81/2010 Sb.
The DECREE
of 23 December 2003. March 2010,
amending Decree No 51/2006 Coll., on conditions for the connection to the
the electricity grid
The Energy Regulatory Office shall determine under section 98a of paragraph 1. 2 (a). g) of the Act
No. 458/2000 Coll., on conditions for business and the public administration in
energy sectors and on the amendment of certain laws (Energy Act),
as amended by law No 158/2009, code:
Article. (I)
Amendment to Decree No 51/2006 Coll., on conditions for connection to the power
System
Decree No 51/2006 Coll., on conditions for connection to the power
system, shall be amended as follows:
1. the heading of section 1, including:
"section 1
The subject of the edit
This Decree lays down the conditions for production of electricity,
distribution systems and offtake points customers to the electricity
system and method for determining the share of the costs associated with the connection and the
by ensuring the desired wattage. ".
2. In section 2 (a). and the comma, point 1), after the word "involvement" is deleted.
3. In section 2 (a). and (2)) for the word "sampling", the words "instead of
or a pass-through ".
4. In section 2 (b)):
"(b)) reserved performance
1. the value of the additional power production plants of electricity in the delivery place
the transmission system in the MW in the basic involvement reduced by value custom
electricity consumption in the production of electricity or for the electricity and
heat,
2. the value of the additional power production plants of electricity in the delivery place
the distribution system in kW, less the value of own consumption of electricity
for the production of electricity, or
3. the value of the power (in MW) negotiated with the transmission system operator for
pass-through space distribution system or with the operator negotiated
the distribution system for the transmission, distribution system, instead of the other. "
5. In article 2, points (c)) and (e)) including footnote 1 shall be deleted.
Existing subparagraph (d)) shall become point (c)) and the letters f) and (g))
renumbered as subparagraph (d)), and (e)).
6. In section 2 (a). (d)) for the word "sampling" is inserted after the word "electric".
7. In section 2 (a). e), the words "or other production plants of electricity ' shall be deleted.
8. sections 3 and 4, including headings and footnotes 1 and 2:
"section 3
The conditions of the device connection to the transmission system or the applicant
distribution system
(1) the conditions of connection device to the transmission system or the applicant
distribution system are
and request a connection),
(b) presentation of a study for the connectivity) conditions pursuant to Section 4a,
(c)) the conclusion of the Treaty on the connection between the applicant and the operator
the transmission system operator or distribution system operator or change the
existing connection agreements ^ 1).
(2) the applicant shall only request for the conclusion of a Treaty on the connection or
change the existing connection agreements, if there is no change in the
technical conditions of connection when
and a change of the holder) operating equipment without interruption
the production plants of electricity connection to the transmission system or distribution
system, or
(b) replace or modify the Bootmaker) electricity, when there is no crossing
existing negotiated the amount of the reserved performance while maintaining the standard
the conditions of the transmission or distribution of electricity.
(3) when the first change of electricity supplier in the conclusion of the Treaty on
connection progresses according to the electricity market rules ^ 2), which
lay down the terms and procedure for change of the supplier of electricity.
(4) the payment of the share of the costs associated with connecting and securing
the required input or output (hereinafter referred to as "qualifying share
the cost ") shall not apply in the cases referred to in paragraph 2 or 3, or
If the market share of the eligible costs already paid another natural or
a legal person. This does not apply, if the elapse of the time booking power
According to § 7 (2). 7 to 9.
(5) where the applicant for connection, which is the simultaneous holder of licenses
on the distribution of electricity and the production of electricity, it is considered that the requesting
connect distribution system, if the technical documentation
It proves that the simplest device has the character of the production plants of electricity.
If the device is a participant of the electricity market, which is the parallel
holds the licences for the distribution of electricity and the production of electricity, already
connected to the transmission system or distribution system, it is considered that,
that is connected to the distribution system, if the technical documentation
It proves that the connected device has the character of the production plants of electricity.
(6) Manufacture of electricity is also possible to connect in the sampling site. About
the production plants of electricity connections in the sampling site asks a customer. When
connecting the production plants of electricity into a pass-through space other production plants
electricity, as in the case of connection of electricity production plants in
the sampling location.
(7) where the connection to the transmission system or distribution system
an applicant who is licensed to distribute electricity or
the license for the production of electricity, is reserved for the submission site
booked double power performance.
