REPUBLIC OF INDONESIA No. 304, 2017 KEMEN-ESDM. EXCESS POWER. UTILIZATION
COAL.
REGULATION OF ENERGY MINISTER AND MINERAL RESOURCES
REPUBLIC OF INDONESIA
NUMBER 19 YEAR 2017
ABOUT
COAL UTILIZATION FOR POWER GENERATION
AND THE PURCHASE OF EXCESS POWER GENERATION (EXCESS POWER)
WITH THE GRACE OF THE GOD ALMIGHTY
MINISTER OF ENERGY AND MINERAL RESOURCES OF THE REPUBLIC OF INDONESIA,
DRAWS: A. that in order to increase utilization
coal optimally in the development
power plant, as well as improving the role
power plant of the operating permit holder to
keep the availability of electrical power on the system
local notorials, need to set the provisions
regarding the coal utilization for plant
electricity and the purchase of excess power (excess
power);
b. that based on consideration as
referred to in letter a, it needs to set the Regulation
Minister of Energy and Mineral Resources on
Coal utilization for Power Plants and
Purchase of Excess Power Electricity (Excess Power);
www.peraturan.go.id
2017, No. 304 -2-
Given: 1. Law No. 30 Year 2007 on Energy
(sheet Of State Of The Republic Of Indonesia In 2007
Number 96, Additional Gazette Republic Of The Republic
Indonesia Number 4746);
2. Law No. 4 of 2009 on
Mineral Mining and Coal (State Sheet
Republic of Indonesia 2009 No. 4, Supplement
sheet of state of the Republic of Indonesia Number 4959);
3. Law No. 30 Year 2009 on
Fame of the Republic of Indonesia
in 2009 Number 133, Additional Sheet Country
Republic of Indonesia Number 5052);
4. Government Regulation No. 23 of 2010 on
Implementation Of Mineral Mining Efforts and
Coal (State Of The Republic Of Indonesia Year
2010 Number 29, Additional Gazette Republic
Indonesia Number 5111) as it has been several times
amended last with Government Regulation No.
1 Year 2017 on the Fourth Change of the Year
Government Regulation No. 23 of 2010 on
Implementation of the Undertaking Activities Mineral Mining and
Coal (State Sheet of the Republic of Indonesia Year
2017 Number 4, Additional State Sheet Republic
Indonesia Number 6012);
5. Government Regulation No. 14 of 2012 on
The Activities of Supplying Electric Power (Sheets
State Republic Of Indonesia In 2012 Number 28,
Additional Sheet Republic Of Indonesia Number
5281) As has been amended by Regulation
Government Number 23 Year 2014 on Change
over Government Regulation No. 14 Year 2012
on the Activities of the Electrical Energy Provision
(State Sheet of the Republic of Indonesia Year 2014
Number 75, Additional State Sheet Republic
Indonesia Number 5530);
www.peraturan.go.id
2017, No. 304 -3-
6. Government Regulation No. 79 of 2014 on
National Energy Policy (Republican Gazette
Indonesia Year 2014 Number 300, Extra Sheet
State of the Republic of Indonesia Number 5609);
7. President Regulation No. 68 of 2015 on
Ministry of Energy and Mineral Resources (Sheet
State of the Republic of Indonesia 2015 Number 132)
as amended by the Presidential Regulation
Number 105 of the Year 2016 on the Change of
Presidential Regulation No. 68 of 2015 on
Ministry of Energy and Mineral Resources (Sheet
State of the Republic of Indonesia 2016 Number 289);
8. Regulations Minister of Energy and Mineral Resources
Number 09 of 2016 on the Tata Way of Supplies and
Coal pricing for Power Plants
Mouth Mouth (Republic of Indonesia State News
2016 Number 512) as amended with
The Regulation of the Minister of Energy and Mineral Resources
Number 24 of 2016 on Change of Regulation
Minister of Energy and Mineral Resources Number
09 Year 2016 on Tata Cara Provision and
Coal pricing for Power Plants
Mine Mouth (State News of the Republic of Indonesia of the Year
2016 Number 1367);
9. Regulation of the Minister of Energy and Mineral Resources
Number 13 of 2016 on Organization and Work
Ministry of Energy and Mineral Resources (News
State of the Republic of Indonesia 2016 Number 782);
DECIDED:
SET: REGULATION OF MINISTER OF ENERGY AND RESOURCES
MINERALS ON THE UTILIZATION OF COAL FOR
POWER GENERATION AND EXCESS PURCHASE
ELECTRICAL POWER (EXCESS POWER).
www.peraturan.go.id
2017, No. 304 -4-
BAB I
provisions of UMUM
Article 1
In this Ministerial Regulation referred to:
1. Coal is the precipitate of carbonan organic compounds
that is formed naturally from the remainder growing-
plants.
