Purpose and scope



section 1 of this Regulation applies to aid granted that, subject

availability of funds, may be used in certain municipalities to

conduct an inventory of where there is land in the municipality as

can be considered suitable for the construction of student housing.



Conditions for support



section 2 of the aid may be granted to a municipality that



1. have University or high school located in the municipality or in

connection to the municipality, and



2. intends to carry out an inventory of land

the municipality that may be suitable for the construction of student housing

that meets the conditions for a building permit under Chapter 9.

30-32 of the planning and building Act (2010:900) and student residences

meet the conditions for temporary planning permission according to

Chapter 9. 33 § the same law.



paragraph 3 of the aid may be granted for inventory that the beneficiary intends to

complete by 31 december 2013.

The amount of aid



section 4 of the aid shall be equal to the entire estimated cost of

inventory. The aid may not exceed 200 000 kroons

per beneficiary.

The examination of a case



section 5 Questions on aid review by Swedish authorities at the request of a

such beneficiaries as defined in section 2.



section 6, An application for aid must be submitted to Swedish authorities last

on 31 October 2013.



paragraph 7 of the decision on aid shall be subject to conditions



1. If at any time the beneficiary shall submit a

such final report referred to in section 9,



2. where the last day of the request for payment of the aid, and



3. necessary to satisfy the purpose of the aid.

Payment of the aid



section 8 a request for payment of the aid shall be notified to

Building and planning by 30 november 2013, unless housing Board

decides otherwise.



Payment may only be made if the beneficiary has begun

inventory when the request for payment of the aid has come in

to building and planning.



Monitoring and evaluation once an inventory has been completed



§ 9 When an inventory is completed should the beneficiary in a

final report to the Housing account for how the work with

the inventory has been conducted and the results achieved. In

the final report shall also be shown what costs

the beneficiary of the inventory.



section 10 of the national housing Board shall monitor and evaluate the beneficiaries '

inventory and by 30 June 2014, report this in a

report to the Government.



section 11 of the beneficiary must supply the information to the Swedish authorities that

needed for such monitoring and evaluation referred to in

section 10.



Refunds and chargebacks



section 12 of the beneficiary is obliged to refund if



1. the receiver by providing incorrect information or

any other way has caused that the aid has been provided on

false pretense or with excessive amounts,



2. the aid for any other reason has been provided on false pretense

or with too high amount and the recipient should have realized

This,



3. the aid in whole or in part have not been used or has not

used for the purpose referred to in paragraph 1,



4. the recipient has not provided such final report referred to in

§ 9, or



5. the terms of the decision on the aid have not been respected.



section 13, if the beneficiary is obliged to refund under section 12,

to Swedish authorities decide to fully or partially recover

the aid. If there are special reasons for it, building and planning

waive recovery in whole or in part.



Authorization



section 14 of the national housing Board may provide for the enforcement of

This regulation.



Appeal



15 § Housing decisions pursuant to this Regulation shall not