§ 4
The application for the device connection to the transmission system or distribution
System
(1) the request shall be filed for each sampling or pass-through space separately.
The application for the device connection to the transmission system or the applicant
distribution system serving
and before the construction or connection) new equipment,
(b)) before the increase reserved power or performance of an existing
the connected device,
(c)) before the change the nature of the sampling according to annex No. 7 of this Decree,
(d) in the case of changes), the production plants of electricity,
(e) in the case of a change of destination) connection to the production plants of electricity transmission
system or distribution system.
(2) the requirements for an application for connection electricity production plants or part thereof to the
the transmission system or distribution system are listed in the annex.
1 to this notice.
(3) a part of the production plants of electricity connection request the consent of the owner of the
real estate with the placement of production plants of electricity on his property and in
the case of the production plants of electricity with an installed power
and from 30 kW) to 5 MW, including the planning information on the conditions
the issue of land-use decisions, from which it is clear that the construction of production plants
electricity in accordance with territorial planning documentation
(b)) over 5MWpřipojované to the distribution system and production plants of electricity
to connect to the transmission system planning information
conditions of release planning,
c) above 0.5 MW schedule for preparation of the construction of a plant producing electricity.
(4) the timetable for the preparation of the construction of a plant producing electricity contains a list of
the decision, of the opinions and comments of the public authorities and
the dates of their issue, in particular as regards the conclusions of the
the discovery of the procedure for the assessment of effects on the environment, the location of the
the construction of the integrated permit, authorisation, construction and occupancy,
which are necessary for the realization of the construction of a plant producing electricity.
(5) the requirements for an application for the device connection to the distribution system,
the transmission system or distribution system are listed in the annex.
2 to this Decree.
(6) the requirements for an application for connection to the electrical equipment of the sampling
the transmission system or distribution system from voltage levels especially
high voltage, high voltage and high voltage are listed in the
Annex No. 3 to this notice.
(7) the requirements for an application for connection to the electrical equipment of the sampling
the distribution system of low-voltage voltage levels are listed in
Annex No 4 to this notice.
1) § 50 paragraph. 3 the Energy Act.
2) Decree No. 541/2005 Coll., on the electricity market rules, the principles of
pricing for electricity market operator's activities and the implementation of
some of the other provisions of the Energy Act, as amended
regulations. ".
9. in section 4, the following new Section 4a, which including the title:
' Section 4a
A study of connectivity
(1) the operator of a transmission system operator or distribution
system may request from the applicant processing study of connectivity,
and) if having regard to all the circumstances of the obvious, that the equipment to which the
the connection applicant, will have an impact on the reliability of the transmission
system operator or distribution system operator, or
(b)) asks if the device connection to the high voltage and voltage level
higher.
(2) if the applicant Asks about the connection to the distribution system, the transmission
system or to increase the power or the performance of the booked in delivery
place between distribution and transmission system, processing
study together connectivity, the transmission system operator and
the distribution system operator.
(3) the subject of a study of the production plants of electricity or connectivity, sampling
electrical equipment is the assessment of the expected environmental effects of the device connection
the reliable operation of the Czech transmission system or distribution system.
Subject of studies the distribution system to the transmission connectivity
system or distribution system to the distribution system is hereinafter
the assessment of the possible variations of the desired connection in terms of their
costs.
(4) the operator of a transmission system operator or distribution
the system may require the processing of study connectivity within 30 days from the
applying for the connection. At the same time must define the scope of the
a study of connectivity.
(5) if the applicant so requests, the transmission system operator or
distribution system operator of the supporting documents for the processing of study
connectivity, not later than 30 days after receipt of the application for
processing, the transmission system operator or the operator
the distribution system will provide the applicant with the supporting documents necessary for processing
a study of connectivity within 15 days of their request. Thereafter, if
the applicant a transmission system operator or distribution
system of documentation for processing study of connectivity, within 30 days after the
receipt of the application for processing, the transmission system operator
or the distribution system operator request is examined.
(6) unless otherwise requested by a transmission system operator or the operator
study of the processing distribution system connectivity, within the time limit referred to in
paragraph 4, or if the applicant does not provide the documentation required for processing
a study of connectivity, it is considered that processing studies
connectivity is not required.