2. The next power-selling agreement
referred to as the PJBL is a power-buying agreement
electricity between PT Companies Electric Negara (Persero)
as a buyer with the seller as the seller.
3. The Price of Coal For Mouth Power Plant
Mine is a specially designated price for
Batubara used as fuel
mine mouth power plant.
4. The mine-mouth power plant is the plant
electric power plant and gas power plant
Batubara, which uses Batubara fuel,
which is guaranteed the availability of Batubara by the company
mine On the sale deal for the coal.
5. Mine company is a company that
carried out the activities of its Batubara mining business.
6. The Mine Mouth Power Plant is the
holder of an electric power supply venture that
operates the Mine Mouth Power Plant.
7. The next PT Corporate Electricity Company (Persero)
called PT PLN (Persero) is the state-owned enterprise
state established under Government Regulation
No. 23 of 1994 on Disposition of Forms
The Company General (Perum) Power Of State To
Company Of Perseroan (Persero).
8. The underlying cost of the next generation of Regenerating
called the Dissenters ' BPP is the provision of the provision
electric power by PT PLN (Persero) in the generation
electric power, excluding the power supply charge
electricity.
www.peraturan.go.id
2017, No. 304 -5-
9. Power Systems Network Rules (Grid Code) are
a set of rules, requirements, and standards for
guarantees the safety, reliability and operation and
efficient system development in the meet
An increase in the need for electrical power in the power system
electricity.
10. Commercial Operation Date later abbreviated
COD is the start date of the plant's operation
electric power to channel electrical energy into
the electric power grid of PT PLN (Persero).
11. Capacity Factor further abbreviated to CF was
capacity factor, comparison between flat-capacity-
flat in megawatt (MW) of production during the period
specified for the installed capacity.
12. The Electric Power Dissenters ' Agency is
an electric power producer company other than PT PLN
(Persero) which conducts a power-buying agreement
electricity with PT PLN (Persero).
13. The Minister is the minister who organizes affairs
governments in the field of energy and mineral resources.
Article 2
The Regulation of the Minister governs the provisions regarding
utilization of Batubara to the plant electric and
purchase of excess power (excess power) from
operating permit holder.
BAB II
Coal-fueled power plant
Part Kesatu
General
Article 3
(1) In order to meet the power provision obligations
electricity, holder power supply permit
which has an enterprise area can do
www.peraturan.go.id
2017, No. 304 -6-
The purchase of electric power from power generation
bakar Batubara.
(2) The purchase of electric power as referred to
paragraph (1) is executed on the venture plan
The provision of electric power.
(3) Coal-based power plants
as referred to in paragraph (1) may be:
a. The Mine Mouth Power Plant; or
b. mining nonmouth power plant.
(4) Purchase of electric power from the Mulut Power Plant
Mine as referred to in paragraph (3) the letter a
can be done through the direct designation.
(5) Purchase of the power power from nonmouth power plant
mine as referred to in paragraph (3) letter b
is done in accordance with regulatory provisions
laws.
Second Quarter
Mine Mouth Power Plant
Article 4
(1) In the framework of the construction of the Mulut Power Plant
Mine, PT PLN (Persero) and the Effort
Dissenters of Electric Power required to ensure that
alokasi/supply of Batubara corresponds to the PJBL.
(2) Coal supply as referred to
paragraph (1) is conducted under the purchase agreement
Batubara between the Mine Company with
The Company of the Mine Mouth Power Plant.
(3) the Company The Mine Mouth Power Plant
as referred to in paragraph (2) may be:
a.
integrate with the following: electric power supply authorization holder
generation.
www.peraturan.go.id
2017, No. 304 -7-
(4) Coal provision for Plant development
Mine Mouth power may be supplied by more than 1 (one)
Mine Company.
Section 5
(1) Purchase of electrical power from Mouth Power Plant
Mine as referred to in Article 3 of the paragraph (3)
the letter a is exercised under the PJBL.
(2) The PJBL as referred to in paragraph (1) is exercised
for a period of 30 (thirty) years since
COD.
