(Adopted by the 98th Standing Committee of the People's Government of San Sussi Province on 21 March 2007, No. 204 of the People's Government Order No. 204 of 21 April 2007 (Act of 10 May 2007)

Article 1 encourages and attracts social funding for the construction of new water resources, in line with the People's Republic of China Water Act, the State Department's decision on investment institutional reform, to develop this approach in the light of the actual province.
Article 2 refers to social funding as a result of non-governmental inputs, including funds raised by businesses, social organizations and individuals.
This approach refers to projects that plan new constructions to urban water, industrial water and agricultural water in the administrative areas of the province.
Article 3. The Government of the people at the district level should incorporate the construction of new water resources in the overall planning of socio-economic development in the region.
The management and supervision of the Ministry of Water Administration at the district level for the construction of new water resources. Other relevant sectors of the population at the district level are responsible for building new water resources works in accordance with their respective responsibilities.
Article IV
The construction of new water resources should be subject to the overall planning of watersheds and regional water resources, flood prevention planning, water resource development planning, water resource development planning and water functional areas, taking into account the benefits of downstream, shores and related areas, and to the full benefits of water resources.
Article 6. New water works are divided into three categories of public goods, quasi-publicity and business according to their functions and roles.
The construction of the main function of water conservation, drainage, drought, water and emergency water supply for urban residents is a public good project, which is the main function of water conservation, drainage, drought, urban water and emergency water supply tasks, as well as operating functions such as water supply, water power generation, tourism and nutrient development, and works for industrial water supply, services and hydropower.
Article 7. Public interest projects are dominated by government investment and encourage social funding to participate in investment-building.
The quasi-public projects are combined with government investment and social financing, with public investment in the public sector, such as flood prevention, drought resistance, etc., and the business component of water supply, hydropower, etc., is dominated by investment in social finance.
Investments in business projects are the subject of social funds and encourage businesses, social organizations and individuals to develop business in the form of sole-source, joint ventures, cooperation, joint ventures, shares, etc.
The proportion of investment in new water resources works is based on a combination of investment-sharing and efficiency-sharing. The proportion of government investment is implemented in accordance with the relevant national provisions.
The water treasury works are determined by the proportion of investment in government and social funds, which is dominated by agricultural irrigation, and the Government can absorb social funding in addition to investment based on the proportion of protected arsenal.
The Government investment can be reimbursed as part of its public interest as a profitable proportion of the profitable investments in the water supply, electricity generation, tourism, nutrient-driven business projects and good-birrigated public goods.
Article 9. New water construction projects are jointly planned by the Government to inform society that investors choose to declare their own projects. The business component of a public interest project should be made available to the community for the purpose of identifying investment actors and project legal persons. In order to ensure the benefits of the project's public interest, investors have the priority to develop other construction projects related to this project.
In the wake of the construction of the Hurricane project, investors can receive compensation from the river engineering maintenance fee.
New land for urban protection is owned by all countries, which can be used by more than the people at the district level for immigration resettlement or other public goods construction projects.
Water supply and electricity construction can be collateral for the expected yields and productive capacities of water prices and for bank loans and social financing.
The expropriation and immigration work of the new water resource construction project is carried out by the State. Removal and immigration resettlement funds, which are dominated by public investment, are included in the project investment estimates, in public interest projects that are dominated by drought. The Government's contribution is determined in proportion to the operational nature of water supply and electricity generation.
Article 11 is a Government-led project on new water resource construction, which is subject to the authority and procedures established by the State.
Article 12 Project units will be required to submit requests for projects to government investment authorities.
The application reports should include the following:
Prevention of flood security;
Engineering safety;
Water resources development use;
Ecological environmental protection;
Water worksb;
Other provisions of the law, legislation and regulations.
The elements of the protection of flood safety, water resource allocation and water construction should be validated by the provincial Government's water administration authorities and assessed the financial, technical and managerial capacities of the investors.
The provincial administration projects were approved by provincial investment authorities; the projects in the area of urban, district management rivers were approved by the municipal investment authorities.
Article 13, Investment in Social Funds, is not part of a new water-related construction project within the Government-approved portfolio of investment projects, and is in place.
The investors do not carry out new water resources construction at the work stage, and the water administration authorities at the district level are responsible for their remedial measures, with the duration of the period. Until such time as progress has not been met, the water administration authorities at the district level may commercially approve the sector and report to the provincial Government's water administration authorities to identify investors separately.
Article XIV projects that invest in social funds in the construction of new water resources that are pro-poor, drainage, agro-industry and quasi-public, can offer subsidies, credits, post-interest requests to Governments.
Article 15 project legal persons are responsible for the management, operation and maintenance of the works and shall not undermine the legitimate rights and interests of water users and other consumers.
The operation of the new water source works should be governed by the flood control movement control and the movement of water resources by water administration authorities.
Article 16
Article 17 Governments of more people at the district level should provide adequate compensation for the public good benefits generated by new water projects. The provision for the rehabilitation of water banks constructed by social funds should be subsidized by the current Government; the Government's movement response, drought resistance and ecological water should be compensated by the current Government for project operators by the agricultural irrigation water price.
The price of water for new water resources works in Article 18 consists of water production costs, costs, profits and taxes.
The cost of water production includes direct wages, direct materials, other direct expenditures and established asset charges, repairs, water resources costs, etc. during the normal water production process.
The cost of water production includes reasonable sales costs, management costs and financial costs incurred in the organization and management of water production.
Water-water profits include a reasonable gain approved by the water operators for normal water production.
The tax pay is payable by the water operators in accordance with national tax laws and may be credited for the water price.
The price of new water resources works in Article 19 is based on the principle of cost of compensation, reasonable benefits, good prices, fair burdens, and is adjusted in due course, in accordance with the changes in water costs, costs and market supplies.
The price of water for new water supplies constructed by social funds should result in the ability of water operators to compensate for costs, costs and repayments during the operation period, the ability to pay bonds and profitable. The period of operation has been determined on average in accordance with the length of the depreciation provided by the national financial authorities.
The price of water for new water resources works is governed by government guidance and different prices for different uses of water.
The price of water in the provincial and cross-construction areas is governed by the provincial price authorities in the same level of finance, water administration.
The price of water for new water supply works in urban and trans-zonal areas (markets, zones) is approved by the municipal price authorities in the area and by the water administration authorities.
The price of water for new water resources works in the counties (markets, zones) is approved by the same-level finance and water administration authorities.
Article 21, when the water operators apply for the development and adaptation of water prices, they should provide the price authorities with information on the operation and cost of water production, as well as relevant books, documents and other relevant information.
The new water source engineering water supply system should be introduced. Water operators must strictly implement national water price policies and no unauthorized change in water prices.
Article 2: The electricity sector should arrange for the sale of the new hydroelectric power plants attached to the work of the water source, which are approved by the price authorities in accordance with the prescribed procedures.
Article 23. Administrative organs and their staff do not carry out their duties in accordance with the law, abuse of their functions, impartiality, damage to the legitimate rights and interests of investors, are governed by the law by the superior authority or by the administrative inspectorate, which constitutes a crime, and are criminally criminalized by law.
Article 24, in violation of article 15 of this approach, provides that damage to the legitimate rights and interests of water users and other consumers shall be terminated by law by the administrative authorities of higher-level water at the district level; in the event of a serious fine of up to 50,000 dollars.
Article 25