Advanced Search

Executive Order On The Grid Connection Of Wind Turbines And Wind Turbine Produced Electricity For Surcharges, Etc.

Original Language Title: Bekendtgørelse om nettilslutning af vindmøller og pristillæg for vindmølleproduceret elektricitet m.m.

Subscribe to a Global-Regulation Premium Membership Today!

Key Benefits:

Subscribe Now for only USD$40 per month.
Table of Contents

Chapter 1 Scope, definitions and common conditions

Chapter 2 Cost allocation for network connection and so on

Chapter 3 Definition of existing windmills

Chapter 4 Land turnips for windmills

Chapter 5 Detapotions of price allowance

Chapter 6 Move wind turbines

Chapter 7 Information to be confidential

Chapter 8 Decisions

Chapter 9 The completion of full cargo hours for existing windmills per 1. April 2001

Chapter 10 Appeal access

Chapter 11 Penalty provisions

Chapter 12 Entry into force

Completion on network connection of windmills and price corps for wind turbine electricity and so on. 1)

In accordance with section 30, section 39, paragraph 1. 8, section 42, paragraph. 8, section 43, paragraph. 2 and 3, sections 53, 57 and 61, section 65 (3). 3, sections 68, 70 and 73 of Law No 1392 of 27. In December 2008, on the promotion of renewable energy, as amended by law no. 622 of 11. June 2009, and Article 85 a in the electricity supply, cf. Law Order no. 516 of 20. The year May 2010 shall be :

Chapter 1

Scope, definitions and common conditions

§ 1. The announcement shall apply to the electricity-producing windmills of land and on the sea, which are connected to the power grid.

Paragraph 2. The following definitions shall apply in this notice :

1) A windmill shall mean a windmill that has been laid down on the sea territory or in the exclusive economic zone.

2) A designated wind turbine area means an area designated by the State or of the municipality in a local authority plan specifically designated for the setting up of one or more windmills, in accordance with the case of the local authority. circular planning and landing zone clearance for windmills.

3) For the purpose of installed power, the nominal power of the windmilled windmills shall be understood as specified in the technical approval, cf. the technical approval arrangements for the design, manufacture, construction, maintenance and service of windmills.

4) The first accession of wind turbines to the electricity network in Denmark or abroad is understood by the initial agreement.

5) The time of network connectivity is the point at which the windmill supplies electricity to the collective electricity network shall be the date of windmill.

6) The production of electricity shall mean the production of electricity produced or calculated for the operation of wind turbines since the original connection.

7) In the case of production in a full loading period, production corresponding to an hour ' s production with the installed power of the windmill shall be understood.

8) For the purposes of a settlement, a meter used for registration of power generation or electricity consumption shall be used.

§ 2. A windmill may only be connected to the power network if it is established in accordance with the provisions in force in the law on the promotion of renewable energy, the law on electricity, the planning and the building code, as well as rules issued with legal basis in the said laws.

Paragraph 2. If the conditions of network connection are fulfilled, the network and transmission company have a duty to connect the windmill to the power grid.

Chapter 2

Cost allocation for network connection and so on

§ 3. For the network connection of a windmill on the land, the net company shall show a connection point at the nearest point of the electricity grid where the electricity from the new windmill can be taken, cf. However, section 4. The network company determines the voltage level.

Paragraph 2. The net cost of the electricity building and the net support of a network of wind turbines shall be borne by the network.

Paragraph 3. In the event of the approval of a windmill in its own consumption installation, the possible extraction and reinforcement of the windmill owner shall be responsible for the development of the windmill

Paragraph 4. In the windmill at transmission level, paragraph shall be found. 1 and 2 accordingly applicable to the transmission company.

§ 4. In the case of the establishment of one or more wind turbines in a designated wind turbine area, the net undertaking shall be obliged to carry out the power grid to a point in wind turbine area when there is sufficient certainty that windmills with a windmills are shown ; total installed power of at least 1,5 MW. Adequate security may be a bank guarantee or equivalent security. The network company determines the voltage level.

