Introductory provisions
section 1 of this regulation provides for exceptions to the
the requirement on net concession pursuant to Chapter 2. section 1 of the electricity Act (1997:857).
2 section With internal network "means one or more starkströmsledningar
which the holder uses for the transmission of electricity for own use.
§ 3 If the holder of an internal network has commissioned someone
else to answer for the operation of the grid, the transmission of electricity
the holder shall be deemed to be made on its own behalf.
section 4 On an internal network operated without the support of the network licence
in accordance with the provisions of this regulation,
transmission of electricity on behalf of others does not take place in other cases
than those specified in §§ 23 to 31. Regulation (2012:163).
Exemptions from licence requirement
Internal networks in some areas
section 5 internal networks, which are located on or within a building,
may be built and used without network concession.
section 6, an internal network, in which electricity is transferred to the facilities
and buildings not intended for residential and located
in the immediate vicinity of a residential building may be constructed and used
without network concession.
section 7 of the internal networks in a fenced area that is intended for
holder's own account and where the general public does not own
access may be built and used without network concession.
section 8 an internal network within the area of an industrial plant,
built and used without network concession. The same is true between the
parts of such areas, which are separated only by a
traffic ranks.
section 9 of an internal network within the scope of a general or individual
institution may be built and used without network concession.
The same is true between the parts of that area, which is separated
access only by a road.
With the institution referred to one or more buildings where care,
teaching, research or similar activities are carried out.
section 10 of an internal network within the area of an airport approved
for general use, belong to the State or used for
State purposes may be built and used without network concession.
section 11 of an internal network within the area of a construction site or
other temporary work place may be built and used without
Online concession.
section 12 of an internal low-voltage networks in the area of a
agricultural property must be built and used without network concession.
The owner of an agricultural property, with no network licence
build and use an internal low voltage also outside
agricultural property if the net is intended for the operation of the
Agriculture.
section 13, an internal network within the area of a road, a channel or
other water traffic led with associated buildings and
used to meet the needs of traffic may be built and
be used without network concession. Regulation (2013:4).
section 14 of an internal network with a maximum of forty thousand Volt voltage within
the area of such a facility within the total defence whose
existence or location shall be kept secret may be built and
be used without network concession.
section 15 of an internal network within the transport for rail,
tram, Metro or trolleybus operation and used for
to meet the needs of traffic may be built and used without
Online concession.
section 16 of an internal network within a range of leisure activities,
such as sports ground, engine course, riding stables, horse-and/or
Racecourse, park theater, amusement park, swimming pool, campground and
similar may be built and used without network concession.
section 17 of an internal network within the area for a Yacht Club, a marina,
Marina, winter lay-up site for recreational boats or
similar facility may be built and used without network concession.
section 18 of an internal network within the area of a cemetery,
built and used without network concession.
section 19 of an internal network within the area for a garden center,
built and used without network concession.
Certain types of internal networks
section 20 of an internal part of a telecommunication system,
built and used without network concession.
section 21 of an internal low voltage network used exclusively for
signalling, control or measuring purposes may be built and used without
Online concession.
section 22 of an internal network which is intended for the operation of a
lighting system may be constructed and used without
Online concession.
22 a of an internal network that connects two or more electrical
installations for the production, which constitute a functional unit,
may be built and used without network concession.
Regulation (2008:897).
22 b of an internal low voltage system intended primarily
for Automotive electrical needs must be built and used without
Online concession. Regulation (2012:163).
Transmission of electricity on behalf of others on internal networks
section 23 of such electricity network which was originally
used for the transmission of electricity exclusively for his own account and
which may be used without the aid of power concession, transfer of
electricity on behalf of others take place in the cases set out in paragraphs 24 to 31.
The first subparagraph applies only if there are
noteworthy reason for transmission of electricity on behalf of others
should be take place on the grid. In determining whether there is
such grounds shall take into account, first, how the transfer affects
the network activities carried out by the holders of
Online concession and, on the other hand, the costs of connecting relevant
users of electricity to the electricity grid that is used with the support of
Online concession. Regulation (2012:163).
section 24 transfer of electricity on behalf of another person may take place on a
electricity transmission grid is located at or within a building that may
be used without the aid of net concession. This also applies if the network
as a whole did not originally have been used for the transfer of
electricity exclusively for his own account.
section 25 of the transfer of power on behalf of another person may take place on a
electricity networks that are located within the area of an industrial plant and
which may be used without the aid of net concession.
section 26 of the transmission of electricity on behalf of another person may take place on a
electricity networks that are located within the area of an airport approved
for general use, belong to the State or used for
State purpose and which may be used without network concession.
paragraph 27 of the transfer of power on behalf of another person may take place on a
low-voltage power supply network that is located within the area of a
agricultural property and may be used without the aid of
Online concession.
section 28 of the transfer of power on behalf of another person may take place on a
electricity networks that are located within the area for recreational activities, such as
sports ground, engine course, riding stables, horse-and/or race track,
Park theater, amusement park, swimming pool, campground, and similar
and that may be used without network concession.
section 29 of the transfer of power on behalf of another person may take place on a
electricity networks that are located within the area of a boat Club, marina,
Marina, winter lay-up site for recreational boats or
similar facility and which may be used without the aid of
Online concession. This also applies if the network as a whole
originally not used for the transmission of electricity exclusively
for its own account.
section 30 On such internal network referred to in article 22,
transmission of electricity between the installations take place even if the
plants which are part of the functional unit has different
holders. This also applies if the network as a whole
originally not used for the transmission of electricity exclusively
for its own account. Regulation (2008:897).
section 31 in such internal low voltage system referred to in paragraph 22 (b)
may the transfer of electricity on behalf of others. This applies to
Although the net as a whole did not originally have been used for
transmission of electricity exclusively for his own account.
Regulation (2012:163).
Transitional provisions
2007:215
1. This Regulation shall enter into force on 1 June 2007.
2. the holder of an electricity network which at the entry into force of this
Regulation is used without the aid of power concession, even then
use the net without the support of network concession.
However, this applies only
a. electricity networks in kolonistugeområden,
b. electricity networks that transmit electricity in hotels, Conference and
ski resorts, and
c. electricity networks that transmit electricity to apartment buildings.
On these grids may also transfer of electricity for the cardholder's
counting take place.
3. If the transmission of electricity in a power grid referred to in section 27 at
the entry into force of this regulation is done on behalf of others
outside the agricultural property, this transfer
even then, take place.