA,



(e)), the proposed conservation and safety zones, the scope of restrictions and conditions

protection under other legislation.



(B) the protection of the population of 7.



Meet the essential requirements in terms of performance of the tasks of the protection

of the population.



(B) 8 principles of organization of construction



and critical needs and consumption) of media and materials, their security,



(b) drainage of construction site)



c) connection of the construction site on the existing transport and technical

infrastructure,



(d) the impact on the execution of the project), the surrounding buildings and land,



(e) around the construction site and protection) requirements related to the remediation of,

demolition, cutting down trees,



f) maximum land for construction site (temporary/permanent),



g) maximum produced quantities and types of waste and emissions during construction,

their disposal,



h) earthwork, requirements for the supply or the repository of Earth,



I) environmental protection during the construction,



j) principles of safety and health at work on the construction site,

assess the need for the Coordinator for safety and health at work

under other legislation ^ 5),



to edit for barrier-free use of) the construction of the buildings concerned,



l) policy for traffic engineering measures



m) the determination of the special conditions for the execution of the project (implementation

construction operation, measures against the effects of the external environment when

construction, etc.),



n) construction, partial dates.



(C) the Situational drawings



C (1) block plan of the wider relations



a) scale 1:1 000 and 1:50 000,



(b) building on the transport) and the technical infrastructure,



c) existing and proposed safeguards and safety zones,



(d) the designation of the boundaries of the territory).



(C) 2 Total block plan



and) scale of 1:200 to 1:1 000, for large buildings 1:2000 or 1:

5 000,



(b) existing buildings, transport) and technical infrastructure,



c) boundaries,



(d)) the boundaries of the territory being tackled,



e) base and positioning, altimetry



(f)), designed the building,



g) determination of altitude 1. floor in buildings (+-0, 00) and

the height of the modified terrain; the maximum height of buildings,



h) communications and paved areas,



I) areas of vegetation.



C. 3 Coordinating block plan



and) scale of 1:200 to 1:1 000, for large buildings 1:2000 or 1:

5 000 for changes to the building, which is a listed building, in the building in the historic

reservation or in the zone at a scale of 1:200,



(b) existing buildings, transport) and technical infrastructure,



(c) the boundaries of the land parcel) number,



(d)) the boundaries of the territory being tackled,



e) existing altimetry and positioning,



f) represent each designed and of buildings and

the technical infrastructure,



g) determination of altitude 1. floor in buildings (+-0, 00) and

the height of the modified terrain; the maximum height of buildings,



(h)) to the proposed communication and paved area, connection to public transport

infrastructure,



I) solution of vegetation,



j) dimensioned spacing of buildings,



the plot of the new technical infrastructure), the connection of the constructions of the technical

infrastructure,



l) existing and proposed safeguards and safety zones, conservation

reservations, zone, etc.



m) maximum land (temporary/permanent),



n) designation of geotechnical probes



about the data, determine the geodetic) coordinates of the layout of the network



p) distances including the definition of fire hazardous areas,

access communications and boarding areas for fire equipment and resources

fire water.



(C). 4 the cadastral block plan



and according to the scale used) the cadastral maps,



(b) the plot of building land) and the proposed building,



(c)) the designation of the links and impacts on the surrounding area.



C. 5 Special block plan



Drawings, drawn up as appropriate situational awareness in an appropriate scale

showing the special requirements of objects, technological equipment,

technical networks, infrastructure or related engineering

measures:



and transportation, including editing) the situation for persons with reduced mobility

and orientation,



(b)) the situation of the vegetation.



(D) Documentation of the objects and technical and technological equipment



Documentation structures, engineering, technical or

technological equipment is processed through the objects and files

technical or technological devices in the following breakdown in

a reasonable range:



(D) 1 of the building or the engineering Documentation object



D. 1.1 architectural-building solutions



and) technical report (architectural, fine art, material, the disposition

and operational solutions, barrier-free use of the work; the design and construction

the technical solution and the technical characteristics of the building; building physics-

thermal technology, lighting, insolation, acoustics/noise, vibration-description

the solution, a statement of the standards).



(b) the Drafting section (s) of the construction trench, floor plans of the foundations, floor plans

individual floors and roofs indicating the dimensions of the main dividing

structures, openings in the peripheral structures and the overall dimensions of the mass

construction; with a description of the purpose of use of the rooms, equipped with automatic surface acreage including the

graphical resolution characteristic material solution basic

structures; characteristic slices are the basic design solutions

including the sections documenting the maintenance of existing buildings, in particular with

given the depth of the Foundation of the proposed buildings and structures existing, with the

number of dimensions linked to the existing terrain including graphic

resolution characteristic material solution basic

structures; views showing the basic height solutions

use of color and characterization of materials surfaces; postcards documenting

the integration of the building into existing buildings or landscapes).



D. 1.2 Design Construction



(a) technical report for a description of the proposed design of the building,

the result of the survey of the current status of the carrying system construction in the design

its amendment; the proposed materials and the main structural elements; the values of the

utility, climate and other loads anticipated in the design of load-bearing

construction; proposal for a special, unusual structures or

technological processes; ensure the construction trench; technological

the conditions for the progress of work that could affect the stability of your own

construction, or neighbouring buildings; guidelines for the implementation of the demolition and

podchycovacích work and the consolidation of structures or penetrations; the requirements of the

on the control of zakrývaných structures; list of supporting documents, standards,

technical regulations, technical literature, computing programs, etc.;

specific requirements for the scope and content of the documentation for the implementation of the

construction, or documentation provided by the contractor).



(b) the Drafting section (s) of the foundations, if these structures are not

displayed in the construction drawings of the foundations; the shape of the monolithic

concrete structures; drawings of parts of prefabricated concrete

construction; layout drawings of metal and wooden structures, etc.).



(c) assessment (validation) static basic conceptual solution support

construction; assessment of the stability of the structure; determining the dimensions of the main

elements of the structure, including its foundation; dynamic calculation, if

on the construction works dynamic loading).



(d)) the control plan (determination of the structure reliability checks

reliability design of the building in terms of their future use).



D. 1.3 fire safety solutions



(a) technical report used documents listing, description, and location of the building

and their objects, Division of works and objects into fire departments,

assessment of the size of the fire departments, fire risk, calculation

determination of the degree of fire safety assessment of proposed construction

structures in terms of fire resistance, including requests to increase the

their fire resistance evaluation of construction products in terms of

classes of reaction to fire, dripping in terms of fire, speed of propagation

the flame on the surface, the appreciation of the evacuation and the determination of the type and number of

escape routes, their capacity, design and facilities, the determination of the

odstupových distance, where appropriate, safety distance and their

appreciation in relation to the surrounding buildings, the definition of fire-hazardous

the space and its evaluation in relation to the surrounding buildings and the neighboring

land, evaluation of the implementation of the intervention, including the definition of the fire

escape routes, the appreciation of the access roads, boarding areas

for fire technology, security building fire water and other

hasebními resources, including the deployment of external and internal consumption

determining the number of places, the species and how the deployment of fire extinguishers,

or other material means of fire protection or fire


techniques, evaluation of technical or technological equipment

construction, assessment of the security requirements of the building fire

safety devices including the conditions and the way they design

location, installing them into the buildings and the determination of requirements for

building construction, the scope and the deployment of warning and

safety signs and tables).



(b) the Drafting section () block plan of fire protection in a scale of 1:500

or 1:1, 000, the floor plans of individual floors with the designation and description

fire departments, in accordance with the requirements of other legislation that

regulates the technical conditions for fire protection).



D. 1.4 Environmental Engineering Technology



The documentation of the individual professions shall designate in technical equipment and systems

details illustrating the compliance with the code of values and legal

regulations. Define the basic material, technical and technological,

disposition and operating characteristics of equipment and systems. Presents the basic

quality and safety requirements for equipment and systems.



The documentation is processed separately for each part (the profession)

According to the specific building characteristics such as:



-sanitary installations,



-air-conditioning and heating, cooling,



-measuring and regulation,



-heavy-current electrical engineering,



-electronic communications and more.



The content and extent of the documentation is processed in accordance with common principles. Will

adapted to the nature and the technical complexity of the buildings and equipment.

The organizational arrangement of the documentation of the individual parts (professions)

expedient to organize under the procedure construction.



In particular, the documentation includes:



(a) technical report listing the standards-standard values and

legislation; the default background and building program; requirements for the profession-

the award, the climate of the site-the calculated parameters

outdoor air-winter/summer; the required climatic conditions-

Winter/summer, minimum health benefits of fresh air, the share of

air circulation; information on the determination of emissions of pollutants and their

the concentration; operating conditions-the number of people, heat loss, heat

loads, etc., operating mode-continuous, intermittent, continuous; Description

the proposed solution and the dimensioning, the description of the functions and arrangement of the installation and

System; the balance of energy, the media and the necessary materials; privacy policy

health, safety in the operation of the equipment; the protection of the

environment, protection against noise and vibration, fire-fighting measures; the requirements of the

on the process of implementation of the work and the conditions of the designer for the realization of works,

putting into service and operation during the lifetime of the building).



