Advanced Search

Electricity Act (1997:857)

Original Language Title: Ellag (1997:857)

Subscribe to a Global-Regulation Premium Membership Today!

Key Benefits:

Subscribe Now for only USD$40 per month.
Chapter 1. Introductory provisions



The scope of the law



paragraph 1 of this law provides for electrical installations, if

in some cases, electricity and electrical safety. Law (2008:265).



Definitions



2 section With electrical installation referred to in this Act a plant

with the component specific articles for production, transmission

or use of electricity.



If different parts of one and the same plant have differing

holders, each such part as a separate facility.

If a facility for use of electricity is connected to one or

several other such facilities and are the plants in the same

holder's hand, the plants are regarded as one and the same

facility.



paragraph 3 of the electrical installations are divided with respect to

hazard rate in power plants and

weak-current installations.



The detailed arrangements for this Division will be announced by the Government

or the authority, as the Government determines.



4 section With network operations intended to make electrical

starkströmsledningar available for the transmission of electricity.

network operations also include the design, construction and maintenance of

wiring, electrical switchgear and transformer stations, connecting

electrical installations, measurement and calculation of the transferred

power and energy and other activities necessary to

transmit power to the electrical grid.



With the connection of the electrical installations means also

reconnection of an existing facility and increase

contractual effect in input-or outtake.

Law (1999:770).



4 a of With riser, a pipe with a voltage of 220

kilovolts or more.



With regionledning, a line which is covered by a

Online concession for the line and where the voltage is less than 220

kilovolts. Law (2009:892).



4 (b) repealed by laws (2008:265).



section 5 With the power tariff refers to the fees and other terms of

transmission of electricity and for connection to a line or a

grids.



5 a of the revenue framework referred to in this law, the total revenue

a nets concessionaires at most may collect from network operations

during a regulatory period. Law (2011:712).



5 (b) § With backbone companies referred to in this law, the holder of the

Online concession for the backbone or the majority thereof.

Law (2011:712).



section 6 with the electricity supplier is the professional supplier of electricity

produced by himself or someone else.



An electricity users who import electricity shall fulfil the obligations

incumbent on a utility company.



The Government may provide for derogations from the first subparagraph of

activities within a building or limited area.

Law (1999:770).



section 7 of the Government shall designate an authority which shall deal with the

matters under this Act or under the regulations

issued by virtue of the law is on the power authority.

Law (1999:770).



Chapter 2. Online concession, etc.



General information about the network licence



§ 1 an electric heavy duty may not be built or

used without permission (network licence). To the construction of a

the guidance also includes excavation, logging, or

similar measures to make way for the lead.

Team (2013:207).



1 a of the power authority hears questions about network concession pursuant to

in this chapter, unless otherwise specified.



(B) in section 1, paragraph 4 (a), paragraph 5 of the second paragraph, paragraph 11 (a)

subparagraph (a), section 15, paragraph 15 (b), 15 (j) section,

16 section, fourth paragraph, paragraph 16 (a), section 17 of the third

the paragraph and section 18, third paragraph, there are provisions relating to

the Government hears questions about network concession in some cases.



The Government may also consider such issues if the network concession

has importance to the military, about the armed forces.

The power authority shall communicate in such a case, the question of

the review authority to the Government for decision.

Team (2013:207).



1 b of the Government hears cases on the grant of

network licence, if the matter relates to a foreign connection or

in case there is a question about permission to expropriation

that should be considered by the Government. Team (2013:207).



section 2 A network licence shall relate to a management team with mainly

fixed route (network concession line) or a

wiring in a given area (network licence for

area).



In a decision on network concession area to a maximum

allowable voltage of the grid are specified. When such a

voltage is determined, the following shall in particular be taken into account:



1. the excitement that can be predicted, may be needed to operate the

grid,



2. the impact on the environment in a future expansion of the network,



3. ensuring an economically justified

development of the network, and



4. consequences for affected customers.

Team (2013:207).



section 3 a transformer or a switching station to be connected

to one or more new lines for which

Online concession for the line should not begin until the

Online concession has been granted for the construction of at least one of the new

the wires.



section 4 of the Government may provide for exceptions from the

the requirement on net concession pursuant to § 1 and the ban to begin

build according to paragraph 3, in the case of some kind of wiring or

stations or lines or stations within

some areas. Such a provision should not, however, refer to

foreign relations.



The power authority shall, in each case, after the application of

Anyone who intends to construct or use an electric

heavy duty, leave a binding statement on whether

the executives covered by regulations issued pursuant

of the first paragraph.



Application for a binding information may also be made by the holder

of net concession for the area, where the management or

the wires are located. Team (2013:207).



4 a of the power authority may grant a derogation in an individual case

from the requirement on net concession under section of wires that were

introduced on 1 January 1998. Such an exemption decision shall

refer to a specific time, which may be extended.



The Government hears questions about exempting, on

the case relates to a foreign link. Team (2013:207).



§ 5 the power authority may, if there are special reasons, allow

to an electric heavy duty may be built even before the

the necessary network concession is issued, or that a

transformer or switching station may be built despite the

as specified in section 3. When such a leadership is ready to be

use, power authority may grant to the lead until

Furthermore, for a maximum of three years pending the submission of the application for

Online concession proceed to judgment.



The Government is examining the issues of consent, if the matter relates to a

foreign relations. Team (2013:207).



Conditions for the grant of the power to licence



6 § Network concession may be notified only if the facility is

suitable from a general point of view.



section 7 A network licence for line must only if there are

special reasons for a line which is intended for

voltage which does not exceed the maximum voltage for the

areas with net concession concerned by the management.



section 8 a concession for the line must not conflict with a

detailed plan or area regulations. If the purpose of the plan

or provisions not countered, may be minor deviations

be made. Act (1998:854).



8 a of when assessing issues of communication of network licence

for the line, the provisions of 2-4. and Chapter 5. paragraph 3 of the

the environmental code, shall apply.



An environmental impact assessment shall be included in an application for

Online concession for the line. For the procedure, the requirements for

environmental impact assessment as well as plans and planning documents

apply to Chapter 6. the environmental code.



Despite what is stated in the first and second subparagraphs need questions

that has been tried in a case or case for authorisation under

the environmental code not be re-examined in case of net concession.

If in the case or the case of a permit under the environmental code

There is an environmental impact assessment that describes the direct

and indirect effects on human health and the environment

the line can cause, there need not be any particular

environmental impact assessment (EIA) in concession case.

Law (2010:893).



8 b of the Government may provide for exceptions from the

the requirement for environmental impact assessment in accordance with paragraph 8 (a)

subparagraph for facilities whose environmental impact is likely to be

less significant. Team (2013:207).



§ 9 Network concession area may be notified only about the area

represent a given network operations appropriate device.

Network licence shall not be granted for an area that is wholly or

overlap with another concession area.



10 § Network concession may be granted only from public

point of view is suitable to practice network activities. Online concession

area may be granted only to that which is appropriate to

conducting network activities within the requested range.



Network licence for a foreign marriage may be granted and

held by only a backbone enterprise or a legal person

where an undertaking has a dominant influence.



NET other concession may be granted if the lead is of the

less significance to the total transmission network to

the rest of the world. Law (2011:712).



Conditions for network licence



section 11 A network licence shall be accompanied by the conditions needed

in order to protect public interests and individual rights as well as with the

conditions for the plant's performance and utilization required by

safety reasons or to otherwise protect human health

and the environment against damages and inconveniences and promote a long-term

good management of soil and water, and other resources or

as for other reasons is required from a general point of view. Act (1998:854).



11 a of A network licence, for their validity to be made dependent on

to the holder of the concession set security for


the cost to remove the pipe and associated facilities

and to take other measures to restore. The State,

municipalities, county councils and local authorities do not have to ask

Security.



If it can be assumed that the security is no longer

sufficient, the Government, or, after the Government's

authority, the power authority to decide on additional security.



In terms of the nature of the security concerns Chapter 2. section 25

the enforcement code. The security shall be examined by the authority

examining the issue of net concession and kept by the County Administrative Board.

Act (1998:854).



section 12 of the boundaries of a network licence for the area may be changed by

the power authority, if required for an effective

network operations and it can be done without extreme inconvenience to the

the concession holder.



In Chapter 5. 25 and 27 §§ contains provisions on the allocation of

the revenue framework for amending the concession boundaries.

Law (2009:892).



Network licence validity



section 13 A network licence is valid until further notice.



An online concession line may be confined to apply to

a certain amount of time, if the applicant so requests or if it otherwise

special reasons. Period may in such cases be

up to fifteen years.



The period of validity of a concession for the line announced

following the withdrawal of a concession pursuant to section 18 of the

the first subparagraph of paragraph 2 or 3 shall not extend beyond the

validity period of the CRL network concession. Team (2013:207).



Extension of the duration



section 14 A network licence for the line, which has been issued for a

certain period of time in accordance with section 13, second paragraph, may be extended by up

to fifteen years after the application of

Online concession holder. If the applicant so requests, the

decided to network the concession instead shall apply until

on.



During the examination of an application within the meaning of the first subparagraph shall apply

6-8 a, §§ 10 and 11.



An application referred to in the first subparagraph shall be made not later than two years prior to

the concession period. Online concession valid until its

that the application has been examined.



If there are special reasons, get a network licence

period of validity may be extended even if the period of validity has not expired

out. Team (2013:207).



section 15 if there are special reasons may, on the application of

Online concession holder, the validity of a network licence

for the line, which has been granted for a certain period of time, be extended

temporarily on unchanged terms. A temporary extension

may be granted for a maximum period of five years.



A case referred to in the first subparagraph may be settled without any

other than the applicant had the opportunity to be heard.

Team (2013:207).



15 a of the Government hears cases relating to the renewal of a

network licence validity period in accordance with section 14 or 15, if the case

refers to an external link. Team (2013:207).



Review of net concession



15 b of a concession for the line that is valid until further notice,

be reconsidered in terms of managerial stretch, permissible voltage

and conditions.



A review may be made only forty years after the

Online concession was announced. If network concession valid until

Furthermore, after a decision under section 14, first subparagraph, second

the sentence, however, the time is counted from the date of the decision.



Government to reconsider a network licence relating to a

foreign relations. Team (2013:207).



15 c § Network Administration may decide that a review under

15 (b) § shall be initiated at the request of network concessionaire

or a municipality or a County Board of Directors concerned by

Online concession. The power authority may also decide to initiate

a review on its own initiative.



An application for review shall be submitted to the authority.

Team (2013:207).



15 d § A review under section 15 (b) should be initiated, if a

reconsideration is warranted, taking into account the interests of the

specified in 2-4 Cape. the environmental code, or any other important

general interest.



A review should also be initiated on application by

network concessionaire, if a review is justified in order to

ensure an efficient and effective operation of the

network operations. Team (2013:207).



15 e § If the power authority decides that a review under section 15 b

should be initiated in the case of a network licence relating to a

international relations, the authority shall investigate the matter and

then with private opinion refer the case to the Government's

trial. Team (2013:207).



15 f § A review under section 15 (b) should refer to the following requirements:



1. that the facility is appropriate from a general standpoint,



2. that the management is intended for such a voltage as specified in

section 7, and



3. to power the concession complies with requirements of section 8.



Online concession may review be reconciled with such conditions

as set out in section 11. Team (2013:207).



15 g § in the case of a review under section 15 (b) applied 2-4 Cape. and

Chapter 5. section 3 of the environmental code.



Network concessionaire shall establish a

environmental impact assessment for a reconsideration. For

the procedure, the requirements of environmental impact assessment as well as

plans and planning documents apply Chapter 6. the environmental code.



The Government may provide for exemptions from the requirement

on environmental impact assessment in accordance with the second subparagraph of

facilities whose environmental impact is likely to be less

significant. Team (2013:207).



15 h § Network concessionaire shall provide the investigation

needed for the review.



The power authority may submit to the network the concessionaire to submit

the investigation is needed. Such a decision on the injunction

may be subject to a penalty. Team (2013:207).



15 paragraph Since a review under section 15 (b) have been made, a

such a review shall be made on the new first forty years after decision

in the previous review the matter. Team (2013:207).



Modification of terms and conditions



15 j § criteria for a network licence may be amended or repealed

on application of net concession holder.



The Government is examining the issues referred to in the first subparagraph, if the case

refers to an external link. Team (2013:207).



15 k § criteria for a network licence for the area will also receive

without the application be reconsidered since twenty-five years after the

that condition last announced. Online franchise will then unite

with the new conditions. Team (2013:207).



Transfer of net concession



section 16 A network licence may not be transferred without permission.



During the examination of an application for the transfer of net concession

section 10 shall apply. The same applies for the examination of an

application for network licence in respect of the revocation of a

network licence under section 18, first paragraph 2 or 3.



If a revenue framework for transfer shall be allocated in accordance with Chapter 5.

paragraph 25, are allowed to transfer not

be submitted unless the Division has been approved under section 26 of the first

paragraph, the same chapter.



The Government is trying cases for authorization referred to in the first subparagraph,

If the case relates to a foreign link. Team (2013:207).



Completion of the guidance



16 a of a holder of a concession for the line to be last

five years after the decision to notify network licence

res judicata have completed the leadership program

Online concession relates.



If there are special reasons, time of completion

may be extended upon application of power the concessionaire. A decision

If the extension will be granted for a certain period of time.



The Government is trying cases for extension to other

subparagraph, if the matter relates to a foreign link.

Team (2013:207).



16 b of a holder of a concession for the line to be last

three months before the time of completion in accordance with section 16 (a)

runs out to the power authority to account for the extent to which

the pipeline is completed. Team (2013:207).



16 c § holder of a concession area, to

the power authority to notify the lines with a higher voltage than

20 kilovolt network concessionaire has built in the area.

The notification shall be made not later than six months after the lead

been finalised. Team (2013:207).



The right to take the leadership from use



section 17 a concessionaire may occasionally take a leadership

covered by network concession line. Management

must not, however, without permission to be out of service for longer than

a total of three years.



Conditions referred to in the first subparagraph shall be granted if it is

inappropriate from the point of view of electricity supply. A State must

be granted for a certain period of time.



The Government is trying cases for authorization referred to in the first subparagraph,

If the case relates to a foreign link. Team (2013:207).



