Subscribe Now for only USD$40 per month.
delivered a certificate of deposit of 5% (five percent) of the total PLTA development investment in the slowest term of 30 (thirty) days from the date of the business establishment as the water power manager for the power plant;

h. a statement has understood and is able to run the PJBL contents of the PLTA with a capacity of up to 10 MW (ten megawatts) published by PT PLN (Persero); and

i. the statement of willingness to be consciously and responsible for accepting and carrying out sanctions, including to lease a number of funds to the State Kas, as set out in this Minister Regulation.

(3) PT PLN (Persero) complete verification The technical terms of the initial eligibility study document (pre-feasibility study) are accepted in full.

(4) Requests as referred to in paragraph (1) are submitted by the business entity in writing to the Dirjen EBTKE by using the mail format application and letter of statement as set forth in Appendix II of the letter A and the letter B which is an inseparable part of this Minister ' s Regulation.

www.peraturan.go.id

2014, No. 594 6

Article 8

(1) Dirjen EBTKE conducted the research and evaluation of the application of the business designation as the hydropower manager for the power plant.

(2) Based on research and evaluation as set forth in paragraph (1), Dirjen EBTKE sets out a grant decision or refusal of an application to be a hydropower manager for the longest power plant 30 (thirty) business days since the application is accepted. complete.

(3) The decision of awarding the business agency as a hydropower manager for the power plant to be delivered to the applicant with a gust to the Director General of Fame and the Board of Directors PT PLN (Persero).

(4) In regard to the application of the assignment of the agency to be a hydropower manager for the power plant to be rejected, Dirjen EBTKE informed it in writing to the applicant for his refusal.

Article 9

The agency of the venture has been designated as the water power manager for the power plant as referred to in Article 8 of the paragraph (3) to submit a report on the progress of the development of the PLTA every 6 (six) months from the beginning of its date to the General Secretary. EBTKE up to commercial operation date (COD) with stews to Director General of Employment and Directors of PT PLN (Persero).

Article 10

(1) The entity that has been designated as the hydropower manager for the power plant is required to deliver a deposit certificate of 5% (five percent) of the total PLTA development investment to the slowest Dirjen EBTKE 30 (30) business days from the date of the date as the hydropower manager for the power plant.

(2) In terms of after 30 (thirty) business days the business entity is unable to deliver a certificate of deposit as referred to in a paragraph (1), then its suppressor as the hydropower manager for the power plant is revoked by Dirjen EBTKE, and to the entity imposed a ban on applying for same-sex requests for a term of 2 (two) consecutive years from the revocation date.

www.peraturan.go.id

2014, No. 5947

Section 11

(1) The business entity that has delivered a certificate of deposit to the Dirjen EBTKE as referred to in Article 10 of the paragraph (1) must apply to obtain the IUPTL while appropriate to the the provisions of the laws.

(2) In the slowest 3 (three) business days after obtaining a temporary IUPTL, the business agency must deliver a temporary copy of IUPTL to the Dirjen EBTKE.

Section 12

(1) Within the slowest 90 (ninety) business days after the date of the publication of IUPTL provisioned, the business agency must deliver a feasibility study (feasibility study) and the necessary documents for The purpose of signing the PJBL is complete to PT PLN (Persero).

(2) PT PLN (Persero) and the mandatory business entity signing the PJBL in the slowest term of 30 (thirty) business days after the business entity completes the overall document that requires and delivers a copy of the PJBL referred to EBTKE.

(3) In case PJBL has not been signed by PT PLN (Persero) and the business entity within 30 (thirty) business days after the business entity completes the entirety of the document required as it is referred to in paragraph (2), then:

A. The assignment of the agency as the water power manager for the power plant was revoked by Director General EBTKE;

b. to such entities are subject to a ban on applying for a similar request for a term of 2 (two) consecutive years from the revocation date; and

c. funds of 25% (twenty-five percent) of the value of the deposit have been submitted its certificates to belong to the state.

Article 13

PT PLN (Persero) is required to provide a PJBL model of PLTA with a capacity of generation up to 10 MW (ten megawatts), and publish the intended model through website PT PLN (Persero) the slowest 60 (sixty) business days since the promulgations of Regulation This Minister.

Section 14

(1) Within the slowest 15 (fifteen) month period from the date of the signing of the PJBL, the mandatory business entity reaches fulfillment

www.peraturan.go.id

2014, No. 594 8

financing (financial close) for the physical development needs of the PLTA and presenting the evidence to Dirjen EBTKE.