(b) the drafting section of the location and arrangement of critical equipment,

machines, basic mechanical components, power sources, etc.;

the basic definition of the area to their location in the building; Basic

the overview diagrams wiring and equipment, basic technology

schemes; floor plans of the Basic pipeline and cable distribution systems in

1-line display, any cuts coordination nodes; the location of the

fixtures; requirements for the construction and solution

Special spaces of the art environment of buildings).



(c)) the list of machinery and equipment and technical specifications (a list of

the critical machinery and equipment, the essential mechanical components,

energy sources, etc.; description of the basic technical and performance

parameters and related requests).



D. 2 Documentation technical and technological equipment



The building can be, depending on the nature, broken down into operating units, which are further

divided into operational files and partial operational or functional files files.

Technological equipment are the manufacturing and nonmanufacturing.



Non-productive technological equipment are e.g.:



-power cord and wiring all the technical infrastructure

(electric energy, electronic communications, gas,

heating plants, media distribution systems, etc.) including related equipment,



-shifting management of the technical infrastructure,



-device, vertical and horizontal transport of persons and goods, equipment

for the transport of persons with reduced mobility, evacuation

or fire equipment,



-dedicated technical equipment,



-dedicated fire-safety devices and more.



The documentation is processed by the operational or functional

files and devices.



The following content and extent of the documentation is listed as maximum and

the specific case will be adapted to the nature and the technical complexity of

the construction. Characteristics:



(a) technical report description of the program for non-production structures;

description of the purpose, the list of supporting documents; description of the technological process

production, the need for materials, raw materials and the quantity of the products, the basic composition

technological equipment-purpose, description and basic parameters of, description

warehouse management and material handling requirements for the manufacture,

internal and external transport, the impact of technological equipment for construction

the solution, the data about the need for energy, fuels, water and other media, including

requirements and places the connection).



(b)) the drafting section (contains only the position and arrangement of the decisive

equipment, machinery, basic mechanical components, energy sources

, etc.; the basic definition of the area to their location in the building,

basic overview diagrams wiring and fittings, floor plans of the basic

pipe and cable distribution systems in 1-line display, any cuts

coordination nodes, building requirements and solutions special

areas of technological equipment, whose layout is

usually a part of construction drawings; the basic technology

documenting the purpose of the schemes and the level of the proposed manufacturing process,

the layout and location of the main machinery and equipment and the way they

installation-floor plans, sections, usually at a scale of 1:100).



(c)) the list of machinery and equipment and technical specifications (a list of

the critical machinery and equipment, the essential mechanical components,

energy sources, etc.; description of the basic technical and performance

parameters and related requests).



E Book part



This section contains evidence of compliance with the requirements under other

the legislation issued by the competent administrative authorities or the relevant

persons and documentation processed by persons authorised under other

legislation.



E. 1 Binding opinions, opinions, decisions, opinions of the concerned

authorities



E.2. The opinions of the owners of public transport and technical infrastructure



E.2.1 the opinions of the owners of public transport and technical infrastructure

the possibility and the way of connection, for example, drawing on the situation noted



E.2.2 the opinion of the owner or operator to the conditions for the establishment of a

construction, execution of works and activities in the trade and

security zones under other legislation



E.3. Geodetic basis for project activities handled by other

legislation ^ 4)



E. 4 project processed Mining Designer ^ 6)



E. 5 energy performance of the building according to the law on the management

energy ^ 7)



E. 6 other opinions, observations, opinions, and the results of the negotiations conducted

during the processing of the dossier



Č. 5



The scope and content of the project documentation for construction of the Declaration referred to in §

paragraph 104. 1 (b). a) to (e)) of the building Act or building

enable



Project documentation contains sections:



And the accompanying message



(B) a summary technical report



(C) the Situational drawings



(D) Documentation of the objects and technical and technological equipment



E Book part



Project documentation must always include parts A to E, with the

the scope and content of the various parts will be adapted to the nature and importance of

the building, its location, constructional and technical implementation, use,

impact on the environment and the duration of the construction.



And the accompanying message



A.1 identification data



A.1.1 information about construction



and the name of the building),



(b)) instead of (address, numbers, cadastral, land

the numbers of the land),



(c)) the subject of the project documentation.



And data on the client;



and) name, surname and place of residence (individual) or



(b)) the full name, business name, registration number, if assigned, place

business (natural person-entrepreneur) or



(c) the business name or name), registration number, if assigned, registered address

(legal person).



And 1.3 information about the processor project documentation



and) the full name, business name, registration number, if assigned, place

business (natural person-entrepreneur) or business name, or the name,

CORPORATE ID, if allocated, the address of the registered office (legal entity),



(b) main) name and surname of the designer, including the number, under which the

registered in the register of authorized people led by Czech architects

or the Czech Chamber of authorised engineers and technicians active in

construction, with the declared scope or specialization of its authorization,



(c)) first and last names of designers of different parts of project

documentation including the number under which you are enrolled on the register

authorized people led by Czech architects or the Czech

Chamber of Chartered Engineers and technicians active in construction, with


indicate the scope, where appropriate, specialising their authorization.



And 2 a list of input documents



And 3 information on the territory



and the solution to the range of the territory)



(b) information on the protection of the territory) under other legislation (^ 1) Memorial

reservations, heritage zone, the specially protected territories, floodplain

etc.),



(c) data on runoff ratios),



d) details of the conformity with the spatial planning documentation, if it has not been released

planning decision or territorial measures, where applicable, the absence of a territorial

consent,



e) details of the conformity with the land use decision or public-law agreement

land use planning decision or approval of the replacement, or with

the regulatory plan, to the extent in which replaces territorial decision, and in

case of a change in the use of the prerequisites for the adjustment of the construction details of the

its consistency with spatial planning documentation,



(f) General) information on the requirements for the use of the territory,



g) data on the meet the requirements of the bodies concerned,



h) exception list, and úlevových solutions



I) list of related and underlying investments



j) list of land and buildings concerned by any construction (according to the cadastre

real estate).



And 4 information about construction



and new construction) or change the finished structure,



(b) the purpose of use of construction works,)



c) permanent or temporary building,



(d) protection of data on buildings) under other legislation (^ 1) cultural

Monument etc.),



(e) compliance with) the data on technical requirements for the construction and General

belonging to the barrier-free use of the technical requirements of buildings,



f) data on compliance with the requirements of the concerned bodies and the requirements

from other legislation ^ 2)



g) exception list, and úlevových solutions



(h) the proposed capacity building) (built-up area, built-up area,

floor area, number of functional units and their sizes, the number of

users/workers, etc.),



I) basic balance construction (needs and consumption of media and materials,

management of rainwater, the total produced quantity and types of

waste and emissions, energy performance of buildings, etc.),



j) basic assumptions of the construction (the time data on the implementation of the construction work,

breakdown on stage),



indicative costs of the building).



And 5 the breakdown of the construction on the objects and the technical and technological equipment



(B) a summary technical report



(B) a description of the territory of construction 1



and characteristics of building land,)



(b)) and the conclusions of the surveys carried out by the enumeration and analysis (geological survey,

hydrogeological survey, architectural and historical survey, etc.),



(c)) the current protection and safety zones,



(d)) position relative to the záplavovému territory poddolovanému territory, etc.



(e) the construction of the surrounding) the effects of construction and land protection area, the influence of the construction

the flow conditions in the territory,



f) requirements for sanitation, demolition, cutting down trees,



g) requirements for the maximum land agricultural land resources or

the land intended for the performance of the functions of the forest (temporary/permanent),



h) territorial technical conditions (in particular, the possibility of connection to the existing

transport and technical infrastructure),



I) accruals binding construction, contingent upon, developed, related

investment.



(B) a general description of the construction of the 2.



(B) the purpose of use of construction works 2.1, the basic capacity of the functional units



(B). 2.2 the overall urban planning and architectural design



and urban-territorial control), composition space,



(b)) architectural design-composition shape, material and solutions

the color of the solution.



(B) 2.3 Overall operational solutions, production technology



(B) the use of the buildings accessible to the disabled.



(B) 2.5 safety during the use of the building



B. basic characteristics of objects 2.6



and building solutions)



(b) structural and material solutions),



c) mechanical resistance and stability.



B. basic characteristics of technical and 2.7 of the technological equipment



and the technical solution)



b) enumeration of technical and technological equipment.



