Advanced Search

Real Decree 907/2007, Of 6 July, Which Approves The Regulation Of The Hydrological Planning.

Original Language Title: Real Decreto 907/2007, de 6 de julio, por el que se aprueba el Reglamento de la Planificación Hidrológica.

Subscribe to a Global-Regulation Premium Membership Today!

Key Benefits:

Subscribe Now for only USD$40 per month.

TEXT

Article 129 of Law 62/2003, of December 30, of administrative fiscal measures and of social order, proceeded to the modification of the recast text of the Water Law, approved by Royal Legislative Decree 1/2001, of 20 July, in order to incorporate into our legal order Directive 2000 /60/EC of the European Parliament and of the Council of 23 October 2000 establishing a Community framework in the field of water policy.

By virtue of this standard, the corresponding modifications were made in Title III of the recast text of the Water Law, corresponding to the hydrological planning. In particular Articles 40, 41 and 42 were amended and Article 40a was introduced. Modifications were also introduced in other titles that are in close relation to the process of hydrological planning and the achievement of its aims, such as the new definition of the river basin and the introduction of the concept of demarcation. hydrographic (Articles 16 and 16a), changes in the Public Water Administration, with the creation of the Demarcation Water Council and the Committee of Competent Authorities (Articles 35, 36 and 36a), the new objectives environmental, the state of the water bodies and the programmes of measures for the attainment of such objectives (Articles 92 (a), 92 (b) and 92 (c)), the register of protected areas (Article 99a), the express introduction of the principle of recovery of the costs of services related to water management (Article 111a) or the time-limits for the achievement of environmental objectives and for public participation (additional provisions 11th and 12th).

Subsequently, Law 11/2005 of 22 June, amending Law 10/2001 of 5 July, of the National Hydrological Plan, amended the wording of Article 42 (1) (c) of the recast of the Law on Water, establishing a definition of ecological flows and the figure of natural river reserves, and added a new paragraph 5 to Article 46 concerning hydraulic works of general interest.

The legal framework for hydrological planning is completed with the Regulation of the Public Administration of Water and Hydrological Planning, approved by Royal Decree 927/1988, of July 29, in the development of the Titles II and III of the Water Act, and with the Order of 24 September 1992, approving the instructions and complementary technical recommendations for the elaboration of the hydrological plans of inter-community basins.

In compliance with the provisions of Law 29/1985, of 2 August, of Aguas, by Royal Decree 1664/1998, of July 24, the hydrological plans of the North I, North II, North III, Duero, Tajo, Guadiana I, Guadiana were approved II, Guadalquivir, Sur, Segura, Júcar, Ebro and Intra-Community basins of Catalonia. Subsequently, by means of Royal Decree 378/2001 of 6 April, the Hydrological Plan of the Balearic Islands was approved and by Royal Decree 103/2003, of 24 January, the Hydrological Plan of Galicia-Costa was approved.

The normative content of these plans was made public by the Ministerial Orders of 13 August 1999 (plans of the North, Duero, Tajo, Guadiana, Guadalquivir, Segura, Júcar and Ebro) and of 6 September 1999 (plan of the South), and by an Edict of the Board of Waters of the Generality of Catalonia of 16 March 1999 (plan of the Internal Watersheds of Catalonia).

Finally, the planning scheme provided for in Law 29/1985 of 2 August of Aguas was completed with the approval of the National Hydrological Plan by Law 10/2001 of 5 July, which was subsequently amended by the Law 11/2005, of June 22.

In the framework described above, and with the aim of fulfilling the mandates contained in the recast text of the Water Act and Directive 2000 /60/EC, as well as in Decision 2455 /2001/EC, this Regulation is drawn up Hydrological Planning, which replaces, inter alia, the provisions laid down in Title II of the Regulation of the Public Administration of Water and Hydrological Planning. The amendment of this regulation had already been announced in the single additional provision of Royal Decree 1664/1998 of 24 July, with a limited scope if the planning processes in force were compared with the new ones. requirements of Directive 2000 /60/EC to simplify the ongoing process of updating the river basin management plans.

The regulation that is now approved refers exclusively to the hydrological planning and does not develop the aspects related to the Public Administration of Water. This circumstance implies the need to coordinate this regulatory development with the modifications that are made in the regulation of the Public Water Administration, given the special links that logically occur between the two countries. However, the recent enactment of the Royal Decrees 125/2007 of 2 February, for which the territorial scope of the river basin districts is set, and 126/2007, of the same date, should be taken into account. regulate the composition, operation and allocation of the committees of competent authorities of river basin districts with inter-community basins.

The regulatory development occurs in the light of the amendments made to the recast text of the Water Act and those aspects of Directive 2000 /60/EC relating to the hydrological planning which, by its excessive detail, were not incorporated into the transposition that resulted in the modification, in 2003, of the recast text of the Law of Waters. The new Regulation of the Hydrological Planning is part of the existing regulation in order to keep as much coherence as possible with the whole body of law of the right of waters. For this reason, the text responds to the regulatory development mandates contained in the recast text of the Water Law, with the current Regulation of the Public Administration of Water and Planning as basic pillars. Hydrologic and Directive 2000 /60/EC.

Another recent modification of our Ordinance, the one produced by the entry into force of Law 9/2006, of April 28, on the assessment of the effects of certain plans and programs in the environment, must also be dyed for the purpose of coordinating the procedures and actions provided for in this Regulation with those laid down in this Regulation.

As a complement to the above, the accumulated experience in the hydrological planning processes in Spain has to be considered. In this respect, it is important to highlight the importance of the report that the National Water Council issued on the current river basin management plans in 1998 and whose recommendations have been presented in the drafting of the proposed modifications. Similarly, the experience gained from the participation in the Common Strategy for the Implementation of the Water Framework Directive agreed on 24 October 2000 by the Member States, Norway and the European Commission, and in particular, can be cited. their application in the case of the Sugar Pilot Basin.

Finally, and as is logical, the statements in the Spanish case-law regarding the hydrological planning, in particular the judgment of the Constitutional Court 118/1998, of 4 of 4, have been taken into account. June, on positive conflicts of competition promoted by the Government of the Basque Country, by the Executive Council of the Generality of Catalonia and by the Council of Government of the Regional Council of Cantabria in relation to the current Rules of Procedure the Public Administration of Water and Hydrological Planning.

On the other hand, Article 100.2 of the recast text of the Water Act requires the application of the combined approach in the drafting of discharge authorizations. This principle is not provided for in Article 256 of the Regulation of the Public Hydraulic Domain, which is why a new wording is necessary as it is done in Article 51 of the regulation which is adopted.

The project preserves the merchant marine competences provided for in Law 27/1992, of 24 November, of Ports of the State and of the Merchant Navy, attributed to the State by Article 149.1.20. Thus, its fourth final provision enables the Ministry of Public Works to implement and develop its own field, and therefore in matters of maritime safety, navigation, human life at sea and prevention and fight against pollution of the marine environment and maritime transport, in accordance with the provisions of Law 27/1992 of 22 November 1992, of Ports of the State and of the Merchant Navy, as well as of the applicable sectoral legislation.

As for the formal structure of the regulation it has been organized in a preliminary title followed by four other titles. The preliminary title contains the general provisions and deals with the objectives and criteria of the hydrological planning, its territorial scope and the definitions. The title first addresses the substantive aspects of hydrological planning, based on the contents of the hydrological plans. The second title is devoted to the procedural aspects of the preparation and approval of the hydrological plans and the third title to the follow-up and review procedures. Finally, the fourth title is dedicated to the effects of the plans.

The regulation has been reported favourably by the full National Water Council held on October 30, 2006.

In its virtue, on the proposal of the Minister of the Environment, in agreement with the Council of State, and after deliberation of the Council of Ministers at its meeting of July 6, 2007.

DISPONGO:

Single item. Approval of the Hydrological Planning Regulation.

The Hydrological Planning Regulation whose text is included below is approved.

Single repeal provision. Regulatory repeal.

As many provisions of equal or lower rank are repealed, they oppose the provisions of this Royal Decree, and in particular:

(a) Articles 2.2 and 4 and Title II of the Regulation of the Public Administration of Water and Hydrological Planning, under the development of Titles II and III of the Water Law, approved by Royal Decree 927/1988, of 29 July.

b) Article 256 of the Regulation of the Public Hydraulic Domain, which develops the preliminary titles, I, IV, V, VI and VIII of Law 29/1985, of 2 August, of Aguas, approved by Royal Decree 849/1986, of 11 April.

Final disposition first. Competence foundation.

1. Articles 1, 2, 3, 4, 5, 6, 7, 8, 9.1, 10, 15, 16, 17.2, 19.1, 40, 42.1, 64, 65, 66.1, 67, 68, 69, 70, 71, 76.1, 78.1, 83, 84, 85, 86, 87.3, 4, 5, 6, 7, 8 and 9, 89.2, 4 and 5, 90, 91.1 and 3 of this Regulation are of a basic nature and are given under cover Article 149.1.13. of the Spanish Constitution, which reserves to the State the competence in terms of bases and coordination of the general planning of economic activity.

2. Articles 23.1, 24.1, 2 and 4, 25.1 and 2, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 43, 44, 55, 59.3 of this regulation are of a basic nature and are dictated by Article 149.1.23. of the Spanish Constitution, which reserves the State competition in the field of basic environmental protection legislation, without prejudice to the powers of the autonomous communities to lay down additional standards of protection.

3. The other articles of this regulation are dictated by the article 149.1.22. of the Spanish Constitution, which reserves the State competence on the legislation, management and granting of resources and hydraulic exploitation when the waters run by more than one autonomous community.

Final disposition second. Temporary development.

The temporary development of the measures provided for in the standard will be based on the economic availability of the autonomous communities, provided that this solution is compatible with the coordination of actions between the competent public administrations and with the exception that the competent authorities will have to ensure that the environmental objectives for the water bodies are achieved in 2015.

Final disposition third. Incorporation of European Union law.

This Regulation incorporates into Spanish law Directive 2000 /60/EC of the European Parliament and of the Council of 23 October 2000.

Final disposition fourth. Regulatory enablement.

The Minister of the Environment and the Minister of Public Works, in the field of their respective competences, are authorised to make any necessary provisions for the implementation and development of the Planning Regulation. Hydrologic.

Final disposition fifth. Entry into force.

This royal decree will enter into force on the day following its publication in the "Official State Gazette".

Given in Madrid, July 6, 2007.

JOHN CARLOS R.

The Minister of the Environment,

CRISTINA NARBONA RUIZ

HYDROLOGICAL PLANNING REGULATION

PRELIMINARY TITLE

General provisions

Article 1. Objectives and criteria for hydrological planning.

1. The hydrological planning will have for general objectives to achieve the good state and adequate protection of the hydraulic public domain and the waters object of the recast text of the Law of Waters, approved by the Royal Legislative Decree 1/2001, 20 July, the satisfaction of water demands, the balance and harmonization of regional and sectoral development, increasing the availability of resources, protecting their quality, saving their use and rationalizing their uses in harmony with the environment and other natural resources.

2. In order to achieve the objectives referred to in the previous paragraph, hydrological planning shall be guided by sustainability criteria in the use of water through integrated management and long-term protection of water resources, prevention of deterioration of the state of water, protection and improvement of the aquatic environment and aquatic ecosystems and reduction of pollution. Also, hydrological planning will contribute to alleviating the effects of floods and droughts.

3. The water policy is in the service of the strategies and sectoral plans that on the various uses establish the public administrations, without prejudice to the rational and sustainable management of the resource that must be applied by the Ministry of Environment, or by competent water administrations, which will condition any future authorisation, concession or infrastructure requested.

Article 2. Territorial scope.

1. The planning will be carried out through the river basin management plans and the National Hydrological Plan. The territorial scope of each river basin management plan shall be consistent with that of the corresponding river basin district.

2. In the case of international hydrographic demarcations in which an international basin hydrological plan is not drawn up, the territorial scope of the hydrological plan shall be that of the Spanish part of the demarcation.

Article 3. Definitions.

For the purposes of hydrological planning and the protection of the waters covered by the recast of the Water Act, the following definitions shall apply:

(a) aquifer: one or more underground layers of rock or other geological strata having sufficient porosity and permeability to permit either a significant flow of groundwater or the extraction of quantities significant groundwater.

(b) inland waters: all waters on the surface of the ground and all groundwater located to the ground from the line serving as a basis for measuring the width of territorial waters.

(c) surface waters: inland waters, except groundwater; transitional waters and coastal waters, and, as far as the chemical state is concerned, also territorial waters.

(d) groundwater: all waters under the surface of the soil in the saturation zone and in direct contact with the soil or subsoil.

e) good quantitative status of groundwater: the quantitative status achieved by a groundwater mass when the annual average rate of long-term extraction does not go beyond the available water resources and is not subject to Anthropogenic alterations that may impede the achievement of environmental objectives for the associated surface waters, which may cause significant damage to associated terrestrial ecosystems or which may cause an alteration of the flow which generates salinization or other intrusions.

f) good ecological status: the state of a surface water mass whose biological quality indicators show low distortion values caused by human activity, deviating only slightly from the values normally associated with unaltered conditions in the corresponding type of mass. Hydromorphological indicators are consistent with the achievement of these values and the physico-chemical indicators are within the range of values that ensure the functioning of the specific ecosystem of the type and the achievement of the values of the biological indicators specified above. In addition, concentrations of pollutants do not exceed established standards.

g) good chemical status of groundwater: the chemical state reached by a body of groundwater whose chemical composition does not have salinity effects or other intrusions, does not go beyond the established quality standards, does not prevent the associated surface waters from reaching environmental objectives and does not cause significant damage to the associated terrestrial ecosystems.

h) good chemical status of surface water: the chemical state reached by a surface water mass that complies with environmental quality standards with respect to priority and priority hazardous substances control, as well as the other established environmental quality standards.

i) good ecological potential: the state of a very modified or artificial mass of water whose biological quality indicators show slight changes compared to the values corresponding to the mass type most closely comparable. The hydromorphological indicators are consistent with the achievement of these values and the physico-chemical indicators are within the ranges of values that guarantee the functioning of the ecosystem and the achievement of the values of the biological indicators specified above. In addition, concentrations of pollutants do not exceed established standards.