(3) The purchase price of electric power from the Power Plant
The Mine Mouth as referred to in paragraph (1)
is specified with the following conditions:
a. in terms of Dissenitan BPP in the system
local composure is the same or below
average national Disobedience BPP, price
highest benchmark of 75% (seventy-five
percent) of BPP Dissenters in the system
local notoriality; or
b. in terms of Dissenters BPP in the system
local notoriality above average BPP
National Dissenters, the highest benchmark price
by 75% (seventy-five percent) of the average
BPP Dissenters nationwide.
(4) The terms of the purchase of electric power purchase price as
referred to in paragraph (3) are designated as CF's assumption
a plant of 80% (eighty percent).
(5) Dissenters in the local system of composure
and the average national Disseness BPP as
referred to in paragraph (3) is the Dissenters ' BPP at
the local system of composure and the average BPP
The national disobedience of the previous year that
has been established by the Minister based on the proposal of PT PLN
(Persero).
www.peraturan.go.id
2017, No. 304 -8-
Section 6
In order for the implementation of power grid development
electricity for the power evacuation of the Mulut Power Plant
Mine to the dial point of PT PLN (Persero),
construction The network can be done by the Business Agency
Disobedience of Electric Power based on the mechanism that
mutually beneficial (business to business).
Third Part
Non-Mulut Electric Power Plant
Article 7
(1) Purchase of electrical power from nonmouth power plants
mine as referred to in Article 3 of the paragraph (3)
letter b is performed under the PJBL.
(2) The PJBL as referred to in paragraph (1) is exercised
for a period of 30 (thirty) years since
COD.
(3) The purchase price of electric power from the power plant
nonmouth of the mine as referred to in paragraph (1)
is set for the following capacity:
a. larger than 100 MW (one hundred megawatts); and
b. up to 100 MW (hundred megawatts).
Article 8
(1) The purchase price of electric power from power generation
nonmouth mine with greater capacity than
100 MW (hundred megawatts) as intended
in Section 7 of the paragraph (3) letter a, set to
terms as follows:
a. in terms of Dissenitan BPP in the system
local composure is the same or below
average BPP National Plant, benchmark price
highest of BPP Dissenters in the system
local notoriality; or
www.peraturan.go.id
2017, No. 304 -9-
b. in terms of Dissenitan BPP in the system
local composure above average BPP
National Disobedience, highest benchmark price
of the national Dissenters BPP.
(2) The purchase price of the power plant from the plant electric
nonmouth mine with capacity up to 100
MW (hundred megawatts) as intended in
Section 7 of the paragraph (3) letter b, specified with the provisions
as follows:
a. in the case of the Dissenters BPP in the system
local composure is the same or below
average national Disseness BPP, price
The highest benchmark of BPP Dissenters at
local notoriality system; or
b. in terms of Dissenitan BPP in the system
Local composure above average BPP
National Dissenters, power purchase prices
electricity set based on auction or
mutually beneficial mechanisms (business to
business).
(3) The provisions of the purchase price of electric power as
are referred to in paragraph (1) letter a and paragraph (2) letter a,
using the price of Batubara for the power plant
mine nonmouth corresponds to the principle passthrough
based on the assumptions of Batubara prices at the time
using the BPP in the local notoriagalism system.
(4) The terms of the purchase of electric power purchase as
are referred to in paragraph (1) and paragraph (2) is set with
assumption of generating plant by 80% (eighty
percent).
(5) Dissenters in the local system of composure
and the average national Disseness BPP as
referred to in paragraph (1) and paragraph (2) are BPP
Dissenters in the local system of composure and
average national Dissenters BPP in the year
previously specified by the Minister
based on the proposed PT PLN (Persero).
www.peraturan.go.id
2017, No. 304 -10-
Article 9
In order to perform the construction of the power grid
electricity for the power evacuation of the nonmouth power plant
mine to the dial point of PT PLN (Persero),
network development may be performed by the Enterprise
Disobedience of Electric Power based on the mechanism that
mutually beneficial (business to business).
Article 10
(1) Purchase of electric power from Mouth Power Plant
Mine and mine nonmouth power plant
as referred to in Section 5 and Section 8
using a co-building pattern to build, have,
operate, and assign (build, own, operate,
and transfer/BOOT).
(2) Further provisions regarding the same pattern of cooperation
as referred to in paragraph (1) are set in PJBL.
Fourth Quarter
The Lyric Energy Purchase From Expansion Plant
Article 11
(1) In terms of the purchase of electric power from the plant
expansion electricity at the same location, it can be performed
through direct appointment with the purchase price
electrical power must be below the benchmark price
as referred to in Section 5 and Section 8.
