Acceptance Of Soil And Water Conservation Facilities Of Development Construction Project Management

Original Language Title: 开发建设项目水土保持设施验收管理办法

Subscribe to a Global-Regulation Premium Membership Today!

Key Benefits:

Subscribe Now for only USD$40 per month.
(October 14, 2002 the Ministry of water resources announced, 16th) first to strengthen acceptance of soil and water conservation facilities of development and construction projects, according to the People's Republic of China soil and water conservation law and its implementing regulations, these measures are formulated.
    Second approach applies to the preparation of the report on the soil and water conservation plan of development and construction projects of soil and water conservation facilities of acceptance.
    Compiling water and soil conservation programmes report development and construction projects of soil and water conservation facilities for inspection, can be performed in accordance with the measures.
    Article development and construction projects of local people's Governments at or above the county level, where the water conservancy administrative departments, on soil and water conservation on a regular basis the implementation of the programme and supervise the implementation of soil and water conservation facilities to run checks.
    Article fourth after acceptance, the development project of soil and water conservation facilities, this project can be put into production or use.
    Fifth water Administrative Department of the people's Governments above the county level shall be responsible for acceptance of soil and water conservation facilities of development construction project implementation and supervision.
    Development and construction of water Administrative Department of the people's Governments above the county level in accordance with the project of soil and water conservation plan approval authority, responsible for the acceptance of soil and water conservation facilities.
    Competent administrative departments of local people's Governments at or above the county level water organizations complete acceptance of soil and water conservation facilities of materials, shall be water Administrative Department of the people's Governments at a higher level for the record.
    Sixth section the scope of acceptance of soil and water conservation facilities should be consistent with the soil and water conservation program and the approval document approved.
    Acceptance of soil and water conservation facilities of main contents: check whether the water and soil conservation facilities design, construction quality, investment and management responsibility for implementation, evaluation of effect of control soil and water loss, dealing with comments on the problem. Seventh article soil and water conservation facilities meet following conditions of, party can determine for acceptance qualified: (a) development construction project soil and water conservation programme approval procedures complete, soil and water conservation engineering design, and construction, and supervision, and financial spending, and soil erosion monitoring report, information complete; (ii) soil and water conservation facilities by approved of soil and water conservation programme report book and design file of requirements built, meet subject engineering and soil and water conservation of requirements; (three) governance degree, and stopped slag rate, and vegetation recovery rate, and Soil erosion control, such as indicators meet the approval of soil and water conservation plans and approval documents and the requirements of national and local technical standards and (iv) soil and water conservation facilities have normal operating conditions, and sustainable, secure, and efficient operation, meet the delivery requirements.
    The management of soil and water conservation facilities, maintenance measures implementation. Eighth in completion phases of the project development and construction, the construction unit shall, together with the unit of the soil and water conservation program, based on the approval of the soil and water conservation plan reports, design documents and quantities, check on the completion of soil and water conservation facilities, preparation of the summary report and the implementation of soil and water conservation scheme of soil and water conservation facility completion of a technical report (preparation of the outline, see annex).
    Meet the acceptance criteria set out in article seventh, before approving the conservation authorities apply for acceptance of soil and water conservation facilities.
    Nineth water Administrative Department of the people's Governments above the county level shall, within 3 months from the date of receiving the application for acceptance of completed inspection.
    Article tenth water Administrative Department under the State Council is responsible for the acceptance of the development and construction of projects, technical assessments should be conducted.
    Provincial water conservancy administrative departments responsible for acceptance of the development and construction of the project, can be performed according to the specific reference to the provisions of the preceding paragraph.
    And County development and construction projects of water conservancy administrative departments are responsible for acceptance, you can direct acceptance.
    11th technical assessment by Advisory evaluation of soil and water conservation ecological building qualified institutions.
    Undertake technology assessment agencies should organize aspects of soil and water conservation, water, plant, financial and economic experts, according to the approved water and soil conservation plan, document and assess the acceptance standards for soil and water conservation of soil and water conservation facilities, and to submit an assessment report. 12th water Administrative Department of the people's Government at or above the county level shall receive upon acceptance of the application, shall organize on behalf of the relevant units and experts to set up inspection groups, based on acceptance of applications, information on the results and check construction site, acceptance of views put forward.
    Among them, these measures are in accordance with article tenth, you need to conduct a technical assessment of development and construction projects, the construction unit acceptance of submitted applications should be accompanied by a technical assessment.
    Employer, the soil and water conservation programming, design, construction units, supervision, monitoring, reporting entities shall participate in the on-site inspection.
    13th acceptance more than two-thirds must be approved by the inspection group members agreed that acceptance by the group members and representatives of the been and acceptance signing the acceptance of the outcome document.
    Article 14th on the acceptance of the project, the water conservancy administrative departments should timely acceptance procedures, issue a certificate of acceptance of soil and water conservation facilities, and development as an important basis for completion of construction projects.
    Projects to unqualified acceptance, check the water conservancy administrative departments shall order rectification unit until acceptance.
    15th stage or put to use building and stage of development and construction projects, the appropriate water and soil conservation facilities should be phased acceptance in accordance with these measures.
    Article 16th after the acceptance and use of soil and water conservation facilities, employer or management should strengthen the management and maintenance of soil and water conservation facilities, ensure the safe and effective operation of soil and water conservation facilities.
    17th article in violation of these regulations, built of soil and water conservation facilities, without acceptance or unqualified acceptance, main part of the project has been put into operation, by approving the soil and water conservation plan of construction project of water conservancy administrative departments ordered to finish building the project and the acceptance formalities, fails to go through, it may impose a fine of less than 10,000 yuan.
    Article 18th development costs related to the acceptance of construction project of soil and water conservation facilities, borne by the project owner.
    19th article this approach by the Ministry of water resources is responsible for the interpretation.

