396/2011 Sb.



DECREE



of 5 April 2004. December 2011,



amending Decree No. 545/2006 Coll., on the quality of the supply of gas and

related services in the gas industry



The Energy Regulatory Office shall, pursuant to section 98, para. 2 (a). (c)) of the Act

No. 458/2000 Coll., on conditions for business and the public administration in

energy sectors and on amendments to certain acts (the Energy Act),

as amended by Act No. 158/2009 Coll.:



Article. (I)



Decree 545/2006 Coll., on the quality of the supply of gas and related

services in the gas industry, is amended as follows:



1. in the introductory sentence, the words "§ 98 para. 7 "shall be replaced by" section 98a of paragraph 1. 2

(a). (c)) "," 670/2004 "is replaced by" 158/2009 "and the words"

for the implementation of section 17(2). 7 (b). and) Energy Act "shall be deleted.



2. In paragraph 1, the word "deadlines" shall be replaced by the words "procedures and deadlines".



3. In article 2 (2). 1, § 2, paragraph 1. 2, § 14 para. 1 and 2, the word "underground"

repealed.



4. In article 2 (2). 2 the words "the end" are replaced by the word "to".



5. In article 2 (2). 2, section 4, paragraph 4. 1, § 6 (1). 1 and 2, section 10, paragraph 1. 2, § 11

including the title and paragraph 1. 1, § 11 (1) 2, § 12 para. 1, § 13 para. 1

(a). and, section 13 paragraph 1). 1 (b). (b)) § 13 para. 1 (b). (c)), § 14 para. 1

(a). and, § 14 paragraph 2). 1 (b). (b)), section 15, including the title and paragraph 1. 1, § 15

paragraph. 2, § 16 para. 1 (b). and section 16, paragraph 1). 1 (b). (b)), the word

"final" is deleted.



6. § 3, including the title reads as follows:



"§ 3



The application of refunds



(1) the customer or trader of gas which, on the basis of the Treaty on

associated gas supplies gas supply services to the customer (hereinafter referred to as

"supplier of pooled services"), or apply a claim for supplier



and failure to comply with the standard by) section 8 within 60 calendar days from the date of

following the date on which it should be according to the standard restrictions or

the interruption of transmission, distribution, or storage of gas started or

discontinued in the transmission or distribution system, which

the gas device is connected, the customer



(b) failure to comply with standards based) § 4, 6 and 7, section 9 to 11, § 13 to 16 to

60 calendar days from the day following the date on which

the time limit according to the standards, in



1. the transmission or distribution system, to which the gas

device is connected to the customer's



2. the operator of the storage tank, with which it has concluded a contract of

gas storage,



3. the transmission or distribution system, for which the requesting

connection, or



4. the supplier or vendor combined services, which based on

the contract gives the customer the gas.



(2) if the customer shall negotiate with supplier of syndicated service treaty

associated gas supply services, can assert the standards referred to in paragraph 4,

6, 7, 8, 11 and 13 to 15 and of compensation for non-compliance with the vendor

syndicated service that reaches the customer's request a refund

the operators of the respective gas devices. In this case,

shall be borne by the operator of the gas equipment to pay customer

through vendor services and associated deadlines for fulfilment of the

standards extend about 2 working days for a vendor combined

services that are used for ensuring the transmission of information between the supplier

syndicated services and operator of the respective gas. ".



7. in section 4, paragraph 4. 1, the words "or a pass-through" and "operator

local distribution system or operator of underground gas storage

gas ' are deleted.



8. In section 4, paragraph 4. 4, § 8 para. 2 and § 10 (1). 3 letters a) to (c)):



"and 1 500 Czk) for the category of residential and home; the Grand total

compensation does not exceed 15 000 CZK



(b)) 6 200 Eur for the medium category of the Subscriber; the total sum of compensation is

no more than 124 000 CZK



(c)) 10 500 $ for the commercial customer category; the total sum of compensation is

not more than 210 000. ".



9. in section 4, paragraph 4. 4, § 6 (1). 2 and 3, § 7 (2). 1 (b). a), b) and (c)), § 7

paragraph. 2, § 8 para. 1 and 2, section 10, paragraph 1. 3, § 11 (1) 2, § 13 para. 2, §

14. 2, article 15, paragraph 2. 2 and § 16 para. 2, the word "final" is deleted.



10. in paragraph 5, the word "final" is deleted.



11. In paragraph 6 (1). 3, § 11 (1) 2, and article 15, paragraph 2. 2 a) to (c)):



"and $375) for the category of residential and home; the total sum of refunds

is less than $3 750



(b)) 1 250 Czk for the medium category of the Subscriber; the total sum of compensation is

a maximum of 25 000 CZK



(c) for category 2 200 Czk) commercial customer; the total sum of compensation is

no more than 44 000. ".



12. In paragraph 7 (2). 2, § 13 para. 2, § 14 para. 2 and § 16 para. 2 a)

(c)):



"and $750 for the category) residential and home; the total sum of refunds

does not exceed 7 500 CZK



(b) for category 3 100 Czk) central subscriber; the total sum of compensation is

not exceeding 62 000 CZK



(c) Eur 7 900 for the category) the commercial customer; the total sum of compensation is

a maximum of 158 000. ".



13. In section 8 including the title, the words ", distribution or warehousing"

replaced by the words "or distribution".



14. in § 8 para. 1 and 2, the words ", distribution or warehousing"

replaced by the words "or distribution".



15. In § 8 para. 1 and 2, the words "or underground gas storage"

shall be deleted.