Withdrawal of the network licence



18 § A network licence shall be revoked in whole or in part,



1. If a pipeline or a pipeline network is no longer needed for

a secure electricity supply,



2. If the State, with the backing of the chapter 1. section 5 of the Act (2004:875) if

management of certain electrical installations, fix

in the lines provided with power concession,

or



3. If the power concession holder no longer satisfies the conditions laid down

According to the first sentence of the second paragraph of section 10 for holding

Online concession.



A network licence may also be revoked in whole or in part, if

Online concession holder has not completed a leadership in law

time in accordance with section 16.



Asked if the withdrawal of a licence relating to an

international relations are being assessed by the Government. Team (2013:207).



Recovery actions



Article 19 If a network licence expires, is the last

had the network concession required to remove lead with

related facilities and take other steps

restore, if necessary, from the public or individual

point of view.



When the nets franchise expires, the power authority

fix concessionaire obligations under the first

paragraph.



If the last have had network concession does not comply with its

obligations under the first subparagraph, the power authority


submit to him under penalty to fulfil the obligations or

decide that measures shall be taken on the concessionaire

the expense. A decision on the measures to be taken at

the concessionaire's expense may be executed.



section 20 If an electric heavy duty has been built without

network licence, where required, shall submit to the power authority

pipe holders to remove management and associated

facilities and take other measures to restore, if it

needed from the General or individual point of view.



If management's owner fails to fulfil the obligations imposed on

first subparagraph, the power authority, submit to him under penalty of

fulfil the obligations or decide that the measures shall

taken at the expense of the concessionaire. A decision to

measures shall be taken at the expense of the concessionaire shall

enforced.



section 21 On someone else's land needs to be used for such

recovery operations referred to in section 19 or 20

the power authority may decide that the access to the land to be provided

during a certain period of time.



Recovery actions will be carried out in such a way that the minimum damage and

infringement caused. Buildings may be erected or roads be built

only if the land owner and the holder of access rights or

easements in respect of the land agreed to it or the power authority

given permission for the operation. Permission may be granted only if the

the measure is strictly necessary to

recovery actions will be taken.



If the recovery actions causing damage or intrusion,

shall receive compensation for this is provided. Action for compensation brought

at the land and Environment Court in whose area the ground or

most of this is. Law (2010:935).



Transfer of management in certain cases



section 22 of the owner of an electrical line that has been drawn up

in the area of an existing public roads, private road which is held

open to traffic, rail, Metro or tramway or channel

or other such water road (route) is required,

by change of carriageway, take the steps with the cord that

needed for the change of the traffic route.

Pipe holder shall bear the costs related to these

measures.



section 23 Of the objective of management is to transfer electricity for lighting

by a public road, the road authority shall pay the management's

holders for the costs referred to in section 22. If management also

serve different purposes, compensation shall be determined after what

that is reasonable in the circumstances.



If, in the cases referred to in section 22 has taken measures with a

the direction where this crosses a road, the managing

traffic ranks for the cost of replacing the wire holders

other than moving the pole, rod or similar

device in the traffic area of trail.



section 24 If a line has been drawn up in the territory of a

existing road leading to increased costs for traffic trail

maintenance, the holder of the management replace these increased

costs.



section 25 of the labour code on a line which is located in the area of

other road than public roads may have an impact on road safety

or if the work involves greater intervention in the traffic route, the

be performed after the instructions of managing traffic ranks

or by his. Management's owner is responsible for

the cost of the work, subject to the provisions of section 23.



In the case of work with the leadership in the area of public roads applies

Special provisions.



section 26 of the holders of a high current wiring within the area of

rail to replace the cost and damage that may be

added the railway undertaking by that management is drawn up,

used or maintained.



Chapter 3. Network activities, etc.



Introductory provision



§ 1 a company that conducts network operations is responsible for the operation

and maintenance and, if necessary, developing its pipeline network

and, where applicable, its connection to other

grids. The company is also responsible for its pipeline network is

secure, reliable and efficient and that in the long

term to meet reasonable demands for the transmission of electricity.

Act (2005:404).



Separation of network activities



1 a of A legal person who carries out the network activities must not

carry out production of or trade in or A backbone enterprises

may not engage in production of, or trade in

natural gas.



Notwithstanding the first subparagraph, the production of electricity, will be carried out

together with network activities by the same legal entity, if

production



1. exclusively to cover network losses, or



2. place temporarily in order to replace the lost electricity at

power cuts. Law (2011:712).



1 b of a company engaged in network operations and included in



a group whose combined electricity networks have at least 100 000 users

going to their organization and their decision-making be

away from companies engaged in the production of, or trade

with electricity. electricity users must, of course, the one under

agreement with the operator of network operations take out electricity from

the electricity grid in one or multiple exit points.



In an Internet company referred to in the first subparagraph may not be a

Board Member, Executive Director or authorised signatory

at the same time be a Board Member, Executive Director or

signatory in a company engaged in the production of or

trading with El. Law (2009:1045).



1 c § an Internet company as referred to in paragraph 1 (b),

not grant employees in management salaries or other

benefits based on earnings in those parts of the

the Group engaged in the production of, or trade in electricity.

Law (2009:1045).



1 d section network undertakings referred to in paragraph 1 (b) of the first subparagraph shall

like its parent company, ensure that the power company has the

actual decision-making power which is independent in relation

to the rest of the group with respect to assets

as the power company needs to operate, maintain and

development of the network.



It provided for in the first subparagraph shall not prevent the

online business owner has such visibility and exerts such control

required to ensure a reasonable return on the

investments made in the online company. A parent carrier shall

not, however, give instructions for the ongoing management

or for specific decisions concerning the construction or upgrading of

grids, unless the instructions relating to the decision

In addition to the financial framework laid down by the general meeting of shareholders

or equivalent body in a subsidiary. Law (2009:1045).



1 e § Government or, after the Government's authorization,

the power authority may provide for the conditions to be

apply to the requirements laid down in 1 (b) and (d) sections should be

met. Law (2009:1045).



1 f § A backbone companies independent of the companies that

engaged in the production of, or trade in electricity or natural gas.

Law (2011:712).



1 g § The program alone or together with any other exercises

control of a company engaged in the production of or

trade in electricity or natural gas, cannot exercise control over

or any right over a backbone enterprises.



The who, alone or together with any other exercises

control of a backbone enterprises, may not exercise control

over or any right over an undertaking performing any of the

production of or trade in electricity or natural gas.



The who, alone or together with someone else may designate

members of the Board of directors or equivalent body in a

backbone companies, may not exercise control or any

right vis-à-vis an undertaking engaged in the production of

or trade in electricity Law (2011:712).



1 h section that referred to in paragraph 1 g does not apply to control or

right that is exercised by the State through the Government.



As set out in paragraph 1 (g), first and second subparagraphs if companies

engaged in the production of, or trade in electricity does not apply a

electricity users who produces or supplies electricity or

alone or with someone else, make sure a

enterprises engaged in such activities, provided that

user of electricity are net consumers and the value of the electricity they

sell to anyone else is insignificant in relation to the other

trade or business.



For the purposes of the second paragraph, the user of electricity is considered to be

NET consumers if the average power consumption is

greater than production per year. In production at

the estimate included the electricity user of electricity itself produces and

his share of the electricity produced by a company

user of electricity control alone or together with any

other. Law (2011:712).



1 the provisions of § 1 (f) and (g) sections shall not prevent a

backbone enterprises engaged in the production of electricity referred to in

1 a paragraph or included in the same group as a

companies engaged in the production of electricity which are solely

related to the operation of backbone Enterprise grids.

Law (2011:712).



1 j § A Board Member, Executive Director,

signatory or another person with similar status in a

backbone company shall have a corresponding position

in a company engaged in the production of, or trade in electricity

with the exception of such production companies as referred to in

1 in §. Law (2011:712).



1 k section If a backbone business is part of a group where another

some engaged in the production of, or trade in electricity, the measures

taken by companies in the group to ensure that

the requirements laid down in 1 (f), 1 g and 1 j sections are satisfied does not mean that

personal or commercially sensitive information is transferred from the

backbone company to a company engaged in the production of

or trade in electricity Law (2011:712).



Accounting of network activities




section 2 of the network activities to financially separately from other

activity. Law (2008:265).



paragraph 3 of the Report of the network activities based on the network licence

for area shall relate to each area for themselves. The power authority should

However, the concession holder may decide that a network all areas

that are geographically close to each other must be collected, if

not the areas taken together constitute a network activities unsuitable

device.



Decision in the matter of the areas referred to in the first subparagraph shall

covered by the consolidated presentation should be made when there is a

final decisions on the grant of a concession

According to Chapter 2. section 1, amending the boundaries of a

Online concession area pursuant to Chapter 2. section 12, if the State

to transfer a net concession pursuant to Chapter 2. 16 § or

If the withdrawal of a concession pursuant to Chapter 2. section 18. A

such a decision may also be taken as otherwise amended

conditions causing it.



In a decision on consolidated presentation or modification of such

decision shall state when aggregate accounts shall

commence or cease. Law (2015:259).



3 a of the Network licence for area shall be accounted for separately from

Online concession for the line.



Accounting of net concession area shall, however, also

include network concession line concession, on network

line refers to a direction that organizational, technical and

functional part of a network that is held with the support of

Online concession area and partly or entirely located

within the concession area. Law (2015:259).



section 4 of the Government or, by authority of the Government,

the power authority may notify the methods of accounting

of network activities. Law (2008:265).



Revision



paragraph 5 of the auditor of the network activities should make a

special audit of the accounts of the business.



The auditor shall annually in a special certificate express an opinion in

the issue of disclosure of network activities in accordance with

the provisions in force. The certificate shall be submitted by the company to

the power authority.



The Government may announce details relating to the revision of

network activities. Law (2008:265).



Obligation to connect plant



section 6 of The concession for the line that has the power, if it does not exist

specific reasons, required to connect one on reasonable terms

electric plant to management.



Disputes concerning the obligations of the concessionaire under the first

the paragraph is tested by the power authority. Decision in such a case

shall be taken within two months of receipt

to the power authority. Where the authority needs additional time for

to determine the case, power authority may extend the time with two

months or, if the applicant admits that, with the additional time

that may be needed for the matter to be arbitrated.



The power authority's decision under the second subparagraph shall be effective immediately.



A dispute concerning the conditions of accession are examined not, if it appears

that application for review submitted to the power authority later than

two years after the network concessionaire sent a written

position on the interested party under his last known

address. Act (2005:404).



section 7 of the one who has power concession area is, if it does not exist

specific reasons, required to connect one on reasonable terms

electric plant in the field to the grid.



Disputes concerning the obligations of the concessionaire under the first

the paragraph is tested by the power authority. Decision in such a case

shall be taken within two months of receipt

to the power authority. Where the authority needs additional time for

to determine the case, power authority may extend the time with two

months or, if the applicant admits that, with the additional time

that may be needed for the matter to be arbitrated.



The power authority's decision under the second subparagraph shall be effective immediately.



A dispute concerning the conditions of accession are examined not, if it appears

that application for review submitted to the power authority later than

two years after the network concessionaire sent a written

position on the interested party under his last known

address. Act (2005:404).



7 a of a concessionaire that is required to connect a

facility under section 6 or 7 shall carry out the connection in the

a reasonable period of time.



Connection the obligation shall be fulfilled within two years from the

to power the concessionaire has received a request for

connection, unless a longer time is necessary with regard

to the extent of the connection and technical design or

There are special reasons. Law (2014:270).



7 b of an undertaking performing network operations shall have

standardized procedures for connection of

power generation plants. Such procedures shall, to the extent

is possible and appropriate, ensure a quick and easy

connection. Law (2014:270).



section 8 Would anyone connect an electric plant to a management

covered by a concession for the line instead of to the

a pipeline network covered by the concession for a network area,

may the one who has the power to make concession for the line connection

only with the consent of the person who has power concession

area.



If such consent is not provided, the power authority, if it

There are special reasons, authorize the connection.



Obligation to transmit electricity



section 9 of the one who has the power to licence on reasonable terms is required to

transmit electricity on behalf of others.



The transfer of power must be of good quality.



A network concessionaire is obliged to make good the shortcomings of

transfer to the extent that the costs to remedy

the shortcomings are reasonable in relation to the nuisance for

consumers who are associated with deficiencies.



The Government or the authority that the Government may

provide for the conditions that must be met for

that transfer of power must be of good quality.

Act (2005:1110).



9 a § unless more stringent requirements follows from section 9, second and third

paragraphs or by regulations made under section 9

fourth subparagraph, a nets concessionaires to ensure that

interruption in the transmission of electricity to the electricity users never

exceed twenty-four hours.



The first subparagraph shall not apply if the concession holder demonstrates that

the interruption is due to an impediment beyond the concessionaire

control that the concessionaire could not reasonably

have foreseen and the consequences of the concessionaire nor

reasonably have avoided or overcome. Act (2005:1110).



9 b of the power authority may in a particular case waive

the requirement in paragraph 9 of part of a concession area if



1. the requirement is unfair burden with respect to

the economic situation of the concessionaire, or



2. There are serious reasons.



Dispensation may be granted in a maximum of three years. Act (2005:1110).



Documentation and information about delivery



9 c § the operator network operations with the support of

Online concession for the line with a voltage of less than 220

kilovolts or concession area shall annually establish



1. a risk and vulnerability assessment with regard to security of supply

in the grid, and



2. an action plan showing how the supply security in the private

the electric network should be improved.



A report based on risk and vulnerability analysis, and

the action plan shall be submitted to the authority. Law (2010:164).



9 d § the operator network operations with the support of the network licence

for the line with a voltage of 220 kilovolts or less than

Online concession area shall inform consumers about

security of supply in electricity grid and on the right to

interrupt compensation and damages under Chapter 10 and 11.

Act (2005:1110).



9 e § Government or authority the Government determines

may provide for



1. substance and accounting and disclosure of

analyses and action plans in accordance with paragraph 9 (c),



2. information for consumers in accordance with section 9 (d), and



3. obligation to report power outages to the authority

the Government determines. Law (2010:164).



Duty to measure and calculate the transmitted electric



10 § whoever has the power to licence is obliged to carry out the measurement of the

the quantity of transferred electricity and its distribution over time.



If a users has a fuse subscriptions of up to 63 amperes

shall network concessionaire instead, first preliminary estimate

the quantity of transferred electricity and its distribution over time (preliminary

inputs), and the final measure the quantity of transferred electricity and

calculate its distribution over time (final inputs).

This is not an electricity users who requested that the amount of

transfer of power and its distribution over time is to be measured.