(j) ecological flow rate: a flow rate that contributes to the good or good ecological potential in rivers or in the transition waters and maintains, at least, the fish life that would naturally inhabit or inhabit the river. river, as well as its riverside vegetation.

k) water demand: volume of water, in quantity and quality, which users are willing to acquire to meet a certain production or consumption target. This volume will be a function of factors such as the price of services, the level of income, the type of activity, technology or others.

l) state of surface water: the general expression of the state of a surface water mass, determined by the worst value of its ecological status and its chemical status.

m) state of groundwater: the general expression of the state of a groundwater mass, determined by the worst value of its quantitative status and its chemical status.

n) ecological status: an expression of the quality of the structure and the functioning of aquatic ecosystems associated with surface water.

o) quantitative status of groundwater: an expression of the extent to which direct and indirect extractions affect a groundwater mass.

p) surface water mass: a differentiated and significant part of surface water, such as a lake, a reservoir, a stream, river or canal, part of a stream, river or canal, a transitional water or a stretch of water coastal.

q) mass of groundwater: a clearly differentiated volume of groundwater in an aquifer or aquifers.

r) mass of artificial water: a mass of surface water created by human activity.

s) very modified mass of water: a mass of surface water which, as a result of physical alterations produced by human activity, has undergone a substantial change in its nature.

t) maximum ecological potential: the state of a very modified or artificial mass of water whose relevant biological quality indicators reflect, as far as possible, those corresponding to the type of surface water mass more closely comparable, given the physical conditions resulting from the artificial or very modified characteristics of the water body. In addition, the hydromorphological indicators are consistent with the achievement of these values and the physico-chemical indicators correspond fully or almost entirely to those of unaltered water mass type conditions. comparable.

u) very good ecological status: the state of a surface water mass whose biological quality indicators show the values normally associated with the mass type under unaltered conditions and show no signs of distortion, or show signs of minor importance. Furthermore, there are no anthropogenic alterations in the values of the hydromorphological and physicochemical indicators corresponding to the type of surface water mass, or there are very minor alterations.

v) ecological potential: an expression of the quality of the structure and the functioning of aquatic ecosystems associated with a mass of artificial water or highly modified.

w) significant pressure: pressure that exceeds a defined threshold from which compliance with environmental objectives can be put at risk in a water mass.

x) available groundwater resources: average year-on-year value of the total recharge rate of the groundwater mass, minus the average year-over-year flow required to achieve the ecological quality targets for water associated surface, to prevent any significant decrease in the ecological status of such waters, and any significant damage to the associated terrestrial ecosystems.

and) water-related services: all activities related to the management of waters that enable their use, such as the extraction, storage, conduction, treatment and distribution of water surface or underground, as well as the collection and purification of waste water, which subsequently pour into the surface water. Activities resulting from the protection of persons and goods in the face of floods shall also be understood as services.

z) sub-basin: the area of land whose surface runoff flows in its entirety through a series of streams, rivers and, eventually, lakes to a certain point of a water course (usually a lake or a confluence of rivers).

aa) uses of water: the different classes of use of the resource, as well as any other activity having significant effects on the state of the water. For the purposes of applying the principle of cost recovery, water uses shall at least consider the supply of stocks, industrial uses and agricultural uses.

TITLE I

Plan Content

CHAPTER I

Basin hydrological plan content

Section 1. Mandatory Content of Basin Hydrological Plans

Article 4. Mandatory content of river basin management plans.

Basin hydrological plans will necessarily comprise:

a) The general description of the river basin district, including:

a ') For both continental and coastal surface waters and transition, maps with their boundaries and localisation, ecoregions, types and conditions of reference. In the case of artificial and highly modified waters, the statement of reasons for such a qualification shall also be included.

b ') For groundwater, maps with the location and limits of water bodies.

c ') The inventory of surface and underground resources including their hydrological regimes and basic water quality characteristics.

b) The general description of the uses, pressures and significant anthropic incidents over the waters, including:

a ') Existing uses and demands with an estimate of pressures on the quantitative status of water, point-and-time source contamination, including a summary of soil use, and other significant conditions of human activity.

b ') The criteria of priority and compatibility of uses, as well as the order of preference between different uses and uses.

c ') The allocation and reserve of resources for current and future uses and demands, as well as for the conservation or recovery of the natural environment. To this end, they will determine the ecological flows and the natural river reserves, in order to preserve, without alterations, those sections of rivers with little or no human intervention. These reserves shall be strictly limited to the goods of hydraulic public domain.

d') The definition of a single operating system for each plan, in which, in a simplified manner, all partial systems are included, and with which the overall analysis of behavior is possible.

c) Identification and maps of protected zones.

(d) Control networks established for the monitoring of the status of surface water, groundwater and protected areas and the results of this control.

e) The list of environmental objectives for surface water, groundwater and protected areas, including the time limits for their achievement, the identification of conditions for derogations and extensions, and their accompanying information.

f) A summary of the economic analysis of water use, including a description of the situations and reasons that may allow exceptions in the application of the principle of cost recovery.

g) A summary of the Action Programmes adopted to achieve the intended objectives, including:

a ') A summary of the measures needed to implement the legislation on water protection, including those relating to drinking water separately.

b ') A report on the practical actions and measures taken for the implementation of the principle of recovery of water usage costs.

c ') A summary of controls on water extraction and storage, including records and identification of control exceptions.

d') A summary of planned controls on specific discharges and other activities with an impact on the state of the water, including the management of direct and indirect discharges to the public hydraulic domain and the water protection by the recast text of the Water Act, without prejudice to the exclusive state competence in the field of discharges with origin and destination in the marine environment.

e ') An identification of cases where direct discharges into groundwater have been authorised.

f ') A summary of measures taken on priority substances.

g ') A summary of the measures taken to prevent or reduce the impact of incidents of accidental contamination.

h ') A summary of the measures taken for water bodies with little chance of achieving the environmental targets set.

i ') Details of the accompanying measures deemed necessary to meet the environmental objectives established, including protection perimeters and measures for the conservation and recovery of the resource and affected environment.

j') Details of the measures taken to prevent an increase in marine water pollution.

k ') The guidelines for the recharge and protection of aquifers.

l') Basic standards for improvements and changes in irrigation that ensure the best use of the set of water resources and available land.

m ') The criteria for the assessment of energy use and the fixing of the conditions required for its implementation.

n') The criteria for studies, actions and works to prevent and prevent damage due to floods, floods and other hydraulic phenomena.

o ') The basic infrastructures required by the plan.

(h) A record of the most detailed hydrological programmes and plans relating to sub-basins, sectors, specific issues or categories of water, together with a summary of their contents. It shall include the relevant determinations for the river basin hydrological plan derived from the National Hydrological Plan.

i) A summary of the public information and query measures taken, their results, and the consequent changes made to the plan.

j) A list of designated competent authorities.

k) The contact points and procedures for obtaining the basic documentation and information required by public consultations.

Section 2. General Description of the Hydrographic Demarcation

Article 5. Identification and delimitation of surface water masses.

1. The situation and limits of the surface water masses shall be determined in each hydrographic demarcation and a characterization of these masses shall be carried out by classification into categories and types. Different bodies of surface water may be grouped for the purpose of this characterization. The situation and limits of surface water bodies shall be defined by means of a geographical information system.

2. The surface water masses within each river basin district shall be classified in the category of rivers, lakes, transitional waters or coastal waters, specifying in their case whether they are artificial water bodies or water bodies. modified.

Article 6. Ecoreregions and types of surface water bodies.

1. The rivers and lakes will be classified in two ecological regions or ecoregions called the Pyrenees and the Iberian-Macaronesian Region, the first of which corresponds to the Pyrenean area and the second to the rest of Spain. The ecological regions of the transitional and coastal waters will be the Atlantic Ocean and the Mediterranean Sea.

2. For each surface water category, water bodies shall be classified by type. These types can be defined using the ecological regions defined in the previous point and the descriptors set out in the tables in Annex I (system A), or by means of mandatory descriptors and optional descriptors or combinations of descriptors listed in the tables in Annex II (B system).

3. If the second procedure of the previous point is used, at least the same degree of discrimination should be achieved with the first one and the values of the descriptors required to ensure that they can be used must be used. to reliably obtain the specific biological reference conditions of each type.

4. For artificial and highly modified surface water bodies, the classification shall be carried out in accordance with the descriptors corresponding to the category of surface water which most resembles the mass of artificial water or very modified in question.

Article 7. Reference conditions for the types of surface water bodies.

1. For each type of surface water mass, specific hydromorphological and physico-chemical conditions representing the values of the hydromorphological and physicochemical quality indicators for the very good state shall be established. ecological. Specific biological reference conditions shall also be established in such a way that they represent the values of the biological quality indicators for the very good ecological status.

2. The specific conditions of each type may be obtained from measurements made in a reference network for each type of surface water mass, modelling or combination of both methods. Where it is not possible to use any of these methods, expert advice may be sought to establish such conditions. When defining the very good ecological status with regard to concentrations of pollutants, the limits of detection shall be those which can be achieved in accordance with the techniques available at the time the conditions are laid down. type-specific.

3. The reference network for each type of surface water mass shall contain a sufficient number of points in very good condition in order to provide a sufficient level of confidence on the values corresponding to the reference conditions, in a function of the variability of the values of the quality indicators corresponding to a very good ecological status for that type of surface water mass and the modelling techniques applied.

4. The biological reference conditions of the type based on a modelling may be obtained using prediction models or ex-post analysis methods. The methods shall use the available historical, paleontological and other data and provide a sufficient level of confidence in the values corresponding to the reference conditions to ensure that the conditions under this form is consistent and valid for each type of surface water mass.

5. Where it is not possible to set specific reliable reference conditions of the type corresponding to a quality indicator in a type of surface water mass, due to the high degree of natural variability of that indicator, not only as seasonal variations, this indicator may be excluded from the assessment of the ecological status of that type of surface water. In such circumstances, the reasons for this exclusion shall be stated in the hydrological plan.

Article 8. Artificial and highly modified water bodies.

1. A surface water mass may be designated as artificial or highly modified when:

(a) Changes in the hydromorphological characteristics of such a mass that are necessary to achieve good ecological status have considerable negative impacts on the environment, in navigation (including port facilities or recreational activities), in the activities for which water is stored (such as the supply of water intended for the production of water for human consumption, energy production, irrigation or other), in the regulation of water, in the protection against floods, in the defense of the integrity of the coast and in the drainage of land or other equally important sustainable human development activities.

(b) Benefits arising from the artificial or modified characteristics of the water body cannot be reasonably achieved, due to the technical possibilities or disproportionate costs, by other means which constitute a significantly better environmental option.

2. In the case of very modified or artificial surface water bodies, references to the very good ecological status will be interpreted as references to the maximum ecological potential. The values for the maximum ecological potential corresponding to a water mass, as well as the reasons for their consideration as artificial or highly modified, shall be reviewed every six years in the hydrological plan.

Article 9. Identification and delimitation of groundwater bodies.

1. In each river basin district the situation and the limits of the groundwater bodies fully within its territory shall be determined by means of a geographical information system and a characterisation of these bodies shall be carried out. masses.

2. The river basin hydrological plans will make a proposal for groundwater masses shared with other demarcations, which will be taken into consideration in the National Hydrological Plan for its delimitation and characterization, as indicated in Article 67 of this Regulation.

Article 10. Characterization of the groundwater masses.

1. An initial characterisation of all bodies of groundwater will be carried out in order to assess the extent to which these waters could no longer be in line with environmental objectives. Different bodies of groundwater may be grouped for the purpose of this initial characterization.

2. The analysis will use the existing data on hydrology, geology, edaphology and soil use and indicate the location and limits of the groundwater masses, the general characteristics of the suprayacent strata in the the catchment area from which the mass of groundwater and the groundwater bodies from which the surface water or terrestrial ecosystems directly depend are fed to it.

3. Once such initial analysis has been carried out, further characterization of the masses or groups of groundwater bodies that present a risk of not achieving the environmental objectives will be carried out in order to assess the accuracy of the the importance of such a risk and to determine more precisely the measures to be taken.

4. This additional characterisation shall include, where appropriate, information on:

a) The geological characteristics of the aquifer, including the extent and type of geological units.

b) The hydrogeological characteristics of the groundwater mass, including permeability, porosity, and confinement.

c) The characteristics of the surface deposits and land in the catchment area from which the groundwater mass receives its feed, including thickness, porosity, permeability and properties absorbents of the deposits and soils.

d) The characteristics of groundwater stratification within the aquifer.

e) An inventory and description of the associated surface systems, including terrestrial ecosystems and surface water bodies, with which the groundwater mass is dynamically connected, including, where appropriate, their relationship to the spaces included in the protected zone registry.

f) The calculations on the directions and rate of exchange of flows between the groundwater mass and the associated surface systems.

g) Enough data to calculate the average annual global recharge rate over the long term.

h) The characteristics of the chemical composition of groundwater. Typologies may be used for the characterization of groundwater when determining the natural reference levels of these bodies of groundwater. The characteristics that are due to the contributions of human activity shall be specified.