Paragraph 2. In the windmill at transmission level, paragraph shall be found. 1 corresponding use shall apply to the transmission company.

k. 3 The windmill owner is required to dimension the internal connection network between the connection point and the point of departure (the meter) after Energinet.dk's guidelines. The guidelines have been published on the Energinet dk's website www.energinet.dk.

§ 5. In the event of network connection of sea breeders, the transmission undertaking which owns the electric net to which the mergers are connected on the sea or on the country of the sea shall be obliged to hold the cost of setting up the wiring for a collection point at the time of the transmission ; the internal interconnection networks of the sea windmills. This applies to sea windmills, which :

1) they are listed in the ' Ocean of the Sea-Moths Action Plan for Danish waters ' selected main areas of the sea-mill building ; or

2) shall be notified to the opening of an area covered by one of the climate and energy minister, in accordance with the public call for applications, in accordance with the public call for applications. Section 23 of the promotion of renewable energy.

Paragraph 2. The transmission company concerned shall determine the level of voltage.

§ 6. In the case of network connectivity of sea windmills which are not covered by the areas referred to in Section 5, the costs of setting up the wiring shall be responsible for the establishment of the wind turbine owner. From this point of connection, costs for the development and reinforcement of the power grid shall be the network or transmission undertaking which owns the power grid to which the mergers are to be connected on the land.

Paragraph 2. The network or transmission company shall fix the voltage level.

Paragraph 3. The island or mainland shall be the island or mainland where the seq; is to be used.

Paragraph 4. The DEA may, in exceptional circumstances, decide on the distribution of expenditure by the f. Exes. islands. Special circumstances may be that network connection seems undesirable or unjustifiable.

§ 7. If net connection of windmills as referred to in section 3-6 also necessitates the cost of reinforcement of the power grid with tensions up to 100 kW owned by other networks and transmission undertakings, the costs shall be borne by the costs of a proportion of these undertakings ; costs associated with the network connection.

Paragraph 2. Where electricity from windmills covered by section 3-6 is provided to a network or transmission operation by means of a wiring which is not connected to consumers or other power producers other than windmills, the costs of net losses shall be borne in : this wiring from the reicer as part of the net or transmission company ' s cost of windmills is connected to the power grid.

§ 8. The costs of a wind turbine network up to the connecting point referred to in section 3-6 shall be held by the windmill owner, cf. paragraph Two and three.

Paragraph 2. Network connection costs for the opening of a windmill comprises costs for the installation, low-voltage and low-voltage, and the establishment of settlement meters, measuring transforms, and local transformer, power grids and connectivity to the power grid, including phase compensation. Cost of phase compensation for non-supplied reactive power shall be borne by the network or transmission company. Costs for the processing of the collective power supply undertaking shall be the responsibility of the windmill owner.

Paragraph 3. Afreing meters and gauge transforges are owned by network or transmission company.

Paragraph 4. The network connection of wind turbines shall cover documented expenditure and shall be provided by invoice, which shall be furnired to the windmill owner within three months after the wind power of wind power.

Paragraph 5. Costs for the maintenance or replacement of resettlement gauges and meter transforges, calibration and reading of the meters and the settlement of electricity shall be incumbable to the windmill owner. The costs must cover real documented costs relating to the individual windmill. The net or transmission company shall specify the composition of the windmill in accordance with the windmill, cf. 1. pkt., on submission of invoice. The net or transmission shall be documented by the windmill owner on the windmill owner ' s request.

Paragraph 6. If the network or transmission company has not submitted the invoice, cf. paragraph 4, or can document the cost of invoice, cf. paragraph 5, the wind turbine owner may issue the case for the energy supervision, which may impose on the net or transmission company to produce invoice or documentation of expenditure.

Paragraph 7. The cost of setting up the wire, which is the responsibility of the transmission company after paragraph 5, shall be charged as costs through the individual company's tariffs.

Paragraph 8. Net management costs and by means of a windmill being connected to the windmill, which is not referred to in paragraph 1. In the case of a single undertaking, 2, 3 and 5 shall be charged as the cost of the individual company. Section 8 (8) of the power supply. 5.