B. 2.8 fire safety solutions



and the Division of buildings and objects) into the fire sections,



(b)) the calculation of the fire risks and determine the degree of fire safety,



(c) the assessment of the proposed structures) and construction products

including the requirements to increase the fire resistance of building structures,



(d) evacuation of persons including) an assessment evaluation of the escape routes,



(e) the assessment distance and odstupových) definition of fire-hazardous

space,



(f) ensure the necessary quantity of fire) of water or other extinguishing media,

including the deployment of internal and external consumption points,



(g)) the appreciation of the design possibilities (firefighting access

communications, emergency trip),



h) an assessment of technical and technological equipment of buildings (distribution

pipes, air handling units),



I) assessment of the security requirements of the building fire safety

devices,



(j)), the scope and the deployment of warning and safety signs and

tables.



B. 2.9 Energy Management Policy



and heat-technical evaluation criteria),



(b)) the energy performance of buildings,



(c) assessment of the use of alternative sources of) energy.



B. 2.10 health requirements for building work and

municipal environment



Resolution policy parameters of the building (ventilation, heating, lighting,

water supply, waste, etc.) and resolution policy construction

around (vibration, noise, dust, etc.).



(B) Protection of construction before 2.11 negative effects of the external environment



and protection against the penetration of radon) from the ground,



b) protection against stray currents,



(c) technical protection seizmicitou),



(d)), noise protection



e) flood protection measures.



(B) 3 connection to the technical infrastructure



and the technical infrastructure of the adjacent places),



b) connecting dimensions, power capacity and length.



B 4 transport solutions



and a description of the transport solutions)



(b)) to the existing territory, transport infrastructure,



(c)) the right in a calm,



(d)) walking and cycling trails.



B. related 5 solve vegetation and landscaping



a) landscaping,



(b)) used the vegetation elements



c) biotechnical measures.



(B) 6 Description of the effects of construction on the environment and its protection



and) affect construction on the environment-the air, noise, water, waste and

soil,



(b) the impact of the construction on nature) and landscape (protection of species, protection of protected

trees, protection of flora and fauna, etc.), the preservation of ecological

functions and relations in the countryside,



(c) the impact of the construction on the system) protected areas Natura 2000,



(d) taking into account the conditions of) proposal for the conclusion of the fact-finding procedure, or

the opinions of the EIA,



(e)), the proposed conservation and safety zones, the scope of restrictions and conditions

protection under other legislation.



(B) the protection of the population of 7.



Meet the essential requirements in terms of performance of the tasks of the protection

of the population.



(B) 8 principles of organization of construction



and critical needs and consumption) of media and materials, their security,



(b) drainage of construction site)



c) connection of the construction site on the existing transport and technical

infrastructure,



(d) the impact on the execution of the project), the surrounding buildings and land,



(e) around the construction site and protection) requirements related to the remediation of,

demolition, cutting down trees,



f) maximum land for construction site (temporary/permanent),



g) maximum produced quantities and types of waste and emissions during construction,

their disposal,



h) earthwork, requirements for the supply or the repository of Earth,



I) environmental protection during the construction,



j) principles of safety and health at work on the construction site,

assess the need for the Coordinator for safety and health at work

under other legislation ^ 5),



to edit for barrier-free use of) the construction of the buildings concerned,



l) policy for the engineering measures,



m) the determination of the special conditions for the execution of the project (implementation

construction operation, measures against the effects of the external environment when

construction, etc.),



n) construction, partial dates.



(C) the Situational drawings



C (1) block plan of the wider relations



a) scale 1:1 000 and 1:50 000,



(b) building on the transport) and the technical infrastructure,



c) existing and proposed safeguards and safety zones,



(d) the designation of the boundaries of the territory).



(C) 2 Total block plan of the building



and) scale of 1:200 to 1:1 000, for large buildings 1:2000 or 1:

5 000,



(b) existing buildings, transport) and technical infrastructure,



c) boundaries,



(d)) the boundaries of the territory being tackled,



e) base and positioning, altimetry



(f)), designed the building,



g) determination of altitude 1. floor in buildings (+-0, 00) and

the height of the modified terrain; the maximum height of buildings,



h) communications and paved areas,



I) areas of vegetation.



(C) Coordination of the situation 3.



a) scale 1:200 or 1:1, 000, for large buildings 1:2 000, or 1

: 5 000, for changes to the building, which is a listed building, in the building

the conservation reserve or historic in scale of 1:200,



(b) existing buildings, transport) and technical infrastructure,



(c) the boundaries of the land parcel) number,



(d)) the boundaries of the territory being tackled,



e) existing altimetry and positioning,



f) represent each designed and of buildings and

the technical infrastructure,



g) determination of altitude 1. floor in buildings (+-0, 00) and


the height of the modified terrain; the maximum height of buildings,



(h)) to the proposed communication and paved area, connection to public transport

infrastructure,



I) solution of vegetation,



j) dimensioned spacing of buildings,



the plot of the new technical infrastructure), the connection of the constructions of the technical

infrastructure,



l) existing and proposed safeguards and safety zones, conservation

reservations, zone, etc.



m) maximum land (temporary/permanent land),



n) designation of geotechnical probes



about the data, determine the geodetic) coordinates of the layout of the network



p) distances including the definition of fire hazardous areas,

access communications and boarding areas for fire equipment and resources

fire water.



(C). 4 the cadastral block plan



and according to the scale used) the cadastral maps,



(b) the proposed building, plot)



(c)) the designation of the links and impacts on the surrounding area.



C. 5 a special situational drawings



Drawings, drawn up as appropriate situational awareness in an appropriate scale

showing the special requirements of objects, technological equipment,

technical networks, infrastructure or related engineering

measures:



and transportation, including editing) the situation for persons with reduced mobility

and orientation,



(b)) the situation of the vegetation.



(D) Documentation of the objects and technical and technological equipment



Documentation structures, engineering, technical or

technological equipment is processed through the objects and files

technical or technological devices in the following breakdown in

a reasonable range:



(D) 1 of the building or the engineering Documentation object



D. 1.1 architectural-building solutions



and) technical report (architectural, fine art, material, the disposition

and operational solutions, barrier-free use of the work; the design and construction

the technical solution and the technical characteristics of the building; building physics-

thermal technology, lighting, insolation, acoustics/noise, vibration-description

the solution, a statement of the standards).



(b) the Drafting section (s) of the construction trench; floor plans the foundations, floor plans

individual floors and roofs indicating the dimensions of the main dividing

structures, openings in the peripheral structures and the overall dimensions of the mass

construction; with a description of the purpose of use of the rooms, equipped with automatic surface acreage including the

graphical resolution characteristic material solution basic

structures; characteristic slices are the basic design solutions

including the sections documenting the maintenance of existing buildings, in particular with

given the depth of the Foundation of the proposed buildings and structures existing, with the

number of dimensions linked to the existing terrain including graphic

resolution characteristic material solution basic

structures; views showing the basic height solutions

use of color and characterization of materials surfaces; postcards documenting

the integration of the building into existing buildings or landscapes).



D. 1.2 Design Construction



(a) technical report for a description of the proposed design of the building,

the result of the survey of the current status of the carrying system construction in the design

its amendment; the proposed materials and the main structural elements; the values of the

utility, climate and other loads anticipated in the design of load-bearing

construction; proposal for a special, unusual structures or

technological processes; ensure the construction trench; technological

the conditions for the progress of work that could affect the stability of your own

construction, or neighbouring buildings; guidelines for the implementation of the demolition and

podchycovacích work and the consolidation of structures or penetrations; the requirements of the

on the control of zakrývaných structures; list of supporting documents, standards,

technical regulations, technical literature, computing programs, etc.;

specific requirements for the scope and content of the documentation for the implementation of the

construction, or documentation provided by the contractor).



(b) the Drafting section (s) of the foundations, if these structures are not

displayed in the construction drawings of the foundations; the shape of the monolithic

concrete structures; drawings of parts of prefabricated concrete

construction; layout drawings of metal and wooden structures, etc.).



(c) assessment (validation) static basic conceptual solution support

construction; assessment of the stability of the structure; determining the dimensions of the main

elements of the structure, including its foundation; dynamic calculation, if

on the construction works dynamic loading).



(d)) the control plan (determination of the structure reliability checks

reliability design of the building in terms of their future use).



D. 1.3 fire safety solutions



(a) technical report used documents listing, description, and location of the building

and their objects, Division of works and objects into fire departments,

assessment of the size of the fire departments, fire risk, calculation

determination of the degree of fire safety assessment of proposed construction

structures in terms of fire resistance, including requests to increase the

their fire resistance evaluation of construction products in terms of

classes of reaction to fire, dripping in terms of fire, speed of propagation

the flame on the surface, the appreciation of the evacuation and the determination of the type and number of

escape routes, their capacity, design and facilities, the determination of the

odstupových distances, respectively. safety distances and their

appreciation in relation to the surrounding buildings, the definition of fire-hazardous

the space and its evaluation in relation to the surrounding buildings and the neighboring

land, evaluation of the implementation of the intervention, including the definition of the fire

escape routes, the appreciation of the access roads, boarding areas

for fire technology, security building fire water and other

hasebními resources, including the deployment of external and internal consumption

determining the number of places, the species and how the deployment of fire extinguishers,

or other material means of fire protection or fire

techniques, evaluation of technical or technological equipment

construction, assessment of the security requirements of the building fire

safety devices including the conditions and the way they design

location, installing them into the buildings and the determination of requirements for

building construction, the scope and the deployment of warning and

safety signs and tables).



