Advanced Search

Executive Order On Net Settlement For Autoproducers Of Electricity

Original Language Title: Bekendtgørelse om nettoafregning for egenproducenter af elektricitet

Subscribe to a Global-Regulation Premium Membership Today!

Key Benefits:

Subscribe Now for only USD$40 per month.
Table of Contents
Chapter 1 Scope and definitions
Chapter 2 Conditions for the net expense of electricity consumption
Chapter 3 Net settlement decision
Chapter 4 The assessment and measurement of electricity generation and consumption, disclosure obligations etc.
Chapter 5 Appeal and penalty provisions
Chapter 6 Entry into force and transitional provisions

Completion of the net bill for self-producers of electricity

In accordance with sections 8 a and 8 b, section 28 (4), Three, section 85 a, section 88, paragraph. 1, section 90 and after authorization pursuant to section 92 of the power of electricity, cf. Law Order no. 279 of 21. March 2012, as amended by law no. 901 of 4. July 2013 :

Chapter 1

Scope and definitions

§ 1. In the case of net settlement, in accordance with the provisions of this notice, a self-manufacturer shall be exemplised in full or in part to pay amounts to cover public obligations in relation to the electricity consumption of electricity.

§ 2. For the purposes of this notice :

1) The producer : ElConsumer, who produces electricity or heat and electricity for the purpose of wholly or partly to cover its own energy consumption.

2) The electricity consumption of electricity : the share of electricity consumed by self-producers themselves.

3) Elecel-production unit : technical unit for power generation.

4) Nominal electric power : the installed power of the installations corresponding to the power generated by the plant at the most likely to produce and deliver.

5) Public obligations shall mean tasks assigned to the collective power supply undertakings and in which the necessary costs must be covered by the general consumer of electricity as referred to in Article 8 (8) of the power supply. 1, including costs of price allowance for eco-friendly electricity as mentioned in point 6.

6) Privileges for environmentally friendly electricity : the performance of the commercial electricity supply companies by sections 58, 58 a and 58 b, in accordance with section 58, 58 (b) and section 36-50 of the Promoting of Renewable Energy Act.

7) Renewable energy sources : energy sources covered by Section 2 (2). 2 or 3, in the promotion of renewable energy.

Chapter 2

Conditions for the net expense of electricity consumption

§ 3. The electricity producers of electricity production plants, which have a nominal electric power as referred to in paragraph 1. 2, may, at the request of Energinet.dk, have a net check which is charged on an hourly basis by which the producer is relieved to pay amounts to cover price allowance for environmentally friendly electricity in relation to the eget-use of electricity.

Paragraph 2. Net calculation in accordance with paragraph 1. 1 apply to installations with a nominal power output ;

1) 50 kW for solar power plants,

2) 25 kW for windmills and

3) 11 kW for power-heating systems and electricity plants which have not been mentioned in paragraph 1. One or two.

Paragraph 3. Net calculation in accordance with paragraph 1. 1 shall be conditional on the production of the electricity production plant ;

1) connected to the collective power supply network ; and

2) 100%. owned by the consumer, cf. however, paragraph 1 5.

Paragraph 4. The net calculation for electricity produced on a solar or windmill shall also be subject to the production of the electricity production plant in its own consumption installation or on the place of consumption. In the case of electricity produced on plant heating or power plants, which are not a solar panels or windmills, the net settlement shall be subject to the location of the power plant at the consumption site, cf. however, paragraph 1 6.

Paragraph 5. If a power heater located at the place of consumption is not 100%. Owned by the consumer, a net settlement is provided on condition that :

1) the installation is netconnected by the 12. April 2000, and

2) that the consumer by this date has concluded a lease or other financial agreement at the end of this date and shall continue to have such an agreement.

Paragraph 6. If a power heater provides heat to more business operators through the direct heat supply network, the net settlement shall be paid regardless of the location of the plant on condition that :

1) the installation is netconnected by the 12. April 2000, and

2) the facility is owned by one or more of the business operators concerned.

§ 4. The electricity producers of electricity production plants, which have a nominal electric power as referred to in paragraph 1. 2, may, at the request of Energinet.dk, a net check by which the producer is exempt from the payment of amounts to cover the public obligations as a whole in relation to the electricity consumption of electricity. If the producer requests Energinet.dk on this, the net bill will be charged on an hourly basis.