§ 9. Windls, like after the 20th. May 2003 shall be connected to the power grid or to a usage installation from which the electricity can be delivered to the power grid, shall have its own conversion measures which comply with Energinet.dk's power measurement requirements. The recipes have been published on Energinet. dk's website www.energinet.dk.

Paragraph 2. Wenvirons, which are netsigned at the latest 20. In May 2003 and drawn up in groups or parks, they shall have their own conversion measures, as referred to in paragraph 1. 1, where the electricity from each wind mills is subject to a different price allowance.

Paragraph 3. Where the production of wind turbines is not measured on an hourly basis, production shall be distributed on an hourly basis by the system operator in accordance with the requirements referred to in paragraph 1. 1 that is said.

Paragraph 4. Wine mills at 25 kW or less connected to a consumer installation are exempt from the requirement for the own conversion measures in accordance with paragraph 1. 1.

Paragraph 5. Sea-windmills which are notified by the tender shall be granted authorisation to decide in an area covered by the tender, exempted from the requirement for the own conversion measures in accordance with paragraph 1. 1. This does not apply to testing mills.

§ 10. The Net and transmission company has a duty to give an owner of the windmill, requesting network connection, all necessary information, including :

1) a detailed estimate, which includes all expenses, whether or not the connectivity will cost,

2) a reasonable and precise timetable for receipt and processing of the application for network connection and

3) a reasonable indicative schedule for the network connection.

Chapter 3

Definition of existing windmills

§ 11. Existing wind turbines on land and on the sea shall be defined as windmills ;

1) by 31. December 1999 has been purchased by binding, unconditional contract, cf. however, paragraph 1 3,

2) by 31. December 1999 has been notified in accordance with the notice. 1518 of 14. December 2006 on the noise of windmills, and

3) for which no later than 31. In August 2000, a request for connection with the power network shall be submitted, together with proof of fulfilment of the conditions for connection.

Paragraph 2. Existing wind turbines shall at the latest date of 31. December 1999 was notified to the municipality in accordance with the structure of the building code and either :

1) by 31. In December 1999, a final approved local plan has been established, where the opening of windmills is expressly permitted, or

2) by 31. In December 1999, a farmer ' s authorization has been granted, including, where appropriate, the necessary derogations for the construction of the building.

Paragraph 3. The one in paragraph 1. 1, no. The contract may be subject to the necessary regulatory authorisations for the opening of the windmill at the latest by 31 of the said contract. December 1999, and that the conditions for network connection are met by 31 December. August 2000.

Paragraph 4. If a local plane is repealed by the Natural Board due to the relationship associated with the processing of the case, windmills covered by the local plan shall be considered as existing if the municipal management board within six months from ; The termination of the local plan of nature shall definitively adopt a local plan in its unaltered form after public submission and re-examination of the municipal management board.

Paragraph 5. Rae the windmill after the 1. In April 2001, the installed power is the effect that is apparent from the binding contract, cf. paragraph 1, no. 1.

Chapter 4

Land turnips for windmills

Windler degrading in the period from 3. March 1999 to the 31 st. December 2003

§ 12. A wind turbine owner may obtain the scrapping proof of a windmill of 150 kW or less during the period from the third. March 1999 to and with the 31 st. In December 2003, under those referred to in paragraph 1, 2 or 3 conditions mentioned.

Paragraph 2. The turnip certificate for windmills which have been reduced in the period from 1. April 2001 to and with the 31. In December 2003, if this is shown by one of the windmill owner, the farmer ' s principal declaration of windmills shall be obtained from the windmills. Furthermore, the declaration made by one of the network undertaking issued a declaration that the wind turbine has been set up has been in operation and has had a capacity of less than 100 kW or between 100 and 150 kW (both power values inclusive).

Paragraph 3. In the case of windmills which have been reduced in the period from 3. March 1999 to and with the 31 st. In March 2001, the scrapping certificate may be obtained if a statement signed by both the network operator and by the owner of the windmill has been signed. The declaration must indicate that the wind turbine has been in operation, has had a capacity of less than 100 kW or between 100 and 150 kW (both power levels, including) and the time when the windmill has been decommissioned and removed.