Article 11. Inventory of natural water resources.

1. The inventory of natural water resources shall mean the quantitative estimate, the qualitative description and the temporal distribution of these resources in the river basin district. The inventory shall include water which contributes to the input of rivers and which feeds natural water, surface or underground storage.

2. For the purposes of the inventory, the river basin district may be divided into areas and sub-areas. The division shall be carried out in each case on the basis of hydrographic, administrative, socio-economic, environmental or other criteria which in each case may be considered appropriate.

3. The inventory will contain, as far as possible:

(a) Statistical data showing the evolution of the natural regime of flows and storage throughout the hydrological year.

b) Interrelationships of the variables considered, especially between surface and groundwater, and between precipitation and river inputs or aquifer recharge.

c) The zoning and schematization of natural water resources in the river basin district.

d) Basic characteristics of water quality under natural conditions.

4. The hydrological plan will assess the possible effect of climate change on the natural water resources of the demarcation. To this end, it shall estimate the resources corresponding to the climate scenarios provided for by the Ministry of the Environment, which shall be taken into account in the time horizon referred to in Article 21.4.

Section 3. General Description of Significant Anthropic Uses, Pressures, and Incidents

Article 12. Uses of water.

The hydrological plan shall include a table that classifies the uses referred to therein, distinguishing at least those for the supply of populations, irrigation and agricultural uses, industrial uses for the production of electrical energy, other industrial uses, aquaculture, recreational uses, navigation and water transport.

Article 13. Characterization of water demands.

1. To characterize a demand the following data will be accurate:

a) The annual volume and its temporary distribution.

b) The quality conditions that are required for supply.

c) The level of warranty.

d) The cost and other relevant economic variables.

e) Consumption, that is, the volume that does not return to the hydraulic system.

f) The return, that is, the unconsumed volume that is rejoined to the system.

g) Return quality conditions prior to any treatment.

2. The volume of the claim shall be expressed in gross and net terms. In the first case, which corresponds to the concept of detraction of the medium, losses in transport, distribution and application are considered to be included. In the second case, which corresponds to the concept of consumption, no such losses are included.

3. Claims belonging to the same use that share the origin of the supply and whose returns are basically reintegrated in the same area or sub-area shall be grouped into larger territorial units, called demand units. These units will be defined in the hydrological plan and are those that will be integrated as distinct elements for the purposes of the realization of balance sheets and the allocation of resources and establishment of reserves in the defined single operating system in accordance with Article 19.

Article 14. Criteria for estimating water demands.

1. The river basin management plans shall incorporate the estimation of the current claims and the foreseeable requirements in the horizons referred to in Article 19. In particular for the uses of supply to stocks, agriculture, energy and industry, the following criteria will be followed:

(a) The calculation of demand for supply to stocks will be based, taking into account the forecasts of urban planning, on demographic, economic, industrial and service assessments, and will include the required by industries of low water consumption located in the population centres and connected to the municipal network. These evaluations will take into account both the permanent and seasonal population, as well as the number of main and secondary dwellings by typologies. The basic household allocations and the forecasts of the competent authorities for the effects of price changes, the efficiency of the supply systems and the consumption habits of the Community shall also be considered. population.

b) The estimate of agricultural demand shall include agricultural, forestry and livestock demand, which shall be estimated in accordance with the forecast of each sector and the territorial and rural development policies. The estimate of the agricultural demand shall take into account the forecasts of the evolution of the area of irrigation and the types of crops, the systems and efficiencies of irrigation, the saving of water as a result of the introduction of new techniques of irrigation or improvement of infrastructure, the possibilities for water reuse, the concessional review under Article 65 (a) and (b) and the transitional provision sixth of the recast text of the Water Act and the provision for care of isolated use. Account shall also be taken of forecasts for changes in the prices of water services and changes in the context of the markets and of aid for agricultural uses.

c) The estimation of demand for industrial and energy uses will consider the current and long-term sustainable development forecasts for each sector of activity. The calculation shall be carried out for each of them, including the number of industrial establishments, employment, production and other socio-economic characteristics. Consideration will also be given to possible structural changes in the use of raw materials and in production processes, the application of new technologies to improve the use of water and the possibilities for the reuse of water. within the industrial process itself.

2. The estimates made in accordance with the criteria set out in the previous paragraph must be adjusted, for the demands corresponding to the current situation, with the actual data available on stock and consumption in the demand units. more significant of the demarcation.

3. In all cases, the returns to the natural environment of the used waters will be estimated, both in their qualitative and quantitative aspects. In the case of supply to stocks, the hydrological plan shall include a description of the waste water treatment and treatment systems for each unit of demand, indicating the volumes and characteristics of the waste water. quality of the water at the entrance and exit of the facility.

Article 15. Pressures on the surface water masses.

1. The inventory of the type and extent of the significant anthropogenic pressures to which the surface water masses are exposed, as defined in Article 3, shall be collected and maintained in each river basin district.

2. Such information shall include, in particular:

(a) The estimation and identification of significant contamination caused by point sources, produced in particular by the substances listed in Annex II to the Public Hydraulic Domain Regulation, from urban, industrial, agricultural and other economic activities and facilities.

(b) The estimation and identification of significant contamination caused by diffuse sources, produced in particular by the substances listed in Annex II to the Regulation on Hydraulic Public Domain, originating in urban, industrial, agricultural and livestock facilities and activities, in particular non-estabulous, and other types of activities, such as mining areas, contaminated soils or transport routes.

c) The estimation and determination of significant water extraction for urban, industrial, agricultural and other uses, including seasonal variations and total annual demand, and water loss in systems distribution.

d) The estimation and determination of the incidence of significant water flow regulation, including water diversion and diversion, in the overall characteristics of water flow and balances.

e) The identification and incidence of significant morphological alterations of water bodies, including transverse and longitudinal alterations.

(f) The estimation and identification of other types of significant anthropogenic incidence in the state of surface water, such as the introduction of species of aloctonas, contaminated sediments and activities recreational.

g) Land uses, including the identification of major urban, industrial and agricultural areas, erosion areas, fire-affected areas, arid areas and other margin occupations and, if appropriate, fisheries and forests.

Article 16. Pressures on the groundwater masses.

1. In each river basin district, significant anthropogenic pressures will be indicated to which the groundwater masses are exposed, including sources of diffuse pollution, sources of spot contamination, water extraction and artificial water recharge.

2. In cases of bodies of groundwater which may not meet the environmental objectives established or cross the border with France or Portugal, the following data shall be collected, updated and kept, if appropriate:

a) The location of the points of the groundwater mass used for water extraction, with the exception of the water extraction points that supply less than 10 m3 daily and the extraction points of water intended for human consumption that provides a daily average of less than 10 m3 or serves less than 50 people.

b) The average annual extraction rates from these points.

c) The chemical composition of the water extracted from the groundwater mass.

d) The location of the points of the groundwater mass in which an artificial recharge takes place directly.

e) The reload rates on those points.

f) The chemical composition of the waters introduced in the aquifer recharge.

g) The use of soil in the area or natural recharge areas from which the groundwater mass receives its feed, including the contaminant inputs and anthropogenic alterations of the characteristics of the soil. natural recharge, such as the diversion of stormwater and runoff by waterproofing of the soil, artificial feeding, packaging or drainage.

Article 17. Priority and compatibility of uses.

1. The hydrological plan shall contain the criteria of priority and compatibility of uses to be applied in the different territories of the river basin district. In relation to these criteria, and for the entire river basin district, the order of preference between the different uses and the uses shall be established by operating systems.

2. Ecological flows or environmental demands shall not be used as a means of use, which must be regarded as a general restriction on operating systems. In any case, the rule on the supremacy of use for the supply of stocks in Article 60.3 of the recast of the Water Act shall also apply to environmental flows.

3. Similarly, the hydrological plan shall lay down the conditions and requirements necessary for the declaration of public utility of the different classes of water use, for the purpose of the compulsory expropriation of the lower-ranking benefits in the order of preference for each system of exploitation of the river basin district to be determined in the hydrological plan.

Article 18. Ecological flows.

1. The hydrological plan shall determine the regime of ecological flows in the rivers and transitional waters defined in the demarcation, including the water needs of lakes and wetlands.

2. This ecological flow rate regime shall be established in such a way as to enable the functionality and structure of the aquatic ecosystems and associated terrestrial ecosystems to be maintained in a sustainable manner, contributing to the achievement of good status or potential ecological in rivers or transitional waters. For their establishment, the catchment bodies shall carry out specific studies in each section of the river.

3. The process of implementing the ecological flow rate regime will be developed in accordance with a concertation process that will take into account existing uses and demands and their concessional regime, as well as good practices.

4. In the case of prolonged droughts, a less demanding flow rate regime may be applied provided that the conditions laid down in Article 38 on the temporary deterioration of the state of the water masses are met. This derogation shall not apply in the areas covered by the Natura 2000 network or in the list of wetlands of international importance in accordance with the Ramsar Convention of 2 February 1971. In these areas the maintenance of the ecological flow rate regime will be considered a priority, although the rule on the supremacy of use for stock supply will be applied.

5. In determining the average annual flow required for the calculation of the available groundwater resources, the ecological flow rate calculated according to the criteria set out in the preceding paragraphs shall be taken as a reference.

Article 19. Operating systems.

1. The hydrological plan shall define the operating systems in which the territory of the demarcation is functionally divided.

2. Each system of resource exploitation consists of surface and underground water bodies, hydraulic infrastructure works and installations, water utilization standards derived from the characteristics of the demands and rules of exploitation that, taking advantage of natural water resources, and according to their quality, allow to establish the water supplies that make up the supply of resources available from the operating system, fulfilling the objectives environmental.

3. Each system of resource exploitation shall cover a time horizon and shall, in any event, be included in the existing situation when the plan is drawn up. The operating systems will also cover two time horizons, 2015 and 2027, in which the satisfaction of the foreseeable demands will be considered. These horizons will increase over six years in the successive updates of the plans.

4. The study of each system of resource exploitation shall contain:

(a) The definition and characteristics of the water resources available in accordance with the rules for the use of water considered. These resources shall include those from the collection and regulation of surface water, the extraction of groundwater, the reuse, desalination of brackish and marine waters and transfers of other demarcations. The schemes for joint use of surface and underground water resources and the artificial recharge of aquifers will also be specified.

b) The determination of the elements of the precise infrastructure and the fundamental guidelines for their exploitation.

c) Natural water resources not used in the system and, where appropriate, those from territorial areas outside the Plan.

5. Without prejudice to the partial operating systems that may be defined in each Plan, a single operating system shall be defined in which, in a simplified manner, all partial systems are included and with which the analysis is possible Global behavior in the entire river basin district. The plan shall indicate the pooling of resources, demands, storage infrastructure and water bodies carried out from the partial systems, where appropriate, to define the single operating system.

Article 20. Resource reservation.

1. It is understood by reserve of resources that corresponding to the allocations established in anticipation of the demands that it is appropriate to meet in order to reach the objectives of the hydrological planning.

2. The reserves established must be entered in the Register of Waters in the name of the basin agency, which will proceed to partial cancellation as the corresponding concessions are granted. All in accordance with Title II, Chapter II, Section 9. of the Regulation of the Hydraulic Public Domain.

3. The reserves of resources provided for in the river basin management plans shall apply exclusively for the specific destination and within the maximum period laid down in the plan itself. In the absence of such a forecast, the maximum period of six years laid down in Article 89 shall be deemed to be the maximum period, unless otherwise specified in the revision of the relevant plan.

Article 21. Resources balances, allocation, and reserve.

1. The balance sheets between resources and claims referred to in this Article shall be made for each of the operating systems defined in accordance with the above Article. In this balance, the ecological flows shall be regarded as a restriction in the form referred to in Article 17.2. The satisfaction of the demands will be carried out according to the criteria of priority established in the hydrological plan, from a perspective of sustainability in the use of water.

2. The hydrological plan shall establish for the situation existing in the preparation of the Plan, the balance between the resources and the consolidated demands, considering as such the representative of normal conditions of supply in the last years, without In no case can claims be consolidated whose volume exceeds the value of the current allocations.

3. It will also establish the allocation and reserve of the resources available for the foreseeable demands of the year 2015 for the time horizon for the purposes of Article 91 of the Public Hydraulic Domain Regulation and will also specify the demands that cannot be satisfied with the resources available in the river basin itself. This horizon will be increased by six years in the successive updates of the plans.

4. In order to assess long-term trends, for the time horizon of the year 2027 the hydrological plan will estimate the balance or balance between the resources likely to be available and the foreseeable demands corresponding to the different ones. uses. For the purposes of this assessment, account shall be taken of the possible effect of climate change on the natural water resources of the demarcation in accordance with Article 11. The aforementioned time horizon will be increased by six years in the successive updates of the plans.

Section 4. Protected Zones

Article 22. River natural reserves.

1. With the aim of preserving those river aquatic ecosystems which present a high degree of naturalness, the hydrological plan shall include the natural river reserves declared by the competent authorities of the demarcation or by the Ministry of the Environment. These reserves shall correspond to bodies of water of the category river with little or no human intervention. These masses shall be incorporated in the protected zone register.

2. In order to identify these bodies of water, account will be taken of the nature of their basin, the existence of human activities that may influence their physical and chemical characteristics, the ecological status, the incidence of the water flow and the presence of morphological alterations.

