  Traffic Transport Department decided on port engineering completed acceptance approach (traffic Transport Department makes 2014 12th,) for following modified: a, and will second article second paragraph modified for: "this approach by said port engineering completed acceptance, is refers to port engineering completed Hou, and official input using Qian, on port engineering quality, and implementation national and industry mandatory standard situation, and investment using situation, matters of full check acceptance, and on port engineering construction, and design, and construction, and supervision, work of integrated evaluation. "Second, the article is changed to:" after the completion of the port, through examination before they can be officially put into use.

"Third, seventh paragraph (c) is revised as follows:" (c) the need to try running in port engineering, testing run comply with the design requirements ".

Paragraph (d) is revised as follows: "(d) the environment protection facilities, security facilities, occupational-disease-prevention facilities, fire-fighting equipment has been adopted by the relevant departments under the special approval or for the record; navigation aid facilities, as well as other ancillary facilities in accordance with the provisions of the law on ports, and the construction of ports at the same time, and to ensure that regular use." Four, the article is changed to: "the need to test running and operation of port facilities shall comply with the provisions of the regulations for port operation conditions for commissioning and operation, and the permit for port operation of the trial operation period. Trial operating period of port projects eligible for acceptance, it shall go through the port project acceptance procedures. "Five, the 19th is amended as:" port project completion acceptance or acceptance is not qualified may not be officially put into use. "Six, the 20th is revised as follows:" project legal person in violation of the regulations for the pilot run, the harbour is located the port administration authority to order the suspension of trial operation.

"This decision come into force on April 19, 2016.

According to this decision of the measures for the completion of the port be amended accordingly and publish it again. Port Engineering completed acceptance approach (on April 12, 2005 Ministry released according to September 5, 2014 traffic Transport Department on modified straddling port engineering completed acceptance approach of decided first times amendment according to April 19, 2016 traffic Transport Department on modified straddling port engineering completed acceptance approach of decided second times Amendment) first article for specification port engineering completed acceptance work, guarantee port engineering quality, protection people life and property security, according to People's Republic of China port method,

These measures are formulated.

Second approach is suitable for new construction and renovation of the port project completion acceptance activities.

Port Engineering completion approval mentioned in these measures refers to port after project completion, officially put into use before the port project quality, implementation of mandatory national and industry standards, investment matters such as the use of comprehensive check and acceptance, as well as port construction, design, construction and supervision of comprehensive evaluation.

After completion of the third port, through examination before they can be officially put into use.

Fourth Harbor engineering completion approval, should follow the principle of openness, fairness, truth, science.

The fifth project legal person in port engineering, design, construction, supervision and other units should be accepted, with the final acceptance of the work, provided the relevant information shall be true, valid.

Sixth port project acceptance, unified management, graded system of accountability.

Unified management of the Ministry of transport and the national port completion approval work.

Investment Department under the State Council, provincial government investment authorities, approval and provincial transportation authorities for completion of the port, the provincial transport authorities are responsible for.

Remaining port by port local port administration authorities are responsible for final acceptance.

More responsible departments are collectively referred to as acceptance of the completion of the port sector. Seventh article port engineering for completed acceptance should has following conditions: (a) port engineering about contract agreed of the content has basic completed, application completed acceptance of construction project has tail left engineering of, tail left engineering shall not effect construction project of production using, tail left engineering investment can according to actual measuring investment or according to engineering estimates by column of investment included completed accounts report, but shall not over engineering total investment of 5%.

On engineering quality inspection qualified construction units, supervising engineer on the construction quality assessment of conformity, project corporate design, construction, supervision, engineering quality supervision unit for completion acceptance; (b) the main process equipment or facilities by debugging with the production conditions; (c) the need to try running in port engineering, testing run comply with the design requirements.

(Four) environmental protection facilities, and security facilities, and occupational protection facilities, and fire facilities has according to about sector provides through special acceptance or record; beacon facilities and other auxiliary facilities has according to port method of provides, and port while construction, and guarantee regular input using; (five) completed archives information complete, and through special acceptance; (six) completed accounts report prepared completed, and through audit; (seven) clean government contract has perform. Eighth must test running and operation of port facilities shall comply with the provisions of the regulations for port operation conditions for commissioning and operation, and the permit for port operation of the trial operation period.