(b) the Drafting section () block plan of fire protection in a scale of 1:500

or 1:1, 000, the floor plans of individual floors with the designation and description

fire departments, in accordance with the requirements of other legislation that

regulates the technical conditions for fire protection).



D. 1.4 Environmental Engineering Technology



The documentation of the individual professions shall designate in technical equipment and systems

details illustrating the compliance with the code of values and legal

regulations. Define the basic material, technical and technological,

disposition and operating characteristics of equipment and systems. Presents the basic

quality and safety requirements for equipment and systems.



The documentation is processed separately for each part (the profession)

According to the specific building characteristics such as:



-sanitary installations,



-air-conditioning and heating, cooling,



-measuring and regulation,



-heavy-current electrical engineering,



-electronic communications and more.



The content and extent of the documentation is processed in accordance with common principles. Will

adapted to the nature and the technical complexity of the buildings and equipment.

The organizational arrangement of the documentation of the individual parts (professions)

expedient to organize under the procedure construction.



In particular, the documentation includes:



(a) technical report listing the standards-standard values and

legislation; the default background and building program; requirements for the profession-

the award, the climate of the site-the calculated parameters

outdoor air-winter/summer; the required climatic conditions-

Winter/summer, minimum health benefits of fresh air, the share of

air circulation; information on the determination of emissions of pollutants and their

the concentration; operating conditions-the number of people, heat loss, heat

loads, etc., operating mode-continuous, intermittent, continuous; Description

the proposed solution and the dimensioning, the description of the functions and arrangement of the installation and

System; the balance of energy, the media and the necessary materials; privacy policy

health, safety in the operation of the equipment; the protection of the

environment, protection against noise and vibration, fire-fighting measures; the requirements of the

on the process of implementation of the work and the conditions of the designer for the realization of works,

putting into service and operation during the lifetime of the building).



(b) the drafting section of the location and arrangement of critical equipment,

machines, basic mechanical components, power sources, etc.;

the basic definition of the area to their location in the building; Basic

the overview diagrams wiring and equipment, basic technology

schemes; floor plans of the Basic pipeline and cable distribution systems in

1-line display, any cuts coordination nodes; the location of the

fixtures; requirements for the construction and solution

Special spaces of the art environment of buildings).



(c)) the list of machinery and equipment and technical specifications



(a list of critical machinery and equipment, basic mechanical


components, power sources, etc.; description of the basic technical and

performance parameters and related requests).



D. 2 Documentation technical and technological equipment



The building can be, depending on the nature, broken down into operating units, which are further

divided into operational files and partial operational or functional files files.

Technological equipment are the manufacturing and nonmanufacturing.



Non-productive technological equipment are e.g.:



-power cord and wiring all the technical infrastructure

(electric energy, electronic communications, gas,

heating plants, media distribution systems, etc.) including related equipment,



-shifting management of the technical infrastructure,



-device, vertical and horizontal transport of persons and goods, equipment

for the transport of persons with reduced mobility, evacuation

or fire equipment,



-dedicated technical equipment,



-dedicated fire-safety devices and more.



The documentation is processed by the operational or functional

files and devices.



The following content and extent of the documentation is listed as maximum and

the specific case will be adapted to the nature and the technical complexity of

the construction. Characteristics:



(a) technical report description of the program for non-production structures;

description of the purpose, the list of supporting documents; description of the technological process

production, the need for materials, raw materials and the quantity of the products, the basic composition

technological equipment-purpose, description and basic parameters of, description

warehouse management and material handling requirements for the manufacture,

internal and external transport, the impact of technological equipment for construction

the solution, the data about the need for energy, fuels, water and other media, including

requirements and places the connection).



(b) the drafting section of the location and arrangement of critical equipment,

machines, basic mechanical components, power sources, etc.;

the basic definition of the area to their location in the building, the basic

the overview diagrams wiring and fittings, floor plans of the Basic pipeline

and cable distribution systems in 1-line display, any cuts

coordination nodes, building requirements and solutions special

areas of technological equipment, whose layout is

usually a part of construction drawings; the basic technology

documenting the purpose of the schemes and the level of the proposed manufacturing process,

the layout and location of the main machinery and equipment and the way they

installation-floor plans, sections, usually at a scale of 1:100).



(c)) the list of machinery and equipment and technical specifications (a list of

the critical machinery and equipment, the essential mechanical components,

energy sources, etc.; description of the basic technical and performance

parameters and related requests).



E Book part



This section contains evidence of compliance with the requirements under other

the legislation issued by the competent administrative authorities or the relevant

persons and documentation processed by persons authorised under other

legislation.



E. 1 Binding opinions, opinions, decisions, opinions of the concerned

authorities



E.2. The opinions of the owners of public transport and technical infrastructure



E.2.1 the opinions of the owners of public transport and technical infrastructure

the possibility and the way of connection, for example, drawing on the situation noted



E.2.2 the opinion of the owner or operator to the conditions for the establishment of a

construction, execution of works and activities in the trade and

security zones under other legislation



E.3. Geodetic basis for project activities handled by other

legislation ^ 4)



E. 4 project processed Mining Designer ^ 6)



E. 5 energy performance of the building according to the law on the management

energy ^ 7)



E. 6 other opinions, observations, opinions, and the results of the negotiations conducted

during the processing of the dossier



Annex 6



The scope and content of the dossier for the execution of the project



Project documentation contains sections:



And the accompanying message



(B) a summary technical report



(C) the Situational drawings



(D) Documentation of the objects and technical and technological equipment



E Book part



Project documentation must always include parts A to E, with the

the scope and content of the various parts will be adapted to the nature and importance of

the building, its location, constructional and technical implementation, use,

impact on the environment and the duration of the construction.



Common principles:



Project documentation for implementation of construction is processed separately

for each building and civil engineering objects and for technology

device.



The approved project documentation for the announcement of the construction, or

building permit for construction of technical infrastructure

not requiring a building permit or notification of documentation

for the issuance of zoning and planning decision or consent.



Project documentation is processed in the details of enabling

draw up an inventory of the works, supplies and services, with a summary of the assessment.



Project documentation includes technical characteristics, descriptions and

conditions for the implementation of the works.



Detail drawings (detail) binding for the vendor displayed, or

dimensionally complex structures (elements), which puts the designer specific

requirements and that must be respected in the implementation of the construction.



Part of the project documentation for implementation of construction it is not documentation

for odd jobs and construction, production and technical documentation,

documentation of the products to the construction, drawings and installation

documentation. If it is necessary to handle any of these documents,

It is always a part of contractor documents.



Processing plan for safety and health at work on the construction site

other legislation regulates the ^ 5) (plan for safety and health at

work on the site is not included in this annex).



And the accompanying message



A.1 identification data



A.1.1 information about construction



and the name of the building),



(b)) instead of (address, numbers, cadastral, land

the numbers of the land).



And data on the client;



and) name, surname and place of residence (individual) or



(b)) the full name, business name, registration number, if assigned, place

business (natural person-entrepreneur) or



(c) the business name or name), registration number, if assigned, registered address

(legal person).



And 1.3 information about the processor project documentation



and) the full name, business name, registration number, if assigned, place

business (natural person-entrepreneur) or business name or the name of the

(legal person), corporate ID, if allocated, the address of the registered office,



(b) main) name and surname of the designer, including the number, under which the

registered in the register of authorized people led by Czech architects

or the Czech Chamber of authorised engineers and technicians active in

construction, with the declared scope or specialization of its authorization,



(c)) first and last names of designers of different parts of project

documentation including the number under which you are enrolled on the register

authorized people led by Czech architects or the Czech

Chamber of Chartered Engineers and technicians active in construction, with

indicate the scope, where appropriate, specialising their authorization.



And 2 a list of input documents



and) basic information about the decisions or measures on the

the basis of the construction was allowed (the designation/name of the Office building

authorized inspector, date and reference number of the decision

or measures),



(b)) basic information about the documentation or the project documentation, the

the basis was prepared project documentation for implementation

the construction work,



(c)) for more handouts.