3. The ecological status of these reserves will be very good, so they can be considered as reference sites.

4. Any human activity likely to cause significant pressure on the water bodies defined as river natural reserves must be subjected to a specific analysis of pressures and impacts, with the competent administration being able to grant the relevant authorisation in case the negative effects are not significant or pose a long-term risk. The criteria for determining such significant pressures shall be laid down in the hydrological plan.

5. The summary of the programme of measures for the hydrological plan shall include the protective measures taken by the competent authorities of the river basin district in the river's natural reserves.

Article 23. Special protection regime.

1. Certain areas, basins or sections of watersheds, aquifers or bodies of water, due to their natural characteristics or ecological interest, may be declared as special protection in accordance with environmental and nature protection legislation. The hydrological plans shall collect the classification of these zones and the specific conditions for their protection.

2. The competent authorities for the purpose of the matter shall provide the relevant catchment area, during the preparation of the hydrological plans, with the ratio of areas, basins or sections of watersheds, aquifers or bodies of declared water to the basin. special protection for inclusion in such plans, under the supervision of the Demarcation Competent Authorities Committee.

3. The classification and the conditions for its protection shall be collected in the basin hydrological plans in an express way or by referring in a concrete way to the existing precepts of the environmental legislation and of the protection of the nature that could affect you. Those areas shall be part of the protected zone register.

Article 24. Protected zone registration.

1. For each river basin district there shall be at least one register of areas which have been declared as the subject of special protection under specific rule on the protection of surface water or groundwater, or on habitat conservation and species directly dependent on water.

2. The record will necessarily include:

(a) The areas in which a water catchment is carried out for the production of water for human consumption, provided that it provides an average volume of at least 10 cubic metres per day or supplies more than 50 people, as, if any, the fenced protection perimeters.

(b) The areas which, according to the respective hydrological plan, are to be used in the future for the collection of water intended for the production of water for human consumption.

(c) Areas that have been declared to be economically significant aquatic species protection.

(d) Water masses declared for recreational use, including areas declared bathing water.

(e) Areas which have been declared vulnerable under the rules on the protection of waters against pollution caused by nitrates from agricultural sources.

(f) Areas which have been declared sensitive in application of the rules on the treatment of urban waste water.

g) declared habitat protection areas or species in which the maintenance or improvement of the state of the water is an important factor in their protection, including the Places of Community Importance, Special Areas Protection for Birds and Special Areas of Conservation integrated into the Natura 2000 network designated under Directive 92/43/EEC and Directive 79 /409/EEC.

h) The protection perimeters of approved mineral and thermal waters according to their specific legislation.

3. In the register they will also be included:

a) The surface water masses identified as river natural reserves according to the respective hydrological plan.

(b) The areas, basins or sections of basins, aquifers or bodies of water declared as special protection and collected in the hydrological plan.

c) Wetlands of international importance included in the Ramsar Convention List of 2 February 1971 as well as the wetlands included in the National Wetlands Inventory in accordance with the Royal Decree 435/2004, of March 12, which regulates the national inventory of wetlands.

4. The summary of the registration required as part of the hydrological plan shall include maps indicative of the location of each protected area, environmental information and conservation status, where appropriate, and a description of Community, national or regional legislation. local according to which they have been designated.

Article 25. Review, update, and query the protected zone registry.

1. The register of protected areas shall be reviewed and updated regularly and specifically together with the update of the relevant hydrological plan.

2. The competent authorities on the basis of the matter shall provide the relevant basin body with the necessary information to keep the register of protected areas of each river basin under the supervision of the Committee up to date. Competent Authorities of the Demarcation.

3. The register of protected areas shall be of permanent public consultation, without prejudice to requests for information made in accordance with Law 27/2006 of 18 July on the rights of access to information, public participation and access to justice in the field of the environment.

4. In cases where the review is carried out at a frequency lower than that provided for in the update of the hydrological plans, it shall be updated in accordance with the legislation under which the protected zone has been established.

Section 5. State Assessment of Water. Control networks

Article 26. Classification of the state of surface water.

1. The state of the surface water masses will be determined by the worst value of their ecological status and their chemical status.

2. The ecological status of surface water will be classified as very good, good, moderate, poor or bad.

3. For the classification of the ecological status of surface water bodies, biological, hydromorphological and physicochemical quality elements shall be considered in accordance with the normative definitions set out in Annex V. These elements shall be determine by means of indicators and numerical values shall be assigned to each boundary between the classes defined in the previous paragraph. In the case of indicators of the biological quality elements, they shall represent the relationship between the values of the biological parameters observed and the values corresponding to those parameters in the reference conditions.

4. The quality elements applicable to the artificial and highly modified water bodies shall be those which apply to the category of natural surface water which most resembles the mass of artificial or highly modified water in question. In the case of highly modified and artificial waters, the ecological potential shall be classified as maximum, good, moderate, deficient or bad.

5. The chemical status of the surface water will be classified as good or as not reaching the good state.

6. In order to classify the chemical status of the surface water bodies, the environmental quality standards for the hazardous substances in Annex IV, as well as the other environmental quality standards, shall be assessed at the control points. established. In the case of coastal and transitional waters only List I and List II priority of that Annex shall apply.

Article 27. Quality elements for the classification of the ecological status of rivers.

1. The biological quality elements for the classification of the ecological state of the rivers are the composition and abundance of aquatic flora and the benthic fauna of invertebrates and the composition, abundance and age structure of the fauna. ictiological.

2. The hydromorphological quality elements are the hydrological system, including flow rates, hydrodynamics of water flows and connection with groundwater bodies; the continuity of the river and the morphological conditions, including depth and width of the river, structure and substrate of its bed and structure of the riverside area.

3. The physicochemical quality elements are the thermal and oxygenation conditions, salinity, acidification status and nutrients. In addition, they are the contamination produced by the pollutants in Annex II to the Water Public Domain Regulation if they are dumped in significant quantities.

Article 28. Quality elements for the classification of the ecological state of the lakes.

1. The biological quality elements for the classification of the ecological state of the lakes are the composition, abundance and biomass of phytoplankton, the composition and abundance of other aquatic flora and the benthic fauna of invertebrates and the composition, abundance and age structure of the ictiological fauna.

2. The elements of hydromorphological quality are the hydrological regime, including volumes and hydrodynamics of the lake, length of stay and connection with groundwater, and the morphological conditions, including depth of the lake, quantity, structure and substrate of its bed and structure of the riverside area.

3. The elements of physicochemical quality are transparency, thermal and oxygenation conditions, salinity, acidification status and nutrients. In addition, they are the contamination produced by the pollutants in Annex II to the Water Public Domain Regulation if they are dumped in significant quantities.

Article 29. Quality elements for the classification of the ecological status of the transitional waters.

1. The biological quality elements for the classification of the ecological state of the transitional waters are the composition, abundance and biomass of phytoplankton, the composition and abundance of other aquatic flora and the benthic fauna of the invertebrates and the composition and abundance of the ictiological fauna.

2. The hydromorphological quality elements are the morphological conditions, including depth, quantity, structure and substrate of the bed and structure of the tide oscillation zone, and the tidal regime, including fresh water flow and exposure to the swell.

3. The elements of physicochemical quality are transparency, thermal and oxygenation conditions, salinity and nutrients. In addition, they are the contamination produced by the pollutants in Annex II to the Water Public Domain Regulation if they are dumped in significant quantities.

Article 30. Quality elements for the classification of the ecological status of coastal waters.

1. The biological quality elements for the classification of the ecological status of the coastal waters are the composition, abundance and biomass of phytoplankton and the composition and abundance of other aquatic flora and the benthic fauna of invertebrates.

2. The elements of hydromorphological quality are the morphological conditions, including depth, structure and substrate of the coastal bed and structure of the intertidal riparian zone, and the tidal regime, including direction of the currents dominant and exposure to the swell.

3. The elements of physicochemical quality are transparency, thermal and oxygenation conditions, salinity and nutrients. In addition, they are the contamination produced by the pollutants in Annex II to the Water Public Domain Regulation if they are dumped in significant quantities.

Article 31. Assessment and presentation of surface water status.

1. The assessment of the ecological status of each of the surface water bodies shall be based on the values of the biological, hydromorphological and physicochemical indicators obtained from the control programme.

2. The assessment of the chemical status of each surface water mass shall be carried out from the values obtained from the control programme.

3. The hydrological plan shall include maps showing, in each surface water mass, the ecological status or ecological potential and the chemical status of that mass. Such maps shall indicate the bodies of water in which it is not possible to achieve good ecological status or good ecological potential for non-compliance with environmental quality standards for specific pollutants.

Article 32. Classification of the state of groundwater.

1. The state of the groundwater masses will be determined by the worst value of their quantitative status and chemical status.

2. To classify the quantitative status of the groundwater masses, indicators will be used to use as a parameter the piezometric level of the groundwater. This status may be classified as good or bad.

3. To classify the chemical status of the groundwater masses, indicators will be used to use the concentrations of pollutants and conductivity as parameters. This status may be classified as good or bad.

Article 33. Assessment and presentation of groundwater status.

1. The assessment of the quantitative status of the groundwater masses shall be carried out in a comprehensive manner for the whole mass with the indicators calculated from the piezometric values obtained at the control points.

2. The assessment of the chemical status of the groundwater masses shall be carried out in a global manner for the whole mass with the indicators calculated from the values of concentrations of pollutants and conductivity obtained at the points of control.

3. The hydrological plan shall include maps showing, in each groundwater mass, the quantitative status and the chemical status of that mass. The chemical status map will indicate the groundwater masses with a significant and continuous trend of increasing concentrations of any contaminant.

Article 34. Water control programmes.

1. The hydrological plan shall include the control programmes of the waters established in the demarcation: the surveillance control, the operational control and the need for the control of the investigation.

2. The surveillance control aims to obtain a comprehensive overview of the state of the water masses. Its outcome will allow for the effective and effective conception of future control programmes and the assessment of long-term changes in natural conditions or the result of widespread anthropogenic activity.

3. The objective of the operational control is to determine the state of the water bodies at risk of not meeting environmental objectives. It also allows you to evaluate changes that occur in the state of these masses as a result of program measures.

4. In cases where the origin of the non-compliance with the environmental objectives is unknown, when the surveillance control indicates the improbability of the objectives being achieved and no operational control has been put in place at the end of the year, determine the causes for which it has not been possible to reach and to determine the extent and impact of accidental pollution, a research control will be established, from which the programme of measures required for the comply with the environmental objectives and, where appropriate, specific measures to remedy the effects of the accidental contamination.

5. The hydrological plan shall contain maps showing the location and characteristics of the points that make up the control programmes established for surface water, groundwater and protected areas.

6. The hydrological plan shall provide an assessment of the level of confidence and accuracy of the results achieved through the control programmes.

Section 6. Environmental Objectives

Article 35. Environmental objectives.

To achieve adequate water protection, the following environmental objectives must be achieved:

a) for surface water:

a ') Prevent the deterioration of the state of surface water masses.

b ') Protect, improve and regenerate all surface water bodies in order to achieve a good state of water.

c ') To progressively reduce pollution from priority substances and to eliminate or phase out discharges, emissions and losses of priority hazardous substances.

b) For groundwater:

a ') Avoid or limit the entry of pollutants into groundwater and prevent the deterioration of the state of all groundwater bodies.

b ') Protect, improve and regenerate groundwater bodies and ensure the balance between extraction and recharging in order to achieve good groundwater status.

c ') Investing significant and sustained trends in the increased concentration of any pollutant derived from human activity in order to progressively reduce groundwater contamination.

(c) For protected areas: comply with the requirements of the standards of protection that are applicable in an area and achieve the particular environmental objectives to be determined.

d) For the masses of artificial water and much modified water bodies: protect and improve the artificial and highly modified water masses to achieve good ecological potential and a good chemical state of surface water.

Article 36. Deadlines for achieving environmental objectives.

In relation to environmental objectives, the following deadlines must be met:

(a) The objectives shall be achieved by 31 December 2015.

(b) The time limit for the achievement of the objectives may be extended with respect to a given body of water if, in addition to a further deterioration of its status, one of the following circumstances occurs:

a ') When the necessary improvements to achieve the objective can only be achieved, due to technical possibilities, within a period exceeding the set.

b ') When compliance with the deadline is set at a disproportionately high cost.

c ') When natural conditions do not permit an improvement of the condition within the prescribed period.

(c) The extensions of the time limit, its justification and the measures necessary for the achievement of the environmental objectives relating to the water bodies shall be included in the river basin management plan, without any to exceed the date of 31 December 2027. The assumption that natural conditions will prevent the achievement of the objectives will be exempted from this deadline.

Article 37. Less stringent environmental objectives.

1. Where bodies of water which are heavily affected by human activity or natural conditions make it unfeasible to achieve the objectives identified or require a disproportionate cost, less stringent environmental objectives will be identified in the conditions to be established in each case by means of hydrological plans.

2. Such conditions shall include at least all of the following:

(a) that the socio-economic and ecological needs to which such human activity serves cannot be achieved by other means which constitute a significantly better ecological alternative and which does not entail a cost disproportionate.

(b) To ensure the best possible ecological status and chemical status for surface water and the minimum possible changes in the good status of groundwater, taking into account, in both cases, the effects of could not be reasonably avoided due to the nature of the human activity or the contamination.

c) No further deterioration of the status of the affected water mass.

Article 38. Temporary deterioration of the state of the water masses.

1. The temporary deterioration of the state of the water bodies may be allowed if it is due to natural or force majeure which are exceptional or have not been reasonably foreseen, in particular severe floods and prolonged droughts, or the result of circumstances arising from accidents which could not have been reasonably foreseen.