    20th the measures take effect on December 1, 2002.
    Annex 1: summary report outlining the implementation of soil and water conservation plan, objective-related engineering, soil and water conservation programme approval and implementation process of introduction.
    Second, the main part of the project and the survey of soil and water conservation engineering 1, the main part of the project the main technical and economic indicators, the main construction, relevant approval and the process of design files.
    2, water and soil conservation plan approval process, construction, construction time, the investment budget, and soil and water conservation measures identified in the programme design and implementation, adjustment. Three 1, construction management, organization and leadership.
    Include soil and water conservation in leadership and management, soil and water conservation engineering, design, construction and supervision units. 2, rules and regulations.
    About soil and water conservation projects during the construction of established regulations, rules, methods. 3, supervision and management.
    Water Conservancy administrative departments at all levels and soil and water conservation supervision and Management Department inspection and supervision. 4, the construction process.
    Including soil and water conservation project bidding process, contract and its implementation, procurement and supply of construction materials. 5, construction supervision.
    Including overseeing planning and implementing regulation, supervision, organization, personnel, testing methods, the quality of soil and water conservation engineering, scheduling, control of investment. 6, project investment.
    Including approval of soil and water conservation investment budget, funding, annual arrangement, adjustment of budget estimates and expenditure. 7 to complete major projects.
    Including type of measure and quantity changes, the actual completion of soil and water conservation engineering, plants, temporary protective works, such as the type, quantity, volume decreases and causes analysis and design engineering.
    Four, experiences, problems and suggestions on soil and water conservation program the main experiences of the implementation process, there are problems, and recommendations for future management. Five transfer, use, operation and management of soil and water conservation engineering, maintenance responsibilities, ways of management.
    Run-time monitoring of soil and water conservation mandates.
    VI, annex 1, soil and water conservation program and the approval document.
    2, water and soil conservation engineering design approval documents.
    3, soil and water conservation engineering design change approval.
    4 investment in place and usage instructions.
    5, relating to the supervision and inspection of the water conservancy Administrative Department.

    6, the principal part of the project master plan.
    Annex 2: acceptance of soil and water conservation facilities of a technical report prepared outlining a soil and water conservation, and a brief description of the implementation of the programme description.
    II, 1, approved the scope of control soil and water loss prevention and control responsibilities compared with the actual responsibilities, causes of changes.
    2, disturbance of land area, the control rate.
    C, engineering design of soil and water conservation scheme of soil and water conservation measures, design in the design report, major design changes. Four, 1, quantities and progress of the construction.
    Controlling the number of projects completed, implementation time, compared with the approved amount of program implementation, project and analysis of its causes. 2, construction quality management.
    Quality assurance system of construction, employer and the engineer's quality control system, construction accidents and their treatment. 3, engineering-building event.
    Includes documents, larger design changes, the contract agreement, important meetings, and so on. 4, closing.
    Number of approved projects and investment, the construction contract price and the actual settlement price comparison and analysis of reasons for the changes. 1, the project is divided into five, engineering quality.
    Unit project of soil and water conservation engineering, Division of engineering, Division of engineering. 2, quality inspection.
    Quality inspection methods of supervision engineers, quality oversight body, the test results. 3, quality assessment.
    Preliminary acceptance determines the quality level of units on the overall engineering quality evaluation of soil and water conservation. VI 1, initial operation and effectiveness evaluation of engineering projects.
    Soil and water conservation project is completed run, its security and stability, after the storm intact, engineering, plant maintenance replanting. 2, the project benefits

    (1) soil and water conservation. Control soil and water loss area in the test run, controlling soil and water loss area and the level of governance, project area of soil and water loss intensity values.
    Amount of retaining waste soil, gravel, slag, slag block rate, excavation, removal of camp after levelling, lining, quantity of vegetation restoration. (2) changes in vegetation.
    Building before, during, and after construction area of forest-grass vegetation, vegetation index. (3) land management and recovery of production conditions.
    Land remediation rate, number of cultivated land occupied by construction of a temporary recovery, land productivity, recovery. (4) monitoring of soil erosion. According to specific soil and water loss monitoring reports made during construction, the project runs in erosion, state-mandated limits are met.
    Effects on runoff and sediment transport in the water, soil erosion hazard. (5) the evaluation.
    Main engineering construction of soil and water loss and ecological environment of actual impact scope, extent, timing, and control of soil and water conservation engineering, combat effectiveness.
                                                                                                                Seven, attachments and related information after completion of the 1, Figure 2, the scope of soil and water and soil conservation engineering design documents 3, 4, engineering construction contracts, acceptance of soil and water conservation report quality assessment report 5, special monitoring soil and water loss reports 6 acceptance Figure 7, soil and water conservation, soil and water conservation facilities in the course of implementation of image data