16. section 9, including title and footnote No 1 is added:



"section 9



Standard time limits for the assessment of applications for the connection of the device to the customer

a transmission or distribution system



(1) the standard period for examining applications for device connection

customer to the transmission or distribution system, it is the assessment of the application for

the device connects the customer to the transport or distribution system in

the time limit laid down other legislation ^ 1).



(2) For failure to comply with the standard time limits for examining the application for connection

the consumer device to the transmission or distribution system

the operator of a transmission or distribution system for each customer and

day of delay compensation in the amount of



1 500 Czk) for the category of residential and home; the Grand total

compensation does not exceed 15 000 CZK



(b)) 6 200 Eur for the medium category of the Subscriber; the total sum of compensation is

no more than 124 000 CZK



(c)) 10 500 $ for the commercial customer category; the total sum of compensation is

not more than 210 000.



1) Decree No. 62/2011 Coll., on conditions of connection to the gas

the system amending the Decree of the Ministry of industry and trade no. 251/2001

Coll., laying down the rules of operation of the transmission system operator and

distribution system operators in the gas sector. "



17. in section 10, paragraph 1 reads:



"(1) Standard allow the transport or distribution of gas is an option

the implementation of the transport or distribution of gas within 5 working days

from the day when the customer has fulfilled technical conditions of connection and when

customer or vendor combined services requested by the transmission

or distribution system to transport or distribution of gas to the

the sampling space. ".



18. in section 10, paragraph 1. 2 the words "gas under a special legal

prescription ^ 2) "including footnote 2 shall be deleted.



19. in section 10, paragraph 1. 2, § 11 (1) 1, § 13 para. 1 (b). (b)) and § 15 para. 1

the word "ultimate" is deleted.



20. In paragraph 11 (1) 1, § 12 para. 1, and article 15, paragraph 2. 1 the words "7

Calendar "is replaced by" 5 working ".



21. in section 11 (1) 1, the words ", including the costs associated with interruption and

by restoring the transportation or distribution, "and the words", including the cost of

associated with the interruption and restoration of transport or distribution of gas "

shall be deleted.



22. in paragraph 11 (1) 1, the words "with the final" shall be replaced by "shall".



23. in paragraph 11 (1) 1 the words "pass-through, or ' shall be deleted.



24. In article 12, paragraph 2 shall be deleted and shall be deleted at the same time, paragraph

1.



25. In § 13 para. 1 (b). (b)), the words "pass-through, or ' shall be deleted.



26. in § 13 para. 1 at the end of subparagraph (b)) § 14 para. 1 at the end of

(a)) and § 16 para. 1 at the end of subparagraph (a)), the word "and" shall be replaced

the word "or".



27. in § 13 para. 1 (b). (b)), the number "80" is replaced by "90".



28. in § 14 para. 1 (b). (b)) after the word "system", the words "or

stack gas ".



29. in article 15, paragraph 2. 1, the words ", including the costs associated with interruption and

Restore supplies, "and the words", including the costs associated with interruption and

restoring gas supplies "are deleted.



30. in article 15, paragraph 2. 1, after the words "supplier", the words "or with the

supplier of pooled services. "



31. in article 16, paragraph 1, the following paragraph 2 is added:



"(2) if the reason for the billed gas supplies in your Bill

transmission, distribution or storage of gas and the supplier or vendor

pooled service within the time limit referred to in paragraph 1 (b). and he/she is the expense report)

transmission, distribution or storage of the gas referred to in § 2, the time limits referred to in

paragraph 1, for the processing of complaints under section 14 is not running. ".



The former paragraph 2 becomes paragraph 3.



32. the annex to the Ordinance reads as follows:



"The annex to Decree No 545/2006 Sb.



PATTERN



A summary statement of compliance with the standards for the year...........

----------------------------------------------------------------------------------------------

The Number Of The Number Of Paid Average

section Standard cases of refund


standard paid a total in thous. CZK

refunds in thous. CZK

----------------------------------------------------------------------------------------------

4 recovery of transport or distribution of

gas, after the malfunctioning

----------------------------------------------------------------------------------------------

6 deadline for the settlement of the complaint on the quality of

gas

----------------------------------------------------------------------------------------------

7 deadline for the removal of the causes of reduced

gas quality

----------------------------------------------------------------------------------------------

8 compliance with the planned restrictions or

interruption of the transport or distribution of

----------------------------------------------------------------------------------------------

9 deadline for examining the application for connection

the device of the applicant to transport or

distribution system

----------------------------------------------------------------------------------------------

10 allow the transport or distribution of gas

----------------------------------------------------------------------------------------------

11 the transport or distribution of gas recovery

After a break in the carriage or distribution

because of the delay of the customer or

the vendor associated with the payment service

payment for the carriage or

distribution of gas

----------------------------------------------------------------------------------------------

13 deadline for settlement of the complaint measurement

supply of gas

----------------------------------------------------------------------------------------------

14 deadline for settlement of the complaint, the expense report

transmission, distribution or storage of

gas

----------------------------------------------------------------------------------------------

15 restoration of gas supplies after the break

because of the customer's delay in payment

payments for the removed gas

----------------------------------------------------------------------------------------------

16 deadline for the settlement of the complaint, the expense report

claim gas supply

----------------------------------------------------------------------------------------------

Total:

----------------------------------------------------------------------------------------------



Article. (II)



The effectiveness of the



This Decree shall enter into force on 1 January 2000. January 2012.



Chair:



Ing. Vaghela in r.