Paragraph 4. The certificate shall allow the owner to receive price allowance in accordance with section 42 (2). 2, on the promotion of renewable energy for the reduced power of the windmill, if this had an installed power of less than 100 kW, the installed power of three (2).

Paragraph 5. The certificate shall allow the owner to receive price allowance in accordance with section 42 (2). 2, in the Prompting of renewable energy for twice the installed power of the windmill, if this had an effective power of between 100 kW and 150 kW (both power values inclusive) and if it was located at a maximum of five kilometres, from a windmill that had an installed power of less than 100 kW, which has itself obtained a scrap of scrap.

Windler depreciated during the period from the 15th. December 2004 to the 15th. December 2011

§ 13. A scrap of scrap metal as referred to in paragraph 1. 2 gives the owner the right to receive price allowance as referred to in section 42 (2). 5, in the promotion of renewable energy for electricity produced in a factory new windmill, from the 1. 1 January 2005 to 31. December 2011.

Paragraph 2. A wind turbine owner may under the windmills of paragraph 1. the conditions referred to in paragraph 3, 4 and 6, and subject to the conditions laid down in paragraph 1 3 the pool shall obtain the scrapping proof of a windmill having an effect of 450 kW or below for the period from the 15th. December 2004s and at the latest and with the 15th. December 2011. A scrapping certificate can be divided into up to 10 independent scrapping evidence.

Paragraph 3. The certificate of casing may be issued only within a pool that corresponds to a total effect of 175 MW in windmills, with an impact of 450 kW and below which has been removed from the 15th. December 2004 to and with the 15th. December 2011.

Paragraph 4. The proof of the certificate shall also be subject to the existence of :

1) a declaration signed by the network undertaking concerned by the fact that the wind turbine has been in operation and has had an effect of 450 kW or there, as well as the time when the wind turbine is detached from the collective ; the electricity supply network ; and

2) a statement signed by the windmill owner that the windmill has been reduced.

Paragraph 5. The network shall deliver the one in paragraph 1. 4, no. 1, the declaration of the windmiller owner no later than eight days after receiving a request for this.

Paragraph 6. Request for scrap heap shall be submitted to Energinet.dk at the latest by 15. December 2011.

§ 14. A wind turbine owner may ask Energinet.dk to give a written advance notice that a scrap of scrap metal may be issued for the collection of a windmill after Article 13. The insurance network cannot be translated. Energinet.dk provides the prehenchness if the company considers it in section 13 (3). 3, the maximum of 175 MW is not exceeded as a result.

Paragraph 2. A forfeit legend gives the windmill owner the right to receive a scrapping certificate, provided that the conditions for receiving a scrapping certificate have been fulfilled and the windmill owner ;

1) within 8 days of the receipt of the handover network, the network is requesting to disconnect the windmill as soon as possible from the collective power supply network ; and

2) within 40 days from the date of receipt of the case of the forehand, cf. however, the one in section 13 (1). The time limit referred to in paragraph 6 shall be submitted by 6, to the request for scrap certificate to Energinet.dk, with proof of the facts referred to in paragraph 1. Paragraph 1 and paragraph 13 (1). 4.

Paragraph 3. Energinet.dk publishes on-going information on electronic media on the size of the power for which scrapping evidence and processing lore have been issued.

Paragraph 4. Energinet.dk is preparing the application material for the issue and processing of scrapping certificates and forcandal folklore.

Common provisions governing the two scrapping schemes

§ 15. In order to make use of a piece of scrap certificate issued under Clause 12 or 13, the proof must be delivered to and endorsed by the company at the latest at the time of the network connection of the new windmill. The endorsement shall indicate the new windmill in which the proof is used. The form of the certificate shall then not be used in other windmills.

Paragraph 2. If a scrap of scrap is not fully utilized in one new windmill, the excess shall lapse.

Paragraph 3. The owner of a scrap certificate which has not been used for the payment of price allowance in accordance with section 42 (5). 2 and 5, in the promotion of renewable energy, can pass this on to others.

Paragraph 4. A windmill which has triggered scrap-scaling evidence in accordance with sections 12 or 13 may not be reconnected to the power grid or to a consumer installation from which the electricity can be delivered to the power grid.

