476/2012 Sb.
DECREE
of 19 December 2003. December 2012,
amending Decree No. 82/2011 Coll., on the measurement of electricity and how to
the determination of damages against unauthorized collection, the unauthorized van,
unauthorized transmission or unauthorized distribution of electricity
The Ministry of industry and trade shall be determined according to section 98, para. 1 (b). and)
Act No. 458/2000 Coll., on conditions for business and public administration
in the energy sectors and on amendments to certain acts (the energy
Act), as amended by Act No. 158/2009 Coll. and Act No. 165/2012 Coll.:
Article. (I)
Decree 82/2011 Coll., oměření of electricity and how to establish
damages against unauthorized collection, the unauthorized van,
unauthorized transmission or unauthorized distribution of electricity, is amended
as follows:
1. in article 1, paragraph 2 reads as follows:
"(2) for the measurement of electricity and the evaluation of the data is used
and measurement of the type A,) which is a continuous measurement with remote transmission of the day
data, and continuous recording of medium power values for measuring interval
measuring equipment, directly or
(b) type B) measurement, which is continuous measurement with remote other than
the daily transfer of information, and continuous recording of medium power values for
the measuring interval is conducted directly by the measuring equipment; If it is not possible
to make the remote transmission of data due to technical reasons, it is possible to transfer
perform data in any other way, or
c) measurement type, which is the measurement with remote data transfer
It is not the measurement type, and even the measurement of type B; If it is not possible to make
remote transmission of data due to technical reasons, it is possible to transfer data
do this in a different way, or
d) measurement of type C, which is the other measurement. ".
2. In article 1 (1). 3 (b). (b)), the words "for voltages above 1 kV" shall be replaced by
"where appropriate".
3. In article 2 (2). 1 letter e) is added:
"e) forward places generating stations with electricity voltage higher than 1 kV
directly connected to the transmission system or distribution system, ".
4. In article 2 (2). 2 (b)):
"(b) the transfer of electricity generating stations locations) with the voltage up to 1 kV direct
connected to a distribution system, ".
5. In paragraph 2, at the end of paragraph 2, the period is replaced by a comma and the following
the letter g) is added:
"(g)) of electricity or food for each of the sources of electricity
the production plants of electricity connected to the transmission system or distribution
system through other production plants of electricity. ".
6. in article 2 paragraph 4 is added:
"(4) the measurement type, with electricity can be measured in sampling locations
customers with the procurement of electricity from the grid voltage to 1
kV. ".
7. In article 2 (2). 5, the words "paragraph 7" is replaced by "paragraph 6" and in the
(a). a), the words "and in forward locations of electricity producers" shall be deleted.
8. In section 2, paragraphs 6 and 8 are deleted.
The present paragraph 7 shall become paragraph 6.
9. In paragraph 2, the following paragraph 7 is added:
"(7) For the application of the support of electricity from renewable energy sources
or from secondary energy sources in the form of the annual green bonus
provided by the manufacturer of electricity for the plant's electricity with installed power
up to 5 kW, including separate measurement of electricity produced at least by measuring
type C in the case of the application of the per-hour green bonus ensures
electricity metering the electricity produced by the measurement type (B). ".
10. In section 6 (1). 1 the second sentence, after the words "places"
the words "or transfer points".
11. In paragraph 6 (1). the third sentence is added: "For the reconstruction, for these purposes,
considers the exchange of elektroměrového Cabinet or feed
leadership. ".
12. in section 6 paragraph 5 is added:
"(5) on application by the manufacturer or the customer, and if it
measurement allows the transmission system operator shall provide or
the distribution system operator electricity producer or customer
Pulse outputs from the 24-hour measurement directly in the delivery location or in the
point of use. Provision of measured values by the operator
distribution system using other communication interfaces of the meter
It is not electricity producers, or to a customer without the consent of the operator
the transmission system operator or distribution system operator allowed to. ".
13. In paragraph 6, the following paragraph 6 is added:
"(6) in the delivery of electricity production site with a voltage up to 1 kV connected to
the distribution system with the newly installed or the changing of the measurement
devices evaluated the flow direction of electricity in individual stages. ".
14. in paragraph 10, the word "Annex" is replaced by "annex 1".
15. in paragraph 10, the following new paragraph 10a to 10 c, which including the following title:
"The extent and timing of the transmission of data to the market operator
section 10a
The transmission system operator, and transmission system operator
distribution system operators shall transmit to the market operator for the
processing and registration information on our sites, electricity, for which the
a future contract on the connection, or the connection agreement
and set your dates and conditions for the connection
and to issue State) authorizing the construction of production plants
the electricity Ministry and
(b)) message processing on future expected consumption of electricity and gas and
How to secure a balance between the supply and demand of electricity and
gas.
section 10b
(1) the operator of a transmission system operator or distribution
the system passes the market operator
and data on the production of electricity) to the extent provided for in annex 2 to this
the decree and the
(b) data on the makers of electricity) to be out of the market operator
evidence to be discarded.
(2) the operator of a transmission system operator or natural gas
distribution system passes the information about production and the market operator electricity
to the extent referred to in annex 3 to this Decree, if electricity production
will be connected to the gas network.
section 10 c
(2) the transmission system operator, and transmission system operator
distribution system operators shall update the data referred to in annex No.