(2) In terms of the purchase of electric power from the plant
the expansion electricity at different locations on the system that
same, can be done through direct elections
with the purchase price of an electric power must be below
the benchmark price as referred to in Section 5 and
Article 8.
www.peraturan.go.id
2017, No. 304 -11-
BAB III
PURCHASE OF ELECTRIC EXCESS OF
OPERATING PERMIT (EXCESS POWER)
Article 12
(1) Licensee's business permit provision of which is
has an area of effort to purchase excess power
electricity (excess power) of the operating permit holder to
strengthen the local electric power supply system.
(2) Purchase of excess electrical power (excess power)
as referred to a paragraph (1) can be greater
of the electrical power used to be alone and in accordance with
the conditions or needs of the local system of notorialism
.
(3) Power plant operations of the plant
operating permit holders must refer to the Rules
Network Power Systems (Grid Code) on the system
local or electrical power distribution rules.
Article 13
(1) The purchase price of excess power (excess power)
at the highest of 90% (ninety percent) of
BPP Dissenters in the local system of notoriality.
(2) Dissenters in the local notorialization system
as referred to in paragraph (1) is BPP
Dissenters in the local system of notoriality at
the previous year that has been set by the Minister
based on the proposal of PT PLN (Persero).
(3) Purchase of excess power (excess power)
as referred to in Section 12 of the paragraph (1) can
be done through an overpowered purchasing agreement
the power of futures.
(4) the sale Agreement purchase excess power power futures
as referred to in paragraph (3) may be less or
more than 1 (one) years based on the conditions and
local system needs.
www.peraturan.go.id
2017, No. 304 -12-
Article 14
(1) PT PLN (Persero) performs a purchase price evaluation
excess power (excess power) as
is referred to in Article 13 of the paragraph (1) every year
based on Disobedience BPP changes in the system
local notoriality.
(2) Dissenters in the local system of composure
as referred to in paragraph (1) are BPP
Dissenters in the system of notoriality local that
has been set by the Minister based on the proposal of PT PLN
(Persero).
BAB IV
TRANSITIONAL provisions
Section 15
At the time the Minister's Ordinance came into effect, against
The Board of Dissenters of Power Power:
a. has done the auction process and already offers
price;
b. set as an auction winner;
c. has signed a letter of appointment (letter of intent);
or
d. has signed the PJBL,
process of implementation of its purchase and power price
in accordance with the provisions set out in the regulations
laws before this Minister Regulation
promulgled.
Article 16
The purchase agreement of excess power (excess power)
before the signing of this Ministerial Regulation
remains in effect until the end of the agreement
sell the buy excess power power (excess power).
www.peraturan.go.id
2017, No. 304 -13-
BAB V
PROVISIONS
Article 17
At the time the Minister's Ordinance came into effect:
1. The provisions of the excess power (excess
power) as referred to in Article 13 and Section
14 Regulation of the Minister of Energy and Mineral Resources
Number 01 2015 of the Cooperation of the Supplies
Electric Power and Mutual Benefit Network
Electric Power (Indonesian Republic News Of The Year
2015 Number 3);
2. Regulation of the Minister of Energy and Mineral Resources
Number 03 of 2015 on the Purchasing Procedures
Electric Power and Power Purchase Risk
Electricity from PLTU Mulut Mine, PLTU Batubara,
PLTG/PLTMG, and PLTA by PT PLN (Persero) Through
Direct election and Direct Show (News
State of the Republic of Indonesia Year 2015 No. 49); and
3. the provisions of the excess power (excess
power) as referred to in Article 16 and Section
17 Regulation of the Minister of Energy and Mineral Resources
No. 21 Year 2016 on the Purchase of Electric Power
of the Biomassa Power Plant and Plant
Biogas Electricity by PT Companies Power Negara
(Persero) (Republic of Indonesia State News 2016
No. 1129),
revoked and declared no apply.
Article 18
The Minister ' s Regulation is beginning to apply on the date
Put it down.
www.peraturan.go.id
2017, No. 304 -14-
For everyone to know, ordered
the invitational of the Minister's Regulation with its placement
in the Republic of Indonesia News.
Specified in the Jakarta
on February 14, 2017
MINISTER OF ENERGY AND MINERAL RESOURCES
REPUBLIC OF INDONESIA,
ttd
IGNASIUS JONAN
It was promulded in Jakarta
on the 17th February 2017
DIRECTOR GENERAL
REGULATION
MINISTRY OF LAW AND HUMAN RIGHTS
REPUBLIC OF INDONESIA,
ttd
WIDODO EKATJAHJANA
www.peraturan.go.id