Chapter 5

Detapotions of price allowance

§ 16. A wind turbine owner may deselect the receipt of price allowance and other benefits under section 36 to 42 of the Promotes of Renewable Energy. In addition, the wind turbine owner may reopen the receipt of the said price allowance and other benefits. The right to resumption does not include owners of sea windmills established in accordance with the supply.

Paragraph 2. Dissenting and re-opening after paragraph 1 shall take effect from the first day of a month and with prior notice of at least one month if there is a VU or price allowance for the electricity following the provisions of section 36 to 42 of the Promovation of renewable energy.

Paragraph 3. In the case of the calculation of original production for the calculation of full last hours in accordance with this notice and section 36-42 of the promotion of renewable energy, production shall also be included in the opt-out as referred to in paragraph 1. 1.

Paragraph 4. The required administrative costs of the opt-out and the resumption of the network or transmission company and the system responsible business shall be paid by the wind turbine owner on the basis of inventory of these costs.

Paragraph 5. Energinet.dk prepasts application material for the selection of the price allowance.

Chapter 6

Move wind turbines

§ 17. In the case of relocation and new networks of windmills, the results obtained shall be achieved by a windmill, other than price allocation to an existing windmill where the price post shall be in accordance with section 39 (2). 3, in the Promoted Renewable Energy Act, and for the electricity, a price allowance shall be granted, together with the required market price according to section 51 the promotion of renewable energy sources constitute 43 cents per. kWh, cf. § 39, paragraph. Four, on the promotion of renewable energy.

Paragraph 2. In the event of moving wind turbines connected to its own consumption installation, which has an installed effect of 25 kW or thereunder, cf. Section 41 of the promotion of renewable energy, follows the price supplement, which together with the fixed market price amounts to 60 cents per. kWh, single windmill, if the wind turbine is again connected in its own consumption installation.

Paragraph 3. In the case of relocation of wind turbines which have previously been directly connected to a new connection in its own consumption installation, the windmills will achieve the price supplement, which together with the fixed market price amounts to 60 øre per. kWh, cf. Section 41 of the promotion of renewable energy, provided that these have an installed power of 25 kW or less.

Chapter 7

Information to be confidential

§ 18. The owner of a windmill shall be obliged to make such information, including accounts and similar documentation, to be the owner of a windmill, including accounts and similar documentation for the purposes of this Regulation ; the implementation of the notification provisions relating to network connection and price allowance.

Paragraph 2. It shall be incumbated to the owner of a windmill to notify the net company, transmission company and Energinet.dk for ownership change, previous network connections, and the changing circumstances, in the case of compliance with the conditions for network connection and for the receipt of price allowance for the supplied electricity.

Chapter 8

Decisions

§ 19. The network undertaking which has or has applied for the granting of the supply area shall take a decision on network connection, including the fulfilment of the conditions for the approval of the supply. In addition, the undertaking shall decide on the allocation of costs, as mentioned in Section 8.

Paragraph 2. In the case of windmills directly to a transmission network, the transmission company shall decide on network connection, including whether the conditions for connection are met. In addition, the transmission undertaking shall decide on the allocation of costs, as mentioned in Section 8.

Paragraph 3. The network shall decide as to whether a windmill on land meets the conditions laid down in the definition of existing windmills in accordance with section 11, cf. however, paragraph 1 5.

Paragraph 4. Energinet.dk takes a decision whether a sea windmill meets the conditions of the definition of existing windmills after paragraph 11, cf. however, paragraph 1 5.

Paragraph 5. The DEA will decide whether a windmill satisfies the conditions laid down in the definition in accordance with section 11 of existing windmills in all cases where a new windmill has been purchased for the period from the third. March 1999 to and with the 31 st. December 1999.

Paragraph 6. Decision on the completion of full cargo hours for windmills in accordance with section 36-42 of the Promotion of Renewable Energy is taken by the net company. If the wind turbine is directly intended for a transmission network, the transmission company shall decide on this.

20. Energinet.dk shall decide on the following :

1) Priviations and other services to electricity from wind turbines in accordance with section 36 to 42 of the promotion of renewable energy sources.