And 3 information on the territory



and the solution to the range of the territory)



(b) information on the protection of the territory) under other legislation (^ 1) Memorial

reservations, heritage zone, the specially protected territories, floodplain

etc.),



(c) data on runoff ratios),



d) details of the conformity with the spatial planning documentation, if it has not been released

planning decision or territorial measures, where applicable, the absence of a territorial

consent,



e) details of the conformity with the land use decision or public-law agreement

land use planning decision or approval of the replacement, or with

the regulatory plan, to the extent in which replaces territorial decision, with

the authorization of the construction, and in case of a change in the underlying editing

the use of the construction details of its compliance with the spatial planning documentation,



(f) General) information on the requirements for the use of the territory,



g) data on the meet the requirements of the bodies concerned,



h) exception list, and úlevových solutions



I) list of related and underlying investments



j) list of land and buildings concerned by any construction (according to the cadastre

real estate).



And 4 information about construction



and new construction) or change the finished structure,



(b) the purpose of use of construction works,)



c) permanent or temporary building,



(d) protection of data on buildings) under other legislation (^ 1) cultural

Monument etc.),



(e) compliance with) the data on technical requirements for the construction and General

belonging to the barrier-free use of the technical requirements of buildings,



f) data on compliance with the requirements of the concerned bodies and the requirements


from other legislation ^ 2)



g) exception list, and úlevových solutions



(h) the proposed capacity building) (built-up area, built-up area,

floor area, number of functional units and their sizes, the number of

users/workers, etc.),



I) basic balance construction (needs and consumption of media and materials,

management of rainwater, the total produced quantity and types of

waste and emissions, energy performance of buildings, etc.),



j) basic assumptions of the construction (the time data on the implementation of the construction work,

breakdown on stage),



indicative costs of the building).



And 5 the breakdown of the construction on the objects and the technical and technological equipment



(B) a summary technical report



The points will be taken from the project documentation for the report

construction or building permit for construction of the technical

infrastructure not requiring a building permit or notification will be

taken from the documentation for issuance of zoning and planning decision or territorial

consent, where revisions and additions to them

result:



a) requirements for the processing of vendor documentation,



b) processing requirements plan for safety and health at work

on the construction site,



(c)) the conditions of implementation work will be carried out in the trade or

security zones, the other structures,



d) special conditions and requirements for the Organization of the construction site and the implementation of the

work on it, resulting in particular from the nature of the works, property

a building site or a builder's requirements on the implementation of construction, etc.,



(e)) environment protection during construction.



(C) the Situational drawings



C (1) block plan of the wider relations



a) scale 1:1 000 and 1:50 000,



(b) building on the transport) and the technical infrastructure,



c) existing and proposed safeguards and safety zones,



(d) the designation of the boundaries of the territory).



(C) 2 Total block plan



and) scale of 1:200 to 1:1 000, for large buildings 1:2000 or 1:

5 000,



(b) existing buildings, transport) and technical infrastructure,



c) boundaries,



(d)) the boundaries of the territory being tackled,



e) base and positioning, altimetry



(f)), designed the building,



g) determination of altitude 1. floor in buildings (+-0, 00) and

the height of the modified terrain; the maximum height of buildings,



h) communications and paved areas,



I) areas of vegetation.



C. 3 Coordinating block plan



and) scale of 1:200 to 1:1 000, for large buildings 1:2000 or 1:

5 000 for changes to the building, which is a listed building, in the building in the historic

reservation or in the zone at a scale of 1:200,



(b) existing buildings, transport) and technical infrastructure,



(c) the boundaries of the land parcel) number,



(d)) the boundaries of the territory being tackled,



e) existing altimetry and positioning,



f) represent each designed and of buildings and

the technical infrastructure,



g) determination of altitude 1. floor in buildings (+-0, 00) and

the height of the modified terrain; the maximum height of buildings,



(h)) to the proposed communication and paved area, connection to public transport

infrastructure,



I) solution of vegetation,



j) dimensioned spacing of buildings,



the plot of the new technical infrastructure), the connection of the constructions of the technical

infrastructure,



l) existing and proposed safeguards and safety zones, conservation

reservations, zone, etc.



m) maximum land (temporary/permanent),



n) designation of geotechnical probes



about the data, determine the geodetic) coordinates of the layout of the network



p) distances including the definition of fire hazardous areas,

access communications and boarding areas for fire equipment and resources

fire water.



(D) Documentation of the objects and technical and technological equipment



Documentation structures, engineering, technical or

technological equipment is processed through the objects and files

technical and technological devices in the following breakdown in

a reasonable range:



(D) 1 of the building or the engineering Documentation object



D. 1.1 architectural-building solutions



(a) technical report the purpose of an object, function, capacity data;

architectural, fine art, material and layout

barrier-free use of the work; the total service solutions, technology

production; the design and construction technical solutions and technical characteristics

construction; safety in the use of the construction works, health and work

environment; building physics-thermal technology, lighting, sunlight,

Acoustics/noise, vibration-description solutions, energy management, policy

protection of buildings from the negative effects of the external environment; the requirements for the

fire protection of structures; information on the quality of the proposed

materials and the required quality of workmanship; description of non-traditional

technological procedures and the specific requirements for the implementation and quality of the

the proposed structures; the requirements for the drawing up of documentation provided by the

contractor of the construction-the content and scope of manufacturing and shop floor documentation

the contractor; the determination of the required checks and zakrývaných structures

any control measurements and tests, if they are required above

the framework of mandatory-technological regulations and by applicable

standards; a listing of the standards).



(b) the Drafting section (s) of the construction trench, floor plans and foundations-

If they are not contained in part D of the 1.2, floor plans of individual floors with

indicating the dimensions of all structures, openings in structures, with a description of

the purpose of the use of rooms with an areal acreage including the video resolution

the characteristic material solution structures, with a description or

marking of products and links to the details; the characteristic cuts

the basic design solutions, with dimensions related to the

the existing terrain including the video resolution of the characteristic

material solution design; minor cuts to the extent necessary and

scale; drawings of roofs or roof; views on all the faces

the façade with base dimensions height solution related to the

the existing terrain, with an indication of color and characteristics of materials

surfaces).



c) documents the details (of the song structures, lists of parts, products and

the work, a critical detail design and atypical products).



D. 1.2 Design Construction



(a) technical report for a detailed description of the proposed support system construction

resolution of individual structures by type, technology and

the proposed materials; final cross-sectional dimensions of each

structural elements, where appropriate, a reference to the drawings; data on the

anticipated loads in static calculation-stable, usable,

the climate, from antenna systems, extra, etc.; information on the

the quality of the materials proposed; description of non-traditional technology

procedures and specific requirements for the implementation and quality of the proposed

structures; ensure the construction trench; the determination of the required checks

zakrývaných structures and any control measurement and testing, if

are required, beyond the mandatory-laid down by the competent

technological regulations and standards; in the case of alterations to existing buildings-

description of the construction, its current status, technological process with

calling attention to the necessary measures to maintain the stability and loading capacity of the own

construction, or immediately adjacent objects; the requirements for the

elaboration of documentation provided by the contractor of the construction-content and

range, the minimum load carrying capacity, which must

construction must comply; fire protection requirements for structures; for a list of

used documents-regulations, standards, literature, computing programs

, etc.; safety requirements in the implementation of load-bearing structures-link

the appropriate regulations and standards).



(b)) detailed static calculation



Static calculation must be controlled, must therefore be clear to

It was possible to track the progress of the calculation, design load, the considered

static schema, and computational model.



The static calculation of the documentation for the construction is based on the

the static calculation, referred to in the preceding stage of project

documentation. Is a complete basis for the drawing up of technical specifications

components and drawings for construction.

Provides sizing of all structures that are part of the

the documentation provided by the contractor of the construction (drawings of concrete

monolithic and prefabricated structures, supply documentation

metal and wooden structures). Detailed static calculation contains

in particular, the accompanying message to the static (dynamic) calculation, briefly

book to recap the basic concept of the solution structure and the differences from the

the preliminary calculation, which was drawn up in the framework of the previous grade

project documentation; supporting documents-used standards, legislation, literature,

computer programs, etc.; static schema design; data on the

materials and technologies; recap of the load, load

including load factors and combinations of factors; models of computation,

Computational schemes; design and assessment of all support elements; the calculation of the

effects on the fundamentals, dimensioning of the Foundation; the design and

the assessment of all of the details of Assembly, contacts, etc., that the decisive


way affect the safety of the structure; the production process-casting,

the formwork, Assembly, prestressing, backfilling the completed structures

etc.