2. To allow such deterioration all the following conditions must be met:

(a) That all feasible measures be taken to prevent further deterioration of the state and not to endanger the achievement of environmental objectives in other bodies of water not affected by these circumstances.

(b) The conditions under which such circumstances may be declared as rationally unforeseen or exceptional, including the adoption of appropriate indicators, are specified in the hydrological plan. In the case of extreme hydrological situations, these conditions shall be derived from the studies to be carried out in accordance with Article 59 and the indicators set out in the drought plans shall be included in the register. in the hydrological plan, as referred to in Article 62.

(c) The measures to be taken in such exceptional circumstances shall be included in the programme of measures and do not jeopardise the recovery of the quality of the water body after the circumstances have ceased.

(d) that the effects of circumstances which are exceptional or which have not been reasonably foreseen are reviewed annually and all feasible measures to return the situation are taken as soon as reasonably practicable; water mass to its previous state for the purposes of those circumstances, without prejudice to the provisions of the additional provision (11th 1.b) of the recast text of the Water Act.

e) That the following update of the hydrological plan includes a summary of the effects produced by these circumstances and of the measures that have been taken or are to be taken.

Article 39. Conditions for new modifications or alterations.

1. Under the conditions set out in paragraph 2, new modifications of the physical characteristics of a surface water mass or alterations in the level of groundwater bodies may be permitted even if they prevent a good state from being achieved. ecological, good groundwater status or good ecological potential, if any, or assume the deterioration of the state of a surface water or groundwater mass. In addition, and under the same conditions, new human activities of sustainable development may be carried out even if they cause deterioration from the very good condition to the good condition of a surface water mass.

2. The following conditions must be met in order to accept such modifications or alterations:

a) That all feasible measures be taken to alleviate the adverse effects on the state of the water mass.

b) That the reasons for the modifications or alterations are specified and specifically explained in the hydrological plan.

(c) The reasons for changes or alterations are of higher public interest and that the environmental and societal benefits of achieving environmental objectives are compensated for by the benefits of new modifications or alterations to public health, maintenance of human security or sustainable development.

(d) that the benefits obtained from such modifications or alterations of the water mass cannot be achieved, for reasons of technical feasibility or disproportionate costs, by other means constituting an option; significantly better environmental.

Section 7. Economic Analysis of Water Use

Article 40. Economic analysis of water use.

The hydrological plan will include a summary of the economic analysis of water use that will comprise the economic characterization of water use and the cost recovery analysis of water services.

Article 41. Economic characterization of water use.

1. The economic characterization of water use will include an analysis of the importance of this resource for the economy, the territory and the sustainable development of the river basin, as well as the economic activities to which the water contribute significantly, including a forecast on their possible evolution.

2. This characterization shall comprise at least for each activity the following indicators: value added, production, employment, dependent population, social structure and productivity of water use.

3. The forecasts for the determining factors, the evolution of economic activities, the demands for water and the pressures correspond to the scenario that would occur if measures were not applied. This scenario shall be the reference point necessary for the analysis of the effectiveness of the programme of measures taken in the hydrological plan.

4. The design of this scenario will take into account the forecasts of the temporal evolution of the determining factors, including demography, the evolution of the habits of water consumption, the production, the employment, the technology or the effects of certain public policies. The hydrological plan shall include different scenarios for the evolution of these factors.

5. The economic characterization of water use shall be carried out both in the demand units defined in the hydrological plan as set out in Article 13 as a whole for the set of the river basin district.

Article 42. Recovery of the cost of water services.

1. The competent authorities shall take into account the principle of recovery of the costs of services related to water management, including environmental and resource costs, in the light of the long-term projections of their supply. and demand.

2. The hydrological plan shall include the following information on the recovery of water service costs:

a) Water services, describing the agents that provide them, the users who receive them, and the rates applied.

(b) Capital costs of the investments required for the provision of the different water services, including accounting costs and grants, as well as administrative, operating and maintenance costs.

c) Environmental and resource costs.

d) Discounts, such as those due to street lamination or to future users.

e) Users ' income from water services.

f) The current level of cost recovery, specifying the contribution made by the various water uses, broken down, at least, in supply, industry and agriculture.

3. For each operating system, the forecast of investments in services shall be specified in the horizons of the Plan.

4. The hydrological plan shall incorporate the description of the situations and reasons for exceptions in the application of the principle of cost recovery, analysing the social, environmental and economic consequences as well as the conditions the geographical and climatic conditions of each territory, provided that this does not compromise the aims or the achievement of the established environmental objectives, in accordance with the provisions of Article 111 bis 3 of the recast of the Water Law.

5. The cost recovery analysis shall be carried out on the demand units defined in the hydrological plan as set out in Article 13 as a whole for the whole of the river basin district.

Section 8. Action Programs

Article 43. Program of measures.

1. For each river basin district a programme of measures shall be established, taking into account the results of the studies carried out to determine the characteristics of the demarcation, the impact of human activity on its waters, as well as the economic study of water use therein.

2. The aim of the programme of measures shall be to achieve the environmental objectives set out in Article 92a of the recast of the Water Act.

3. The programmes of measures must comply with criteria of economic rationality and sustainability in the achievement of environmental objectives.

4. The measures may be basic and complementary:

(a) Basic measures are the minimum requirements that must be met in each demarcation and are set out in Articles 44 to 53, both inclusive.

(b) The accompanying measures are those which in each case should be applied in addition to the achievement of the environmental objectives or to achieve additional water protection.

5. The programme of measures shall be integrated by the basic and complementary measures which, in the field of their competence, are approved by the competent authorities in the protection of waters.

6. The selection of the most appropriate combination of measures, especially in the case of complementary measures, will be supported in a cost-effectiveness analysis. This analysis will consider the economic, social and environmental aspects of the measures.

7. The selection of the set of measures will take into account, in addition to the results of the cost-effectiveness analysis, the effects of the various measures on other environmental and social problems, even if they do not directly affect ecosystems aquatic, in accordance with the process of strategic environmental assessment of the plan indicated in this regulation.

8. The application of the basic measures cannot, under any circumstances, directly or indirectly lead to further contamination of surface water, except in the case that, in the absence of such measures, further contamination of the surface water is not possible. environment as a whole.

Article 44. Relationship of Basic Measures.

The following measures are considered basic:

(a) Measures necessary to implement the legislation on water protection, including those relating to the protection of water intended for the production of water for human consumption provided for in the fourth final provision of the text recast of the Water Act and, in particular, those aimed at reducing the necessary treatment for the production of water for human consumption.

(b) Measures for the implementation of the principle of recovery of the costs of water management services.

(c) Measures to promote the efficient and sustainable use of water in order to contribute to the achievement of environmental objectives.

(d) Control measures on water extraction and storage, in particular those relating to the Water Register.

(e) Control measures on discharges and other activities having an impact on the state of the water, including the management of direct and indirect discharges into the public hydraulic domain and the waters under protection by the text recast of the Water Act.

f) Prohibition of direct discharges into groundwater, except under certain conditions.

(g) Measures for the dangerous substances listed in List I, list II preferred and priority II listed in Annex IV.

h) Measures to prevent or reduce the impact of episodes of accidental contamination.

i) Guidelines for the recharge and protection of aquifers.

Article 45. Measures to implement legislation on water protection.

1. They shall be all measures necessary to ensure that the objectives laid down in Community legislation on water protection, as set out in Annex III, are met, in accordance with the incorporation of the legislation in question.

2. The hydrological plan shall contain all of these measures, including separately those related to water for human consumption.

3. In addition, the hydrological plan shall include plans and programmes which the competent authorities have developed to comply with water protection legislation, including in particular those relating to sanitation and purification of water. urban agglomerations and action programmes in areas vulnerable to nitrate pollution.

Article 46. Measures for the implementation of the principle of recovery of water usage costs.

1. The hydrological plan shall include information on the measures intended to be taken by the competent authorities to take account of the principle of the recovery of the costs of services related to the management of the waters, including environmental and resource costs.

2. These measures may include proposals for the revision and updating of tariff structures, in particular in relation to the incorporation of environmental and resource costs, including environmental damage assessment formulas.

Article 47. Measures to promote the efficient and sustainable use of water.

1. The hydrological plan shall include information on the measures to be taken, in particular related to the water price policy, which provide appropriate incentives for users to use water resources efficiently and, therefore contribute to the fulfilment of the environmental objectives pursued.

2. In the event that no water pricing policies have been implemented that provide adequate incentives for the fulfilment of the environmental objectives, the hydrological plan shall include a report justifying the reasons.

3. The hydrological plan shall also incorporate information on other market economic instruments, incentives and voluntary measures to promote the efficient and sustainable use of water.

4. The hydrological plan will contain a list of measures in the field of urban supply conducive to the rational and sustainable management of water, including awareness campaigns in society, the use of savings devices (a) the elimination of water supply networks, the reuse of water treatment plants in the irrigation of parks and gardens, and others that fall within the basic principles of water conservation and management of water, demand.

5. The hydrological plan shall include a list of measures in the field of irrigation that contribute to the achievement of good water status, including the basic standards conducive to the adoption of the most appropriate irrigation methods for the different types of climates, lands and crops, the necessary water resources for the various alternatives and the conditions of drainage required, as well as the promotion of adapted agricultural production and water saving irrigation techniques. They shall also include conditions for the reuse of irrigation water and any other conditions that are necessary to ensure the best use and conservation of the water and land pool and sustainable development. The adaptations to be made, where appropriate, by both the competent authorities and by individuals in the existing realizations, shall be collected in order to ensure the rational use of these natural resources.

6. The hydrological plan will lay down the criteria to be applied for the evaluation of industrial and energy use, which will mainly cover the economic, social, demand and opportunity aspects. to ensure the protection of waters and the achievement of good status.

7. In order to promote more efficient and sustainable use of water, the hydrological plan shall establish the criteria for concessional review under Article 65.c) and the transitional provision sixth of the recast text of the Water Act.

8. Indicators of efficiency and sustainability will be included in the hydrological plan to monitor measures throughout the development of the plan.

Article 48. Control measures on water extraction and storage.

1. The control measures on water extraction and storage include the update of the Water Register defined in Article 80 of the recast of the Water Act and other measures set out in Title II of the Domain Regulation. Hydraulic Public.

2. The hydrological plan shall include the measures to be taken to control the volumes brought and the actual consumption in the river basin district, including the criteria for the installation of meters and other measuring instruments.

Article 49. Control measures on spot discharges and other activities having an impact on the state of the water.

1. In the case of specific discharges which may cause contamination, the measures shall include, inter alia, the requirement for the authorisation of discharges of waste water.

2. In the case of diffuse sources which may lead to contamination, measures shall be taken to prevent or control the entry of pollutants. Such measures may consist of a requirement of prior regulation, such as the prohibition of the entry of pollutants into the water, the requirement for prior authorisation of activities to generate diffuse pollution or the requirement of registration based on general rules of a binding nature, where this requirement is not otherwise laid down in the legislation. Such checks shall be reviewed regularly and, where appropriate, updated.

3. For any other significant adverse effects on water status, measures shall be included to ensure in particular that the hydromorphological conditions of the water bodies are in line with the achievement of the necessary ecological status. or the good ecological potential of water bodies designated as artificial or highly modified. The checks carried out for this purpose may consist of the requirement of prior authorisation or registration based on general binding rules, where this requirement is not otherwise established in the legislation. Such checks shall be reviewed regularly and, where appropriate, updated.

4. In addition, the measures set out in Title III of the Regulation of the Public Domain of Water for the Protection of the Water Public Domain and the Quality of Continental Waters shall be considered.

Article 50. Direct discharges into groundwater.

1. Without prejudice to the prohibition of discharges as referred to in Article 100.1 of the recast of the Water Act, the hydrological plan shall identify, if available, those cases in which direct discharges to bodies of groundwater are authorised. as well as the conditions of such authorization.

2. The measures laid down in Title III, Chapter II of the Regulation on Hydraulic Public Domain, and in particular those provided for in Section IV concerning discharges into groundwater, shall apply.

Article 51. Measures with regard to hazardous substances.

1. The measures include, inter alia, the requirement for the authorisation of all discharges of waste water with dangerous substances in Annex IV to this Regulation which shall be limited in accordance with Article 100.2 of the text. recast of the Water Law. Such authorisations shall consider the emission limit values for hazardous substances with specific regulation, as well as the environmental quality standards that have been approved in regulation or which are approved in the future.

2. Measures to progressively reduce or eliminate the dangerous substances in Annex IV, and in particular those listed in the priority II list, shall be considered.

Article 52. Measures to prevent or reduce the impact of episodes of accidental contamination.

1. Measures will be taken to prevent or reduce the effects of accidental pollution caused by industry, by livestock facilities, by the stormwater tanks of urban waste water treatment plants and others. These measures shall include the use of automatic systems to detect or alert them.

2. Accidental pollution from floods shall include, inter alia, the use of automatic systems to detect or alert them.

3. All appropriate measures to be taken to reduce the risk of damage to the aquatic ecosystem in the event of accidents that could not have been reasonably foreseen shall be included.

Article 53. Guidelines for the recharge of aquifers.

1. The hydrological plan will collect, when they exist, the areas of artificial recharge of groundwater bodies, for which the objective of the recharge will be detailed, as well as the origin, quantity and quality of the resources applied, including the authorization allowing the reloading. The successive reloading areas to be determined will be incorporated into the Plan as they are authorised.