(7) an applicant for the device connection to the distribution system shall transmit to the
the distribution system operator study, connectivity, within 90 days from the
the date when the distribution system operator shall forward the documents to the applicant
necessary for the processing of the study. If the applicant asks about the connection of the device to the
the transmission system, transmission system operators shall transmit to the applicant
study on connectivity to 180 days from the date when the operator of a transmission
the system forward to the applicant documents necessary for processing the studies, if
the applicant, with the transmission system operator concerned agree otherwise.
(8) if it is not processed in the range of connectivity, the study defined
transmission system operator or distribution
system, the transmission system operator or the operator
distribution system to request its addition or extension. The operator
the transmission system operator or distribution system operator may request
addition or extension studies connectivity, not later than 30 days from the
transmission study of connectivity.
(9) if the transmission system operator of the tween, or extension
the study, together with the applicant passes the connectivity or advanced study
connectivity within 90 days of the date on which it received the request of the operator
the transmission system operator, unless agreed otherwise. For the processing and transfer of
the new study, connectivity, paragraph 7 shall apply mutatis mutandis.
(10) if the distribution system operator shall supplement or
the extension of the study, the applicant supplemented by connectivity, transmit or
an extended study of the connectivity within 30 days of the date on which it received the
request a distribution system operator. For the processing and transfer of
the new study, connectivity, paragraph 7 shall apply mutatis mutandis. ";"
10. section 5, including the title and a footnote 3 is added:
"§ 5
The assessment of the applications for connection to the transmission system or device
distribution system
(1) the operator of a transmission system operator or distribution
the system assesses the application for the connection of the device with regard to the
and the place and the way required) connection,
(b) to the desired size of the reserved power) or the performance of, and the time
the progress of the load,
(c) the reliability of electricity supply)
(d) the nature of the reaction device) of the applicant on the transmission or
distribution system,
(e) the planned development system)
(f)) and the order of the lodgment of applications
g) limits the performance of the electricity system trimmer set
the transmission system operator.
(2) if it is necessary for a proper examination of the application, it shall invite the
the transmission system operator or distribution system operator
the applicant no later than within 15 days from the date of receipt of the application for the supplement
of the data provided to the extent needed and shall lay down to ensure adequate
the time limit. At the same time notify the applicant, in the case of nedoplnění data in
to the extent required by the deadline will not be considered in the application.
(3) if the applicant has been invited to supplement the information provided in accordance with paragraph
2 the applicant not having done so, the transmission system operator or
the distribution system operator request is examined. This fact
shall inform the applicant without undue delay.
(4) if they are not given the reasons set out by the law, for which energy
the applicant cannot be a device to the transmission system or distribution system
connect to ^ 3), the distribution system operator shall provide to the applicant within 30
days, or in the case of devices connecting to voltage levels high
or very high voltage within 60 days of the submission of a complete application for
connection or from the date of transmission of the study, if connectivity
processing study of connectivity required design connection agreements
or a proposal for a Treaty on the future of the connection. In the case of devices
to attach to the transmission system, the time limit for the submission of the proposal
connection agreements or contracts for the future to connect for 90 days
from the submission of a complete application for connection or from the date of transmission of the study
connectivity, if the processing of a study requested by connectivity.
The transmission system operator or distribution system operator
determined in the draft Treaty on the future of the connection or the Treaty on
the connection time limit for the adoption of the draft Treaty of 30 days, if it is
the device connects to the voltage low voltage level, or 60 days,
If this is about the connection of the device to the surface voltage of high voltage
or higher.
(5) If you cannot connect to the device of the applicant for the reasons set out
energy law ^ 3), the transmission system operator or
the distribution system operator shall notify this fact to the
to the applicant within 30 days from the submission of a complete application for connection or from the date of
transmission study of connectivity if it has been processing studies
connectivity, you requested. The transmission system operator or
distribution system operator shall also specify the particular reasons for the
You cannot connect to the device of the applicant. However, if the device can be
applicant attach under different conditions and the content of the application or of the
the circumstances in which the application was made, it can be assumed that the applicant
such connections will have an interest in, the transmission system operator
or distribution system operator in writing of such fact
shall notify the applicant, including the reasons for which cannot be under the required device
conditions to join, and submit the draft contract to the applicant in accordance with paragraph 4.
