276. Regulation of the Board of Management of E-Control, which changes the Gas Market Model Regulation 2012 (GMMO-VO Novelle 2015)

Due to § 41 Gaswirtschaftgesetz 2011-GWG 2011, BGBl. I n ° 107/2011 in the version of the Federal Law BGBl. I No 174/2013, iVm § 7 para. 1 Energy Control Act-E-ControlG, BGBl. I No 110/2010 in the version of the Federal Law BGBl. I No 174/2013, shall be arranged:

The regulation of the Board of Management of E-Control on gas-market model regulations (Gas-Market Model Regulation 2012), BGBl. II No. 171/2012 in the version of the GMMO-VO Novelle 2014, BGBl. II No 234/2014, shall be amended as follows:

1. In accordance with § 2 (1) Z 16a, the following Z 16b shall be inserted:

" 16b.

"Regulation (EU) No 984/2013", Regulation (EU) No 984/2013 of the Commission of 14 June 2013. October 2013 establishing a network code on mechanisms for capacity allocation in transmission networks and supplementing Regulation (EC) No 715/2009 of the European Parliament, OJ L 327, 22.12.2009, p. No. OJ L 273, 15.10.2013; "

2. § 4 reads:

" § 4. (1) Capacity products shall be bundled in accordance with the requirements of Regulation (EU) No 984/2013 at the boundary coupling points where transmission networks are connected to each other.

(2) Transmission system operators may also offer bundled or unbundled capacity with allocation requirements in order to maximise the supply of bundled capacity. "

3. In § 6 (1), after the word order "in a transparent and non-discriminatory procedure" replaced by the phrase "according to the requirements of Regulation (EU) No 984/2013" .

4. Section 6 (3) is deleted.

5. § 8 reads:

" § 8. At the limit coupling points, the shares of the annual technical capacity referred to in Article 8 (6) to (8) of Regulation (EU) No 984/2013 shall be withheld and shall not be available at the earliest in the annual auction for annual capacity and/or annual capacity, respectively. to offer quarterly capacity. Shares exceeding this minimum level may, in accordance with the results of a needs survey to be coordinated by the transmission system operators, and after consultation of adjacent transmission system operators, may be subject to a limit coupling point proposed. This proposal shall be approved by the regulatory authority. Capacity contracts existing at the date of entry into force of this Regulation shall be excluded from the application of this provision. "

6. In Section 9 (2), the word order shall be "The Operator of the Online Platform" replaced by the phrase "The Online Platform" and after the phrase "and the trade of secondary capacity" the phrase "according to the requirements of Regulation (EU) No 984/2013" inserted.

7. § 9 (3) deleted.

8. In § 9 (6), after the word order "the requirements of this Regulation" the phrase "and Regulation (EU) No 984/2013" inserted.

9. § 10 (2) shall be deleted.

10. In Section 11 (3), the unit shall be "kWh" replaced by "kWh/h" and after the phrase "Day Ahead-" the phrase "and Within Day" inserted.

11. In Section 11 (5), the word "Exceeds" replaced by the phrase "Over-or Fallen Below" and the phrase "Part crossing the allowed area" replaced by the phrase "the permissible range above or below the threshold" .

12. § 11 (9) and (10) shall be the order of the word "pursuant to § 6 (3)" is deleted.

13. In § 13 (3), at the end of the sentence "Capacity extensions shall be dealt with in the order of their arrival in time." .

14. In § 14 (3), after the second sentence, the sentence shall be: "Network access contracts with operators of storage and production facilities shall be concluded in accordance with the requirements of the distribution area manager, in so far as these contracts have an impact on the management of the distribution system." inserted.

15. In § 15, the following paragraph 4 is inserted after paragraph 3:

"(4) The distribution area manager shall book the necessary capacity at the limit coupling points in the distribution network, through which parts of the market area are exclusively fed through an adjacent market area."

16. In § 16 (1), after the second sentence of the sentence " If storage undertakings do not comply with the request of the network operators to book capacity within the reasonable time limit set by the network operators, the last-booked capacity of the respective storage company for the following year shall be: on the basis of this. " inserted.

17. In Section 16 (1a), after the word order "by means of a network access request" the phrase "for the duration of the contract of reserved capacity" inserted.

18. In § 17 (1), after the second sentence of the sentence " If producers and producers of biogenic gases do not comply with the invitation of the network operators to book their capacity within the reasonable time limit set by the network operators, the last booked capacity of the respective producer or producer shall be the same. To base the producer of biogenic gases for the following year. " inserted.

19. In § 26 (6), the fifth sentence reads:

"The calculation shall take place on the basis of the general conditions of the market area manager, taking into account the overall status of the system in the form of the balance of the market area."

20. In § 26 (6), the sentence shall be: " Per 1. This structural contribution will be set at a maximum of 0.4 cent/kWh in January 2013. " is deleted.

21. In § 27 (1), at the end of the sentence "Consumption volumes arising from the use of network services without allocation of the counting point to a balance sheet group shall be included in the special balance sheet group for distribution networks." inserted.

22. In § 37 (4), at the end of the sentence "Consumption volumes arising from the use of network services without allocation of the counting point to a balance sheet group shall be included in the special balance sheet group for distribution networks." inserted.

23. In accordance with Section 47 (9), the following paragraph 10 is added:

" (10) § 2 para. 1 Z 16b, § 4, § 6, § 8, § 9 and § 26 paragraph 6 in the version of the GMMO-VO Novelle 2015, BGBl. II No. 276/2015, will enter into force on 1 November 2015, 6 a.m. All other provisions of this amendment will enter into force on 1 October 2015, 6 a.m. "

Annex 1, point III.1 (3) reads as follows:

" (3) The distribution system operator and the distribution area manager shall only be obliged to take part in the application and the counter-production of the capacity extension contract. the distribution system operator and the upstream network operators and the distribution area manager shall not be obliged to take the necessary development measures until the applicant has concluded the capacity extension contract within the The distribution system operator and the time limit set by the distribution area manager have to be legally signed and the conditions set out in the capacity extension contract-such as (b) the provision of security benefits-has been complied with within the time limit laid down. In the event of a non-timely, legally binding signature of the capacity extension contract or if the fulfilment of the conditions set out in the capacity extension contract is not fulfilled within the prescribed period, the capacity extension shall lose its effectiveness. "

25. In Annex 1, point III.1 (4), after the word order "the applicant" a dash and the phrase "the distribution area manager" inserted.