I. Basic vocational training |
Lfd. No. |
Part of the training profession |
Skills and knowledge to be mediated |
Timeframe values in weeks in the training year |
1 |
2 |
3 |
1 |
2 |
3 |
4 |
1 |
Vocational training, labour and collective bargaining (Section 4 (1) (1)) |
-
a)
-
The importance of the training contract, in particular the conclusion, duration and termination of the contract,
-
b)
-
Mutual rights and obligations arising from the training contract
-
c)
-
The possibilities of continuing vocational training
-
d)
-
call essential parts of the employment contract
-
e)
-
the main provisions of the collective agreements applicable to the establishment of the establishment
|
throughout the training |
2 |
Establishment and organisation of training (Section 4 (1) (2)) |
-
a)
-
Explaining the structure and tasks of the training company
-
b)
-
Explaining the basic functions of the training company such as offer, procurement, manufacturing and administration
-
c)
-
The relationship between the training company and its employees on economic organisations, professional representatives and trade unions
-
d)
-
Describe the basics, tasks and working methods of the executive bodies of the training company or personnel representation of the company
|
3 |
Safety and health at work (Section 4 (1) (3)) |
-
a)
-
Identify risks to safety and health at work and take action to avoid them
-
b)
-
apply occupational health and safety and accident prevention regulations
-
c)
-
Describe behaviour in the event of accidents and initiate initial measures
-
d)
-
Apply preventive fire safety rules; describe behaviour in fires and take measures to combat fires
|
4 |
Environmental protection (Section 4 (1) (4)) |
contribute to the prevention of operational environmental pressures in the field of occupational exposure, in particular:
-
a)
-
explain possible environmental pressures through the training establishment and its contribution to environmental protection
-
b)
-
apply environmental protection rules applicable to the training establishment
-
c)
-
Use the possibilities of economical and environmentally friendly use of energy and materials
-
d)
-
Avoid waste, supply substances and materials with environmentally friendly disposal
|
5 |
Order failover, performance collection, job plan, and expiration plan (Section 4 (1) (5)) |
-
a)
-
Identify the target of the work order
-
b)
-
Planning work items, work equipment, and backup measures
-
c)
-
Setting construction and construction aids
-
d)
-
Set devices, tools, and tools
-
e)
-
check executed work based on preferences
-
f)
-
Creating work reports
|
6 *) |
|
|
6 |
Setting up, securing and spaces of construction sites (Section 4 (1) (6)) |
Workplace at the construction site:
-
a)
-
Setting up, maintaining and clearing the workplace, taking ergonomic aspects into account
-
b)
-
Save My Computer
Working and protective scaffolders:
-
c)
-
Set up, maintain and dismantled working and protective scaffolders according to specifications
-
d)
-
Participate in the testing of the operational safety of work and protective scaffold
Tools, equipment and machines:
-
e)
-
Provide tools, devices, and machines
-
f)
-
Detecting and reporting problems on devices and machines
-
g)
-
Maintain tools, devices and machines
-
h)
-
Operating equipment and machines, melting, welding and soldering equipment under supervision
|
7 |
Testing, storage and selection of building and building materials (Section 4 (1) (7)) |
-
a)
-
Testing construction and construction aids as well as installation parts for usability
-
b)
-
Get construction and construction aids as well as installation parts according to specifications, transport them on site and store them
|
8 |
Reading and applying drawings and plans, making sketches, carrying out measurements (Section 4 (1) (8)) |
Sketches, drawings and plans:
-
a)
-
Reading and applying sketches of views and cuts
-
b)
-
Reading architectural drawings and laying plans
-
c)
-
Sketches completed measurements:
-
d)
-
Perform measurements with tape size and link scale
-
e)
-
Transfer heights with spirit level and hose balance
-
f)
-
Curse straight
-
g)
-
Apply and secure measurement points
-
h)
-
apply and check right angles
|
9 |
Manufacture of masonry, plaster and concrete (Section 4 (1) (9)) |
-
a)
-
Distinguishing mortar groups by use
-
b)
-
Select binders and aggregates for mortar and concrete
-
c)
-
Manufacture wall, plaster and paint mortars and assess them in their consistency
-
d)
-
Manufacture brickwork parts from stones