2. The resources applied for the artificial recharge may be obtained from any surface water, underground, regenerated or desalted, provided that the use of the source does not compromise the achievement of the environmental objectives set for the Source or mass of recharged water and may not generate risk situations for public health.

Article 54. Guidelines for the protection of aquifers.

1. The hydrological plan shall determine the basic criteria for the protection of groundwater against the various causes of deterioration, including saline intrusion.

2. The hydrological plan shall include the ratio of the groundwater masses at risk of not achieving good status, which have been designated as such by the basin body, as well as the measures taken to avoid such risk.

3. The measures referred to in the preceding paragraph shall include an action programme for the recovery of the good state of the water mass. The action programme will order the extraction regime and the rules on water use to achieve a rational exploitation of resources until the good state of the groundwater masses is achieved.

4. The hydrological plan shall establish for each groundwater mass, as required, rules for granting concessions, referred to the maximum instantaneous flow rate, distances between the use of water, drilling and installation of pumps, sealing of abandoned or disused wells, as well as the conditions to be met by the concessions to be considered of minor importance.

Article 55. Accompanying measures.

1. The programme of measures shall include the accompanying measures which in each case should be applied with additional character for the achievement of the environmental objectives or for the achievement of additional water protection.

2. Complementary measures may include legislative, administrative, economic or fiscal instruments, agreements negotiated in the field of the environment, codes of good practice, establishment and restoration of wetlands, management measures of the demand, reuse and desalination, construction and rehabilitation projects, as well as educational, research, development and demonstration projects. In particular, the programme of measures shall include the accompanying measures detailed in Articles 56 to 60 inclusive.

Article 56. Measures for water bodies with little chance of achieving environmental objectives.

1. In those bodies of water where the results of the risk assessment indicate that the environmental objectives are unlikely to be achieved, the additional measures necessary to achieve them, including those which can be found, will be established. the establishment of stricter environmental quality standards, unless the circumstances referred to in the following paragraph are provided.

2. Where the causes of failure to achieve environmental objectives are natural, force majeure or have not been reasonably foreseen, in particular severe floods and prolonged droughts, it may be determined that it is not feasible to adopt measures additional and allow temporary deterioration in accordance with Article 38.

Article 57. Protective perimeters.

1. The hydrological plan may fix the protective perimeters referred to in Article 97 of the recast of the Water Act, prohibiting the exercise of activities which may constitute a danger of contamination or degradation of the water. Hydraulic public domain. In these perimeters the rules laid down in the Regulation of the Public Hydraulic Domain for the police zones are applicable.

2. The perimeters referred to in Article 56 of the recast of the Water Law, established in order to protect the state of the groundwater masses, will also be collected in the hydrological plan.

3. The Plan shall include the areas for the protection of water supplies for human consumption included in the register of protected areas.

Article 58. Measures to prevent an increase in marine water pollution.

1. It will be all measures aimed at disrupting or phasing out discharges, emissions and losses of priority hazardous substances, with the ultimate aim of achieving concentrations in the marine environment close to the basic values with regard to substances of natural origin and close to zero in respect of man-made synthetic substances, as laid down in Article 108a of the recast text of the Water Act.

2. These measures will be in line with the objectives laid down in the existing regulations which, in order to avoid an increase in the pollution of marine waters, will recognise the Kingdom of Spain in application of the international conventions of protection of the marine environment of which it is a party, as well as the normative provisions laid down in Community law, national law and regional law in the field.

3. The hydrological plan shall separately collect those established to prevent an increase in marine pollution.

Article 59. Extreme hydrological situations.

1. The hydrological plan, with the historical data available on rainfall and maximum and minimum flows, will establish the criteria for carrying out studies and the determination of actions and works related to hydrological situations. extreme. As a result of these studies, the conditions under which temporary deterioration may be permitted in extreme hydrological situations, as well as the water bodies referred to in Article 38, shall be determined.

2. It shall establish the measures to be taken in exceptional circumstances corresponding to extreme hydrological situations, including the implementation of specific plans or programmes such as those referred to in Article 62.

3. The competent authorities shall delimit the flood zones taking into account the studies and data available to the catchment bodies to be transferred to them, in accordance with the provisions of Article 11.2 of the recast text of the Law. Water. To this end, they shall have the technical support of these bodies and, in particular, with the information relating to maximum flows in the river network, which the hydraulic administration shall provide.

Article 60. Basic infrastructure.

1. For the purposes of their mandatory inclusion in the hydrological plan, basic infrastructure shall be defined as the works and actions which form an integral part of the operating systems making possible the supply of resources provided for in the Plan. for the different time horizons and the fulfilment of the environmental objectives set for the water bodies.

2. The hydrological plan shall incorporate the catalogue of basic infrastructures which shall include the corrective actions for the achievement of the environmental objectives, for the different time horizons referred to in Article 19 with the the definition of what is available at that time.

Article 61. Cost-effectiveness analysis of the measures.

1. Cost-effectiveness analysis will be an instrument to take into account for the selection of the most appropriate measures to achieve the environmental objectives of the water bodies, as well as to analyse the alternative measures in the cost analysis. disproportioned.

2. In order to carry out the cost-effectiveness analysis, the assessment of the state of the water masses corresponding to the trend scenario and its difference with respect to the environmental objectives will be carried out. The assessment of the states involved in the implementation of the various measures and the difference in the environmental objectives will make it possible to analyse the effectiveness of each of these measures.

Section 9. Other Required Content

Article 62. Record of the most detailed programs and plans.

1. The hydrological plans will take into account in their elaboration the special plans of action in situations of alert and eventual drought, elaborated by the basin agencies in compliance with article 27 of the Law 10/2001, of July 5, of the Plan National Hydrologic, which will incorporate a summary, including the system of indicators and operating thresholds used and the main measures of prevention and mitigation proposed.

2. They will also take into account the plans drawn up in the territorial area of the demarcation related to flood protection, which will incorporate a summary, including risk assessment and measures. adopted.

3. The hydrological plan shall take into account in its preparation those plans and programmes which are more detailed on the waters carried out by the competent authorities in the area of demarcation of which the relevant summaries will be incorporated.

Article 63. Public and query information measures.

The hydrological plan shall contain a summary of the public information and consultation measures that have been applied during its processing, its results and the consequent changes made to the plan, as indicated in Articles 71 to 80 inclusive.

Article 64. List of designated competent authorities.

The hydrological plan shall include the following information on the competent authorities of the river basin district:

(a) Name and official address of the designated competent authorities.

(b) Description of the equivalent status or legal document of the competent authorities.

(c) Description of the legal and administrative responsibilities of each competent authority and its role within the river basin district.

d) Summary of the institutional relationships established to ensure coordination, in the case of river basin districts that include river basins shared with other countries.

Article 65. Contact points and procedures for obtaining documentation and information.

The hydrological plan will include the contact points and established procedures to obtain the base documentation and information required by public consultations.

Section 10. Previews of river basin management plans

Article 66. Water and land reserves.

1. In the river basin management plans, reserves, water and land may be established, necessary for the actions and works envisaged.

2. The reserve of resources shall be established in accordance with Article 20. The reserve of land shall comprise those necessary for the implementation of the basic infrastructure referred to in the hydrological plan referred to in Article 60.

3. The catchment bodies shall forward to the competent public authorities in the field of spatial planning and urban planning the delimitations of the areas subject to reserve for the purposes referred to in Article 43.3 of the text. recast of the law of waters.

CHAPTER II

National Hydrological Plan Content

Article 67. Content of the National Hydrological Plan.

1. The National Hydrological Plan shall be approved by standard or standards with a law range and shall contain, in any case:

(a) The necessary measures for the coordination of the different river basin management plans.

b) The solution for possible alternatives that those offer.

c) The forecast and conditions for transfers of water resources between territorial areas of different river basin management plans.

(d) Changes to be made in the planning of the use of the resource and affecting existing uses for population supply or irrigation.

2. The National Hydrological Plan shall also contain the delimitation and characterization of the groundwater masses shared between two or more demarcations, including the allocation of resources to each of them.

3. The declaration as hydraulic works of general interest for the infrastructure necessary for the transfer of resources, as referred to in Article 67,1 of this Regulation, may be carried out only by the legal standard which it approves or amends National Hydrological Plan.

Article 68. Coordination of river basin management plans.

1. The measures for the coordination of river basin management plans shall be governed by the general principles of precaution, rationality, sustainability, protection of the public hydraulic domain, the good status of water and the protection of water flows. ecological.

2. The coordination of the different hydrological plans will be carried out in the National Hydrological Plan considering the various sectoral plans of general character, in particular the agricultural, the energetic, the planning of the territory and the urban planning, as well as the protection of the environment and nature, all within the framework of the general policy of the State and its economic planning.

Article 69. Conditions for transfers.

1. In the drafting of the National Hydrological Plan, the transfers of resources between different hydrographic districts will be contemplated and specified, establishing the conditions to be adjusted. For each of the planned transfers, the annual volume as well as the conditions that may temporarily modify the volume shall be established.

2. The forecasts and conditions of the transfers referred to in Article 67,1 (c) shall not result in the failure to meet the environmental objectives set out in Section 6 of Chapter I of this Title.

3. The National Hydrological Plan project may include, where appropriate, the determining conditions for the technical exploitation and economic management of the transfer of water resources which is appropriate, or to entrust the Government with its establishment.

Article 70. Modifications to the resource usage schedule.

In addition, in the drafting of the National Hydrological Plan, modifications will be made that according to the planning of the use of the resource will affect existing uses for the supply of populations or irrigation.

TITLE II

Elaboration and approval of hydrological plans

CHAPTER I

Of Basin Hydrological Plans

Section 1. General Provisions

Article 71. General provisions.

1. The drawing up and proposal of subsequent reviews of the river basin management plans shall be carried out by the relevant catchment area or by the competent hydraulic administration in the basins covered in full in the area. territory of the autonomous community.

2. The procedure for the elaboration and revision of the river basin management plans is regulated in this regulation and must include, in any case, the programming of calendars, work programmes, elements to be considered and previous drafts for enable appropriate public information and consultation from the start of the process.

From this start and at all stages of the process, the appropriate means of coordination will be sought for the effective integration of the land and sea area of the demarcation in the elaboration of the plans.

In addition, consideration should be given to the preparation, by the competent authorities, of the programmes of basic and complementary measures referred to in Article 92 (c) of the recast of the Water Law and the Articles 43 et seq. of this regulation, which are conducive to the achievement of the environmental objectives set out in the recast of the Water Act. The programme of measures shall be coordinated and integrated into the hydrological plans.

In an express manner, programs related to coastal and transitional waters developed by the General Administration of the State, or by autonomous communities, should be coordinated for integration into the hydrological plan. participate in the Committee of Competent Authorities of the Demarcation and which have littoral.

3. The drawing up and review of river basin management plans will require the participation of the ministerial departments concerned, the time limits for submission of proposals by the relevant bodies and the action taken. Government subsidiary in case of lack of proposal. Public participation in the entire planning process will be ensured, in any case, both in the phases of prior consultation and in the development and approval or review of the plan. For such purposes, the time-limits provided for in the additional twelfth provision of the recast of the Water Act shall be met.

4. The hydrological plans shall be drawn up in coordination with the various sectoral schedules affecting them, both in terms of water uses and land use, and in particular with regard to the planning of irrigation and other uses. farm.

5. The Government may make the declaration of public utility of the works, studies and research required for the elaboration and review of the hydrological plans carried out by the services of the Ministry of the Environment, Geological and Mining Institute of Spain or any other body of public administrations.

6. The hydrological plans shall be subject to the strategic environmental assessment procedure as laid down in Law 9/2006 of 28 April on the assessment of the effects of certain plans and programmes on the environment.

Section 2. Public Participation

Article 72. Organization and procedure for making public participation effective.

1. The basin organizations shall formulate the project of organization and procedure to be followed to make public participation in the planning process effective.

2. The project shall include at least the following contents:

(a) Organisation and timetables of the procedures for public information, public consultation and active participation of the hydrological plan as indicated in this Regulation.

b) Coordination of the process of strategic environmental assessment of the hydrological plan and its relationship with the above procedures.

c) Description of the methods and techniques of participation to be used in the different phases of the process.

Article 73. Public information.

1. The process of drawing up the plans will incorporate the requirements set out in Law 27/2006, of July 18, in particular those concerning the active supply of substantive information for the planning process and that will result additional to that listed in this Regulation.

2. This information shall be accessible on paper and in digital format on the electronic pages of the Ministry of the Environment and on the respective hydrographic demarcations.

Article 74. Public consultation.

1. The public consultation shall be carried out on the documents referred to in Articles 77 to 80, including those which may be added to other documents, of a divulgative nature, to facilitate this process.

2. These documents shall be accessible on paper and in digital format on the electronic pages of the Ministry of the Environment and on the respective hydrographic demarcations.

3. The duration of the public consultation process for each document shall be at least six months. Contributions from the public consultation will be integrated into reports that will be part of the planning process and will be included in an annex to the plan.

Article 75. Active participation.

1. The catchment bodies shall encourage the active participation of stakeholders in the planning process by extending such participation to the general public.

2. They may also constitute forums or working groups involving, in addition to the interested parties, persons of recognized prestige and experience in the field of water that advise in the process of elaboration of the hydrological plans.

Section 3. Elaboration

Article 76. Stages in the preparation of river basin management plans.

1. Prior to the preparation and proposal for the revision of the hydrological plan, a work programme shall be prepared including, in addition to the timetable for the phases envisaged for such preparation or revision, the general study on the demarcation corresponding.