(c) the Drafting section (s) of the floor plans of supporting structures in the scale of 1:

50, 1:100, including the folded down slices; the corresponding slices

views and details with the necessary accuracy display; from the drawings must

be clearly identifiable shape design, all construction elements

and details; drawings of the monolithic or prefabricated area

the foundations, pile foundations and base grid, if these constructs

are not sufficiently concise way shown in construction drawings

the foundations; the details of the contacts, anchoring, etc. on a scale of 1:20 or 1:10 or

1:5; Assembly drawings, details, and anchoring of prefabricated

building components, parts of metal, composite or wooden

structures; drawings of the locations of structures containing floor plans and the island

NET, cuts and views of uniquely identifying the support structure with the designation

cross sections of all the elements and details of a structure and its

anchoring; scale/contour drawing of prefabricated building components;

layout drawing of the reinforcement, monolithic concrete structures

containing the views and a sufficient amount of sample lines clearly

determining the quality of concrete and steel, location and cross-sectional area, or

the number of inserts the appropriate profile; layout drawing of the reinforcement is used to

the static calculation as a basis for drawing up the

detailed drawings provided by the contractor of the reinforcement-documentation

of the building).



D. 1.3 fire safety solutions



Revisions and additions to the documentation for the announcement of the construction, or for the issue of

a building permit for construction of technical infrastructure maintenance-

a building permit nor report the revision of and additions to the documentation

zoning and planning decision or consent, including the designation of land use changes in the

fire safety solutions processed the documentation for reporting

construction or building permit for construction of the technical

infrastructure not requiring a building permit nor report in

documentation for issuance of zoning and planning decision or consent.



D. 1.4 Environmental Engineering Technology



The documentation of the individual professions shall designate in technical equipment and systems

details illustrating the compliance with the code of values and legal

regulations. Define the basic material, technical and technological,

disposition and operating characteristics of equipment and systems. Presents the basic

quality and safety requirements for equipment and systems.



The documentation is processed separately for each device characteristics

for example:



-sanitary installations,



-gas sampling device



-air conditioning,



-heating,



-cooling,



-measuring and regulation,



-heavy-current electrical engineering including lightning protection,



-electronic communications and more.



Each part is processed according to common principles. The content and scope of

documentation is provided as a framework and in the particular case will be

adapted to the nature and the technical complexity of the buildings and equipment and

the link to the above profession. If any part of the building

not occur, it will not be included in the documentation. Organisational set-up

documentation professions it is expedient to organize under the procedure construction

and supply chain security. Therefore, it is possible to merge the professions into one

part.



In General (in relation to professions) documentation contains:



and) technical report (technical data that contains basic parameters

the prescriptive requirements for individual professions-balance needs

media and energy pressures, and the network connections types

of the services provided, the amount of waste generated by the operation, including the

waste water treatment, etc.; description of the technical solution, function and arrangement

installation and system; description of the Terminal elements and devices and systems,

plumbing fixtures; the description and conditions of connection to the public or local

the technical infrastructure; principles of safe operation including the protection

people, animals and property before the injury, or from damage; fire

measures, protection against noise and vibration, noise in the inner

and the outdoor environment; the principle of protection of the environment; technical

the calculations demonstrating the safety of the design, if such a calculation is required;

the list of required documents needed for placing the building into use;

a listing of the standards, including the date of issue).



(b) the drafting section (the situation) with the unions and other necessities

profession; or pre-select the longitudinal profiles of connections including the necessary

details; the location of the individual machines and equipment; drawings, floor plans

pipe and cable routes, where appropriate, on each floor;

axonometric view needed, vertical or flat slices, if

cannot be sufficiently indicate the plans; installation drawings and plans;

drawings of pipe and cable routes, including connecting

equipment and instrumentation for measurement and control circuits or management

System; Briefing power scheme, the scheme of earthing and interception

system and others; the arrangement, binding and communication systems; related

for details, if necessary).



(c)) the list of machinery and equipment and technical specifications (a list of machines and

equipment, mechanical components, power sources, etc.; Description

technical and performance parameters and related requirements; lists

material for construction, wiring, pipes, coatings, insulation).



D. 2 Documentation technical and technological equipment



The building can be, depending on the nature, broken down into operating units, which are further

divided into operational files and partial operational or functional files files.

Technological equipment are the manufacturing and nonmanufacturing.



Technological equipment of buildings and public technical infrastructure:



-elevated and underground electronic communication network management

communications, antennas and masts, including mainstays of overhead,

or vytyčovacích points of underground communication lines, phone booth

and towable communication leadership electronic communications networks and

related communications equipment including electric hook-ups,



-underground and above-ground transmission or distribution system management

electricity including supporting points and measuring systems, protective, control,

security, information and telecommunications technology,



-the management of the transmission or distribution system (or flammable gas

liquids) and related technological objects, including systems management,

security, information and telecommunications technology,



-distribution of heat energy and associated technological objects, including

systems management, security, information and telecommunications technology,



-the management of the public lighting network including masts and systems management,

security, information and telecommunications technology,



-building for the production and transformation of energy, with the exception of the construction of the water

works,



-water, sewage and energy connections, including connections construction

and the sampling device



-tanks for liquefied petroleum gases or flammable liquids,



-water tanks or other non-flammable liquids,



-trays for the storage of agricultural products, animal feed and fertilizers,



-the water tank, if it is not a water works,



-water supply network, water-supply, sewerage and drainage networks, wastewater treatment plant

waste water treatment plants, including systems management, security, information and

telecommunications technology.



Non-productive technological equipment are for example:



-device, vertical and horizontal transport of persons and goods, equipment

for the transport of persons with reduced mobility, evacuation

or fire equipment,



-dedicated technical equipment,



-dedicated fire-safety devices and more.



The documentation is processed after individual operating, or functional

files and devices.



The following content and extent of the documentation is listed as maximum and

the specific case will be adapted to the nature and the technical complexity of

the construction. Characteristics:



(a) technical report description of the program for non-production structures;

description of the purpose, the list of supporting documents; description of the technological process

production, the need for materials, raw materials and the quantity of the products, the basic composition

technological equipment-purpose, description and basic parameters of, description

warehouse management and material handling requirements for the manufacture,

internal and external transport, the impact of technological equipment for construction

the solution, the data about the need for energy, fuels, water and other media, including

requirements, and the places of connection; the list of required documents needed for the

putting the building into use; a listing of the standards, including the date of issue).



(b)) the drafting section (contains the location and layout of equipment, machinery,

mechanical components, power sources, etc.; definition of the area to

their placement in the construction, distribution and equipment inventory schemes,

floor plans of pipeline and cable distribution systems and their possible cuts,

the location of the apparatus, appliances and fixtures; the requirements for the

construction and solution of special areas of technological equipment,


the layout is usually a part of the construction drawings;

technological schemes supporting the purpose and the proposed level of

process layout and location of the machinery and equipment and the way they

installation-floor plans and sections in an appropriate scale).



(c)) the list of machinery and equipment and technical specifications (a list of machines and

equipment, mechanical components, power sources, etc.; Description

technical and performance parameters and related requirements; lists

material for construction, wiring, pipes, coatings, insulation).



E Book part



This section contains evidence of compliance with the requirements under other

the legislation issued by the competent administrative authorities or the relevant

persons and documentation processed by persons authorised under other

legislation.



E. 1 Layout drawings of the individual objects processed by the other

legislation ^ 4)



E. 2 Project processed Mining Designer ^ 6)



Annex 7



1. scope and content of the documentation of the actual construction



The documentation contains sections:



And the accompanying message



(B) a summary technical report



(C) the Situational drawings



(D) drawing documentation



(E) the Geodetic part



The documentation must always include parts A to E, with the scope and content of

the various parts will be adapted to the nature and importance of the construction work, its

location, construction-technical design, the purpose of the use, effects on

the environment and duration of construction.



And the accompanying message



A.1 identification data



A.1.1 information about construction



and the name of the building),



(b)) instead of (address, numbers, cadastral, land

the numbers of the land).



And the information about the owner;



and) name, surname and place of residence (individual) or



(b)) the full name, business name, registration number, if assigned, place

business (natural person-entrepreneur) or



(c) the business name or name), registration number, if assigned, registered address

(legal person).



And 1.3 information about the processor documentation



and) the full name, business name, registration number, if assigned, place

business (natural person-entrepreneur) or business name, or the name,

CORPORATE ID, if allocated, the address of the registered office (legal entity),



(b)) first and last name (individual).



And 2 a list of input documents



and) basic information about all decisions or measures

associated with the construction of the Building Authority (designation/name

authorized inspector, date and reference number of the decision

or measures), if these documents have been preserved, indicate the likely

year of completion of construction,



b) basic information on the documentation, project documentation or other

technical documentation (identification, date of issue, identification

about the contractor, documentation), if preserved,



(c)) for more handouts.



And 3 information on the territory



Information about the protection of areas under other legislation (^ 1) Memorial

reservations, heritage zone, the specially protected natural areas, the flood

the territory, etc.).