-
e)
-
Making chimneys of stones and mouldings
-
f)
-
making single-layer wall plaster
-
g)
-
Making Brettschalungen
-
h)
-
Cutting concrete steel mats
-
i)
-
Replacing reinforcements with spacers
-
k)
-
Producing, introducing, compacting and retreating concrete
|
4 |
|
|
10 |
Processing of wood and manufacture of timber components (Section 4 (1) (10)) |
-
a)
-
Wood and wood-based materials according to the intended use
-
b)
-
Carry out preventive wood protection measures, in particular with regard to plant and animal pests
-
c)
-
Distinguishing sorting and cutting tholt classes
-
d)
-
Storing wood and wood-based materials
-
e)
-
Working with wood, in particular by means of tearing, stamping, sawing, planing and drilling
-
f)
-
Select nails and screws according to the standard
-
g)
-
Making wooden connections and wooden fixtures
|
11 |
Processing of plastics and bituminous materials (Section 4 (1) (11)) |
-
a)
-
Check the surfaces of the deck underlay for their suitability for seals
-
b)
-
Thermoplastics, thermosets and elastomers differ according to their properties
-
c)
-
Deforming thermoplastics and elastomers
-
d)
-
Duromere cutting, drilling and bonding
-
e)
-
Distinguish, cut, nail and fix plastic and bitumen webs by designation and intended use
-
f)
-
Distinguish and process adhesive, paint and sealants
-
g)
-
Plastic and bitumen webs stir and weld
|
8 |
|
|
12 |
Manufacture of thermal insulation, additional measures in roof coverings (Section 4 (1) (12)) |
Distinguish and replace thermal insulation materials according to properties and the intended use |
24 |
|
|
13 |
Processing of slate, roof panels and shingles (Section 4 (1) (13)) |
-
a)
-
Shapes of slate, roofing panels and shingles
-
b)
-
Slate and roofing slabs and lobe
-
c)
-
Sort slate
-
d)
-
Sawing and cutting shingles
-
e)
-
Distinguishing cover types, covering subareas of roof and wall surfaces according to specification
|
14 |
Processing of roof tiles and roofing tiles (Section 4 (1) (14)) |
-
a)
-
Roof tiles and roofing tiles distinguish and process, in particular behauen, tearing, cutting, cutting, dividing and drilling
-
b)
-
Distinguishing cover types, covering sub-areas of roof surfaces according to specification
|
15 |
Processing of metals (Section 4 (1) (15)) |
-
a)
-
Distinguishing properties of steel and non-ferrous metals
-
b)
-
Edit, in particular tearing, cutting, folding, folding, rounding, flanging, sawing, drilling, filing, riveting and soldering, sheet metal and profile
-
c)
-
Select and apply fasteners for sheet metal
-
d)
-
Implementing measures of corrosion protection
|
6 |
|
|
16 |
Mounting and mounting of installation parts (Section 4 (1) (16)) |
Distinguishing and replacing components for roofs and walls according to the intended use |
4 |
|
|
-
*)
-
To mediate in connection with other training contents.
|
|
II. Vocational training |
Lfd. No. |
Part of the training profession |
Skills and knowledge to be mediated |
Timeframe values in weeks in the training year |
1 |
2 |
3 |
1 |
2 |
3 |
4 |
1 |
Order failover, performance collection, job plan, and expiration plan (Section 4 (1) (5)) |
Order failover, performance collection:
-
a)
-
Review work order in terms of preferences
-
b)
-
Technical regulations, in particular regulations of the roofing craft, building regulations and general technical terms and conditions for construction services as well as work instructions, apply
-
c)
-
Preliminary performances of other trades on the view examine job plan and flow plan:
-
d)
-
Estimate time and personnel support
-
e)
-
Set the work steps and coordinate them according to specifications and take measures to ensure the work flow
-
f)
-
Taking account of weather conditions for the performance of work
|
|
4 *) |
|
|
2 |
Setting up, securing and spaces of construction sites (Section 4 (1) (6)) |
Setting up, safety and health at the construction site:
-
a)
-
Assessing the suitability of transport routes and making use of measures for use
-
b)
-
Establish and maintain light sources and shuttles
-
c)
-
Apply ergonomic working methods
-
d)
-
Detect hazardous substances and estimate possible hazards
-
e)
-
Ensure the storage of hazardous substances
-
f)
-
Hazards due to overhead lines and operating machines on the construction site
-
g)
-
Ensure ventilation of work spaces
-
h)
-
Use protective equipment and take measures to protect people from construction sites
-
i)
-
in the event of accidents at work, take emergency measures to supply injured persons, secure the accident site
