Advanced Search

Subscribe to a Global-Regulation Premium Membership Today!

We are constantly working to improve the site, and to add more laws to our database. If you are receiving value from using our site please consider signing up for a subscription to support the site and to get many additional benefits for you.

Key Benefits:

  • Unlimited Searches
  • Weekly Updates on New Laws
  • Access to 5,345,848 Global Laws from 110 Countries
  • View the Original Law Side-by-Side with the Translation
  • No Ads

Subscribe Now for only USD$40 per month.

(You can close this ad by clicking anywhere on the page.)

WAC 344-16-015: Permits-Fee-Conditions of issuance-Duration


Published: 2015

Subscribe to a Global-Regulation Premium Membership Today!

Key Benefits:

Subscribe Now for only USD$40 per month.
Print







WACs > Title 344 > Chapter 344-16 > Section 344-16-015











344-16-010    

344-16-020







No agency filings affecting this section since 2003







WAC 344-16-015









Permits—Fee—Conditions of issuance—Duration.









Drilling permits for offshore sampling shall be issued upon the payment of a fee of $50.00. No permit shall be valid for a period longer than one year. As a condition of issuance, each permittee shall agree to pay to the supervisor, to defray the cost of observers required by this resolution;
(1) For each necessary observer, the sum of $407.00 monthly in advance for each month or portion of the month during which drilling operations are to be conducted; and
(2) Such additional sum as equals the amount by which actual costs for observers exceed the sums paid in advance, said additional sums to be paid to the supervisor upon receipt of a statement therefor from the supervisor.
[Resolution No. 3, § 3, filed 6/28/63.]