Trial operating period of port projects eligible for acceptance, it shall go through the port project acceptance procedures.

Nineth port projects meet the acceptance criteria, legal seat of the port should be port administration authorities applied for acceptance.

For a built in port engineering design, staging, project Corporation has built and meet the acceptance criteria can be part of the proposed phased acceptance of port engineering applications. Tenth provincial Transport Department is responsible for the completion of the port project, organized by the port administration authorities, where the port of the preliminary acceptance.

After passing the initial acceptance by the port administration acceptance application to provincial transportation authorities.

11th port engineering completion approval authority should be received within 5 working days from the date of final acceptance of the application to review the application materials that do not meet the acceptance criteria shall be promptly returned and informed the reason; for meet the acceptance criteria, should accept an application for acceptance. Port Engineering completion approval or initial inspection should be completed within 20 working days from the date of receipt.

Cannot be completed within 20 working days after completion approval of the Department head, and can be extended by 10 working days.

12th project completion acceptance by the acceptance of the port sector organizations for quality supervision agency, the local maritime authorities, relevant administrative departments, relevant experts acceptance Committee.

Port engineering project legal person, design, supervision, construction units should participate in the work acceptance.

13th article port engineering completed acceptance of main according to is: (a) according to national about provides should has of port engineering construction project of approval, and approved, and record file; (ii) preliminary design, and construction figure design, and change design and the estimates adjustment, file; (three) tender file and the contract text; (four) main equipment technology specifications or manual,; (five) national and traffic Transport Department issued of technology specification and standard and the legal, and regulations, and regulations of related provides.

14th article port engineering completed acceptance of content is: (a) Review Port Engineering whether has national provides of approval file and the related procedures; (ii) check Port Engineering entity quality; (three) check Port Engineering contract performance situation, review about completed archives information; (four) check national and industry mandatory standard implementation situation; (five) approved terminal by parking grade, and Huff capacity and access port of channel grade; (six) check environmental protection, and labor security health, and fire, and archives, special acceptance situation;

(G) the check port works on audit of completion final accounts report; (h) check the implementation of the construction contract and (IX) quality grade is determined; (j) dealing with comments on the problems and engineering, (11), adopted and signed the book of project acceptance and identification of the port.

Section 15th of the acceptance, port engineering completion approval departments shall port identification project completion acceptance within 10 working days from the date of signing of the book, issued by the port certificate of completion.

16th unqualified acceptance of, and legal persons should be in accordance with the completion of the project acceptance Committee process for rectification.

After the completion of rectification, new port project completion acceptance should be applied for project legal person.

Upon completion of the 17th port project acceptance, shall, within the time prescribed by the State for the transfer of fixed assets and other related procedures.

18th by the provincial transport authorities and port local port Administration Department is responsible for the acceptance, completion and acceptance of completed, provincial transportation authorities and port should be acceptance by the port administration, where relevant to the Transport Ministry.

19th port project completion acceptance or acceptance is not qualified may not be officially put into use.

Article 20th project commissioning and operation of the legal persons who breach these rules, by location port administration authority to order the suspension of operation of the port.

21st port works without the acceptance of unauthorized use, the port local port administration authorities shall order to stop using the correct within may be fined a maximum of 50,000 yuan.

22nd article acceptance Department staff in the completion and acceptance of abuse of power, favoritism, bribe, shall be given administrative sanctions constitutes a crime, criminal responsibility shall be investigated according to law.

23rd final acceptance of the Committee members in the acceptance of negligence, malpractice caused heavy losses constitute a crime, criminal responsibility shall be investigated according to law.

24th line with the use of the World Bank, the Asian Development Bank and other international financial organizations or foreign government loans or aid in port engineering, lender, provider of funds for completion as otherwise provided can apply its provisions, but must not violate the People's Republic of China laws and regulations and social and public interests.

25th article of the project acceptance and identification of the port and the port the completion inspection certificate shall, in accordance with Department of transportation under the harmonized format. 26th article of the rules take effect on June 1, 2005, the Ministry of port construction projects (projects) completion and acceptance measures (base (1995), 155th) repealed simultaneously. These measures announced prior to the implementation of the relevant provisions are in contravention of these measures, from the date of implementation of this method to stop execution.