Working and protective scaffolders:
-
k)
-
Building and disassembling work and protective scaffolders
-
l)
-
Assessing the operational safety of scaffold
Equipment and machinery:
-
m)
-
Select, request, transport, store and prepare for the operation of the equipment and machines for the work flow
-
n)
-
Use conveyor and transport equipment as well as use load-bearing and stop means
Environmental protection:
-
o)
-
Separating the waste at the construction site in a variety of places and preparing for the transport
-
p)
-
Cause hazardous substances to be disposed of
-
q)
-
Measures of nature conservation in roofs and exterior wall coverings, especially for birds and bats
Spaces:
-
r)
-
Preparing building materials, equipment and machinery for transport
-
s)
-
Submit Construction Site
|
3 |
Testing, storage and selection of building and building materials (Section 4 (1) (7)) |
-
a)
-
Determine, request and provide construction and construction aids as well as installation parts
-
b)
-
Test construction and construction aids for dimensional accuracy and shape accuracy
|
4 |
Reading and applying drawings and plans, making sketches, carrying out measurements (Section 4 (1) (8)) |
-
a)
-
Check drawings for compliance with the conditions on the construction site
-
b)
-
Applying the laying plans
-
c)
-
Make sketches for dimensions
-
d)
-
Measuring and testing components with measuring instruments
|
5 |
Processing of wood and manufacture of timber components (Section 4 (1) (10)) |
-
a)
-
Select wood and wood-based materials
-
b)
-
Wooden constructions, especially for roof chairs and timbered walls,
-
c)
-
Roof and wall surfaces, slats and shells
-
d)
-
Apply pre-cover panels to formwork
|
|
|
8 |
|
6 |
Processing of plastics and bituminous materials (Section 4 (1) (11)) |
-
a)
-
Take up melting and welding equipment as well as bitumen cookers, comply with safety regulations
-
b)
-
Construction of ventilated and non-ventilated roofs with seals, layer sequence as well as structural and physical differences in construction
-
c)
-
Making connections and closures in roof seals
|
|
7 |
|
|
7 |
Manufacture of thermal insulation, additional measures in roof coverings (Section 4 (1) (12)) |
-
a)
-
Heat insulation in ventilated and non-ventilated inclined roof structures as well as in external wall coverings, design and physical differences in construction
-
b)
-
Carry out additional measures, in particular under-roofs, undercovers and undervoltages
-
c)
-
Connect and attach connectors
|
|
11 |
|
|
8 |
Processing of slate, roof panels and shingles (Section 4 (1) (13)) |
Cover areas of roof and wall surfaces with slate, roof panels and shingles in different cover types |
9 |
Processing of roof tiles and roofing tiles (Section 4 (1) (14)) |
-
a)
-
Covering parts of roof areas with roof tiles and roof tiles in different types of covers, incorporating moulded parts
-
b)
-
Connect and attach connectors
-
c)
-
Laying ridge tiles and ridge bricks in mortar and with dry elements
|
10 |
Processing of metals (Section 4 (1) (15)) |
-
a)
-
Take soldering equipment into service, comply with safety regulations
-
b)
-
Cover parts of roof and wall surfaces with metal sheets in different types of cover
-
c)
-
Making covers
-
d)
-
Establish degrees
|
|
|
6 |
|
11 |
Manufacture of substructures of the clothing type for exterior wall coverings (Section 4 (1) (17)) |
-
a)
-
Set the structure of the substructure accordingly
-
b)
-
Testing ground, in particular with regard to the anchorage of substructures
-
c)
-
Select anchoring means
-
d)
-
Aligning and securing substructures
|
|
|
5 |
|
12 |
Installation of devices for the derivation of surface water (Section 4 (1) (18)) |
-
a)
-
Apply barns and wedges made of metals and plastics
-
b)
-
Install the roof gullys
-
c)
-
Producing external drainage
-
d)
-
Connecting internal drainage
|
|
4 |
|
|
13 |
Processing corrugated sheets (Section 4 (1) (19)) |
-
a)
-
Cutting and drilling corrugated sheets made of different materials
-
b)
-
Cover parts of roof and wall surfaces with corrugated panels, install mouldings
|
|
|
3 |
|
14 |
Installation of energy collectors and energy converters (Section 4 (1) (20)) |
-
a)
-
Incorporating energy collectors and energy converters, in particular solar panels and photovoltaic elements, in roof and wall surfaces
-
b)
-
Make connections to roof coverings, roof seals and exterior wall coverings
|
|
|
4 |
|
-
*)
-
To mediate in connection with other training contents.