(2) In the event after a term of 15 (fifteen) months since the signing of the PJBL, the business entity does not provide the entire fund and delivers the evidence as referred to in paragraph (1), then:

a. The assignment of the agency as the water power manager for the power plant was revoked by Director General EBTKE;

b. to such entities are subject to a ban on applying for a similar request for a term of 2 (two) consecutive years from the revocation date; and

c. funds of 50% (fifty percent) of the deposit value it has been submitted Its certification becomes state property.

Article 15

(1) The business entity that has signed the PJBL and has done the fulfillment of financing (financial close) is required to apply to obtain the IUPTL in accordance with the provisions of the IBM International Economic and Financial Services Act. Laws.

(2) In the slowest term 3 (three) business days after obtaining IUPTL as referred to in paragraph (1), the business agency must deliver a copy of IUPTL to the Dirjen EBTKE.

Article 16

(1) The Entity ID may use the deposit as referred to in Article 10 of the paragraph (1) gradually for the physical development needs of the PLTA after the publication of IUPTL.

(2) The proposed use of funds as referred to in paragraph (1) is delivered to the Dirjen EBTKE by attaching evidence to the availability W (ten

www.peraturan.go.id

2014, No. 5945

megawatt), first delivered a request to Dirjen EBTKE to be assigned as the hydropower manager for the power plant.

(2) The invocation as referred to in paragraph (1) must be supplemented with the requirements as follows:

a. attempt body profile;

b. Licensing documents from the Government or Local Government in accordance with the provisions of the laws of the Law;

c. results of preliminary feasibility studies (pre feasibility study) which are technically verified by PT PLN (Persero);

d. the estimated total investment required for the construction of the PLTA;

e. development schedule for development up to commercial operation date (COD);

f. estate availability statement;

g. Statement of statement 1.25

5. Maluku and North Maluku

1,075.0 x F 750.0 x F 1.30

6. Papua and West Papua

1,075.0 x F 750.0 x F 1.60

7.

Low Volt

(s.d. 250 kW)

Java, Bali, and Madura

1.270.0 x F 770.0 x F 1.00

8. Sumatra 1.270,0 x F 770.0 x F 1.10

9. Borneo and Sulawesi

1.270.0 x F 770.0 x F 1.20

10. West Nusa Tenggara and East Nusa Tenggara

1.270,0 x F 770.0 x F 1.25

www.peraturan.go.id

2014, No. 59413

11. Maluku and North Maluku

1.270.0 x F 770.0 x F 1.30

12. Papua and West Papua

1.270.0 x F 770.0 x F 1.60

MINISTER OF ENERGY AND MINERAL RESOURCES

REPUBLIC OF INDONESIA,

JERO WACIK

www.peraturan.go.id

2014, No. 594 14

ANNEX II

REGULATIONS MINISTER OF ENERGY AND MINERAL RESOURCES REPUBLIC OF INDONESIA

NUMBER 12 YEAR 2014

ABOUT

THE PURCHASE OF ELECTRIC POWER FROM HYDROELECTRIC POWER PLANT BY PT STATE ELECTRICITY COMPANY (PERSERO)

A. WATER POWER MANAGER ' S APPLICATION FOR POWER GENERATION

KOP TO BUSINESS

Number: ... ..., 20 ...

Attachment: ...

Things: Water Power Manager Request

For The Power Plant

Dear,

Director General Of New Energy, Renewable, And Energy Conservation

Jl. Eastern Pegangsaan No. 1, Menteng, Jakarta

In order to meet the requirements to be designated as the hydropower manager for the power plant in accordance with the Regulation of the Minister of Energy and Mineral Resources on the Purchase of Electric Power From the Air Power Plant by PT Corporate Electric Company (Persero), we hereby apply for designation as the hydropower manager for the power plant with the following documents and information as follows:

1. Enterprise Profile

a. attempt body name:.

b. $. The foundation and its changes are:. The subject matter is:..

f. passage of the legal entity:. The management of the business entity: A licensing document of the Government or local government in accordance with the provisions of the laws of the law; (as attached)

3. The results of an early feasibility study (pre feasibility study) which were technically verified by PT PLN (Persero);

4. Estimated total investment required for the construction of the PLTA;

www.peraturan.go.id

2014, No. 59415

5. Construction schedule for development up to commercial operation date (COD) (in table/graph);

6. Land availability statement, including the location of potential water power; (as attached)

7. Statement of statement delivered a deposit certificate of 5% (five percent) of the total construction investment of hydroelectric power plants (PLTA) in the slowest term of 30 (thirty) business days since the date of assignment as manager. water power for power generation; (as attached)

8. The statement has been understood and is capable of running the contents of the PJBL Purchase Agreement (PJBL) of the PLTA with a capacity of up to 10 MW (ten megawatts) that has been published by PT Corporate Electricity (Persero); (as Attached) and

9. The statement is fully aware and responsible for accepting and carrying out sanctions, including to lease a number of funds to the State Kas, as set out in the Regulation of the Minister above (as attached).