It is the responsibility of network concessionaire to report the results of

the measurements and calculations referred to in the first and second

paragraphs.



The methods of the specified obligations issued by

the Government or the authority, as the Government determines.

Act (2005:404).



10 a of the reporting of results of measurements and calculations according to

section 10 shall be made to the system operators the authority and

kontoföringsmyndigheten and relevant network concessionaire,

electricity, electricity generators, balance responsible and

electricity suppliers. On demand should the report be made at a

companies that user of electricity or power producer has designated.

Law (2015:259).



Costs for measurement and calculation



section 11 of The electricity users who request that electricity consumption will be measured on

otherwise than in accordance with the regulations issued on the basis of

section 10 shall be charged by the concessionaire of additional cost for power

This measurement and the reporting of the results of these

measurements. On the measurement of elanvändarens consumption thereby

requires a different measuring equipment than by measurement according to the mentioned


regulations, user of electricity are charged the cost of

the meter and associated collection equipment and for its

installation in the outtake.



Other costs of measurement than those now mentioned may not

charged to individual users. Despite what is said in the first

subparagraph, a electricity users, who have entered into a contract for the supply

of electricity requires that the quantity of transferred electricity is measured per

hour, will not be charged additional costs for this.



Disputes in matters referred to in the first or second paragraph be examined

by the power authority. A dispute be adjudicated unless it is shown that

application for review submitted to the power authority later than

two years after the network concessionaire sent a written

position on the interested party under his last known

address. Law (2012:510).



11 (a) repealed by laws (2003:117).



section 12 is repealed by Act (1999:770).



13 repealed by law (1999:770).



section 14 of the cost of a meter and its associated

collection equipment and its installation in

the entry point of a producer shall by

Online concession holder is charged power producer. This applies to

not the generators as referred to in Chapter 4. section 10.



Disputes in matters referred to in the first subparagraph shall be reviewed by the

the power authority. A dispute be adjudicated unless it is shown that

application for review submitted to the power authority later than two

years after the network concessionaire sent a written

position on the interested party under his last known

address. Lag (2003:117).



Compensation for input of electricity



section 15, the holder of a production facility is entitled to

replacement of the nets concessionaires whose pipeline network

the plant is connected. The compensation shall be equal to



1. the value of the reduction of energy losses as data input

the electricity from the plant brings the power of the concessionaire

grids, and



2. the value of the reduction of network concessionaire fees

to have its management network connected to other

Online concession holders ' grids as possible by

the plant is connected to the grid.



The Government may announce details relating to the calculation of

the compensation referred to in the first subparagraph.



Disputes in matters referred to in the first subparagraph shall be reviewed by the

the power authority. A dispute be adjudicated unless it is shown that

application for review submitted to the power authority later than two

years after the network concessionaire sent a written

position on the interested party under his last known

address. Law (2002:121).



Acquisition of electricity needed for network operations



section 16 of the one who has the power to licence must not place conditions

that excludes electricity generators from providing electricity that is

intended to cover network losses, or necessary for the operation of

grid with reference only to the labour law.



Network concessionaire shall procure the electricity which is intended for

such purposes as specified in the first subparagraph in an open,

non-discriminatory and market based procedures.

Law (2014:270).



Efterfrågeflexibilitet



16 a of an undertaking performing network operations shall not make

up technical requirements or other conditions that make it difficult

the provision of services in the form of the amended

electricity consumption, unless the condition is justified by the

a secure, reliable and efficient operation of the

the pipe network.



The Government or the authority that the Government

determines may provide for the technical conditions

which may be set up by the power companies such

services referred to in the first subparagraph. Law (2014:270).



Preparation of monitoring plan



section 17, a company that conducts network operations and included in

same group as a company engaged in the production of or

trading with electricity shall establish a compliance programme and ensure that

the plan is followed.



The monitoring plan shall indicate the measures to be

be taken to counter discriminatory behaviour vis-à-vis

other participants in the electricity market. The plan shall specify the

specific obligations which the employees have to this case

is to be achieved.



The Government or, by authority of the Government,

the power authority may provide for the content of

the monitoring plan. Law (2011:712).



17 a of an Internet company that is required to prepare a

monitoring plan under section 17 shall appoint a compliance officer,

as an independent establishment and shall monitor compliance with the plan.

The power company to ensure that the compliance officer has the

powers and access to the information required for

to accomplish the mission.



The compliance officer shall draw up each year a report on

the measures taken in accordance with the monitoring plan and submit

report to the power authority. The power company is required to disclose

the report.



The Government or, by authority of the Government,

the power authority may provide for the appointment of

compliance officer and his information and if

publication of the annual report. Law (2011:712).



17 b of a joint venture shall establish and implement a

monitoring plan, if



1. the company has been formed to implement a cooperation

aims to integrate markets for electricity in the Nordic countries and

The European Union, and



2. it is among the companies that have formed the joint venture is

power companies in the same group as the company, without

be productive undertakings referred to in paragraph 1 in, engaged in production

of or trade in electricity.



Of the monitoring plan should indicate what actions

the company must take to prevent discriminatory and

anti-competitive behaviour vis-à-vis the other operators on the

the electricity market. The plan shall specify the particular separate

obligations of company employees have to prevent

this.



The monitoring plan shall be approved by the Agency for the cooperation of

energy regulators. The plan shall be submitted to the Agency for

examination of such approval. Law (2012:335).



Easing of requirements on power concessionaires in some cases



section 18 of the Government or, by authority of the Government,

the power authority may provide for exceptions from the

the requirements of 9 c and 9 d § § in the case of wires that essentially

input power from plants for the production of renewable electricity.

Law (2010:164).



section 19 of the Government or, by authority of the Government,

the power authority may provide for exceptions from the

the requirements of section 17 in respect of network concessionaire whose wires

mainly feeds electricity from installations for the production of

renewable electricity. this Regulation shall not, however, refer to

network undertakings referred to in paragraph 1 (b). Law (2010:164).



section 20 of the power in the particular case, the authority may, on the application of

the holder of a line or that of building a

leadership, announce a binding information whether the management

subject to exemption under section 18.

Law (2010:164).



section 21 of the power in the particular case, the authority may, on the application of

a company carrying on or intending to carry on

network industries, announce a binding statement on whether

company subject to exemption under article 19.

Law (2010:164).



section 22 A binding information according to § 20 or 21, may be subject to

terms and conditions. These should be indicated in the announcement. Law (2010:164).



Communication with consumers and the general public



section 23 If an Internet company and a company engaged in the production

of or trade in electricity is included in the same group, the companies

When they turn to individual users, or the public

define its identity in such a way that it is clear

What business the company is engaged in. Law (2011:712).



Chapter 4. Network tariffs



General information about the network tariffs



1 § network tariffs shall be objective and non-discriminatory.

They shall be designed in a way that is consistent with a

efficient use of the power grid and an efficient electricity production

and electricity use.



The Government or, by authority of the Government,

the power authority may provide for how network tariffs

should be designed to promote the efficient use of

mains or an efficient electricity generation and electricity use.



In Chapter 5. lays down rules on the determination of the revenue framework.

Law (2014:270).



1 a of a concessionaire may not enter into agreements on access

to a pipeline or a pipeline network until the methods

has been used to draw up the terms of the contract have been tried by

the power authority. The power authority will approve the procedures, if they

likely to lead to that complies with the requirements set out in

Article 1, first paragraph. The trial should not, however, include methods

to design fees for the transmission of electricity and for

connection.



If the power authority does not approve the methods proposed in a

the application, it shall specify in the order the methods in

rather than should apply.



Decisions referred to in the first and second subparagraphs shall be effective immediately.

The power authority shall notify the decision under paragraph 49 1

and the second paragraph of Service Act (2010:1932). Law (2012:335).



2 § network tariffs for the transmission of electricity shall be designed so that

paid connection fee giving the right to use the electric

network within the country, with the exception of foreign relations.



The Government may provide for paid connection fee giving the right

to use even foreign connections to one or more

countries. Such a provision may also refer to:

foreign connections to a part of a country.



Regulations referred to in the second subparagraph shall be notified in the case of a

country or part of a country whose electricity market can be regarded as a

common market with the Swedish electricity market.



Contracts relating to access to a foreign relations and that

have been concluded before the Government announces the regulations under other


subparagraph shall still apply. Act (1998:1651).



Especially if the network tariffs for the transmission of electricity for the area



section 3 network tariffs for the transmission of electricity for the area must not

be designed taking into account was within the field of a connection is

located.



If one or more areas are merged, in whole or in part,

a unified network tariff for the new area of application

at the latest three years after the merger. Law (2009:892).



4 § in areas that accounted for the single according to Chapter 3. 3 section a

unified network tariff applies from the day on which the power authority

Specifies in the order. The date must not be later than five years

from the decision on the comprehensive report or decision amending

by such a decision.



The comprehensive report is made in accordance with Chapter 3. paragraph 3 (a),

shall, where the application of the provisions of this chapter a

network management covered by the concession for the line that is reported

together with network concession area is covered by

Online concession area. Law (2015:259).



Especially if the network tariffs for the transmission of electricity for the line



Regionledning



5 § On a regionledning may not network tariff for transmission

of electricity at each voltage level take account of was a

outtake is located in relation to management's

connection to another network management that the concession holder

subject network concession line.



Authorization for deviation from what is stated in the first paragraph

may be communicated in accordance with paragraph 6.



Network tariff for an electrical installation which takes out the electricity directly

from a transformer on a regionledning will be designed with

the basis of the net rate for the voltage level immediately before

the transformer with a reasonable addition for

nedtransformeringen. Law (2009:892).



section 6 of the Net rate for an individual users whose installation is

connected to a regionledning, shall, if necessary, the power authority on

application of net concession holder or the relevant electricity users have

announced permission, take account of where on the

or regional management team elanvändarens outtake is located.



Permit referred to in the first subparagraph may be notified only if the

relevant outtake existed on 1 July 1995 and an agreement,

implying that the price for the transfer of power is based, inter

more on withdrawal point's plight, was implemented on 1 July

1995.



Licences shall be valid from the specific date and communicated to the designated

time, not more than thirty years.



If the authorization granted shall, when determining the net rate

for user of electricity, withdrawal point location is taken into account in the same

extent of the agreement referred to in the second subparagraph.



section 7 If a cash point location is changed or is intended to be changed or

If the appointment is raised or the effect of the outtake is intended to be

height after the Power Authority announced the authorization pursuant to

section 6, shall notify the network concessionaire

the power authority.



Where such a notification has been made, the power authority examine in

the extent to which and the time during which the State could reasonably

shall apply.



section 8 On a regionledning shall, within every normal

voltage range power tariff anticipate

network concessionaire expenses for all regionledningar

throughout the country that can be attributed to the respective

voltage range.



The portion of the estimated costs represented by the payment

for transmission on the backbone and other regionledningar should

However the single only for network concessionaire

all regionledningar within the same region.

Law (2009:892).



Riser



§ 9 On a riser receives power tariff for the transmission of electricity

take account of where in the network the concessionaire

wiring a connection point is located. Law (2009:892).



Especially if the network tariffs for connection to a line or

a wiring loom



9 a of A network tariff for connecting to a line or a

wiring should be designed so that the power of the concessionaire

reasonable costs for the connection is covered. SCP

geographical location and the date of effect of the

the connection point shall in particular be taken into account. Law (2009:892).



section 9 (b) if the State under an agreement with the holder of a

Online concession has financed measures necessary for

to increase grid capacity in order to facilitate the connection of

installations for the production of renewable electricity, the net rate

for the connection to be designed so that those who want to connect a

facility replaces network concessionaire expenses for

such actions in the part corresponding to the plant's share

of the total capacity increase. This is true even if

Online concession is transferred. Law (2014:391).



Especially if the network tariffs for smaller production plants



section 10 of the holder of a production facility that can

deliver a power not exceeding 1 500 kilowatts, for transfer

pay electricity only the part of the fee according to the power rate

that is equivalent to the annual cost of measurement, calculation and

reporting on the power network of the concessionaire. The holder shall

In addition, pay the one-time fee for the connection.



If several such facilities that are located in the vicinity of

each other communal feeds electricity to the grid,

the plants are regarded as separate installations at

the application of this clause.



An electricity users who have a hedging plan of up to 63

amps and producing electricity whose input can be done with a

power not exceeding 43.5 kW shall not pay any fee

for input. However, this applies only if the user of electricity in

a calendar year has taken out more electricity from the electrical system than he has

entered on the system.



Disputes in matters referred to in the first and third paragraphs

examined by the power authority. A dispute be adjudicated unless it

shows that the application for review submitted to the power authority

later than two years after the network concessionaire sent a

written position to the interested party under his

last known address. Law (2010:164).

Right to information relating to network tariffs, etc.

section 11 of the one who has the power to licence shall on request promptly

provide written indication of their network tariff.



In the new connection request, the task referred to in the first

the paragraph must be provided within a reasonable time.



The one who has the power to licence shall publish its online tariff

to the extent that it relates to the fees and other terms of

the transmission of electricity.



The Government or, by authority of the Government,

the power authority may notify the

publication of network rate referred to in the third subparagraph.

Law (2002:121).



12 § network concessionaire that has received an application for

connection of a power generation plant to set a schedule

for the processing of the application.



When the task referred to in paragraph 11 will be left in the case of

connection of a power generation plant,

network concessionaire also set a timetable for accession.



The Government or the authority, as the Government determines

announce details relating to the formulation of a timetable

under the first or second paragraph. Law (2010:602).



paragraph 13 of the one who has the power to licence shall publish principles of

how the costs of technical adaptations should be allocated at the

connection to the mains. Law (2010:602).



Chapter 5. Net income from concessionaire network operations



Equity of net concession holders ' income



The establishment of a revenue framework



1 § revenue framework shall be fixed in advance for each

supervisory period.



In paragraphs 22 to 24 are specific provisions laying down

revenue-framework for a network licence holders ' income from different

network. Law (2009:892).



section 2 A network concessionaire shall submit a proposal to

the revenue framework to the power authority together with the information

required to consider the proposal. Law (2009:892).



section 3 of the power authority shall notify the decision establishing

the revenue framework not later than two months before the supervisory period begins.



The decision shall indicate the tasks and methods

used in determining the framework. Law (2011:712).



4 section A supervisory period shall be four calendar years, unless

There is a particular reason for a different time period. Law (2009:892).