(6) the Treaty of the Treaty to the future of the connection is closed normally,
If the applicant requires the connection of the device construction technical measures
in the transmission system or distribution system, whose implementation
requires a decision on the location of the building or the territorial agreement referred to in
the building Act.
(7) if the examination of the application on the connection necessary to measure
or network with a voltage of 110 kV network operation verification, the term
referred to in paragraph 4 or 5 of the time required for measurement or verification operation
the network, a maximum of 30 days. On the necessity of implementation of measurement or verification
network operation and the extension shall inform the operator of a transmission
system operator or distribution system operator the applicant not later than
15 days from the date of receipt of the request for a connection.
(8) the operator of a transmission system operator or distribution
the system suggests the connection of the device, so that the technical implementation
connection of the device was based on the planned development of the system during the
considering the interest of the applicant to minimize the costs of
the device connects to the transmission system or distribution system.
(9) the transmission system operator, or the operator of a distribution
the system reserves the the applicant desired power or power from the moment
submission of the draft of the Treaty referred to in paragraph 4.
(10) if the applicant does not accept the proposal of the contract within 30 days for a connection to the
voltage low voltage level, or up to 60 days for the connection to the voltage
the surface of the high voltage and higher performance or booking, reservation
input ceases to exist.
section 24, paragraph 3). 10 (a). and § 25 paragraph). 11 (a). and) energy
of the law. ".
11. In section 6 paragraph 1 including the footnote No. 4:
"(1) Short-term connection means the connection of the provisional devices
According to Czech technical standards ^ 4) to a distribution system for a specified period.
ČSN 33 2000-4)-1. ".
12. In section 6 (1). 3, the words "the issue of requests for opinions" be deleted and the
the words "the provisions of section 5" shall be replaced by the words "§ 4 to 5 and section 7".
13. In section 6 (1). 4, the last sentence shall be replaced by the phrase "Share on
eligible costs under section 10 (a). ".
14. In section 6 paragraph 5 is added:
"(5) after the completion of connection agreements lapse booked input; section 7 of the
paragraph. 7 to 9 shall not apply. ".
15. In section 6, the following paragraph 6 is added:
"(6) If a due to the realization of the short connections to distribution
the need to increase system reserved power in forward locations
between the distribution system, in which to implement the short-term connection
occurred, and a distribution system, proceed in accordance with paragraph 4. ".
16. the title of section 7 including:
"section 7 of the
The device connects to the transmission system or distribution
System
(1) connect the device to the transmission system or distribution
the system is implemented on the basis of the Treaty.
(2) the Treaty concerning the connection of one applicant can include multiple sampling
or transfer jobs, if each of them separately in the contract
stated.
(3) the applicant shall be borne by the advance on the share of the eligible costs referred to in
Annex No 6 to this Decree, in the amount of 50% of the value of the share on the
eligible costs, but not more than 50 0000 0000 Czk. The applicant shall pay
the advance on the market share of the eligible costs within 15 days from the date of the conclusion of the
connection agreements or contracts for the future.
(4) if the applicant does not pay the advance on the share of the eligible costs referred to in
paragraph 3 or in additional reasonable period of time provided by the operator
the transmission system operator or distribution system operator and
the transmission system operator or distribution system operator
for this reason, terminate the contract or a contract on connection contract
the future of connectivity, or reservation booking performance input termination
the contractual relationship ceases to exist.
(5) if the connection does not require the applicant's implementation of construction equipment
technical measures in the transmission system or distribution system,
out the transmission system operator, or the operator of a distribution
system and the applicant, the term connection of electricity production plants using
solar radiation to electricity plant was connected by
180 days from the date of conclusion of the contract about connection, in the case of production plants
electricity using solar radiation with installed power of 30 kW
up to 1 year from the date of conclusion of the contract about connection.
(6) if the applicant within the time limits referred to in paragraph 5 shows that despite all the
the efforts made not in connection to the implementation of the agreed deadlines
the production plants of electricity, for reasons that have occurred or are there regardless of the
his will, the transmission system operator or the operator
distribution system operators shall negotiate with the applicant an extension of the deadline for the connection
as long as necessary.