2) Issue of scrapping certificate, as referred to in Chapter 4 of this notice, including the fulfilment of the conditions for obtaining the proof.

3) The deselection and reopening of the payment of the price allowance and other services in accordance with section 16 of this notice.

4) The completion of full cargo hours for windmills in accordance with section 39 of the Promotion of Renewable Energy.

§ 21. Notwithstanding the provisions of section 19 (1). 1-3 and 6, a network or transmission operation may ask Energinet.dk to take a decision in accordance with the said provisions on behalf of the network or transmission company. Energinet.dk may, in such a case, require the net or transmission company to reimburse the costs incurred by such a request to intake Energinet.dk.

Chapter 9

The completion of full cargo hours for existing windmills per 1. April 2001

§ 22. The network shall draw up an inventory of the amount of full cargo hours per day ; 1. April 2001. The statement will be updated at each payment of the price allowance.

Paragraph 2. The inventory shall be based on the production of electricity produced. If the conversion data does not exist back from the original concoction of the windmill, the missing production data is calculated. The recalculation shall be calculated by means of a windage average calculation on the available billing data. This will only be corrected for the whole year. The production of the year in which a windmill net connects for the first time is calculated proportionally, whereby a month ' s production is regarded as 1/12 of a year's production.

Paragraph 3. The average calculation for the calculation of the production data recalculation shall not be included as a year in which the wind-corrected production is deviated by 25%. or more from the end of the year. To the extent that the resettlement data is longer than five years in the network or the company responsible for the system responsible, these must be included in the calculation. If the wind turbine owner can document electricity conversion data longer than five years, this is used instead of a calculated figure.

Paragraph 4. If several windmills are connected to the same gauge, the production shall be divided between the windmills based on the wine-corrected annual production of vines. kW.

Paragraph 5. In the case of windmills which are connected to its own consumption installation and which have an installed effect of more than 25 kW, the production of production shall be calculated on the basis of an annual production of 2 200 full-last hours.

Chapter 10

Appeal access

-23. Decisions on Section 19 (3). 1, 2 and 6, and sections 20 and 21 may be enclamed for the Energy supervision.

Paragraph 2. Complaguing shall be submitted in writing within 4 weeks of the fact that they are in accordance with paragraph 1. 1 above decisions have been announced. Complained to the network, transmission company or Energinet.dk, which shall be forwarded within four weeks of its receipt, the review of the Energy supervision of a statement and the information which has been given to the decision.

§ 24. Decisions on Section 19 (3). 3 and 4 can be claimed for the Agency for Energy Management.

Paragraph 2. The decisions of energy management cannot be complained to the climate and energy minister.

§ 25. Decisions taken pursuant to section 19 (1). 5, sections 23 and 24 may be imparted to the Energy Board Board.

SECTION 26. Clause of sections 24 and 25 shall be submitted in writing within 4 weeks of notification of the decisions.

Chapter 11

Penalty provisions

§ 27. Unless higher penalties have been inflished on any other law, the penalty shall be penalised by the penalty which :

1) provide untimely information in connection with the request for network connection and receipt of price allowance and other services for electricity ; or

2) omits to submit notification of changes in the meaning of network connectivity and pricing and other services for electricity or which provide inaccurate information in such notification.

Paragraph 2. Companies can be imposed on companies, etc. (legal persons) punishable by the rules of the penal code 5. Chapter.

Chapter 12

Entry into force

§ 28. The announcement shall enter into force on the 15th. September, 2010. § 8 (3) 6, however, enter into force on 1. January, 2011.

Paragraph 2. Publication no. 1365 of 15. In December 2004, the net endorsement of windmills and the price of wind turbine-produced electricity must be lifted.

DEA, the 7th. September 2010

Ib Larsen

-Hanne Windemuller

Official notes

1) The announcement contains provisions which implement parts of Directive 2009 /28/EC of the European Parliament and of the Council of 23. April 2009, on the promotion of the use of renewable energy sources and amending and subsequent repealing of Directive 2001 /77/EC and 2003 /30/EC, (EU Official Journal 2009) L 140, page 16).