2. After these preliminary work, the procedure for the preparation of the river basin management plans will be carried out in two stages: a first one, in which an outline of the important issues of water management in the basin will be developed. Hydrographic demarcation, and another drafting of the plan itself.

Article 77. Work program.

1. The proposal for a work programme for the elaboration of the basin plans will be developed by the basin agencies.

2. This programme will include the main tasks and activities to be carried out, the planned timetable, the overall study of the demarcation and the consultation formulas.

3. It will collect the contact points and procedures required to obtain the basic documentation and information required by the public consultations.

4. The programme shall coordinate the own consultation processes of the plan and those required by the strategic environmental assessment, taking as a reference the information referred to in this Regulation.

5. The proposal for a work programme shall be made available to the public at least three years before the start of the procedure for the approval of the plan for the formulation of comments and suggestions for a period of time. less than six months, all in the form set out in Article 74.

Article 78. Contents and elaboration of the general study on demarcation.

1. The general study on the river basin demarcation included in the work programme shall incorporate a general description of the characteristics of the demarcation, a summary of the impact of human activity on the state of the water. surface and groundwater and an economic analysis of water use, in accordance with the provisions of Article 41.5 of the recast of the Water Act.

2. The general description of the characteristics of the demarcation shall include:

a) Description of the administrative, physical and biotic framework of the demarcation, as well as the territorial model, including landscape and hydraulic heritage.

b) The location and limits of the surface water masses, both continental and coastal and of transition, including artificial and highly modified water bodies, types and specific reference conditions of each type.

c) The location, limits, and characterization of groundwater bodies.

d) The available hydrological statistics on precipitation, evaporations, runoff and how much information is relevant for the adequate quantitative and qualitative assessment of surface water resources and subways.

e) Historical information available on maximum and minimum rainfall and flow rates.

3. The summary of the impact of human activity on the state of surface water and groundwater shall include:

a) Significant pressures on the surface water masses, including point and diffuse source contamination, flow rate extraction and regulation, morphological alterations, and other types of incidence anthropogenic, as well as impact assessment and identification of the masses at risk of not meeting environmental objectives.

b) Significant pressures on groundwater bodies, including point and diffuse source contamination, water extraction and artificial recharge, as well as impact assessment and identification of the masses at risk of not meeting environmental objectives.

c) Water quality statistics.

d) The available statistics on water supplies and consumption in the different areas and sub-areas specifying the origins of the resource applied and the uses to which it is intended.

e) Data on piezometric levels in aquifers.

f) The inventory of large hydraulic infrastructures and their fundamental characteristics from the point of view of the regulation and availability of resources in quantity and quality.

4. The economic analysis of water use will include:

a) The institutional map of water management services.

(b) The information to carry out calculations on the recovery of water services costs, including environmental and resource costs, in line with the long-term projections of their supply and demand and, in their case, the volume forecasts, prices, investments and costs associated with those services.

c) A summary, with global data for the demarcation set, of the cost recovery analysis, including the cost of services for the various water uses and the degree of cost recovery by the users.

d) Information on the forecasts of the potential costs of the measures to carry out the cost-effectiveness analysis for inclusion in the programme of measures.

e) The economic characterization of water use, including trend analysis.

5. The basin bodies, integrating the contributions from the different competent authorities, will develop this general study of the demarcation.

Article 79. Outline of important issues regarding water management in the demarcation.

1. The outline of important water management issues will contain the description and assessment of the main current and foreseeable problems of water-related demarcation and the possible alternatives for action, all of which are the programmes of measures drawn up by the competent authorities. The possible decisions that can be taken to determine the different elements that make up the Plan and offer solutions to the problems listed will also be concretized.

2. In addition to the above mentioned in the preceding paragraph, the scheme will include:

a) The main pressures and impacts to be addressed in the hydrological plan, including sectors and activities that may pose a risk to environmental objectives. Specifically, the potential impacts on coastal and transitional waters will be analysed as a result of pressures on inland waters.

b) Possible alternatives for action to achieve environmental objectives, in accordance with the programmes of basic and complementary measures, including their economic and environmental characterization.

c) The sectors and groups affected by the measures programs.

3. The basin organizations will draw up the outline of important water management issues, provided for in the additional twelfth provision of the recast text of the Water Law, integrating the information provided by the Committee of Authorities. Competent.

4. The provisional scheme of major issues will be submitted, at least two years before the start of the procedure for the approval of the plan, to the interested parties. This consultation shall be carried out in accordance with Article 74, in order for interested parties to submit, within three months, any proposals and suggestions they consider appropriate.

5. At the same time, the provisional scheme will be made available to the public for a period of not less than six months for the formulation of comments and suggestions, all in the form set out in Article 74. During the development of this consultation, the environmental assessment procedure of the plan will be initiated with the initial document, which will incorporate the interim outline of important topics.

6. After the consultations referred to in paragraphs 4 and 5 have been completed, the basin bodies shall make a report on the proposals, comments and suggestions which have been submitted and shall incorporate those which they consider appropriate to the scheme. The Council of Ministers of the European Union

take the necessary measures to ensure that the water resources are not included in the water supply.

Article 80. Project of river basin management plan.

1. In the second stage of the elaboration of the project of hydrological plan, the basin organizations, with the information provided by the Committee of Competent Authorities, will draft the environmental sustainability report and the corresponding proposal of the in accordance with the outline of important issues in the management of water, the contents of the reference document drawn up by the environmental body in the process of environmental assessment of the hydrological plan and taking into account all queries made.

2. The proposal for a project for a hydrological plan and the environmental sustainability report shall be submitted, at least one year before the start of the procedure for the approval of the plan, to the parties concerned to submit, in the three months ' time, proposals and suggestions that they consider appropriate.

3. At the same time, the proposal for a project for a hydrological plan shall be made available to the public for a period of not less than six months for the formulation of comments and suggestions in the form set out in Article 74.

4. In the light of the consultations referred to in paragraphs 2 and 3, the basin bodies shall make a report on the proposals, comments and suggestions which have been submitted and shall incorporate those which they consider appropriate to the proposal for a hydrological plan, which will require the mandatory report of the Water Council of the demarcation. The final wording of the proposal will take into account the environmental memory elaborated in the environmental assessment process.

5. This proposal for a project of hydrological plan, with the agreement of the Committee of Competent Authorities, will be elevated to the Government through the Ministry of Environment, in accordance with article 35.2 of the recast text of the Law of Waters.

Article 81. Formal structure of the river basin management plan.

The hydrological plan will have the following formal structure:

a) Memory. It shall include at least the required content as described in Article 4 and may be accompanied by any such documents deemed necessary.

b) Regulations. It will include the contents of the Plan with a normative nature and will at least be the following: identification and delimitation of surface water bodies, reference conditions, designation of artificial waters and highly modified waters, Identification and delimitation of groundwater bodies, priority and compatibility of uses, ecological flow rates, definition of operating systems, allocation and reserve of resources, definition of natural river reserves, special protection regime, environmental objectives and temporary deterioration of the state of the Water bodies, conditions for new modifications or alterations and organisation and procedure for making public participation effective.

Article 82. Additional technical instructions and recommendations.

The Ministry of the Environment may issue additional technical instructions and recommendations for the elaboration of the hydrological plans that it considers appropriate for the homogenization and systematization of the works. These instructions and technical recommendations shall be given to the departments concerned as soon as they are likely to affect them.

Section 4. Approval

Article 83. Approval of river basin management plans.

1. Projects for river basin management plans drawn up in accordance with Article 80 of this Regulation or in the rules of procedure which may be issued by the Autonomous Communities, where appropriate, shall be submitted by the Ministry of the Environment. Environment to the National Water Council to issue the mandatory report provided for in Article 20 of the recast text of the Water Act.

2. Issued this report, the Ministry of Environment will raise the hydrological plans for approval to the Government if it is sourced.

3. The Government, by means of a royal decree, shall approve the river basin management plans in the terms it considers to be based on the general interest, without prejudice to the following paragraph.

4. River basin management plans which have been drawn up or revised pursuant to Article 18 of the recast text of the Water Act shall be approved if they comply with the requirements of Articles 40.1, 3 and 4 and 42 of the text. recast of the Law of Waters, do not affect the resources of other basins and, where appropriate, are accommodated to the determinations of the National Hydrological Plan.

CHAPTER II

of The National Hydrological Plan

Article 84. Public participation in the elaboration of the National Hydrological Plan.

1. In the preparation of the National Hydrological Plan, the public participation in the entire planning process will be guaranteed, both in the phases of previous consultations and in the development and approval or revision of the Plan, according to established in Article 41.3 of the recast of the Water Act.

2. The proposal for a National Hydrological Plan project should be accessible on paper and in digital format on the electronic pages of the Ministry of the Environment.

3. A direct consultation on the proposal for a National Hydrological Plan project will be carried out.

4. The duration of the public consultation process shall be at least six months. Contributions from the public consultation will be gathered in a report that will be part of the planning process.

5. The National Hydrological Plan shall be the subject of the strategic environmental assessment procedure as laid down in Law 9/2006 of 28 April.

6. The Ministry of the Environment will adopt the necessary measures for public access to the technical documentation that constitutes the background and budgets of the National Hydrological Plan and, to this effect, will order an official edition of the same in the the memory and all its attachments are included.

Article 85. Elaboration of the National Hydrological Plan.

1. It will be up to the Ministry of the Environment to draw up the National Hydrological Plan, together with the ministerial departments related to the use of water resources.

2. To this end the Government shall establish, on a proposal from the Ministry of the Environment, appropriate mechanisms.

Article 86. Approval of the National Hydrological Plan.

1. The National Hydrological Plan Project will be submitted by the Ministry of the Environment to the National Water Council to issue its mandatory report, as provided for in Article 20 of the recast text of the Water Law.

2. The Government, seen in the report of the National Water Council, will approve the National Hydrological Plan project and forward it to the General Cortes for discussion and approval by law.

3. The National Hydrological Plan, without losing its unitary character, may be approved in different legislative acts.

4. The approval of the National Hydrological Plan will involve the adaptation of the river basin management plans and the measures to the forecasts of the basin.

TITLE III

Monitoring and reviewing hydrological plans

Article 87. Monitoring of the hydrological plans.

1. The basin organizations will follow up their respective hydrological plans, and may require, through the Committee of Competent Authorities, how much information is necessary for this purpose.

2. The Committee of Competent Authorities of the Demarcation will promote the elaboration and maintenance of a system of information on the state of the water masses that allows to obtain an overview of the same, having in count also the objectives specific environmental protection of protected areas. This information system, in addition to constituting a basic element for the planning and development of the programme of measures, will be used for the monitoring of the hydrological plan.

3. Without prejudice to the responsibilities of the various public administrations, the Ministry of the Environment shall keep up-to-date information on the state of the water bodies and the development of the implementation of the actions. of the National Hydrological Plan and of the programs of measurement of the basin plans, being able to obtain from the agencies of the basin or the competent administrations how much data are necessary for this purpose.

4. These agencies, in the case of river basin districts with inter-community basins, will report at intervals not exceeding the year to the Water Council of the demarcation and to the Ministry of the Environment on the development of the plans. They shall also inform the administrations to which they have consulted on the relevant extremes. Within three years of the publication of the hydrological plan or of its update, they shall submit an interim report detailing the degree of implementation of the planned programme of measures.

5. The autonomous communities must establish the monitoring of the hydrological plans developed by them, reporting at intervals not exceeding the year to the Ministry of the Environment. In addition, within three years of the publication of the hydrological plan or its update, they shall submit an interim report detailing the degree of implementation of the planned programme of measures.

6. The Ministry of the Environment will publish every four years a follow-up report on the implementation of the river basin management plans and the National Hydrological Plan, in order to keep the citizen informed of the progress made in the area. implementation and facilitating citizen participation in planning. For the purposes of their joint publication, the autonomous communities shall provide the reports corresponding to the hydrological plans of the intra-Community basins.

7. This report will be submitted to the National Water Council, which, according to the results obtained in the implementation of the various hydrological plans, may propose, either to the Government for the inter-Community basins, or to the corresponding autonomic administration for the intra-Community basins, criteria for updating or reviewing them.

8. The Ministry of the Environment shall forward to the European Commission and any interested Member State copies of the approved hydrological plans and of the general study of the demarcation referred to in Article 78. Copies of the hydrological plans shall be submitted within three months of their publication.

9. The Environment Ministry will also establish the criteria for drawing up the reports required by the European Commission on the hydrological plans. The catchment bodies shall draw up these reports in the form and time limits set by the Ministry of the Environment, which shall forward them to the European Commission.

Article 88. Specific follow-up issues.

The following aspects will be specifically monitored:

a) Evolution of natural and available water resources and their quality.

b) Evolution of water demands.

c) Degree of compliance with ecological flow rates.

d) State of the surface water and groundwater masses.

e) Implementation of measures and effects programmes on water bodies.

Article 89. Review of river basin management plans.

1. When changes or deviations observed in the data, hypotheses or results of the hydrological plans so advise, the Water Council of the demarcation may agree to review the Plan, which may also be ordered, after agreement. with the ministerial departments concerned, by the Environment, which will set a deadline for the action or, if appropriate, interested in the relevant autonomous community in the case of plans drawn up pursuant to Article 18 of the Treaty. Recast text of the Water Act.

2. In any case, a complete and periodic review of the Plan shall be carried out every six years from the date of its entry into force.

3. If the new plan has not been submitted for approval, the Ministry of the Environment may require the basin organizations to submit the hydrological plan. If, after six months from the date of the request, it has not been attended, the Government will instruct the Ministry of Environment to draft the corresponding hydrological plan, together with the departments. Ministers concerned, as provided for in Article 41.2 of the recast text of the Water Act.