§ 5 the Government may provide for derogation from the

as stated in section 3(1) and section 4 in relation to income

from the riser. Law (2009:892).



Calculation of revenue frame size



section 6 of the Revenue framework should cover the reasonable costs for conducting

network activities during the period of supervision and provide a reasonable

return on capital required to pursue

operations (capital base). Law (2009:892).



7 § When the revenue framework is determined, account shall be taken of the quality of

network concessionaire way of conducting network activities. A

such an assessment may result in an increase or decrease in what

considered to be a reasonable return on capital.



The assessment referred to in the first paragraph, an interruption in

transmission of electricity is taken into account to the extent that the break does not

entails liability for network concessionaire or

gives the right to interrupt payments under 10 Cape. section 10.



The Government or, by authority of the Government,

the power authority may provide for the

the quality of network concessionaire way of conducting

network operations. Law (2009:892).



7 a § When the revenue framework is determined, account shall be taken of the

extent to which the network operations are conducted in a manner that is

consistent with or contributing to the effective use of

the electricity grid. Such an assessment may result in an increase or

reduction of what is considered to be a reasonable return on

the capital base.



The Government or, by authority of the Government,

the power authority may provide for the

the efficient use of the power grid. Law (2014:270).




Especially if the calculation of the reasonable costs of network operations



section 8 As reasonable costs to carry out network operations shall

be considered costs for the efficient and effective operation of a

network operations with similar objective conditions.



Cost for reimbursement under 10 Cape. section 10 shall not

considered to be a reasonable charge in accordance with the first paragraph.



The Government or, by authority of the Government,

the power authority may announce further provisions concerning

calculation of reasonable costs. Law (2014:282).



Especially if the calculation of a reasonable return



§ 9 the capital base to be calculated on the basis of the

net assets the concessionaire is using to conduct

network operations. Furthermore, consideration should be given to investments and

depreciation during the period of supervision.



An asset that is not needed to carry out its activities,

are considered to be included in own funds, if it would be unreasonable to

Online concession holder to ignore asset.



The Government or, after Government-mandated,

the power authority may announce further provisions concerning

calculation of a reasonable return. Law (2014:282).



Review of the regulatory framework during the period of revenue



section 10 On the application of network concessionaire for reconsideration may

the power authority to change an established revenue framework under

supervisory period if there are circumstances which are considered to

lead to a substantial increase in the revenue framework for a review

under section 12, or if there are special reasons.



An application for re-examination shall be dealt with promptly.

Law (2011:712).



section 11 of the power authority to change an established revenue framework under

supervisory period if



1. the network concessionaire who decision has left

inaccurate or incomplete data in more than call

scope has impacted on revenue frame size,



2. the decision has been taken on a manifestly incorrect or

incomplete dossiers and this in more than insignificant has

impacted on revenue frame size, or



3. There are special reasons. Law (2011:712).



A review of the revenue framework after supervisory period



12 § network concession holder may, within four months after the

supervisory period apply to the power authority that

revenue-framework should be increased.



The application shall be handled promptly. Law (2011:712).



paragraph 13 of the Power Authority shall review the adopted income limits

After the end of the period of supervision, if there is reason to believe that

the frame is greater than is justified by later known

conditions and the departure is not calling.



If there are no particular obstacles, a decision on the issue of

change in income limits will be announced not later than ten months after

supervisory period. If the power authority intends to announce

decision at a later date, should NET the concessionaire

be informed of this within the time mentioned. Have such a

notification has not been made, the authority may not issue a

review decision to the detriment of

Online concession holder. Law (2011:712).



section 14 For review under section 12 or 13 to the power authority

check if the assumptions on which the decision

fixing the revenue framework consistent with the actual

results during the period. In its assessment, the authority shall

apply paragraphs 6 to 9 and shall be deleted from the data and methods

the Agency has used in the determination of the revenue framework and

as is apparent from the order for determination. Law (2011:712).



Review during or after the period of supervision



section 15 If a General Administrative Court have changed a decision

revenue-framework for a nets concessionaires and the Foundation for change

the decision is applicable also for another

nets concessionaires, the power authority, at the request of the

later network concessionaire, reconsider the decision if the revenue framework

that apply to him.



An application for review shall be submitted to the authority

within three months after the Court's decision won

the force of law. Law (2011:712).



section 16 of the power authority shall review a decision if the revenue framework for

a monitoring period, if the authority or a public

the Administrative Court has decided on the amendment in the case of a

previous supervisory period and the decision has become final

force. Law (2011:712).



Accrual



section 17 if there are special reasons, the online authority on

application of a concessionaire to admit that parts of income

during the period of supervision are included in the revenue ledger first

for later periods.



An application referred to in the first subparagraph shall be notified to

the power authority within three months after the period of supervision

the revenue raised. Law (2011:712).



18 repealed by law (2011:712).



Effect of decision



section 19 of the decision by the power authority under 3, 11 to 13, 15 and

16 §§ shall apply without prejudice to the final.

Law (2009:892).



Variances from revenue framework



section 20 of the concession holder for a total net income from

network operations during the supervisory period has deviated from

the revenue framework, the amount by which revenue exceeded

or less than the revenue framework reduce and increase the scope of

the subsequent supervisory period. Law (2011:712).



section 21 If a network licence holders ' aggregate revenue from

network operations during the supervisory period has exceeded

the revenue limits by more than five percent, to a

överdebiteringstillägg calculated in accordance with the second subparagraph, reduce

the revenue part of the subsequent supervisory period.



The calculation of överdebiteringstillägget shall be based on the part

total revenues of the concessionaire of networks from

network operations that exceed the income limits.



Överdebiteringstillägget will be calculated after an interest rate

corresponds to the average reference rate according to § 9

interest Act (1975:635) that during the period of supervision established

of the Riksbank with the addition of fifteen percentage points.

Law (2011:712).



Especially if the revenue from different networks



Revenues from a pipeline in an area



section 22 in determining a revenue framework for a

net income from a concession holder grids within a

area should benefit the framework be established for each area of

themselves.



If the power authority pursuant to Chapter 3. 3 § has admitted that several

network licences in the area, however, is reported to have collected,

These in determining revenue limits, be regarded as an

area.



The comprehensive report is made in accordance with Chapter 3. paragraph 3 (a),

to network licenses in determining revenue limits

be regarded as an area. Law (2015:259).



Income from regionledning



section 23 when determining a revenue framework for a

net income from a concession holder regionledning to

revenue collected under established for network concessionaire

all regionledningar throughout the country. Law (2009:892).



Revenue from riser



section 24 in determining a revenue framework for a

Online concession holders ' income from a riser,

revenue collected under established for network concessionaire

all the lines in the country with the exception of

foreign connections.



If such a provision referred to in Chapter 4. 2 section

given, however, the receipts from the relevant

foreign relations are covered by the revenue framework

determined in accordance with the first subparagraph.



If the power system of the concessionaire has responsibility for electricity under 8

Cape. Article 1, first paragraph, the part of the business that are not

can be attributed to a particular customer or customer group are considered to be included

in network operations.



If network concessionaire participates in European cooperation, which

aims to develop and maintain a working

European electricity market, the business is considered to be part of

network operations. Law (2009:892).



24 a of If a backbone enterprise, which is a State Agency,

has funded the reinforcement of power grid under such

agreements referred to in Chapter 4. section 9 (b), the backbone Enterprise

costs in respect of the contract shall be deemed to have occurred in the

the company's network operations.



Backbone company revenue by reason of the agreement,

covered by the revenue framework established under section 24 of the first

paragraph. Law (2014:391).



Transfer of net concession, etc.



section 25 If a network concessionaire during a regulatory period

assigns a network licence, should the revenue framework

According to § 1 shall continue to apply for övertagaren of

the concession. Övertagaren enters also in other respects in the transferor's

place in the application of the provisions of this

Chapter on network concession.



If a frame has been established for the

Online concession along with other power concession, shall

the assignor and övertagaren distribute the revenue framework

proportional to the amount of

own funds that have been transferred. The same applies for income

that exceeds or falls below the revenue framework and

överdebiteringstillägg. If there are special reasons,

the allocation shall be made in a different way. Law (2009:892).



paragraph 26 of A distribution pursuant to section 25 of the second subparagraph shall be approved

prior to the transfer. Terms of approval are examined by

the power authority. However, the Government will examine the question, if the case

refers to an external link.



A proposed distribution shall be made to the power authority

together with the information required for the examination

the proposal. If the case relates to a foreign connection, the

the power authority should investigate the matter and then with his own opinion

submit the case to the Government's review.



The question of approval of the proposal to be dealt with

promptly. Team (2013:207).



paragraph 27 of the report concerning the transfer of net concession in section 25

the second subparagraph shall apply mutatis mutandis to decisions about

the modification of the concession boundaries according to Chapter 2. section 12.




The power authority decides on the allocation of the revenue framework at

the modification of the concession boundaries. Law (2009:892).



The collection of data



section 28 A nets concessionaires shall submit to the authority of the

information needed to inform decisions under 11, 13, 16

and 27 §§. Law (2009:892).



Chapter 6. Was repealed by law (2002:121).



Chapter 7. Municipal electricity undertakings



§ 1 a legal person as referred to in Chapter 3. 16 (a) and 18 (b) § §

Local Government Act (1991:900) may, despite the provision in Chapter 2. 1 §

the local Government Act of affiliation to the municipal area or its

Members, outside the municipal area engage



1. the production of and trade in electricity and related

activities, or



2. network operations in geographic proximity to the corporate

network activities in the municipality in order to achieve a

for proper network operation. Law (2014:576).



2 § if such legal person referred to in Chapter 3. 16 (a) and 18 (b) § §

Local Government Act (1991:900) carries out activities such as

referred to in paragraph 1, should the business be operated on a commercial basis

and be shown separately. Law (2014:576).



Chapter 8. Overall system responsibility and balance responsibilities, etc.



Overall system responsibility



section 1 the Government shall designate an authority, which has overall

the responsibility for electrical installations combine reliable

so that the balance on the whole or part of the country in the short term

maintained between the production and consumption of electricity

(system operator).



The Government or the authority that the Government may, in

the extent necessary out of regard to the reliability of the

national electricity system, provide for control,

testing or inspection as well as other regulations concerning

electrical installations, devices intended to be connected to

such facilities, electrical equipment or electrical

installations. Act (2005:404).



1 a of The transmission system operators, the authority shall establish targets for

reliability under the foreseeable conditions of the backbone and

on the external links that are connected to the backbone.

The objectives should be objective, transparent and non-discriminatory. The

should be submitted to the Government for approval. Government

determines how the agreed objectives will be published.



The Government or, by authority of the Government, the

transmission system operators, the authority may provide for the

requirements and obligations that must be observed for the

first subparagraph approved objectives to be achieved.



Before regulations are notified to be consulted

transmission system operators in countries whose electrical systems are linked with the

Swedish national grid. Law (2009:582).



section 2 of The transmission system operators, the authority may, to the extent

It is required to exercise the system operator, ordering

electricity generators, against remuneration, to increase or

reduce the production of electricity.



If the system operator cannot be exercised through the measures mentioned in

first subparagraph, the transmission system operator Agency, in the

extent necessary to exercise the system operator,

order marketing network concession to restrict or cancel

transmission of electricity to electricity users. To the extent

system operator agrees to restriction and suspension of

the transfer shall be carried out so that critical electricity users

as a matter of priority.



The Government, or Government authority determines,

provide for the necessary measures to increase the

or reduce the production of electricity within the meaning of the first subparagraph and

to limit or cancel the transfer of electricity to electricity users

in accordance with the second subparagraph. Law (2011:476).



section 3 of the Government may provide for the obligation of

electricity producers and consumers to the transmission system operator

the authority shall provide the information on production or consumption

of the electricity needed for the exercise of the system operator.



3 a of the transmission system operator authority may not set up

requirements that exclude electricity generators from providing

services related to the overall system operator

with reference only to the labour law. The authority shall

obtaining such services from electricity generators in a transparent,

non-discriminatory and market based procedures.

Law (2014:270).



Balance responsibility



4 §/expires U: 2016-01-01/an electricity supplier may only deliver electricity at the exit points where

someone has committed financial responsibility to the

national electricity system is supplied as much electricity as is imposed in

outtake (balance responsibility). Such a commitment should be made

through an agreement with the transmission system operator authority.



The first subparagraph shall not apply during the period referred to in

paragraph 4 (e).



With outtake referred to the point where an electricity users,

According to the agreement with the holder of the concession network, taking out electricity for

consumption. Law (2009:580).



4 section/entry into force: 01/01/2016 an electricity supplier may only deliver electricity at the exit points where someone has assumed financial responsibility for the national electricity system is supplied as much electricity to be charged in the outtake (balance responsibility). With the withdrawal point "means the point at which an electricity users, under contract with network concessionaire, taking out electricity for consumption.



The commitment referred to in the first subparagraph shall be made by agreement with the transmission system operator, the agency that performs settlement between the balance responsible. The agreement with the transmission system operators, the authority shall include an undertaking to ensure balance between supply and withdrawal of electricity. the agreement with the settlement between the balance liable to contain the terms of the settlement.



The first and second subparagraphs shall not apply during the period referred to in paragraph 4 (e). Law (2015:598).



4 a of/expires U: 2016-01-01/terms and conditions of balance agreements shall be objective and non-

discriminatory.



The transmission system operator authority must not include balance agreement

until the methods that have been used to design agreements

approved by the power authority. Authorisation must be given, if

methods may be expected to lead to agreements meet the requirements

under the first subparagraph.



A decision under the second subparagraph shall be effective immediately.

The power authority shall notify the decision under paragraph 49 1

and the second paragraph of Service Act (2010:1932).

Law (2010:1968).



4 a section/entry into force: 01/01/2016/terms of the agreements referred to in paragraph 4 the second subparagraph shall be objective and non-discriminatory.



The authority and the operators that perform the offsetting between the balance responsible may not conclude agreements according to paragraph 4(2) before the methods that have been used to design contracts have been approved by the power authority. Authorisation must be given, if the methods are likely to lead to the terms of the agreements meet the requirements of the first subparagraph.



A decision under the second subparagraph shall be effective immediately.

The power authority shall communicate the decision referred to in paragraph 1 and 49 second subparagraph, procedural law (2010:1932).

Law (2015:598).



§ 4 b/expires U: 2016-01/01/It system operators the authority shall publish the

conditions applied in balance and on demand without

delay, submit written about these terms.