2 and annex No. 3 to this Decree to the last day in the quarter
and forward is the market operator by the 15th. day of the following month. ".
16. The existing annex shall become Annex No 1 to this Decree and
the following new annex No 2 and 3 are added:
"Annex 2 to the Decree No 82/2011 Sb.
Data on the production of electricity transmitted to the transmission system operator
or provozovatelemelektroenergetické distribution system
Part A-information about the production of electricity
(1) the identification of the production plants of electricity
and the name of the production plants of electricity)
(b) the production of electricity) identification number
(2) data on transmission system operators or the operators of the
the distribution system
and) identification of the transmission system operator or service provider.
the distribution system
(b)) in the database Identification číslovýrobny electricity operator
System
(c)) number of the network to which the connection of electricity production is expected
(3) for more information about the production of electricity
and the performance of electricity production) booked
b) Fuel
(c)) number, in which the cadastral territory assumes realization
production of electricity
d) Numbers of the parcels on which the implementation of electricity production
e) information about the switching station transmission system or distribution system, to
that assumes the upbringing of the electricity production performance
f) in the case of photovoltaic power stations for the production location information
roof construction or on open space
g) sampling and pass-through space EAN
(4) the anticipated dates in the preparation and implementation of electricity production
the date of signature of the Treaty) on future contract about connection
(b) the date of signature of the Treaty) of the connection
(c)), the term first parallel connection to the electricity grid
(d) the planned closure Date), if known
e) Dates of interruption and recovery operation, if known
(f)) in stations with an installed output of 30 kW release date of territorial
planning information on the conditions of issue of zoning and planning decision
g) in stations with installed power of 0.5 MW
1. The term opinion to EIA
2. the term of the grant of a State authorization for the construction of electricity production
3. The term of issue of zoning and planning decision
4. The term of issue of the integrated permit
5. term of building permit
6. Start of construction
7. Start trial operation
8. term of issue of the certificate of occupancy
Part B-information about the investor electricity production
(1) personally identifiable information
and investor Type)-a natural person or a natural person-non-entrepreneur
doing business or legal person
(b)) identification number in case that is a natural person
doing business or legal entity
(c)) date of birth in case that is a natural person
(d)) business firmav the case that this is a legal person
e) name and surname in the case that is a natural person
nonentrepreneurial natural person-entrepreneur
(f)) statutory authority in the case that this is a legal person
(2) the registered office or the address of the place of stay
and)
(b)) the municipality
(c)) Street
(d) the number and number) of the Guide
e) ZIP CODE
(3) the address for service
and Municipality)
(b)) Street
(c) the number and number) of the Guide
d) postal code
e) Email
f) phone
g) data mailbox
Part C-information about the network construction sites related with the connection factory
electricity to the electricity grid
(1) information about the construction
and network building identification)
(b)) name of the network construction
(c) a description of the network building)
(2) Implied terms in the preparation and implementation of network structures
and release) the term spatial planning information on the conditions of release
zoning and planning decision
(b)) the term opinion to EIA
(c)), the term release planning
(d) the building permit)
e) start of construction
(f)), the term connection of electricity production for test operation
g) start trial operation
h) Release Date of occupancy
Annex No. 3 to Decree No. 82/2011 Coll.
Data on the production of electricity transmitted to the transmission system operator
or operator of the gas distribution system
Part A-information about the production of electricity
(1) details of the transmission system operator or operators
distribution system and gas consumption data
and) identification of the transmission system operator or service provider.
the distribution system
(b) the production of electricity) identification number in the database operator
the transmission system operator or distribution system operator
(c)) the number of the network to which the connection of electricity production is expected
(d)) the planned natural gas consumption
(2) terms in the preparation and implementation of electricity production
the date of signature of the Treaty) on future contract for connection to natural gas
System
(b) the date of signature of the Treaty) be connected to the gas system
c) expected date of connection to the gas network
Part B-information about the network construction sites related with the connection factory
electricity to the gas network
(1) information about the construction
and network building identification)
(b)) name of the network construction
(c) a description of the network building)
(2) Implied terms in the preparation and implementation of network structures
and release) the term spatial planning information on the conditions of release
zoning and planning decision
(b) the grant of a State) the term authorization of selected gas devices
(c)) the term opinion to EIA
(d)), the term release planning
(e) the building permit)
(f)) start of construction
(g)), the term connection of electricity production for test operation
h) start trial operation
I) Release Date of occupancy ".
Article. (II)
Transitional provision
(1) a producer of electricity, the electricity production was put into operation
until 31 December 2006. December 2012, the making of the electricity measurement of electricity in accordance with
§ 2 (2). 2 (a). g) until 31 December 2006. March 2013.
(2) the transmission system operator and distribution system operators
system operators in the electricity sector for the first time the market operator shall send the data referred to in
section 10b, para. 1 on the status as at 31 December. December 2012 at the latest by 15. January 1, 2013.
(3) the transmission system operator and distribution system operators
systems in the gas industry for the first time the market operator shall transmit the information referred to in section
10B, para. 2 on the status as at 31 December. December 2012 at the latest by 15. January 1, 2013.
Article. (III)
The effectiveness of the
This Decree shall enter into force on 1 January 2000. January 1, 2013.
Minister:
Mudr. Cuba in r.