4. Where, in the case of a hydrological plan to be drawn up by the hydraulic administration of an autonomous community exercising powers over the public hydraulic domain in watersheds within its entirety within its territory, after the time limits laid down in paragraphs 1 and 2 have elapsed without the new Plan being received for approval, the Government shall require the President of the Autonomous Community for the purposes of its approval.

5. The first update of the hydrological plan and all subsequent updates will necessarily include:

a) A summary of all changes or updates made since the previous version of the plan was published.

b) An assessment of the progress achieved in achieving the environmental objectives, including the presentation in the form of a map of the results of the controls during the period of the previous plan and an explanation of the environmental objectives not achieved.

c) A summary and an explanation of the measures provided for in the previous version of the hydrological plan that have not been implemented.

(d) A summary of all the additional transitional measures taken, since the publication of the previous version of the hydrological plan, for water bodies likely to fail to meet the expected environmental objectives.

6. The procedure for reviewing the plans shall be similar to that provided for in Articles 76 to 82 inclusive.

TITLE IV

Effects of hydrological plans

Article 90. General provisions.

1. The hydrological plans shall be public and binding, without prejudice to their periodic update and justified review, and shall not in themselves create rights in favour of individuals or entities, and therefore their amendment shall not give rise to compensation, without prejudice to the provisions of Article 65 of the recast text of the Water Act.

2. The resolutions of the basin bodies and any other public administration in matters relating to the hydrological plans shall comply with the terms of the hydrological plans.

3. Where, as a result of the modifications to the hydrological plans, a review of certain existing concessions is carried out, the injured dealers shall be entitled to the corresponding compensation in accordance with the provisions of the the legislation of compulsory expropriation.

4. The river basin management plans will be suspended in those determinations that are contradictory to those of the National Hydrological Plan. The Council of Ministers, on a proposal from the Ministry of the Environment, by means of a resolution published in the Official Gazette of the State and in that of the Autonomous Communities concerned, will initiate the corresponding process of adaptation of the basin plans. The resolution shall include the essential data to identify those points of the river basin management plan affected by the National Hydrological Plan and which shall be adapted.

Article 91. Other particular effects.

1. The approval of the river basin management plans shall involve the declaration of public utility of the research, studies, projects and works provided for in the Plan.

2. In consequence, the competent administrative bodies may initiate the action necessary for the implementation of the measures to be carried out, in respect of any compensation for temporary occupation of property of the Member State concerned. The law of the European Union is a matter of course for the European Union. The Government may, in accordance with such rules, apply the urgency procedure, as necessary.

3. The forecasts of the hydrological plans referred to in Article 43.1 and 2 of the recast of the Water Law shall be respected in the different instruments of urban planning of the territory.

4. In order to allow for the approval of buildings in the reserved areas referred to in Article 43.1 of the recast of the Water Act, the competent bodies shall obtain prior information from the hydraulic administration, unless they are have reported on a general basis the relevant urban planning instruments.

ANNEX I

Ecological regions and descriptors for classification into types of surface water masses (system A)

Rivers

Type based on the altitude.

Typology

Descriptors

Region

Iberian-macaronesian region.

Pyrenees.

Type

Type

High: > 800 m.

Average Height: 200 to 800 m.

Low Lands: < 200 m.

Tipologia according to size based on the surface of the power basin

Small: 10 to 100 km2

Medium: > 100 to 1,000 km2

Large: > 1,000 to 10,000 km2

Very large: > 10,000 km2

Geology.

Calcareo.

Siliceo.

Organic.

Lagos

Type based on the altitude.

Typology

Descriptors

Region

Iberian-macaronesian region.

Pyrenees.

Type

Type

High: > 800 m.

Average Height: 200 to 800 m.

Low Lands: < 200 m.

Tipoloing according to the measured depth as the average depth.

< 3 m.

3 m to 15 m.

 

15 m.

Tipologia according to the size measured as the surface of the lake.

0.5 to 1 km2

1 to 10 km2

10 to 100 km2

> 100 km2

Organic.

Transition Waters

Typology

Descriptors

Region

Atlantic Ocean.

Mediterranean Sea.

Type

Based on the yearly average salinity

< 0.5%: freshwater.

0.5 to < 5%: Oligohalino.

5 to < 18%: Mesohalino.

18 to < 30%: polyhalino.

30 a < 40%: euhalino.

Based on the average tidal amplitude.

< 2 m: microreal.

2 to 4 m: mesomareal.

4 m: macroreal.

Coastal waters

Typology

Descriptors

Region

Atlantic Ocean.

Mediterranean Sea.

Type

Based on the yearly average salinity

< 0.5%: freshwater.

0.5 to < 5%: Oligohalino.

5 to < 18%: Mesohalino.

18 to < 30%: polyhalino.

30 a < 40%: euhalino.

Based on average depth

shallow water: < 30 m.

Intermedias: 30 to 200 m.

Deep: > 200 m.

ANNEX II

Mandatory and optional factors for classification into types of surface water masses (B system)

Rivers

Alternate Characterization

Physical and chemical factors that determine the characteristics of the river or part of the river and, by The structure and composition of the biological community

Factors

Altitude.

Latitude.

Length.

Geology.

Size.

Factors

Distance from Birth of the river.

Flow Energy (flow and slope function)

Average water width

Average water depth

Average Pending of water

Shape and configuring the main stream.

Category based on river input (flow)

Valley Shape.

Solid transport.

Neutralization capacity of acids.

Media composition of the substrate.

Air Temperature Oscillation

Average air temperature.

Precipitation

Lagos

Alternate Characterization

Physical and chemical factors that determine the characteristics of the lake and, therefore, the structure and composition of the biological community

Factors

Altitude.

Latitude.

Length.

Depth.

Geology.

Size.

Optional Factors

Average depth of water

Lake form

Air Temperature Oscillation

Water stratification mixing scheme (for example, monomictic, dimictic, polymictic).

Acid neutralization capacity.

Natural status of nutrients.

Average composition of the substrate

Water level fluctuation.

Transition Waters

Characterization

Physical and chemical factors that determine the characteristics of the lake and, therefore, the structure and composition of the biological community

Factors

Latitude.

Length.

 

Tidal amplitude.

Salinity.

stream

Exposition to the swell.

Stay time.

Turbidity.

Media composition of the substrate.

Shape.

Water temperature oscillation.

Coastal waters

Alternate Characterization

Physical and chemical factors that determine the characteristics of the lake and, therefore, the structure and composition of the biological community

Factors

Latitude.

Length.

Salinity.

Factors

Stream speed.

Exposition to the swell.

Turbidity.

Stay time (of bays closed)

Composition Substrate media

Water temperature oscillation

ANNEX III

Community legislation on water protection

Directive 2006 /118/EC of the European Parliament and of the Council of 12 December 2006 on the protection of groundwater against pollution and deterioration.

Directive 2006 /7/EC of the European Parliament and of the Council of 15 February 2006 on the management of bathing water quality and repealing Directive 76 /160/EEC.

Council Directive 98 /83/EC of 3 November 1998 on the quality of water intended for human consumption.

Council Directive 96 /61/EC of 24 September 1996 on integrated pollution prevention and control.

Council Directive 96 /82/EC of 9 December 1996 on the control of the risks inherent in major accidents involving dangerous substances.

Council Directive 92/43/EEC of 21 May 1992 on the conservation of natural habitats and of wild fauna and flora. Council Directive 91 /271/EEC of 21 May 1991 on the treatment of urban waste water.

Council Directive 91 /414/EEC of 15 July 1991 concerning the placing of plant protection products on the market.

Council Directive 91 /676/EEC of 12 December 1991 on the protection of waters against pollution caused by nitrates used in agriculture.

Council Directive 86 /278/EEC of 12 June 1986 on the protection of the environment and, in particular, soils, on the use of sewage sludge in agriculture.

Council Directive 86 /280/EEC of 12 June 1986 on the limit values and quality objectives for residues of certain dangerous substances included in List I of the Annex to the Directive 76 /464/EEC.

Council Directive 85 /337/EEC of 27 June 1985 on the assessment of the impact of certain public and private projects on the environment.

Council Directive 84 /156/EEC of 8 March 1984 on limit values and quality objectives for discharges of mercury from sectors other than the electrolysis of alkali chlorides.

Council Directive 84 /491/EEC of 9 October 1984 on limit values and quality objectives for discharges of hexachlorocyclohexane.

Council Directive 83 /513/EEC of 26 September 1983 on limit values and quality objectives for discharges of cadmium.

Council Directive 82/176/EEC of 22 March 1982 on limit values and quality objectives for discharges of mercury from the electrolysis sector of alkaline chlorides.

Council Directive 79 /409/EEC of 2 April 1979 on the conservation of wild birds.

ANNEX IV

List of hazardous substances

Hazardous substances are classified in List I, Preferential List II and Priority List II and are the controlled substances through the following regulations:

(a) List I: controlled substances through the Order of 12 November 1987, from the Ministry of Public Works and Urbanism, on emission standards, quality objectives and reference measurement methods relating to: certain harmful or dangerous substances contained in waste water discharges, as amended by the Orders of 13 March 1989, 27 February 1991, 28 June 1991 and 25 May 1992.

(b) Preferential List II: controlled substances through Royal Decree 995/2000 of 2 June 2000 setting quality targets for certain pollutants and amending the Public Domain Regulation Hydraulic, approved by Royal Decree 849/1986 of 11 April.

c) Priority list II: substances covered by Decision No. 2455 /2001/EC of the European Parliament and of the Council of 20 November 2001 on the list of priority substances in the field of water policy and amending Directive 2000 /60/EC.

These rules remain in force until they are amended by those which, on dangerous substances, are adopted in application of Directive 2000 /60/EC establishing a Community framework for action in the field of dangerous substances. field of water policy.

List I

Substance

Hexachlorobenzene

CAS

Mercury

7439-97-6

cadmium

7440-43-9

Hexachlorocyclohexane (HCH)

608-73-1

Carbon Tetrachloride

56-23-5

dichlorodiphenyltrichloroethane (DDT)

50-29-3

Pentachlorophenol

87-86-5

Aldrin

309-00-2

Dieldrin

60-57-1

Endrin

72-20-8

465-73-6

465-73-6

118-74-1

Hexachlorobutadiene

87-68-3

Chloroform

67-66-3

dichloroethane

107-06-2

Trichloroethylene

79-01-6

Perchloroethylene

127-18-4

Tricrobenzenes

12002-48-1

Preferred II List

Substance

dissolved nickel

CAS

Atrazine

1912-24-9

benzene

71-43-2

Chlorobenzene

108-90-7

Diclorobenzene (orto, meta, and for)

25321-22-6

Ethylbenzene

100-41-4

Metolachlor

51218-45-2

Naftalene

91-20-3

Simazine

122-34-9

Terbutilazine

5915 -41-3

108-88-3

Unapplicable

1,1,1-Trichloroethane

71-55-6

xylene (orto isomers, meta, para)

1330-20-7

Total Cianides

74-90-8

Fluorides

16984-48-8

Total Arsenic

7440-38-2

Copper

7440-50-8

Dissolved Chrome

7440-47-3

7440-02-0

dissolved

7439-92-1

7782-49-2

Zinc

7440-66-6

Priority II List

Substance

Chloropyrifos

Isoproturon

applicable

Trichloromethane (chloroform)

CAS

Alachlor

15972-60-8

Antraceno

120-12-7

Atrazine

1912-24-9

benzene

71-43-2

Broke Diphenylethers

Not applicable

7440-43-9

C10-13 -chloroalkanes

85535-84-8

chlofevinfos

470-90-6

2921-88-2

107-06-2

107-06-2

75-09-2

75-09-2

Di (2-ethylhexyl) phthalate (DEHP)

117-81-7

Diuron

330-54-1

Endosulfan

115 -29-7

(alpha-endosulfan)

959-98-8

206-44-0

Hexachlorobenzene

118-74-1

Hexachlorobutadiene

87-68-3

608-73-1

608-73-1

(gamma-lindane isomer)

58-89-9

34123-59-6

Lead and its composites

7439-92-1

Mercury and its composites

7439-97-6

Naftalene

91-20-3

and its composites

7440-02-0

Nonylphenols

25154-52-3

104-40-5

104-40-5

1806-26-4

(For-ter-octylphenol)

140-66-9

Pentachlorobenzene

608-93-5

Pentachlorophenol

87-86-5

Not applicable

(Benzo (a) pyrene)

50-32-8

(Benzo (b) fluoranthene)

205-99-2

(Benzo (g, h, i) perylene)

191-24-2

(Benzo (k) fluoroanthene)

207-08-9

(Indeno (1,2,3-cd) pyrene)

193-39-5

122-34-9

122-34-9

688-73-3

tributyltin cation of tributyltin

36643-28-4

Tricrobenzenes

12002-48-1

120-82-1

67-66-3

Trifluralin

1582-09-8

ANNEX V

Ecological status classifications normative definitions

Imagen: img/disp/2007/162/13182_001.png

Imagen: img/disp/2007/162/13182_002.png

Imagen: img/disp/2007/162/13182_003.png

Imagen: img/disp/2007/162/13182_004.png

Imagen: img/disp/2007/162/13182_005.png

Imagen: img/disp/2007/162/13182_006.png

Imagen: img/disp/2007/162/13182_007.png

Imagen: img/disp/2007/162/13182_008.png

Imagen: img/disp/2007/162/13182_009.png

Imagen: img/disp/2007/162/13182_010.png