The Government or, by authority of the Government,

the power authority may notify the

publication of the conditions referred to in the first subparagraph.

Act (2005:404).



§ 4 b/entry into force: 01/01/2016/The authority and the operators that perform the offsetting between the balance responsible shall publish the criteria they apply in the agreements referred to in paragraph 4, second subparagraph, and on request, without delay, submit a written statement of terms and conditions.



The Government or, by authority of the Government, the power authority may provide for the disclosure of the terms and conditions referred to in the first subparagraph. Law (2015:598).



4 c §/expires U: 2016-01-01/When the transmission authority becomes aware that

a contract with the Agency of balance responsibility under section 4 first

subparagraph shall cease to have effect, the authority shall, without delay,

notify the holders of power concession on the grids

the exit points are located where balance responsibility will

to be repealed. Holders of the network licence shall, without

immediately inform the relevant suppliers.



When someone, as in a contract with an electricity supplier is committed

balance responsibility in the exit points where electricity supplier

supplies electricity, are aware that this contract shall cease to

apply to the balance responsible, without delay, inform the

transmission system operators, the authority and the holders of

Online concession on whose networks they exit points are located

where balance responsibility thus will cease to apply.

Holders of the network licence shall, without delay, notify the

the electricity supplier.



The Government or, by authority of the Government,

the power authority will notify the

the notification obligation referred to in the first and second subparagraphs.

Law (2009:580).



4 c section/entry into force: 01/01/2016 When the transmission authority becomes aware that an agreement under paragraph 4 the second subparagraph shall cease to be valid, it shall without delay inform the concessionaire on the grids they exit points are located where balance responsibility will cease to apply.

Online concession holders shall, without delay, notify the relevant suppliers.



When someone, as in a contract with an electricity supplier is committed to balance responsibility in the exit points where electricity supplies electricity, are aware that this contract shall cease to be valid, it must balance responsible, without delay, inform the transmission system operators, the authority and the concessionaire on the grids they exit points are located where balance responsibility will cease to apply.


Online concession holders shall, without delay, notify the electricity supplier.



The Government or the authority that the Government can, with the support of Chapter 8. section 7 of the Constitution notify notification obligations laid down in the first and second subparagraphs. Law (2015:598).



4 d § an electricity supplier may enter into contracts for the supply of electricity in a

some outtake only with the electricity users who according to agreement

with network concession holder has the right to take out the electricity in the

the outtake. Law (2006:926).



section 4 (e) an electricity supplier who immediately lost his

balance responsibility owns restore balance responsibility within a period

about 10 working days, but not more than fifteen calendar days. The deadline

begins to run on the day following the then electricity supplier received

or had the opportunity to take part in the first received

the notification referred to in paragraph 4 (c), first and second subparagraphs.



The deadline for restoring balance responsibility as set out in

the first paragraph also applies to an electricity supplier whose contracts for

balance responsibility has been cancelled and will expire before the

output.



The first and second subparagraphs shall not apply if the electricity supplier entered

in liquidation, set up the payments, declared bankrupt

or declared that they have no intention to restore the

balance responsibility.



If the electricity supplier during the period goes into liquidation,

set up payments, bankruptcy, or explains

not intend to restore balance responsibility ceases

the deadline is immediately suspended. Law (2009:580).



section 4 (f) an electricity supplier who during the period resets its

balance responsibility shall inform the relevant network concessionaire on

who has committed balance responsibility in the exit points where

electricity supplier supplies electricity. Such notification shall have

received by the power the concession-holder before the deadline has passed

out.



A balance responsibility as a new balance responsible committed applies,

Despite what is stated in section 9, as from the day following that

relevant network concessionaire receives your application from

the electricity supplier.



If network concessionaire has not received a notification

from electricity supplier who is responsible for this new balance of affected

exit points before the time limit has expired,

Online concession holder the day after the expiry of anvisa

interested consumers an electricity supplier. This shall vis-à-vis

NET the concessionaire undertakes to supply electricity to

electricity users who lack electricity supplier. A balance responsibility as a

new balance responsible committed applies, although the indications referred to in

section 9, as from the date of the instruction.



Online concession holder shall, without delay, notify the

consumers of the electricity supplier who has been instructed and if

Electricity Act on change of electricity supplier. The designated

electricity supplier shall, without delay, notify consumers about

the terms of delivery as the electricity supplier apply.



The Government or, by authority of the Government,

the power authority will notify the details relating to the

the notifications referred to in the first and fourth subparagraphs.

Law (2009:580).



4 g § If an electricity supplier does not own restore balance responsibility

in accordance with paragraph 4 (e), or if such a period referred to therein is terminated

suspended in accordance with paragraph 4 (e), shall

Online concession holder as soon as possible designate the relevant

electricity users an electricity supplier, as against

Online concession holder has undertaken to supply electricity to

electricity users who lack electricity supplier. The new balance of the head

balance responsibility applies, although it referred to in section 9, from

the day of instruction.



Online concession holder shall, without delay, notify the

consumers of the electricity supplier who has been instructed and if

Electricity Act on change of electricity supplier. The designated

electricity supplier shall, without delay, notify consumers about

the terms of delivery as the electricity supplier apply.

Law (2009:580).



section 5 of The electricity supplier that supplies electricity to the electricity users in a

some outtake is, regardless of what's agreed, required to

continue to deliver electricity until the delivery obligation ceases

in accordance with the second subparagraph.



Delivery obligation ceases if the user of electricity stops taking out

electricity in the outtake, if any other electricity supplier begins

deliver electricity to user of electricity in the outtake or if

transmission of electricity under Chapter 11. 3 or 4 or under

Agreement may be canceled due to user of electricity have neglected

its obligations to the electricity supplier.



The electricity supplier that has a fixed-term contract with

user of electricity for the supply of electricity shall be not earlier than 90 days and

no later than 60 days before the expiry of the agreement, inform

user of electricity on



1. date of termination, and



2. consequences of termination.



The provisions of this section do not apply to electricity suppliers

referred to in section 7.



The Government or the authority, as the Government determines

Announcing the elleverantörernas

information obligation referred to in the third subparagraph. Law (2009:580).



5 a of A utility company which supplies electricity to the electricity users

who is entitled to the tax credit for micro production of

renewable electricity under chapter 67. the income tax Act (1999:1229) is

obliged to accept the input from elanvändarens

production facility.



The first subparagraph shall not apply if the user of electricity has entered into an agreement

with someone else about receiving electricity. Law (2014:1467).



section 6 of The electricity supplier, to start delivering power in a

outtake or seize supply to an electricity users in

his withdrawal point, shall notify to the holders of

Online concession. The notification shall also include a statement as to who

committed balance responsibility in the outtake. A notification

about to start delivering electricity to be made immediately.



An electricity supplier may take over the supplies to the electricity users in

his withdrawal point fourteen days after the notification referred to in the first

paragraph.



The provisions of the first and second subparagraphs shall not apply to the

electricity suppliers referred to in paragraph 7.



The holder of the concession network that receives a notification under

the first subparagraph shall send notice of the reason thereof

According to the detailed rules issued by the Government

or, after the Government's authorization, the power authority.

The Government or, by authority of the Government,

the power authority may announce further provisions concerning

elleverantörers obligations under the first subparagraph.

Law (2011:712).



section 7 of The electricity supplier to a specified time deliver

a fixed amount of electricity to the electricity users shall notify

to the electricity supplier which, according to paragraph 5 of the first paragraph is

delivery required in elanvändarens outtake and to it

committed balance responsibility in the outtake.

Law (1999:770).



section 8 electricity users who do not have an electricity supplier shall, by the relevant

holders of power as an electricity supplier concession, specified

against network concessionaire is committed to delivering electricity

to such users.



Online concession holder shall, without delay, notify the

user of electricity on the electricity supplier as instructed, if

the meaning of such instruction, and if the electricity Act regulations

If a change of electricity supplier.



The Government or the authority, as the Government determines

Announcing the details of what the notice in other

the paragraph will contain.



The designated electricity supplier shall, without delay, notify the

user of electricity if the conditions for shipment as the electricity supplier

intends to apply and on the day when the electricity supplier intends to

begin the delivery according to the agreement.



For the consumption of electricity not supplied according to a

supply agreement with a utility company, which is the delivery required

According to section 5, the user of electricity charged to the designated

electricity supplier under the conditions which it administers.

Law (2009:580).



8 a of An electricity users, who have lacked the supply contract with a

According to § 5 delivery required electricity supplier and do not have the

assigned a new electricity supplier according to section 8, for the consumption

of electricity during the time that a user of electricity has lacked such a

supply contracts pay into an electricity supplier designated by

Online concession holder and under the conditions that the designated

the supplier uses. Law (2009:580).



§ 9 The inheriting balance responsibility in a elanvändares

outtake after a notification pursuant to paragraph 6 of the first subparagraph,

do it from the date on which the supplier assumes

the deliveries.



In the other case, the balance responsibility just taken over from

on the first day of a calendar month. The electricity supplier which, according to

paragraph 5 of the first paragraph is delivery guilty in outtake should

in accordance with the detailed rules of which the Government or, after

the Government's authorization, the power authority will notify notify

the relevant holders of network concession if the takeover last a

month before it happens.



The transmission system operator authority may, if there are special

reasons, in the individual case allow balance responsibility in a

outtake to take effect earlier than that resulting from the

second paragraph.



The holder of the concession network that receives a notification under

the second subparagraph shall send notice of the reason thereof

According to the detailed rules issued by the Government

or, after the Government's authorization, the power authority.

Law (2011:712).



section 10 of the holder of the concession in accordance with the power to

regulations announced by the Government or by the

authority that the Government keep the transmission system operator

authority is informed of the change of balance responsible according to

section 4 (f), first and third subparagraphs, paragraph 4 (g) and

§ 9.



In addition, network concession holder keep the transmission system operator

the authority informed about who has committed

balance responsibility for his own purchases. Law (2009:580).



11 §/expires U: 2016-01/01/It system operators the authority shall be responsible for


the settlement between the balance liable under the regulations

the Government or, by authority of the Government,

the Agency Announces. Law (1999:770).



11 §/entry into force: 01/01/2016/The transmission authority shall be responsible for the settlement of the balance. The authority may instruct anyone else to carry out the settlement.

Law (2015:598).



11 a §/expires U: 2016-01-01/A utility company that has supplied electricity to a cash point

where there is a lack of any balance responsible shall at the

transmission system operators shall be considered as responsible authority balance settlement

for the outtake. Compensation shall be paid in accordance with the conditions

as the transmission system operator authority applies against

balance responsible. Law (2006:926).



11 a §/entry into force: 01/01/2016/A utility company that has supplied electricity to a cash point where there is a lack of any balance responsible balance must be regarded as responsible for the outtake at the deduction under section 11. Compensation shall be paid in accordance with the terms and conditions that correspond to conditions of other balance responsible pursuant to the agreements referred to in paragraph 4, second subparagraph, third sentence.

Law (2015:598).



11 b of an electricity supplier shall provide information to the authority

the prices and delivery conditions applied by the electricity supplier

for the delivery of electricity to consumers.



The Government or the authority, as the Government determines

announce details relating to the electric company's obligations

under the first subparagraph. Law (2006:926).



§ 11 c/expires U: 2016-01-01/a balance responsible, using someone else's

production capacity in particular to comply with their obligations

According to the balance agreement, must not set conditions

excludes electricity generators from providing such

capacity with reference only to the labour law. The

balance Manager shall acquire capacity in an open,

non-discriminatory and market based procedures.

Law (2014:270).



§ 11 c/entry into force: 01/01/2016/a balance responsible, using someone else's production capacity, in particular, to fulfil its commitments under the agreements referred to in paragraph 4, second subparagraph, shall not impose conditions which excludes electricity generators from providing such capabilities with reference only to the labour law. The balance officer shall procure capacity on a transparent, non-discriminatory and market based procedures.

Law (2015:598).



An indication of the countries of origin



section 12 of the electricity suppliers is to be on or in connection with invoices

relating to the sale of electricity and in advertising aimed at

users provide information about



1. the contribution of each energy source to the average

composition of energy sources used to produce

the electricity supplier sold during the preceding

calendar year, and



2. the impact on the environment in terms of emissions of carbon dioxide and

the amount of nuclear fuel waste that is the representation of the

sales of electricity has caused.



If the electricity supplier has bought electricity on an electricity exchange or imported

it from companies located outside the European Union may

the data referred to in the first subparagraph 1 is based on data

Power Exchange or companies.



The information set out in item 2 of the first paragraph may be provided through

reference to reference sources which are available to

members of the public.



If an electricity supplier transfer guarantees of origin relating to energy

from renewable energy sources to another holder, the

amount of energy that corresponds to the guarantees of origin are drawn from

share of energy from renewable energy sources when data

pursuant to the first subparagraph 1.



The Government or, by authority of the Government,

the power authority may announce details relating to how such

information referred to in the first to fourth paragraphs shall be calculated and

are reported for consumers. Law (2010:602).



paragraph 13 of the electricity generators shall disclose the information

electricity suppliers need to be able to fulfil their obligations

According to paragraph 12.



An electricity supplier who fails to produce electricity shall, at the request of

other electricity suppliers provide the information they need to

to carry out their obligations under paragraph 12.



The Government or, by authority of the Government,

the power authority may announce details relating to the

obligations referred to in the first and second subparagraphs.

Act (2005:404).



Invoicing and billing



section 14 suppliers and network companies may not charge any

fee for providing consumers invoices and

billing information about energy use. Law (2014:270).



section 15 of An electricity supplier billing of customers should refer to

measured quantities.



If the supplier has not received access to metrics,

the charge is based on estimated consumption. Law (2014:270).



section 16 A electricity supplier invoice should be clear. It shall

contain information on the measured consumption and the

current electricity prices as the invoice is based on.



If the supply agreement assumes that the quantity of transferred electricity is measured

per hour, information may be made available via

electric company's Web site. The invoice should then refer to

the information is available.



Invoicing shall take place at least every quarter.



Invoicing shall be provided in electronic form.

Law (2014:270).



Chapter 9. Protection measures



section 1 of the electrical installations, electrical devices intended to

be connected to such installations, electrical equipment and

electrical installations shall be such and

located and used in such a way that adequate safety

given to the person or damage to property or disruption in the operation of the

own plant or other electrical installations.