Paragraph 2. Net calculation in accordance with paragraph 1. 1 apply to installations with a nominal power output, which is no more than :

1) 50 kW for solar power plants,

2) 25 kW for windmills and

3) 11 kW for power-heating systems and electricity production plants which have not been mentioned in paragraph 1. One or two.

Paragraph 3. Net calculation in accordance with paragraph 1. Paragraph 1 shall be subject to the condition that the electricity production plant concerned meets the conditions for net settlement in section 3 (3). 3-6. In addition, the plant and power plant installations must be connected to its own consumption installation.

Paragraph 4. Energinet.dk shall take a net settlement decision in accordance with paragraph 1. 1 on the basis of information on electricity production plants in the register referred to in Section 6 and shall inform the manufacturer thereof. Any producer who finds that their installation meets the conditions for net settlement may also ask Energinet.dk to take a decision on this subject.

§ 5. For tenants that are not the sellers of electricity, section 3 (3) shall be found. 1-4, and section 4 on the net deriding equivalent use for electricity consumption of electricity produced in a plant which uses renewable energy sources only if :

1) The plant is 100%. owned by the landlord by the landlord,

2) the landowner of the property has made the facility available to the tenant for the purposes of net settlement ; and

3) The tenant is counting on its electricity consumption directly with the network on an hourly basis.

Paragraph 2. The provisions of Chapters 1 and 3 to 5 applicable to own producers of electricity shall apply mutatis mutants to tenants covered by paragraph 1. 1.

§ 6. The net calculation after section 3-5 shall also be conditional on the production of the electricity production plant to the register referred to in section 85 (a) (1). 2, no. 2, in the power of electricity (StamData Register).

Chapter 3

Net settlement decision

§ 7. Energinet.dk shall decide whether the conditions for obtaining a net check in accordance with sections 3 to 6 are met and whether the net bill is the size of the net bill.

Paragraph 2. The producer must lodge a request for a net settlement of existing installations for Energinet.dk before the first day of the month with prior notice of at least one month. The request shall be submitted at the same time as the request for network connection.

Paragraph 3. The manufacturer must submit a notification that the net bill should be discontinued to Energinet.dk before the first day of the month prior to the termination.

Paragraph 4. The producer can only once, in each calendar year, submit a request for a net settlement after sections 3 and 4 or a communication on the cessation of net settlement. The receipt and notification request shall be binding for the rest of the calendar year.

Paragraph 5. Where the conditions for net settlement are not met due to implocable conditions, the net bill shall be discontinued from the date on which the relationship is deemed to be met.

Chapter 4

The assessment and measurement of electricity generation and consumption, disclosure obligations etc.

§ 8. Energinet.dk will net the net settlement on the basis of measuring electricity and measuring electricity to and from the grid grid in accordance with the requirements of the electricity supply network. however, paragraph 1 Two and three.

Paragraph 2. When several consumers are connected to an electric production plant as referred to in section 3 (3), 6, shall be the net charge for the elaps concerned under one.

Paragraph 3. Where, in the same consumption installation, the same utility is connected to several installations using different renewable energy sources and not equipped with a production meter, the electricity production for each plant shall be made proportionately on the basis of the installation ' s premises ; the size and the average power generation for specified facilities, cf. Guidelines determined in accordance with section 11 (4). 1.

§ 9. Measurements necessary for net derisions must be performed by the net company using the net company ' s own meters in accordance with the Energy Networks of Energy Networks referred to in the Notice on the responsible establishment and use of the transmission network, etc.

Paragraph 2. Measures required for measurements as referred to in stk.1, including the set-up of measurements and the performance of measurements, and the administration associated with it, shall be borne by the self-producer.

§ 10. An own manufacturer must notify Energinet.dk on all matters of importance for the eligibility to be net settlement and the calculation of the settlement, cf. § § 3-6. The notification shall take place as soon as the relevant conditions are taken or at the time when the electricity producer has become aware that the relationship will occur.

§ 11. Energinet.dk provides guidelines for a net settlement request, the calculation of net settlement, the specification of the buying and sale of electricity on the electricity market, the performance of measurements to be used for the net calculation and the amount of the sale of electricity ; average power generation for specified facilities. The guidelines are approved by the Energy Management Board.

Paragraph 2. The guidelines and Energinet.dk's form required for net settlement request and the cessation of net calculation of accompanying instructions shall be published on the website www.energinet.dk.

