Decree No. 2012 - 38 January 10, 2012 Laying Down The Schedule Of Claims Due Deadlines To Send The Convention Connection Or Realization Of The Connection Of Electricity Generation Facilities Overflow From...

Original Language Title: Décret n° 2012-38 du 10 janvier 2012 fixant le barème des indemnités dues en cas de dépassement des délais d'envoi de la convention de raccordement ou de réalisation du raccordement des installations de production d'électricité à partir de ...

Subscribe to a Global-Regulation Premium Membership Today!

Key Benefits:

Subscribe Now for only USD$20 per month, or Get a Day Pass for only USD$4.99.
Keywords industry, energy, energy CODE, electrical energy, renewable energy, energy SOURCE, PRODUCTION of electricity, INSTALLATION DE PRODUCTION d ' ELECTRICITÉ, connection CONVENTION, realization of connection, mailing time, connection time, overflow, offence, compensation, scale, PUBLIC electricity network, GRENELLE 2, network PUBLIC of DISTRIBUTION, network PUBLIC DE TRANSPORT ET DE DISTRIBUTION JORF n ° 0010 January 12, 2012 page 599 text no. 53 Decree No. 2012-38 January 10, 2012, fixing the scale of allowances due time overflow mailing of convention connection or realization of the connection of facilities for the production of electricity from renewable sources of energy of a power less than or equal to three kilovolt NOR: INDR1123368D ELI: https://www.legifrance.gouv.fr/eli/decret/2012/1/10/INDR1123368D/jo/texte Alias: https://www.legifrance.gouv.fr/eli/decret/2012/1/10/2012-38/jo/texte interested Publics: managers of public electricity distribution networks.
Subject: fixing the amount of compensation due the time limits for submission of the documents connecting or realization of the connection of facilities for the production of electricity from renewable sources of energy of a power less than or equal to three kilovolt overflow.
Entry into force: the text comes into force the day following its publication.
Notice: Decree lays down, pursuant to article l 342 - 3 of the code of energy, the amount of compensation payable by the Manager of the public network overflow: ― the period of one month for the production of the connection agreement (30 euros);
― the period of two months for the realization of the connection (50 euros, as well as 50 euros per additional month of overflow) for installations for the production of electricity from renewable sources of energy of a power less than or equal to three kilovolt.
References: this decree can be accessed on the Legifrance (http://www.legifrance.gouv.fr) site. Taken for the application of article 88 of the law n ° 2010-788, July 12, 2010, on a national commitment to the environment, which the provisions are described in article l 342 - 3 of the code of energy.
The Prime Minister, on the report of the Minister of ecology, sustainable development, transport and housing and the Minister of economy, finance and industry, seeing the code of energy, particularly its article L. 342-3;
Having regard to the opinion of the Supreme Council of energy dated July 8, 2011;
Having regard to the opinion of the Committee of regulation of energy dated July 26, 2011;
The Council of State (section of public works) heard, enacts as follows: Article 1 more on this article...

Under the conditions laid down in the first paragraph of article l 342 - 3 of the code of energy, claims due to the applicant for connection by the Manager of the public distribution system, the time of dispatch of the convention connection or the time limit for connection to the public network of distribution of electricity of a facility for the production of electricity from renewable energy sources with a lower installed power or equal to 3 kilovolt overflow , are laid down: 1 ° A 30 euros if the timeout set at a month to send the connection agreement, following the receipt of the complete application of connection;
2 ° a 50 euros for exceeding the deadline in two months to make the connections to the public network of distribution, from the receipt, by the Manager of the public network of distribution, of acceptance of the convention's connection by the applicant and, where applicable, EUR 50 per complete month of the supra timeout.


Article 2 more on this article...

The allowances referred to in article 1 are due only when the cause of the delay is exclusively attributable to the Manager of the public distribution system concerned. They are exclusive of any other allowance which would be laid down for the same reason in the fixing of tariffs for the use of public networks of transport and distribution of electricity mentioned in article L. 341 - 3 of the code of energy.


Article 3 read more on this article...

The Minister of ecology, sustainable development, transport and housing, the Minister of economy, finance and industry and the Minister with the Minister of economy, finance and industry, responsible for energy and the digital economy, industry shall be responsible, each in relation to the implementation of this Decree, which shall be published in the Official Journal of the French Republic.


Is January 10, 2012.
François Fillon Prime Minister: the Minister with the Minister of economy, finance and industry, responsible for industry, energy and the digital economy, Eric Besson, Minister of ecology, sustainable development, transport and housing Nathalie Kosciusko-Morizet the Minister of economy, finance and industry, François Baroin