The Government or the authority that the Government may, in

the extent necessary from the security point of view, please let

regulations on inspection, testing or inspection as well as other

regulations concerning electrical installations, appliances

intended to be connected to such facilities, electric

equipment or electrical installations.



section 2 If an electrical facility by the impact on an already

existing such a facility may cause personal injury or property damage

or disturbance in the operation, the holder of the former

the complex of the actions needed at his plant for

to prevent such damage or disturbance.



The first subparagraph shall also apply when an electric

installation can cause damage through impact on an already

existing natural gas pipeline, for which it required concession

under the natural gas Act (2005:403). Law (2007:217).



2 a of the work to be performed on an electrical line or a

the associated protection device in hazardous proximity to an air line

for the strong current, is the proprietor of duty power supply required

to take the lead out of Commission for as long as is necessary for

work, if the other pipe holder requests it.



The Executive holder requesting the outage to replace the

cost and damage that may be done to the holder of the

duty power supply through the break. Law (2009:23).



section 3 of the holder of a plant for the strong current with a

voltages exceeding 1 000 volts between phase conductors where it at

single phase errors can arise from Earth's tilt power with greater strength

than 500 amps, is, in addition to the provisions of paragraph 2, shall be obliged to

observe the following. As soon as he becomes aware that an electrical

plant for low voltage or strong current with a voltage

not exceeding 1 000 volts between phase conductors, he answers for

the measures needed at his plant for the prevention

injury or disorder.



Measures referred to in the first subparagraph shall be devoted to

prevent the plant through the impact on the other

the plant through induction or increased markpotentialer

cause personal injury or property damage, or other disturbance than

audio interference.



section 4 If, in the cases referred to in paragraph 3, the proprietor of a later

-breaking facility by a lack of planning by

the system's version or otherwise have led to

the cost of protective measures have been significantly higher than

necessary, he answers for the additional cost.



§ 5 If an electrical facility be moved or changed as a matter of

performance or operation and the risk of damage or disturbance

Hence, the question of the obligation to answer for

security measures prompted by the increased risk shall be assessed on

the same way as if it was new.



section 6, an electrical installation shall be deemed to have arisen when the

was in use. Have different parts of a plant in use at

different times, each such part in the application of

This chapter is considered as a separate facility.



Article 7 If, in the cases referred to in paragraphs 2 and 3, the necessary protection can

be achieved with better effect or at lower cost through any

action at an establishment other than that whose holders under 2

or section 3 is required to respond to this action, the holder

of the former plant, by agreement or

decision of the General Court, perform the operation.



The holder who performed an action referred to in the first subparagraph are

the right to the person under section 2 or 3 had to answer for

action will be reimbursed for the expenses that were necessary for the

the performed actions. If the performed actions brought

advantage of the system in the form of reduction of expenditure for

its maintenance and operation or other permanent improvement

of operation, the financial contribution shall be reduced accordingly.



section 8 special provisions concerning electromagnetic compatibility

see Act (1992:1512) on electromagnetic compatibility.



section 9, an area of maritime traffic to a considerable extent


operated by vessels that require greater than one vertical clearance

electrical conduction admits, is the owner of management required

to take the necessary steps with the leadership needed to give

by collateral against personal injury or property damage. Management's

the holder shall bear the costs related to the measures.

Law (2009:23).



10 Cape. Damages



Liability for damage by the action of electricity from

power plant



§ 1 does anyone have inflicted on persons or property damage by the action

of electricity from a power plant, the damage, even if it

do not follow the General rules of tort, shall be replaced by

the holder of the power plant from the elen

last come.



Liability under the first subparagraph shall not apply to



1. the holder of a power plant for the production of

electricity where the generator has a rated output not exceeding 50 kilovoltampere,



2. the holder of a power plant intended for

use of electricity utilized on electricity with a voltage of not more than

250 volts between a conductor and Earth or, in the case of non-direct

grounded system, between the two leaders,



3. If the damage occurred on another electric plant or a

natural gas pipeline, for which it required concession pursuant to

the natural gas Act (2005:403), or



4. If the electrical system is made up of a

goods or intended for such an establishment needs

and the damage caused to property that has been received for the

such promotion. Law (2007:217).



Product liability



section 2 If an injury caused by defective in el set in

circulation from an electrical facility with its own generator, or

transformer is the holder, subject to paragraph 3,

liable to pay damages for personal injury and property damage

to property which by their nature are usually intended for individual

purposes, if the injured person at the time of the damage used

the property mainly for such purposes.



With security flaw means that electricity is not as secure as reasonably

can be expected.



Contract terms which restricts liability is without

effect.



section 3 Liability under section 2 is not the one who



1. indicate that he did not put the electricity in circulation in a

trade or business,



2. make the likely lack of safety did not exist when he put

Elen in circulation,



3. indicates that the vulnerability is due to the fact that electricity must be

agree with mandatory regulations issued by a

authority, or



4. shows that on the basis of the scientific and technical

knowledge at the time when he put the electricity in circulation was not

possible to detect vulnerability.



Damages in case of malfunction



4 § has operations at an electric plant been disturbed by

impact of electricity from another such facility and causes

the interference in personal injury, property damage or injury, clean property

the holder of the latter plant damage, if

the disturbance caused by intent or negligence

from his side.



Victim's contributory negligence



§ 5 If negligence on the victim's side has contributed to

damage shall be replaced in accordance with paragraph 1 or paragraph 4 of

apply to Chapter 6. section 1 of the tort liability Act (1972:207).



Damages under section 2 is to be adjusted according to what is equitable, if

negligence on the victim's side has contributed to the damage.



Determination of damages



section 6, in determining compensation for damage referred to in paragraph 1, 2 or 4

apply Chapter 5. the tort liability Act (1972:207).



When compensation for material damage shall be determined pursuant to article 2 of the off-set a

amount of 3 500 kr.



Civil liability



section 7 Is the owner of an electrical power plant opened

the right of use in whole or in part to anyone else, he answers

Yet for the damage shall be compensated in accordance with this act as if he

still held the property. The owner is not responsible

with property other than as granted.



The compensation to the owner may have provided in such cases referred to

in the first paragraph, he may recover by

the tenant.



Statute of limitations



section 8 claim against an electric plant owners or holders

for damages under paragraph 1(1) or section 4 shall be brought

within two years from the date the damage occurred.



Those who want compensation under section 2 shall bring an action in

three years after he had or should have had knowledge of that

the claim could be asserted. Claims for compensation must be

be brought within ten years from the time the alleged

liability provided the electricity.



The who did not bring an action at the time was not right to compensation

According to the specified rules.



Break replacement



§ 9 terms in comparison with the provisions of

10-15 sections are to the detriment of consumers are ineffective against them.



Interrupt payments under sections 10 to 13 shall be deducted from

damages under other provisions of this Act or

other teams are paid on account of the same power outages.

Act (2005:1110).



section 10 Of the outtake is electrically disconnected in one or

several phases from energized koncessionerat networks during a

continuous period of at least twelve hours have user of electricity

the right to interrupt compensation.



User of electricity does not have the right to interrupt compensation if



1. the interruption is due to neglect, elanvändarens



2. the transmission of electricity is interrupted to take measures

motivated by the electrical safety reasons or in order to maintain a

good operational and security of supply, and break not in progress

longer than the operation requires,



3. the interruption is attributable to an error in a

concession holders ' grids and failure is due to an obstacle

outside the control of the concessionaire

the concessionaire could not reasonably have foreseen

and the consequences of which the concessionaire could not reasonably

could have avoided or overcome, or



4. the interruption is attributable to a malfunction of a pipeline network

the lines have a voltage of 220 kilovolts or more.

Team (2013:884).



11 § Interrupt compensation shall be payable by the concession

for the power grid to which the user of electricity is directly connected.

Act (2005:1110).



12 § When the interrupt compensation is calculated to be a period of

interrupted transmission of electricity (interrupt period) is considered to be completed

at the time when the break ended, if the transfer

then has worked continuously for the next

two hours.



Remuneration shall interrupt interrupt for a period of at least

twelve hours and not more than twenty-four hours paid 12.5

percent of elanvändarens calculated annual power cost, however,

not less than 2% of the price base amount referred to in Chapter 2. 6 and 7

of the social security code, rounded to the next higher

hundred crowns.



If the period is longer than twenty-four hours, for

each then stub period more

compensation will be paid with 25 percent of elanvändarens

estimated annual net cost, but not less than 2% of

the price base amount, rounded to the next highest hundred

SEK.



Interrupt the remuneration shall for a break period amount to

a maximum of 300% of the elanvändarens estimated annual

network cost. Law (2010:1269).



section 13 of the obligation to pay compensation of interrupt is unfair

onerous in view of the economic situation of the

who is liable under section 11 and the final

shall pay compensation pursuant to section 16,, the compensation to be adjusted

According to what is equitable.



Compensation may also be adjusted according to what is equitable, if

efforts to get the transfer of electricity have needed

delayed in order not to expose workers to significant

risks. Act (2005:1110).



section 14 of the person who is liable under section 11 shall pay

interrupt compensation for user of electricity without undue delay.

and never later than six months from the end of the month in which

the culprit had or should have had knowledge of the

the interruption.



The replacement obligation shall pay interest in accordance with section 6 of the

interest Act (1975:635), if payment is not made on time.

Act (2005:1110).



section 15 if the user of electricity notwithstanding the provisions of section 14 have not received

interrupt compensation and has not claimed compensation

from the replacement obligation within two years from the time the break

ended, go right to the remuneration lost. Act (2005:1110).



section 16 of the person who is liable under section 11 has, to the extent

the interruption is attributable to an error in another

concession holders ' pipeline network, right from the

concession holder to get compensation for that which according to §§ 10-13

has been paid to the user of electricity. Act (2005:1110).



11 kap. Specific provisions on the transmission and supply of electricity

to consumers



Introductory provisions



section 1 of This chapter apply to the transmission and delivery of electricity to

consumers. Consumer refers to a natural person to whom the

electricity is transferred or delivered mainly for purposes

a user.



§ 2 contractual terms in comparison with the provisions of this

Chapter is to the detriment of the consumer are void against the

the latter.



The interruption of the transmission of electricity due to the consumer's

breach of contract



paragraph 3 of the transfer of power may be interrupted, if consumers balk

their obligations and default is an essential

breach of contract.



Before the transfer is cancelled, the consumer is invited to in

some reasonable time and take corrective action, in other cases than those referred to in

paragraph 4, be informed that the transfer might otherwise be discontinued. Takes place

correction, transfer is not interrupted.



If the circumstances give grounds to fear that a break

would result in not insignificant personal injury or extensive

damage to property, the transfer is not interrupted. It does not, however,


If the consumer is wrongful.



section 4 If the breach consists in that the consumer failed to

pay for transmission or supply of electricity, in addition to what

referred to in paragraph 3, that the consumer since the time of correction gone

out shall be asked to pay within three weeks from the time he

notification of the invitation and a notice to

the transfer might otherwise be discontinued. A communication on the

non-payment shall also be submitted to the social welfare Committee

in the municipality where the consumer receives electricity transferred.



Payment is made or the claim is disputed, the transfer

not be interrupted. The transfer must not be stopped if

the Social Welfare Board within the time specified in the first subparagraph

shall have notified the person who provided notification to

the Board assumes responsibility for payment of the debt.



§ 5 the holder of the concession network and the electricity supplier is entitled

to equitable remuneration by the consumer for any costs which

consequence of the measures mentioned in paragraphs 3 and 4.



section 6 of the Notifications and notifications referred to in paragraph 4 of the first

subparagraph shall be made in accordance with the forms laid down by

the Government or the authority, as the Government determines.



The interruption of the transmission of electricity from the electrical safety reasons etc.



paragraph 7 of the licence holder of networks may interrupt the transmission of electricity

to take measures which are justified by the electrical safety reasons

or to maintain good operations and delivery reliability.

The interruption shall not in any case exceed the operation requires.



If the holder of the concession network can predict other than short-term

interruptions in the transmission, the consumer shall be informed in good time

before the break. The consumer shall be informed personally

or, if appropriate, by appropriation.



Damages for interrupted transmission of electricity



section 8 is interrupted the transmission of electricity due to the consumer's

neglect without the conditions in paragraphs 3 and 4 are

met, the consumer has the right to compensation for damage of the

Online concession holder.



Have the transmission of electricity stopped on request of the supplier,

He shall, in lieu of the concession holder, replace

consumer for the damage suffered.



section 9 If the holder of the concession network has not notified

the consumer, in accordance with article 7 of the second paragraph, the consumer is entitled to

compensation for damage of the concessionaire.



section 10 if the transmission of electricity is interrupted but it depends on

consumer's neglect and without the right to

cancel the transfer under section 7, first paragraph, has the consumer

the right to compensation for damage of the power the concessionaire unless

This shows that the interruption is due to an impediment beyond his

control that he could not reasonably have foreseen

and the consequences of which he could not reasonably have avoided

or overcome.



Interruption depends on someone that the concessionaire has contracted for

to carry out maintenance, repairs or similar work,

the concessionaire is free from liability only if:

also he has hired would be free under the first

paragraph.



section 11 damages according to § § 8-10 includes reimbursement of expenses

and loss of income as well as other loss due to the outage.



If the obligation to pay damages would be unfair

onerous in view of the economic skadeståndsskyldiges

conditions, can the damages to be adjusted according to what is equitable.

The assessment shall also be taken into account in the present insurance

and insurance facilities, the skadeståndsskyldiges

ability to anticipate and prevent injury as well as other

special circumstances.



section 12 of the consumer shall notify the other party if the claim

compensation within two years from the time the injury occurred. He makes

not so, he has lost his right to compensation for the

damage suffered.



Information in contracts



paragraph 13 of the agreement between a consumer and an electricity supplier shall

include information on



1. the electric company's name, address, telephone number and Web site,



2. the electric company's commitment vis-à-vis the consumer,



3. when the agreement is struck, and at what times electricity supplier

plan to take over the supplies to the consumer,



4. where the consumer can find information about the electric company's

prices and other conditions,



5. the conditions laid down for invoicing and payment,



6. the duration of the agreement or whether it is valid until further notice,



7. what applies in respect of the extension of a contract that runs

for some time,



8. the conditions for termination of the contract,



9. how compensation is calculated on the early termination of a

Agreement, which runs for some time,



10. the conditions for the payment of electricity supplier does not comply with the

its commitment under the agreement, and

11. How is the electricity supplier on its website and, upon request, on

otherwise provide the additional consumer related

information referred to in section 18.