And 4 information about construction



and the purpose of the use of the building,)



(b) permanent or temporary building),



(c) data on the protection of the building) under other legislation (^ 1) cultural

Monument etc.),



(d) capacity building (built-up) area, built-up space, usable

area, number of functional units and their sizes, the number of users/

workers, etc.),



(e) the balance of the construction () of the underlying needs and consumption of media and materials,

management of rainwater, the total produced quantity and types of

waste and emissions, etc.).



(B) a summary technical report



and a general description of the construction) (technical description of the building and its technical

device),



(b) assessment of the existing building) technical state,



c) connection to transport and technical infrastructure,



(d) the protection and safety zones),



(e)) the effects of construction on the environment and the protection of special interests.



(C) the Situational drawings



C. 1 Coordinating block plan



and) scale of 1:200 to 1:1 000, for large buildings 1:2000 or 1:

5 000 for changes to the building, which is a listed building, in the building in the historic

reservation or in the zone at a scale of 1:200,



(b) the boundaries of the land parcel) number,



(c)) the current objects and the plot of the surface characters of engineering

infrastructure,



d) existing altimetry and positioning,



e) determining the altitude; the height of the object,



f) dimensioned spacing of buildings,



g) existing communication and paved area, connection to public transport

infrastructure,



h) the existing vegetation, the staff



I) protective and safety zones, conservation area, a conservation zone

etc.,



j) distances including the definition of fire hazardous areas,

access communications and boarding areas for fire equipment and resources

fire water.



C (2) Cadastral block plan



and according to the scale used) the cadastral maps,



(b) the designation of the buildings)



(c)) the designation of the links and impacts on the surrounding area.



(D) drawing documentation



Construction drawings prepared by the actual construction with

special sections and views, with a description of all the spaces and rooms

under the current method of use and with an indication of their size and

area assessment.



(E) the Geodetic part



Numerical and graphical representation of the results the focus of construction, positioning with

výškopisnými data, survey sketches with figures, a list of

coordinates and heights, and the technical report in accordance with other legal

prescription ^ 8).



2. Simplified documentation (passport)



Simplified documentation contains sections:



And the accompanying message



(B) a summary technical report



(C) a simplified sketch



(D) the Simplified drawing documentation



And the accompanying message



A.1 identification data



A.1.1 information about construction



and the name of the building),



(b)) instead of (address, numbers, cadastral, land

the numbers of the land).



And the information about the owner;



and) name, surname and place of residence (individual) or



(b)) the full name, business name, registration number, if assigned, place

business (natural person-entrepreneur) or



(c) the business name or name), registration number, if assigned, registered address

(legal person).



And 1.3 information about the processor documentation



and) the full name, business name, registration number, if assigned, place

business (natural person-entrepreneur) or business name, or the name,

CORPORATE ID, if allocated, the address of the registered office (legal entity),



(b)) first and last name (individual).



And 2 a list of input documents



and) basic information about all decisions or measures

associated with the construction of the Building Authority (designation/name

authorized inspector, date and reference number of the decision

or measures), if these documents have been preserved, indicate the likely

year of completion of construction,



b) basic information on the documentation, project documentation or other

technical documentation (identification, date of issue, identification

about the contractor, documentation), if preserved,



(c)) for more handouts.



And 3 information on the territory



Information about the protection of areas under other legislation (historical

reservations, heritage zone, the specially protected territories, floodplain

etc.).



And 4 information about construction



and the purpose of the use of the building,)



(b) permanent or temporary building),



(c) data on the protection of the building) under other legislation (^ 1) cultural

Monument etc.),



(d) capacity building (built-up) area, built-up space, usable

area, number of functional units and their sizes, the number of users/

workers, etc.),



(e) the balance of the construction () of the underlying needs and consumption of media and materials,

management of rainwater, the total produced quantity and types of

waste and emissions, etc.).



(B) a summary technical report



and a general description of the construction) (technical description of the building and its technical

device),



(b) assessment of the existing building) technical state,



c) connection to transport and technical infrastructure,



(d) the protection and safety zones),



(e)) the effects of construction on the environment and the protection of special interests.



(C) a simplified sketch



Simplified sketch in scale according to the cadastral maps with

showing the construction.



(D) the Simplified drawing documentation



Simplified drawings of actual construction in scale and

the details relevant to the type and purpose of the work describing how

the use of all spaces and rooms.



Annex 8



Demolition documentation requirements



The documentation contains sections:



And the accompanying message



(B) a summary technical report



(C) the Situational drawings



(D) Documentation



E Book part



The documentation must always include parts A to E, with the scope and content of

the various parts will be adapted to the nature and importance of the construction work, its

the location, size, materials, and construction and technical implementation.



And the accompanying message



A.1 identification data



A.1.1 information about construction



and the name of the building),



(b)) instead of (address, numbers, cadastral, land

the numbers of the land).



And the information about the owner;



and) name, surname and place of residence (individual) or



(b)) the full name, business name, registration number, if assigned, place

business (natural person-entrepreneur) or



(c) the business name or name), registration number, if assigned, registered address

(legal person).



And 1.3 information about the processor documentation




and) the full name, business name, registration number, if assigned, place

business (natural person-entrepreneur) or business name, or the name,

CORPORATE ID, if allocated, the address of the registered office (legal entity),



(b)) first and last name (individual).



And 2 a list of input documents



And 3 information on the territory



and data on the territory) in which the building is located, to be deleted.



(b) information on the protection of the territory) under other legislation (^ 1) Memorial

reservations, heritage zone, the specially protected territories, floodplain

etc.),



c) details of the meet the requirements of the bodies concerned,



(d) a list of adjacent land) necessary to perform demolition

(according to the land registry).



And 4 information about construction



and the nature and purpose of use) the discarded buildings,



(b) the protection of deleted data) construction in accordance with other legal

^ Law 1) (information about the cancellation Declaration for cultural heritage

etc.),



c) details of the meet the requirements of the bodies concerned,



(d)) of existing capacity building (built-up area you want, built-up

space, the number of functional units; for the building containing flats-total

floor area of the building, the number and size of insolvent housing, residential and

useful area of insolvent bytes),



(e) the conditions for the removal of) basic construction-time information about the progress of

work breakdown on stage, indicative costs, projected

the removal of the building.



And 5 the breakdown of the discarded construction



(B) a summary technical report



(B) a description of the territory of construction 1



and characteristics of the built) building land,



(b) the existing protection and safety) zone,



c) its position relative to záplavovému territory poddolovanému territory, etc.



(d) removal of the construction on) the effects of surrounding buildings and land, the protection of the area,

the effect of the removal of buildings on flow conditions,



(e) evaluation of the contamination of the building space) substances harmful for the

the environment in the event of their occurrence,



(f) requirements for cutting down trees),



(g)) accruals links; contingent upon, developed, related investments.



(B) a general description of the construction of the 2.



and a brief description of construction or) engineering objects and their

structures,



(b)) a brief description of technical or technological equipment,



(c) the results of the survey, construction) for the presence of asbestos in the building.



(B) 3 connection to the technical infrastructure



and the technical infrastructure of the adjacent places),



b) connecting dimensions, power capacity and length,



(c)) the way to disconnect.



B. 4 landscaping and vegetation after the removal of the construction solutions



and landscaping) after removal of the buildings,



(b)) used the vegetation elements, biotechnical measures.



B. 5 principles of organization demolition



and critical needs and consumption) media and their collateral,



(b) drainage of construction site)



c) connection of the construction site on the existing transport and technical

infrastructure,



(d) removal of the construction on) the effects of surrounding buildings and land,



(e) the protection around the construction site,)



f) maximum land grab,



g) maximum produced quantities and types of waste and emissions during

removal of construction waste, especially hazardous waste,

way to transport and store them or further use or disposal,



h) protection of the environment while removing the structures,



I) principles of safety and health at work on the construction site,

assess the need for the Coordinator for safety and health at work

under other legislation ^ 6)



j) adjustments for barrier-free use of the buildings affected by the removal of the building,



the traffic engineering policy) measures.



(C) the Situational drawings



C (1) block plan of the wider relations



a) scale 1:500 to 1:50, 000, for the removal of buildings, whose declaration

a cultural monument has been canceled, and the removal of buildings in historic

reservation or in the zone at a scale of 1:200,



(b) building on the transport) and the technical infrastructure,



(c) the protection and safety zones),



(d) the designation of the boundaries of the territory).



C (2) Cadastral block plan



and according to the scale used) the cadastral maps,



(b) designation of building and) engineering of objects



(c) the designation of the effects of the demolition works).



(D) Documentation



Documentation of construction or engineering of objects

object handles the following subdivisions within a reasonable range.



(a) technical report description of the demolition and routing

removal of technical or technological equipment; warning on

Special, unusual design, construction details, technology

procedures, etc.),



(b) the Drafting section (documentation) of the current status of designating links to

the adjacent building, schematic drawings of the procedure of the demolition work, if

not sufficient data in the technical report),



(c)) Static assessment of (static or dynamic analysis to assess the

structural stability during the stages of demolition, or

for the design of temporary support structures).