So are our requests, for the attention and concern of Mr Dirjen, we thank you.

Our respect,

Title

the stamp, signature, and stamp

(Full Name)

www.peraturan.go.id

2014, No. 594 16

B. LETTER STATEMENT

KOP OF VENTURE

WAIVER

SIGNING BELOW:

NAME:. (KTP copy attached)

Home address:. Rumah/HP:....

Next act for and on behalf of:

Entity Name: ${${${${${${${${${${${${${${${${${${${$ and fax: {} {\"} {\"} {\"} {\"} {\"} {\"} {\"} {\"}} {\"} Minister of Energy and Mineral Resources on the Purchase of Electric Power From the Hydroelectric Power Plant By PT Corporate Electricity Nation (Persero), with full awareness and without any coercion from any party, we stated that:

1. have available land for the construction of the ____m2 (PLTA) Hydroelectric Power Plant located in the village of ____________, ____________ District, Regency/Kota _____________, Province of _____________, with coordinates point:

The dam's board is located: ____________________

s carrier channel: ____________________

Home plant life: ____________________

The Gardu plant's name is: ____________________, and is a land that is not in a dispute case, and has obtained the utilization permit of the authorized Government instance as attached;

2. can hand over a 5% (five percent) deposit certificate from the total PLTA development investment in the slowest 30 (thirty) business days since the date of assignment as the hydropower manager for the power plant;

3. understand and be able to exercise the contents of the Jual Buy Power Agreement from the PLTA with a capacity of up to 10 MW (ten megawatts) that has been published by PT Corporate Electric Country (Persero); and

www.peraturan.go.id

2014, No. 59417

4. be aware and responsible for accepting and carrying out sanctions, including to lease a number of funds to the State Kas, as set out in the Regulation of the Minister above.

So ...

So Mail This statement is made in fact, and to be used as it should be.

... 20 ...

Our respect,

Title

materai, signature, and stamp

(Full Name)

MINISTER OF ENERGY AND MINERAL RESOURCES

REPUBLIC OF INDONESIA,

JERO WACIK

www.peraturan.go.id

2014, No. 594 18

ANNEX III

REGULATIONS MINISTER OF ENERGY AND MINERAL RESOURCES REPUBLIC OF INDONESIA

NUMBER 12 YEAR 2014

ABOUT

THE PURCHASE OF ELECTRIC POWER FROM HYDROELECTRIC POWER PLANT BY PT STATE POWER COMPANY (PERSERO)

WEIGHTED AVERAGE PRICE

ELECTRIC POWER PURCHASE

OF THE HYDROELECTRIC POWER PLANT

WITH CAPACITY UP TO 10 MW

No.

Electricity Network Stinges

(Plant Capacity)

Location/Average Price Area

weighted Factor

F

1.

Intermediate Range

(s.d. 10 MW)

Java, Bali, and Madura 880.0 x F 1.00

2. Sumatra 880.0 x F 1.10

3. Borneo and Sulawesi 880.0 x F 1.20

4. West Nusa Tenggara and East Nusa Tenggara

880.0 x F 1.25

5. Maluku and North Maluku 880.0 x F 1.30

6. Papua and West Papua 880.0 x F 1.60

7.

Low Volt

(s.d. 250 kW)

Java, Bali, and Madura 970.0 x F 1.00

<(Plant Capacity)

Location/Region

Purchase Price (Rp ./Kwh)

Factor

1st Year s.d. Years

8th

9th Year s.d. Year

20th

1.

Intermediate Range

(s.d. 10 MW)

Java, Bali, and Madura

1,075.0 x F 750.0 x F 1.00

2. Sumatra 1,075.0 x F 750.0 x F 1.10

3. Borneo and Sulawesi

1,075.0 x F 750.0 x F 1.20

4. West Nusa Tenggara and East Nusa Tenggara

1,075.0 x F 750.0 x F