Information about the contractual terms and conditions and the information referred to in the first

subparagraph shall be communicated to the consumer before the contract is concluded or

to be confirmed. Law (2011:712).



section 14 of the agreement between a consumer and a net concessionaire

shall include information on



1. network concessionaire name, address, telephone number and

website,



2. power the concessionaire's commitment vis-à-vis the consumer,



3. when the agreement is struck,



4. where the consumer can find information about

online prices and other conditions of the concessionaire;



5. the conditions laid down for invoicing and payment,



6. the conditions for termination of the contract,



7. the conditions governing the payment of net concession holder does not

meet its commitment under the agreement, and



8. how network concessionaire at their website and on request

otherwise provide the additional

consumer related information referred to in section 18.

Law (2011:712).

Payment way



section 15 of an electricity supplier may not discriminate against a consumer only

due to the method of payment chosen by the consumer.



If a concessionaire operates a system of

prepayment for consumers, this must be reasonable.

Law (2014:270).



Changed terms



section 16 of an electricity supplier who intends to change the terms of a

contracts which run until further notice with a consumer shall inform the

consumers about the change. Notification shall be made by means of a

special message to the consumer. Of the message, the

State that the consumer has the right to terminate the agreement.



The new terms shall not become effective until at least two

months after the message has been sent.

Law (2011:712).



Price increases



section 17 When a price increase has taken place, the consumer shall be informed

about this in the next invoice from the supplier. The

must be indicated when the price change came into effect and how the price

been changed. Law (2011:712).



Information about the consumer's rights



section 18 of the Electricity and power a concessionaire who hits

contracts with consumers on their websites provide clear

information about



1. consumer rights,



2. how the consumer should go about to complain,



3. the bodies which the consumer can turn to for information

or dispute resolution, and



4. independent user advice, where consumers can get advice

If available energy efficiency measures and

comparison profiles.



At the consumer's request, the information shall be provided in any other

way.



Electricity suppliers and network concessionaire shall on or in

connection with invoices to consumers and, in the cases

specified in the first subparagraph 1 – 3, in advertising aimed at

consumers either disclose the information resulting from

the first paragraph or refer to the information available on

the website and on request be provided otherwise.

Law (2014:270).



Change of electricity supplier



19 § a change of electricity supplier shall be carried out without special

the cost to the consumer.



In the event of a change of electricity supplier, the consumer shall receive a final invoice

within six weeks from the date of the withdrawal

electric company's delivery expired. Law (2011:712).



Handling of complaints



section 20 suppliers and networks the concessionaire shall have the

established routines for handling complaints from

consumers. Law (2011:712).



Installation of new meters



section 21 Network concessionaire shall ensure that consumers are

appropriate information in connection with the installation of new

meter.



The Government or the authority that the Government may

provide for the obligations referred to in the first

paragraph. Law (2014:270).



12 Cape. Supervision, etc.



Regulators, etc.



section 1 Supervision over compliance with this Act and the

regulations or conditions that have been notified under the Act

be exercised as regards questions about electrical safety and reliability

of the national electricity system, of the authority or authorities

the Government determines.



Supervision in General over compliance with this Act and the

regulations and conditions that have been notified under the Act

exercised by the power authority.



The supervision referred to in the second subparagraph shall not include provisions of the

7 and 10. and Chapter 11. 1 – 12 §§ nor

compliance with the elleverantörernas obligations under Chapter 8.

1 to 4 sections, section 5, first and second subparagraphs, and 6-11 a § §.



The power authority is the supervisory authority under the European Parliament's

and Council Regulation (EC) no 714/2009 of 13 July 2009 on the

conditions for access to the network for cross-border exchanges in electricity

and repealing Regulation (EC) No 1228/2003.

Law (2011:712).



1 a of the cases of exemption referred to in article 17(1), 17(2) and (3) of the

Regulation (EC) no 714/2009 review by the Government.



The power authority shall investigate the matters referred to in the first subparagraph

and then, with his own opinion, submit the case to the

the Government's review. The power authority shall, in conjunction with


the handover shall make its opinion public.



In the cases referred to in article 17(5) of Regulation (EC) no 714/2009

should the Government announce decision following an opinion from the Office of

cooperation of energy regulators. Law (2011:712).



1 b of a decision by the power authority pursuant to such guidelines

adopted pursuant to Regulation (EC) no 714/2009

It is specified that the decision may be amended or repealed

at the request of the European Commission. Law (2011:712).



section 2 of a supervisory authority has the right to request the

information and to obtain the documents necessary for

supervision. A request may be subject to a penalty.



A decision as referred to in the first subparagraph shall be effective immediately.

Law (2009:892).



section 3 of The regulatory authority may inform the injunctions

necessary to ensure compliance with the rules and

conditions that are subject to supervision. An injunction may

combined with a penalty.



An order effective immediately, if the



1. relating to electrical safety or reliability of the national

the electrical system,



2. refers to the correctness of the submitted information in accordance with Chapter 8.

section 11 (b), or



3. given a notification pursuant to paragraph 14 of the

the first paragraph. Law (2011:712).



3 a of the power authority intends to supervise a

Online concession holders ' power tariff, the concessionaire

be notified of this



1. within one year after the end of the year

network tariff relates, or



2. within five years after the end of the year

network tariff relates, if the power the concessionaire has provided

incorrect or misleading information which had decisive

importance for the power authority's decision not to exercise supervision.



The power authority shall not issue a notice under paragraph 3 of that

refers to an online tariff concession holder for a particular network

fiscal year unless the power authority has notified

network concessionaire pursuant to the first subparagraph. Law (2006:926).



Especially if oversight relating to electrical safety, or operational safety

of the national electricity system



section 4 of the regulatory authority may



1. order the correction of his or her expense, if any

does not comply with a notice under section 3 as appropriate by

electrical safety reasons,



2. prohibit the use of an electric plant which is a

such a condition or used in such a way as to endanger

person or property can occur,



3. prohibit the supply or use of electrical

stock that is in such condition or used in such a

ways that danger to person or property can occur or as

is not controlled, tested, inspected, or documented

under current regulations,



4. prohibit the provision of services involving danger to

person or property as a result of inadequate or improper

installation of electric power plants.



Decision referred to in the first subparagraph shall be effective immediately and shall

enforced.



Decision referred to in the first subparagraph 2-4 may be subject to a penalty.

Act (1998:665).



§ 5 For supervision relating to electrical safety or reliability of

the national electricity system has supervisory authority entitled to receive

access to areas, offices and other areas, however, are not

housing.



If there is a need for regulatory oversight regarding electrical safety,

supervisor of manufacturers, importers, wholesalers and

retailers for tasting take out one or more copies of the

a device, intended to be connected to an electrical installation;

or electrical equipment which have been introduced or to be introduced on

the market.



The Government or the authority that the Government may

provide for compensation for the outlet sample and if

obligation to pay the costs of the supervisory authority

testing.



The police authority shall provide the assistance needed

supervision.



Fees



section 6 of the Government or the authority that the Government may

provide for fees for regulatory activities

is made pursuant to this Act.



Late payment fee



section 7 If a company conducts network operations do not provide

certified copy of such annual report, as well as such auditor's certificate

as set out in the Regulation (1995:1145) on accounting for

network activities, the company shall pay a late fee to

State under section 8.



Decision concerning the late payment fee will be made by the power authority.

Act (1998:1651).



section 8/expires U: 2016-07-01/

A company that conducts network operations shall pay a

late fee if the documents referred to in section 7 has not been

come in to the power authority within seven months from

the end of the financial year. If the company has decided on further

General meeting of shareholders in accordance with Chapter 7. paragraph of the Swedish companies act

(2005:551) or if the continued general meeting according to Chapter 7. 4 §

third subparagraph, Act (1987:667) on economic associations, shall

However the company pay the late fee first if the documents

has not been received within nine months of the fiscal year

output. The fee shall amount to 10 000 SEK.



If the documents referred to in article 7 have not been submitted within two

months from the date of the notification sent to the company if

a decision on late payment fee referred to in the first subparagraph, shall

company pay a new late fee. The new fee will be

amount to $1,000.



If the documents referred to in article 7 have not been submitted within two

months from the date of the notification sent to the company if

a decision on late payment fee in accordance with the second subparagraph, shall

company pay a new late fee. The new fee will be

amount to SEK 20,000. Act (2005:923).



section 8/entry into force: 07/01/2016

A company that conducts network operations shall pay a late fee if the documents referred to in article 7 have not been submitted to the agency within seven months of the financial year. If the company has decided on continued annual general meeting in accordance with Chapter 7. paragraph Swedish companies Act (2005:551) or if the continued general meeting according to Chapter 7. 12 section Act (1987:667) on economic associations, however, the company shall pay late fee only if the documents have not been received within nine months of the financial year. The fee shall amount to 10 000 kroons.



If the documents referred to in article 7 have not been submitted within two months from the date of the notification sent to the company if a decision on late payment fee in accordance with the first paragraph, the company shall pay a new late fee. The new fee shall amount to 10 000 kroons.



If the documents referred to in article 7 have not been submitted within two months from the date of the notification sent to the company if a decision on late payment fee in accordance with the second subparagraph, the company shall pay a new late fee. The new fee will be amount to 20 000 kroons. Law (2016:114).



section 9 if registered by a decision of the company

been declared bankrupt or went into liquidation, the decision on

late fee is not notified. Act (1998:1651).



section 10 of the company within the prescribed period provided in the documents

as indicated in paragraph 7 of the documents but has any flaw that can easily

remedied, the Power Authority announce decision on

late fee only if company has been advised of the

the deficiency and had the opportunity to remedy it, but not done it

within the time specified in the notification. Such

notice may be sent by mail to the adress

the company last reported at net authority. Act (1998:1651).



section 11 of The late payment fee shall be remitted, if failure to

submit the document appears to be excusable in the light of

circumstances for which the company has not been able to control.

The fee shall also be remitted if it seems obvious

unreasonable to take it out.



Provisions for remission shall be taken into consideration although any claim

If this has not been made, if the consequence of what has

occurred in this case. Act (1998:1651).



section 12 If a late fee has not been paid after

demand for payment, the fee shall be paid for the collection.

The Government may require that the recovery does not need to be requested

for small amounts.



Provisions of the Recovery Act (1993:891) if

recovery of State assets, etc. for the recovery,

enforcement under the enforcement code occur. Act (1998:1651).



section 13 a decision late charge may be executed even if the

do not have the force of res judicata.



If a company has the right to get back paid

late fee on the basis of a court decision, the interest

paid on the refunded fines from

month subsequent to that of the late payment fee paid to and

with the month in which the refund is being made. In the case of interest rate's size

apply 65 Cape. the third subparagraph of paragraph 4 of the law on tax procedure

(2011:1244). Law (2011:1386).



Deadlines



section 14 of the power authority shall take a decision in a case within two

months from the time a complaint came in to the authority if

notification



1. has been filed by someone who has an interest in the matter, and



2. includes a claim that a network concessionaire not

comply with the provisions covered by the power authority's supervision

According to § 1.



If the power authority will need additional time to decide

the case, the authority may extend the period by two months or,

If he admits it, with the additional time which can

needed for the matter to be settled.



The provisions of the first and second subparagraphs shall not apply

network concessionaire obligations under Chapter 3. section 6 of the first

subparagraph, paragraph 7 of the first paragraph, first and second paragraphs of section 11,

section 14, first subparagraph, and paragraph 15, and Chapter 4. 10 §

first and third paragraphs. Law (2011:712).



Preservation of information




section 15 of the Government or the authority, as the Government determines

may provide for an obligation for suppliers to

document and preserve data on supply contracts,

derivative financial instruments and transactions relating to such contracts

or instruments, and to provide such information on request

a Swedish Government agency or the European Commission.

Law (2012:335).



Chapter 13. Other provisions



Liability provisions



section 1 to a fine or imprisonment not exceeding one year are judged on that

intentionally or negligently:



1. breach of Chapter 2. 1 or 3 §,



2. breach of terms and conditions issued pursuant to Chapter 2. section 11,

or



3. violates regulations issued pursuant to Chapter 8.

1 paragraph or Chapter 9. Article 1, second paragraph.



To a fine person who willfully or negligently violates

to Chapter 2. section 17.



In minor cases are judged not to liability. Law (2006:926).



2 § To responsibility under this law shall be liable if the Act is not

subject to penalties under the criminal code.



section 3 of The who have breached an imposition of fines is sentenced not to

responsibility under this law for acts covered by the

the injunction.



section 4 electrical installations, devices intended to be connected

to an electrical installation or electrical equipment that has been

subject to offences under this Act shall be declared forfeited;

If it is not manifestly unreasonable. Instead of such property

can the value of the property is declared forfeited. Even the exchange of

offence under this Act shall be declared forfeited, if not

is manifestly unfair.



Appeal



§ 5 the power authority's decision under Chapter 2. 1, 4 – 5, 14, 15,

15 b, 15 j-16 (a) and section 17 section may be appealed to the Government, if

the case relates to a riser. The same applies to the decision not to

initiate a review after an application as described in Chapter 2.

15 c section, if the matter relates to a riser or a

foreign relations. Team (2013:207).



section 6 of the following decisions of the power authority may be appealed to the

land and Environment Court:



1. questions about network concession pursuant to Chapter 2. 1, 4 – 5, 14,

15, 15, 15 j-16 (a) and 17 sections, with the exception of cases

refers to a riser,



2. decisions on the boundaries of a network licence for area under

Chapter 2. section 12,



3. the decision not to initiate a review after an application

described in Chapter 2. 15 c section, if the matter relates to a regionledning that

is not a foreign connection,



4. decision on injunction pursuant to Chapter 2. 15 h section

subparagraph,



5. decision on withdrawal of network concession pursuant to Chapter 2.

section 18, and



6. decisions on recovery actions under Chapter 2. 19 and

20 sections. Team (2013:207).



section 7 the following decisions may be appealed to the General

Administrative Court:



1. the decision by the power authority in respect of



a) consolidated presentation and uniform power tariff in accordance with Chapter 3. paragraph 3 of the

and Chapter 4. paragraph 4, first subparagraph,



b) connection of the installation according to Chapter 3. 6-8 sections,



c) exemptions under Chapter 3. section 9 (b),



d) costs of measurement referred to in Chapter 3. 11 and 14 sections,



e) remuneration for input of electricity pursuant to Chapter 3. section 15,



f) method review under Chapter 4. 1 a of,



g) permit pursuant to Chapter 4. 6 and 7 sections,



h) network tariffs for smaller production plants according to 4

Cape. section 10,



in Chapter 5, ram), according to the revenue. 3, 11 to 13, 15 to 17, paragraphs 26 and 27,



j) approval of methods for designing the balance agreement under

Chapter 8. 4 a of, and



k) late charge under 12 Cape. 8 and 11 sections,



2. decisions of a supervisory authority under Chapter 12. 2-4 sections,

as well as the



3. the decision by the transmission system operator authority for compensation

to the person in accordance with Chapter 8. section 2 of the ordered increase or decrease

the production of electricity.