|
|
III. Vocational training in the fields of speciation |
-
a)
-
In the field of roof, wall and sealing technology
|
Lfd. No. |
Part of the training profession |
Skills and knowledge to be mediated |
Timeframe values in weeks in the training year |
1 |
2 |
3 |
1 |
2 |
3 |
4 |
1 |
Covering of roof and wall surfaces with slate, roofing tiles, shingles, corrugated panels, roof tiles and roof tiles (Section 4 (2) (1) (a)) |
-
a)
-
Covering roof and wall surfaces
-
b)
-
Make connections and closures in covers with slate, roofing panels, shingles and corrugated boards
-
c)
-
Laying grats and gratstones in mortar and with dry elements
-
d)
-
Carry out joint smear, cross-stroke and inner smear
|
|
|
21 |
2 |
Sealing with plastics and bituminous materials (Section 4 (2) (1) (b)) |
-
a)
-
Sealing surfaces against soil moisture and against non-pressing water
-
b)
-
Connect and attach connectors
-
c)
-
Create and seal movement joints
-
d)
-
Surface protection of roof seals, in particular by means of plasterings, gravel shaking and plate coverings
-
e)
-
Establish the structure and layer sequence of extensive and intensive roof justifications
|
|
|
12 |
3 |
Performing coverings with metal sheets (Section 4 (2) (1) (c)) |
-
a)
-
Covering roof and wall surfaces
-
b)
-
Manufacture and install expansion comparators
-
c)
-
Connect
|
|
|
6 |
4 |
Cloak of outer walls Blechen (Section 4 (2) (1) (d)) |
-
a)
-
Making cloths with open and rear joints
-
b)
-
Connect and attach connectors
|
|
|
4 |
5 |
Construction of lightning protection systems for external lightning protection (Section 4 (2) (1) (e)) |
-
a)
-
Determining the grounding resistance of common ground shapes, setting and documenting the dimensions of surface and low-energy sources
-
b)
-
Apply erder cables and piping, which are laid out in the ground
-
c)
-
Creating potential compensation, mounting potential compensation rail, connecting existing earth lines
-
d)
-
Erecting lightning protection systems for external lightning protection in accordance with technical regulations, in particular setting and documenting the arrangement of catch devices and discharge lines, taking into account the proximity of electrical installations
-
e)
-
Measuring, evaluating and documenting resistors of earth-and lightning protection systems
|
|
|
4 |
6 |
Repair of roof and wall surfaces as well as timber constructions (Section 4 (2) (1) (f)) |
-
a)
-
Determine damage, determine causes
-
b)
-
Take the first action to limit damage
-
c)
-
Perform a repair
|
|
|
3 |
7 |
Reporting, offset, quality assurance measures (Section 4 (2) (1) (g)) |
-
a)
-
Check executed work for error-free execution, perform final control
-
b)
-
documenting work carried out, in particular drawing up daily reports and making a measure of the dimensions
|
|
|
2 *) |
|
-
b)
-
in the field of Reetdachtechnik
|
Lfd. No. |
Part of the training profession |
Skills and knowledge to be mediated |
Timeframe values in weeks in the training year |
1 |
2 |
3 |
1 |
2 |
3 |
4 |
1 |
Preparing coverings with Reet (Section 4 (2) (2) (a)) |
-
a)
-
Check reet for usability and sort by scope
-
b)
-
Setting the attachment technique
-
c)
-
Select fastener
|
|
|
6 |
2 |
Cover of flat roof surfaces with Reet (Section 4 (2) (2) (b)) |
-
a)
-
Inspect and manufacture flat roof surfaces
-
b)
-
flat roof surfaces in different fastening techniques, in particular binding, sewing and screwing, covering
|
|
|
12 |
3 |
Manufacture of connectors and connectors (Section 4 (2) (2) (c)) |
-
a)
-
Distinguishing cover techniques for connections and degrees, setting cover technology
-
b)
-
Make a tear in accordance with the knee point
-
c)
-
Make site covers
-
d)
-
Manufacturing fir-covers of different types
-
e)
-
Making grat and throat coverings
-
f)
-
Connecting fittings to fittings, in particular to chimneys
|
|
|
12 |
4 |
Cover of curved and curly roof surfaces with Reet (Section 4 (2) (2) (d)) |
-
a)
-
Test and manufacture cover underlay of curved and curly roofing surfaces
-
b)
-
arched and curly roof surfaces in various fastening techniques, especially binding, sewing and screws, ceilings
-
c)
-
Forming transitions in curved and curly roof surfaces
|
|
|
12 |
5 |
Construction of lightning protection systems for external lightning protection (Section 4 (2) (2) (e)) |
-
a)
-
Determining the grounding resistance of common ground shapes, setting and documenting the dimensions of surface and low-energy sources
-
b)
-
Apply erder cables and piping, which are laid out in the ground
-
c)
-
Creating potential compensation, mounting potential compensation rail, connecting existing earth lines
-
d)
-
Erecting lightning protection systems for external lightning protection in accordance with technical regulations, in particular setting and documenting the arrangement of catch devices and discharge lines, taking into account the proximity of electrical installations
-
e)
-
Measuring, evaluating and documenting resistors of earth-and lightning protection systems
|
|
|
4 |
6 |
Repairing roof surfaces and wooden structures (Section 4 (2) (2) (f)) |
-
a)
-
Determine damage, determine causes
-
b)
-
first measures to limit damage
-
c)
-
Perform a repair
|
|
|
4 |
7 |
Reporting, offset, quality assurance measures (Section 4 (2) (2) (g)) |
-
a)
-
Check executed work for error-free execution, perform final control
-
b)
-
documenting work carried out, in particular drawing up daily reports and making a measure of the dimensions
|
|
|
2 *) |
-
*)
-
To mediate in connection with other training contents.
|