(7) if the agreed reduction of the value of the main circuit breaker before the measurement
device to a value lower than the reserved power of the place
connection device for longer than 24 months,
the value of the reserved power to this value.
(8) If, after the period of 60 months from the date of the last change of the reserved
input not to the negotiation of reserved capacity of at least 90% of the
reserved input, the value of the reserved power is reduced to
value, which is determined by the maximum agreed size reserved
capacity in the period of 60 months from the last changes of the reserved power.
(9) in the case of termination of the contract for the transmission or distribution of electricity takes
booked for existing connection site for a period of 60 months from the
the date of termination of the contract. If the contract for the transmission or distribution of
electricity has not been concluded within 60 months from the date of the agreed connection
in the Treaty, the reservation for place of consumption or for the
place connection. ".
17. section 8 including title:
"section 8
The costs associated with connecting the device to the transmission system or the
distribution system and by ensuring the desired wattage or performance
(1) If an applicant under this Ordinance shall bear the costs associated with
and ensuring the desired wattage or the performance in full
the amount of the costs can be borne by the applicant to include only the costs referred to in
paragraphs 2 to 4.
(2) the costs associated with the connection and to ensuring the desired wattage
or include essential performance incurred eligible costs
related to the acquisition, construction or modification of transmission system
or distribution system, which were raised in the applicant's request
connection with the place and the way to connect his equipment. The acquisition,
construction or modifications to the transmission system operator or distribution system operator are
provided in the extent strictly necessary to the corresponding value input
or the performance of, the desired by the applicant, and the place and how to connect his
the device.
(3) The costs associated with the connection and to ensuring the desired
the wattage or performance will include the cost of the acquisition project
geodetic documentation, focus, easements and other immediately
the related investment costs and fees for the construction, modification or
the acquisition of the transmission system operator or distribution system operator.
(4) The costs associated with the connection and to ensuring the desired
the wattage or performance do not include costs associated with the acquisition,
the construction or modification of transmission system or distribution system,
that exceed the scope strictly necessary corresponding to the value
input or output, requested by the applicant, and the place and the way
the connection of the device.
(5) the construction and adjustment of the transmission system operator is defined from the point of connection
the device of the applicant to the nearest place in the transmission system, where is
or would poprovedení the necessary adjustments in the system was available
the power or the performance of the booked.
(6) construction and adjustment of the distribution system is defined from the point of
connect the device to the nearest location in the distribution system
to the same voltage level, where it is, or would after the execution of the necessary
adjustments in the system was available the booked or power
performance. ".
18. section 9, including the title.
19. section 10 including title:
"§ 10
Market share of the applicant for connection to the transmission system or device
distribution system on legitimate costs
(1) the applicant's share of the eligible costs shall be calculated as the product of
measuring the proportion referred to in annex 6 to this Decree and by the applicant
the required power or the performance of the booked.
(2) in the case of connecting production plants of electricity to the transmission system or the
the distribution system shall be borne by the pin connection to the places the applicant in
full.
(3) if the performance of the parallel input and checked out one applicant in one
a place to connect, the share of the eligible costs, especially for
reservation and booking of performance power. The applicant pays the higher of the two
set out the eligible shares the costs. ".
20. in article 10 the following new section 10a, including title:
"§ 10a
Reconnect the device to the transmission system or distribution
System
Connects to the transmission system operator or the operator
the sampling distribution system, the electrical equipment of the customer
was limited or interrupted the supply of electricity due to unauthorized
collection, transmission or distribution of electricity, shall be borne by the customer market share
of eligible costs in the amount of
1 500 Czk) when connecting to a voltage level low voltage,
(b)) 3 500 Czk in connection to the high voltage or voltage level
higher. ".
21. section 11 including the title:
"section 11
The specific requirements of the applicant for the device connection to the transmission system
or distribution system
(1) if the applicant Requests a connection beyond standard connection
the device or if a specific method of construction or technical
implementation of the device connection to the transmission system or distribution
the system shall be borne by the applicant justified the costs associated with the implementation of
above-standard connection or a specific building or technical
make connections in full.
(2) booked on the surface of low-voltage power can be transferred in the
one or more adjacent real estate property, only if the
It's technically possible and realization of transfer of a reserved power does not raise the
additional costs related to the acquisition, construction or modifications
the distribution system. Similarly, when the transfer of the reserved
power on the surface of a high or very high voltage in one
the nodal region of the appropriate voltage levels.