Leave to appeal is required in case of appeal to the administrative law.

Law (2015:259).



§ 8 Other decision under this Act other than those provided in 6 and

7 sections may not be appealed to a court.



Government Announces rules on appeal to

the Government of decisions other than those referred to in paragraphs 5 to 7.

Team (2013:207).



§ 9 such a non-profit organization or other legal entity that

referred to in Chapter 16. section 13 of the environmental code may appeal the

the power authority's decision under Chapter 2. 1, 4 – 5, 14, 15, 15 b,

15 j-16 (a) and 17 sections, as well as the decision not to initiate a review

After an application as described in Chapter 2. 15 c section, if the decision relates to

installations for overhead electrical power cable with a voltage of

at least 220 kilovolts and a length of 15 kilometres.



Anyone who wishes to appeal under the first paragraph, do

it before the time for appeal has expired for the parties and

sakägarna. Team (2013:207).



Transitional provisions



1997:857



1. this law shall enter into force on 1 January 1998, when the law

(1902:71 s. 1), incorporating certain provisions on electrical

plants, and the Act (1994:618) on trade in electricity, etc.,

shall cease to be valid.



2. For consumers who were charged cost for a

meters with associated collection equipment and for its

installation in the outtake under paragraph 2 of subsection 10. the first subparagraph

Lagen (1902:71 s. 1), incorporating certain provisions on

electrical installations, shall section 2 of 10. the second paragraph said

law continues to apply.



3. In cases where price regulation under section 10 of the Act (1994:618) if

trading with electricity, etc., that are pending before the new law's

entry into force of the older rules are applied.



4. Point 4 of the transitional provisions to the Act (1994:617) if

change in the law (1902:71 s. 1), incorporating certain provisions

If electrical components, as amended by the

1995:1140 shall still apply.



5. paragraphs 2 and 3 of the transitional provisions to the Act

(1994:617) amending the Act (1902:71 s. 1), including

certain provisions for electrical installations, shall remain

apply in cases where the application is made before 1 January 1996.



6. the wiring before the entry into force of this law,

been drawn up according to what is said in paragraph 5 (b) of the Act (1902:71 s. 1),

including certain provisions for electrical installations,

section 5 (b) shall continue to apply.



7. If a pipe has been submitted before 1 July 1982

apply Chapter 2. section 24 only if management were in use that day

or was in use then and recovery actions are

called from a general point of view.



1998:854



1. this law shall enter into force on 1 January 1999.



2. A case for a review of net concession shall be dealt with and

assessed under the older rules, if the matter before

the entry into force of this law. The provisions on

environmental quality standards in the environmental code shall apply

immediately.



1998:1651



1. this law shall enter into force on 1 January 1999.



2. If someone other than the holder of the concession for the network

the backbone or the majority of it has been granted

network licence for a foreign relations before January 1, 1998

the following applies.



a. On such a network licence shall apply Chapter 2. section 10 other

paragraph of its older version.



b. On such a network licence shall apply Chapter 2. section 18 of the first

paragraph of its older version.



3. If the power authority before the entry into force of this law,

granted a derogation as referred to in Chapter 3. paragraph 3 of the first paragraph, 3

Cape. paragraph 3 of the second paragraph of its older version apply to the

the relevant concession areas.



4. If one or several concession areas have been merged

in whole or in part prior to the entry into force of this law shall be 4

Cape. section 3 of its older version apply to the relevant

concession areas.



5. the provisions of Chapter 12. sections 7 and 8 apply in respect of

annual reports and Auditor's certificate for the fiscal year ending

on december 31, 1998 or later.



1999:770



1. this law shall enter into force on 1 november 1999.



2. Electricity suppliers that are delivery required by Chapter 8. paragraph 5 of the

the first subparagraph shall, not later than 1 december 1999 notify

the holder of the licence if the network in question in the exit points the

supplies electricity. This does not, however, the electricity suppliers as before

on november 1, 1999 subject to the provision in Chapter 8. section 5 of the

its older version.



3. The takeover of deliveries or the takeover of

balance responsibility shall not apply with effect from 1 January 2000

or on 1 March 2000. However, this does not exit points where

supply of electricity is carried out according to the delivery contracts concluded before

on 1 november 1999 and under which electricity supply shall

cease in december 1999 or January 2000.



4. Consumption of electricity customers not covered by that provision

in Chapter 3. paragraph 10 of the second paragraph, until the end of 2001 and

calculated in accordance with that provision. The same applies to

input from producers until the end of 2002.

Law (2001:1298).



5. An electricity users whose power consumption over time, according to a

supply agreements in effect at its entry into force, shall be measured

otherwise than in accordance with the regulations on the transitional period passenger transport,

announced pursuant to Chapter 3. section 10, are not covered by

the provisions of Chapter 3. section 11 of the first paragraph under

delivery of the contract validity period remaining until

the end of 2004.



A utility company that has such a supply agreement with a

users shall notify the holder of the

Online concession. In the notification, stating the delivery agreement

period of validity left. Law (2002:122).



6. The provision in Chapter 3. section 12 shall still apply to the

electricity users who were covered by the provision before the law

date of entry into force.



7. disputes under Chapter 5. section 7 or section 10 which, in law

entry into force is pending before the power authority or public

Administrative Court, the older provisions apply.



8. A notification under Chapter 5. paragraph 10 of the second paragraph that has been made

last modified on april 30, 1999 as a notification under the

new provision in Chapter 8. section 6, if the assumption of delivery from


1 november 1999. However, this applies only if the

user of electricity by 31 August 1999, notified to the

the holder of the concession network who shall take delivery of the supplies.



9. A notification under Chapter 5. paragraph 10 of the second paragraph that has been made

After 30 april 1999 but no later than 31 August 1999 concerning

as a notice of takeover of deliveries from

on 1 december 1999 in accordance with the new provision in Chapter 8. section 6.

However, this applies only if the user of electricity by 31 August

1999 has notified the holder of the concession network who should

take over deliveries.



10. A notification under Chapter 8. paragraph 4 of the second paragraph of its

older version shall apply as a notification under Chapter 8. 9

the first paragraph.



2002:121



1. this law shall enter into force on 1 January 2003 in the case of 3

Cape. 10 (a) and 11 (a) sections as well as in General on 1 July 2002.



2. the provisions of Chapter 3. section 3(1) of its new

version used for the first time in terms of accounting for the

financial years beginning on 1 January 2003 or nearest

thereafter.



3. network concessionaire that holds multiple network licences for

area shall, before the end of August 2002 to the power authority

report how the concession holder believes that recognition of the areas

According to Chapter 3. section 3(1) in its new version.

The power authority shall then take a decision on this. If

the power authority within four months from the notification came in

decision in question should be carried out in general ledger accounting

accordance with the notification of the concessionaire. The power authority's

decision may be appealed to the administrative court.

Leave to appeal is required for an appeal to the administrative court.



4. Order issued pursuant to Chapter 3. paragraph 3(1) of the

older version until the Power Authority announced a new

decision pursuant to paragraph 3 or the deadline in paragraph 3 has expired

as well as new accounts shall be commenced pursuant to Chapter 3. paragraph 3 of the third

subparagraph of point 2.



5. the provisions of Chapter 4. § 1 in its new wording applied

first time in terms of network tariffs valid from

the fiscal year beginning on July 1, 2002, or almost

thereafter.



6. the provisions of Chapter 3. section 6, second paragraph, paragraph 7 of the other

paragraph, the third subparagraph of section 11, paragraph and section 15

the third paragraph and Chapter 4. section 10, third paragraph in their new

version apply to disputes in which the appliction

to the power authority on 1 July 2004 or later. Lag (2003:117).



2002:653



1. this law shall enter into force on 1 August 2002.



2. the provisions of Chapter 4. 5 and 8 sections in their new version

apply for the first time in the case of network tariffs valid from

and with the fiscal year that begins on 1 August 2002, or

closest to the next.



3. Chapter 8. clause 8 of their older version apply in cases where a

electricity supplier has been instructed before entry into force.



2005:404



1. this law shall enter into force on 1 July 2006 in the case of Chapter 3.

section 10 and 1 July 2005.



2. the provisions of Chapter 3. section 2 and 3. paragraph 5 of the first and second

in its new wording, apply for the first time, as far as

concerns district heating business, in terms of accounting and

revision for the fiscal year beginning on July 1, 2005 or

closest to the next.



3. the provisions of Chapter 3. section 6, second paragraph and Chapter 3. 7 §

second paragraph in their new version, as well as the provisions of Chapter 3.

the third paragraph and paragraph 6 of Chapter 3. the third subparagraph of paragraph 7 shall apply to

such disputes to which the application arrives at the power authority

July 1, 2005 or later.



4. A concessionaire that before 1 november 2004 has entered into

a contract for the purchase of electricity to cover network losses may

apply the agreement during its remaining term of validity, however,

at the far end of October 2007.



5. the provisions of Chapter 4. section 1 of the first-fourth paragraphs in their

new version is applied to network tariffs valid from

the fiscal year beginning on July 1, 2005, or almost

thereafter.



6. Balance agreement as the transmission system operator authority has entered into

before 1 July 2005 are not subject to the new provision in 8

Cape. 4 a of during the remaining period of validity.



7. the provisions of Chapter 8. section 12 apply from 1

April 2006.



8. the provisions of Chapter 8. section 13 apply from 1

February 2006.



2005:1110



1. this law shall enter into force on 1 January 2011 in the case of 3

Cape. 9 a § and on 1 January 2006.



2. the provisions of Chapter 10. If the interrupt compensation does not apply

for the period of a power outage that occurred prior to 1

January 2006. On the other hand, the provisions applicable to a

such a power outage for the period of interruption, that is after

on 31 december 2005, if the interruption lasted at least 12 hereafter

hours.



2008:265



1. this law shall enter into force on 1 July 2008.



2. Older rules still apply in supervisory matters if

report of the district heating business and in supervisory matters if

the auditor's review in respect of the financial year that started prior to the

on 1 July 2008.



2009:892



1. this law shall enter into force on 1 January 2010 in the case of 1

Cape. 5 a §, Chapter 5., 12. 2 section and chapter 13. § 5, and otherwise

on January 1, 2012.



2. The first regulatory period in accordance with Chapter 5. 1 § 1

January 2012.



3. Older rules still apply for network tariffs which

refers to the period before 1 January 2012.



2010:1968



1. this law shall enter into force on 1 april 2011.



2. Older provisions apply where a decision on notification in accordance with

15-17 sections of Service Act (1970:428) has been taken before 1

April 2011 or if the document has been sent or submitted before

This time.



2011:712



1. this law shall enter into force on 1 January 2011 in the case of 8

Cape. 6 and 9 sections, 1 January 2012 in the case of Chapter 5. 3 and

10-18 sections and otherwise 1 August 2011.



2. A backbone company that has applied for certification under the

Act (2011:710) on the certification of backbone enterprises in electricity

may operate notwithstanding the provisions of Chapter 3. (f) and (g) sections

until a final decision on the issue of certification

has become final, but on 2 March

2012.



2011:1386



This law shall enter into force on 1 January 2012 and apply to

interest relating to the period from 1 January 2013.



2012:335



1. This law shall enter into force on July 1, 2012.



2. The new provisions in Chapter 4. 1 a of does not, however, apply to



a) such agreements on access to a wire or a

grids as a network licensees are included before 1

January 2013, or



b) agreement that includes network concessionaire during the period between the

that an application for review has been submitted to method

the power authority until the authority has announced the decision in

the case, if the application has been submitted before the end of August

2012.



2013:207



1. this law shall enter into force on 1 June 2013.



2. Nevertheless, as stated in Chapter 2. 1 a of to cases that have

initiated prior to the entry into force of the Government but not yet

pending review by the Government.



3. Older rules still apply in the case of

appeal against a decision given before the

the entry into force.



4. A network licence that is valid at the time of entry into force shall take effect

until further notice.



An online concession line that apply upon entry into force,

However, it is considered that such a network under concession for the line 2

Cape. section 13, in its new version is valid for a period of time, if the

last certain validity period is less than twenty-five years

or network concession holder before the date of entry into force has applied

If the period of validity shall be extended for a shorter period of time than

forty years. This does not mean that the term already

has been determined to be limited.



5. an application which has been filed before the entry into force, if

extension of the period of validity of a concession for the line

with forty years should be admissible, if network concessionaire

request it before the end of December 2013. The application shall in

such cases are treated as an application under Chapter 2. section 14 of the

its new wording about the power the concession shall apply until

on.



6. A decision as referred to in Chapter 2. paragraph 14 in its older version to

extend the validity period of a concession for the line with

twenty-five years or more, for the purposes of Chapter 2. 15 (b) §

be treated as a decision to announce network concession.



7. If a decision to announce network concession line has

become final before the entry into force, should the holder of the

online franchise complete the pipeline network franchise

intends by the end of may 2018 instead of within the time

as mentioned in Chapter 2. 16 a of the first subparagraph.



8. Nevertheless, as stated in Chapter 2. 16 c § need a notification

not be made before the end of March 2015 in the case of a management

that was completed before the entry into force.



2014:270



1. this law shall enter into force on 1 June 2014.



2. The new provisions in Chapter 4. Article 1, first subparagraph, second

sentence shall be applied in a method review under Chapter 4. 1 a of the

first time in terms of network tariffs valid from

the fiscal year that begins on January 1, 2015, or next

thereafter.



3. The new provisions in Chapter 5. 7 a § are applied the first time

in the case of an enforcement period beginning after the end of the year

2015.



2015:259



1. this law shall enter into force on July 1, 2015.



2. the provisions of Chapter 3. paragraph 3 (a) applies

first time in respect of the financial statements for the year

starting July 1, 2015, or closest to it then.