E Book part



This section contains evidence of compliance with the requirements under other

the legislation issued by the competent administrative authorities or the relevant

persons.



E. 1 Binding opinions, opinions, decisions, opinions of the concerned

authorities



E.2. The opinions of the owners of public transport and technical infrastructure



E.2.1 the opinions of the owners of public transport and technical infrastructure

the options and how to disconnect



E.2.2 the opinion of the owner or operator of the conditions of implementation

work and activities in the trade and the safety zones defined in

other legislation



E. 3 other opinions, observations, opinions, and the results of the negotiations conducted

during the processing of the dossier



Č. 9



The elements and way of management of construction and a simple record of journal

the construction of the



Construction diary



A. identification data



and the name of the building) (or part thereof), in its report, the construction

permits, public contracts or notification of construction project with

the certificate of an authorized officer, the date of their issue, or

reference number,



(b)) instead of buildings,



c) business name, business address or registered office of construction participants

(if a participant is not entered in the commercial register of the construction of its name and

last name):



-contractor (or contractors part)



-Builder (Investor)



-Designer



-poddodavatelů



(d)) first and last names of people belonging to the professional guidance of the implementation

construction in accordance with § 153 building Act with the scope of their permissions, and

liability,



(e)) and last names of the persons carrying out technical supervision of the Commissioner and

author supervision (if these surveys established)



(f)) name, surname and function of other persons authorized to perform

entries in the diary under § 157 paragraph. 2 the building Act,



g) data on the project and other technical documentation for construction, including

any amendments thereto,



h) list or links to documents and papers to the construction (of the Treaty,

permits, approvals, administrative decisions, the reports on inspections,

the tests, test procedures etc.),



I) changes to the contractors of the building or responsible persons during construction.



The person carrying out selected activities in construction pursuant to section 158 of the construction

the law, demonstrate the permission to the performance of these activities, the imprint of their

stamp and signature in the construction of the journal. The same applies when you change these

people in the course of construction.



(B) records in the construction of the journal



1. Regular daily records include:



and) first and last names of persons working at the construction site,



b) climatic conditions (weather, temperature, etc.) on a construction site and its

status,



(c) the description and the quantity) of work performed and Assembly and their timetable,



(d) supplies of materials, products), machinery and equipment for the building, their

storage and installation,



e) deployment automation.



2. Additional records documenting details about these facts:



and the transmission and receipt of the construction site) (between builders and contractors),



(b)), or start of work deadlines and the reasons for their break, and

recovery, including technological breaks



c) musters, execution of works and their poddodavatelů activities,



(d)) and trained workers with conditions of work, safety

fire protection, environmental protection, technological

the procedures of work and Assembly, and to the potential risks in the construction work,



(e)), details of measures on safety and health at

work, fire protection and environmental protection,



(f)) special precautions for demolition work, work at heights,

the operation, in the protection zones, etc.,



g) handling of soils, construction debris and waste management,



h) geodetic measurements,



I) Assembly and dismantling of temporary structures (scaffolding, shoring,

formwork, etc.), its transmission and reception,



(j)) and the use of machinery, traffic,



to) the results of the quantitative and qualitative inspections of supply for

construction (input control);



l) measures to ensure the construction of embedded or stored products

and equipment against damage, theft, etc.,



m) the implementation and the results of inspections of all kinds,



n) consent to the making of the work (the footing bottom, the reinforcement of concrete,

the underground lines, etc.),



about the justification and approval of change) of materials, construction and technical solutions


deviations from a validated project documentation,



p) the fact important for material, time, and financial performance of the contracts

(extra, unpredictable factors, the occurrence of obstacles on the job site

the results of the additional technical surveys, extraordinary climatic influences

the archaeological research, work in service, etc.),



q) partial acceptance of completed works,



r) the implementation and the results of the tests and measurements (technical and technological

equipment, connections, etc.),



with) damage caused by the construction or other activities, accident, accidents,

losses, injuries and other emergencies, including the adopted measures,



t) transmission and acceptance of the work or its comprehensive parts,



u) rectification of defects and arrears,



in the results of verification visits of the building) (section 133 and 134 of the construction

of the Act),



w results of the activities of an authorized inspector),



x) the establishment, operation and removal of the equipment,



s) unforeseen discoveries of culturally valuable items, details of the work or

protected parts of nature or archaeological finds.



C. Management diary



1. Construction diary



and leads from the date) the transmission and receipt of the construction site until the date of completion of the

structures, where appropriate, to eliminate the defects and faulty items identified in the

the inspection tour of the construction,



(b)) must be available on the site at any time in the course of work on the construction site

all eligible persons



(c)) contains the original leaves and the required amount of copy to the departments

to other persons. Has numbered pages and must not be omitted free

space.



2. A record of the progress of work and their contexts are written the same

day, no later than the day on which the construction works. U

technically simple structures, the records may, with the approval of the construction

the Office carried out a maximum for the period of one working week.



3. In the case that all interested persons are the owners of electronic

the signature can be construction lead journal electronically.



A simple record of the construction



A. Table Of Contents



1. A simple record of the building contains



and the name and location of the building) by the announcement of the construction of the building Office, date

Declaration, or. reference number,



(b)) name, surname and residence of the Builder, business name, location

business or the registered office of the designer and the contractor (contractors

parts of buildings); If the designer is not entered in the commercial register of the

name and surname,



(c) validated data) project documentation, construction



(d)) the list of or links to documents, and papers to the construction (consent

the Building Authority, contracts, etc.),



e) records of the course of execution of construction and building-assembly works and

about the facts that influence the making of the work,



f) records of incidents during the construction.



2. record the activity and the circumstances that affect the



and the progress of work and the use of) materials



(b)), to ensure stability, quality and serviceability of the buildings,



(c)) and the use of the safe installation of the technical equipment and functional parts

the construction work,



(d) electrical equipment, testing) review and revision of the pressure equipment,

flues, chimneys, etc.,



(e) the conditions for safe execution of the project) and the protection of health at work,



(f) implementation of trade agreements, arrangements),



g) protection of public interests, the environment, etc.



h) comply with the particulars contained in the Declaration of the building including the audited

project documentation, or the need for small deviations from it.



(B) a simple record of leadership building



1. A simple record of the construction



and runs from) the start of works on the construction site to the completion of construction,

where appropriate, to eliminate the defects and arrears found during inspection

inspection, construction,



(b)) must be made within the scope and in time intervals so that

caught the real progress of the construction.



2. (C). paragraph 2 of this annex applies to the simple record keeping

the construction of the analogy.



Selected provisions of the novel



Article. (II) Decree No. 62/Sb.



Transitional provisions



1. Documentation and design documentation according to § 1a to 5 order, which

has been processed before the date of entry into force of this Decree and submitted to the

building Office until 31 December 2006. December 2014, is judged according to the existing

of the legislation.



2. Project documentation according to § 3 of the decree can be processed according to the

Decree No. 499/2006 Coll., in the version in force until the date of entry into force of this

the Ordinance, if construction will be started not later than 31 December 2006. December 2014.



1) Eg. Law No. 20/1987 Coll. on State heritage preservation, as amended by

amended.



2) Eg. Act No. 18/1997 Coll. on peaceful uses of nuclear energy and

ionizing radiation (the Atomic Act), and amending and supplementing certain

laws, as amended.



3) Law No. 22/1997 Coll., on technical requirements for products and amending

and additions to certain laws, as amended.



4) Government Regulation No. 430/2006 Coll., on the establishment of surveying

reference systems and the national map works on the territory of the State and mandatory

the principles of their use, as amended by Government Decree No. 81/2007 Sb.



section 12 and 13 of Act No. 200/1994 Coll., on surveying and amending and supplementing

Some laws related to its introduction, as amended

regulations.



section 13 of Act No. 31/1995 Coll., implementing Act No. 200/1994 Coll.

about surveying and amending and supplementing certain laws related to

his introduction, as amended.



5) Act No. 309/2006 Coll., to regulate other requirements

safety and health at work in labor relations and

ensure the safety and health activities or the provision of

services outside of the employment relationships Act (to ensure further conditions

safety and health at work), as amended.



6) Act No. 61/1988 Coll. on mining activities, explosives and the State

Mining Administration, as amended.



Decree No 298/2005 Coll., on professional qualifications and requirements

competence in mining activities, or activities carried out

using mining techniques and on amendments to certain laws, as amended by

amended.



7) Act No. 406/2000 Coll. on energy management, as amended

regulations.



8) § 13 para. 5 (b). and) Decree No. 31/1995 Coll., implementing the

Act No. 200/1994 Coll., on surveying and amending and supplementing certain

laws related to its introduction, as amended.