Introductory provisions
section 1 of this regulation provides that connects to
Act (2011:711) for the certification of some natural gas companies.
paragraph 2 of this regulation, ' transmission networks
high pressure pipeline for transmitting natural gas or a cellular network in
mainly consisting of such management with the exception of
high pressure line is mainly used in the context of local
distribution of natural gas.
Application for certification
section 3 of the application for certification shall be made in writing and filed
to the supervisory authority.
The application shall contain information on the
1. the guidance which the applicant uses or intends to use for
transmission of natural gas,
2. the applicant's organisation and ownership,
3. whether any due to contracts, articles of incorporation, bylaws
or comparable documents has the right to exercise a
control of the applicant or to designate or
dismiss the members of the applicant's Board of directors or equivalent
governing body,
4. whether anyone other than the applicant own or otherwise
disposes of assets used in the activities related to
transmission of natural gas,
5. company that the applicant owns shares in or on
otherwise exercises control over,
6. the name and social security number or, if there is none, date of birth
the Board of Directors, Executive Director, authorised signatory
and other people with similar status of the applicant;
7. whether the Member of the Board of Directors, Executive Director,
signatory or another person with similar status in
the applicant has a corresponding position in a company that
engaged in the production of, or trade in natural gas or electricity, or
otherwise, exerts influence over such companies, and
8. whether the applicant is controlled by or is likely to
controlled by a person or persons from third countries.
section 4 of The application referred to in paragraph 3 of the certificate of registration and shall
the applicant's articles of incorporation or comparable statutes attached.
The applicant must also submit proof of registration for companies
the applicant owns shares in or otherwise have
a controlling influence.
If the applicant is not required to draw up an annual report in accordance with
Regulation (2006:1051) on accounting and auditing
transmission of natural gas, storage of natural gas and the operation of
gasification plant, must also balance sheet, income statement,
notes and the management report for the last financial year
attached.
The final decision of the regulatory authority
§ 5 supervisory authority shall notify a final decision on the
certification to the European Commission. The notification shall
include a statement about the certified company
transmission networks.
Certification in relation to third countries
Notification to the European Commission
section 6 supervisory authority shall report to the European
the Commission, if
1. certification is requested by a company controlled by a
person or persons from a third country, if the applicant owned a
transmission networks or otherwise, is responsible for the operation and maintenance
of such a network, or
2. the Agency becomes aware of a circumstance that could lead
to a person or persons from third countries may control
over a transmission network or a transmission network operator.
Opinion of the Swedish Energy Agency
section 7 of the supervisory authority shall obtain an opinion from the State's
Energy Authority when it hears a case about certification
According to Chapter 4. Act (2011:711) for the certification of certain
natural gas companies.
Specific requirements in terms of security of energy supply
section 8 when the supervisor hears a question about certification
According to Chapter 4. Act (2011:711) for the certification of certain
natural gas undertakings, it shall take account in particular of
1. rights and obligations of the European Union
international law with regard to the third country concerned,
including agreements to which the Union is a party and which concern the security of
energy supply, and
2. Sweden's rights and obligations under the agreement
concluded with the third country concerned, to the extent the agreement is
compatible with EU law.
Publication of decisions
section 9 of the regulator's final decision in a case if the
certification according to Chapter 4. Act (2011:711) for the certification of
some natural gas undertakings shall be published together with the
The European Commission's opinion on the matter.
The supervisory authority will determine how this will be done.
Transitional provisions
2011:715
1. this Regulation shall enter into force on 1 August 2011.
2. the provisions of paragraphs 6 to 9 apply to the time from 3
March 2013.