Key Benefits:
469. Regulation of the Federal Minister for Economic Affairs, Family and Youth, with which the transfer prices for small hydropower as well as for other green electricity for the calendar year 2011 are determined (transfer price-regulation 2011)
Due to § 22b, Section 1 of the Ecoelectricity Act, BGBl. No 149/2002, in the version of the Federal Law BGBl. I No 104/2009, shall be ordered:
§ 1. The following transfer prices shall be determined for the calendar year 2011:
1. |
for electrical energy from small hydropower plants |
8.09 Cent/kWh; |
||||||||
2. |
for electrical energy from other green power plants |
12.76 cent/kWh. |
§ 2. This Regulation shall enter into force 1. Jänner 2011 in force.
Mitterlehner