Chapter 5

Appeal and penalty provisions

§ 12. Energinet.dk's decisions on whether the conditions for net settlement are met and whether the net bill's size cannot be complained to the second administrative authority other than the Energy Board Board.

Paragraph 2. Clause in accordance with paragraph 1 1 shall be submitted in writing within 4 weeks of the notification of the decision.

Paragraph 3. Other decisions following this notice may not be impanted to another administrative authority.

§ 13. Unless higher penalties have been imposed on other legislation, the penalty shall be punished by fine, which shall be liable for incorrect information on conditions in which they are required to provide information in accordance with section 10 or fail to provide such information.

Paragraph 2. Companies can be imposed on companies, etc. (legal persons) punishable by the rules of the penal code 5. Chapter.

Chapter 6

Entry into force and transitional provisions

§ 14. The announcement shall enter into force on 1. September, 2013, cf. however, paragraph 1 2.

Paragraph 2. section 16 (4). 1, no. 3 has effect from the 20. November 2012.

Paragraph 3. Publication no. 1068 of 16. November 2012, on the net bill for the self-producers of electricity, is hereby repealed.

§ 15. The electricity producers of electricity-generated power plants, which are connected to the 20. However, November 2012 may continue after Section 5 of the Notice Notice. 804 of 28. June 2010, on the net bill for self-producers of electricity, shall be net affront on an annual basis up to and with 19. In November 2032, the power-producer depending on the nominal power of the plant is either exempting from paying the amount of public commitments as a whole in relation to the consumption of electricity or exempting the amount of money for the payment of cover for cover ; for price allowance for environmentally friendly electricity in relation to the eget-consumption of electricity, cf. section 4 (4), respectively. Article 3 (2) and section 3 (3). 2, in Notice no. 804 of 28. June 2010 on the net bill for self-producers of electricity. This is conditional on the conformity of the electricity producer in section 5 (5). 2, in Notice no. 804 of 28. June 2010 on the net bill for self-producers of electricity.

Paragraph 2. Paragraph 1 shall also apply to a tenant of housing or non-commercial use when the power plant is connected to the consumption installation of the tenant and the electricity consumption of the Tenant is settled individually, cf. Section 5 (5). 2, no. 3, in the notice. 804 of 28. June 2010 on the net bill for self-producers of electricity, as amended by publication No 2 ; 1637 of 15. December 2010. This is subject to the fact that the person concerned meets the conditions laid down in section 5 (5). 2, in Notice no. 804 of 28. June 2010 on the net bill for self-producers of electricity, as amended by publication No 2 ; 1637 of 15. December 2010.

§ 16. In addition, an owner of a power plant may be owned by a power plant at the request of Energinet.dk on a yearly basis on a yearly basis after section 5 of the notice. 804 of 28. June 2010 on the net bill for the self-producers of electricity up to and with the 19. November 2032 on condition

1) the owner satisfies the conditions under section 5 (5). 2, in Notice no. 804 of 28. June 2010 on the net bill for self-producers of electricity,

2) the owner has made a binding agreement on the purchase of the electricity production plant at the latest by 19. November 2012, cf. paragraph 2,

3) the net company not later than 20. December 2012 has received notification of the installation for registration in the StamData Registry, and

4) the installation is netconnected no later than 31. December, 2013.

Paragraph 2. At the owner ' s request to Energinet.dk relating to net payment, the owner of the purchase invoice or similar evidence shall show written proof that the electricity production plant has been purchased by the 19th. November 2012.

Paragraph 3. A tenant of accommodation or non-commercial use may enter the owner ' s right to net settlement on an annual basis of paragraph 1. 1 if the installation is connected to the tenant ' s consumption installation, and the electricity consumption of the tenant is settled individually, cf. Section 5 (5). 2, no. 3, in the notice. 804 of 28. June 2010 on the net bill for self-producers of electricity, as amended by publication No 2 ; 1637 of 15. December 2010.

Paragraph 4. Energinet.dk shall decide whether the conditions for the year-based net check shall be taken in accordance with paragraph 1. 1 or 3 has been met.

Paragraph 5. Decisions pursuant to paragraph 1. 4 cannot be complained to the second administrative authority other than the Energy Board Board, cf. § 12.

DEA, 26. August 2013

Ib Larsen

/ Flemming G. Nielsen