(3) if the applicant Asks about the connection of the device to a different voltage level than the
to which the device is connected, and the required change of the connection is not
enforced by changing the technical conditions of connection shall be borne by the applicant costs
on the legitimate costs associated with this amendment in full. In such a
If the amount of the original booked the wattage or performance shall stipulate
share of the eligible costs under section 10. The provisions of section 7 (1). 7 to 9
shall not be used. ".
22. In the heading of section 12, the word "households" is deleted.
23. In section 12, the following paragraph 3, including footnote 5.
added:
"(3) for the assessment of whether there is an electrical connection in a built-up
or outside the built-up territory pursuant to the building Act ^ 5), it is critical
the location of the link property.
5) § 2 (2). 1 (a). (d)), the building Act. ".
24. Annexes 1 to 6 are added:
"The annex No. 1 to Decree No 51/2006 Sb.
REQUEST FOR CONNECTION TO THE TRANSMISSION OR PRODUCTION PLANTS OF ELECTRICITY
DISTRIBUTION SYSTEM
Part And
-information on the applicant
1. Business name (applicant-registered in the commercial entrepreneur
the register).
2. the data on the registration in the commercial register, including the file tags
(to be completed by the applicant-entrepreneur registered in the commercial register).
3. The name or the name and surname of the applicant (unregistered in business
the register).
4. Date of birth (to be completed by the applicant-natural person).
5. Registered Office: the State, the County, municipality, with POSTAL CODE, street and house number,
where applicable, the registration number (to be completed by the applicant-legal person).
Place of business in the breakdown: the State, the County, municipality, with POSTAL CODE, street and number
where applicable, the registration number of the descriptive (to be completed by the applicant natural person-
doing business).
6. the name and surname of the person, which is a statutory body, or all of the
persons who are members of the statutory body (to be completed by the applicant-
a legal person).
7. The address of the place of stay in the breakdown: the State, the County, municipality, with POSTAL CODE, street and number
descriptive, or registration number (to be completed by the applicant natural person-
the nonentrepreneurial).
8. connection-phone, e-mail.
9. The address for service.
10. information on the data, if the mailbox has been established.
11. The identification number, if one has been assigned.
12. Tax identification number, if one has been assigned.
Part (B)
-the data on the device
1. The location of the production plants of electricity-region, municipality, cadastral, land
the numbers of the land on which the plant is located, the number of electricity
descriptive, or registration number.
2. the type of electricity production plants.
3. the character of the production of electricity.
4. The term of the connection.
5. basic data on the production of electricity:
5.1. the involvement of the production plants of electricity to the transmission system or distribution
System (insulation level, estimated the site connection,
fit the scheme, territorial connection variants variants of each)
5.2. Description of the production plants of electricity [total installed capacity of the power plant,
achievable performance power, the performance of the individual blocks, electric
scheme of the blocks, block type (coal, water, another paroplynový), a kind of resource
(top, base), the energy produced per year, the rated power factor,
the estimated reliability of the block],
5.3. Description of the block transformer (type, installed power, nominal
the tension, the tension of the short, winding, conversion, a range of branches,
loss of short and loss, short-circuit resistance, etc.)
5.4. Description of the generator (type, installed power the apparent and active,
nominal voltage, the wiring, the type, the switch drivers, dynamic
constants, as are spare, the reactance time constants, constants
of inertia)
5.5. Description of own consumption (total installed power, nominal
voltage, power factor, the starting current).
6. the required reliability of the power outlet.
The applicant declares and confirms the accuracy of his signature and the truth
all of the above data.
"Annex No. 2 to the Decree No 51/2006 Sb.
THE ELEMENTS OF THE REQUEST FOR THE DEVICE CONNECTION TO THE DISTRIBUTION SYSTEM,
A TRANSMISSION OR DISTRIBUTION SYSTEM
Part And
-information on the applicant
1. Business name (applicant-registered in the commercial entrepreneur
the register).
2. the data on the registration in the commercial register, including the file tags
(to be completed by the applicant-entrepreneur registered in the commercial register).
3. The name or the name and surname of the applicant (unregistered in business
the register).
4. Registered Office: the State, in the region, the municipality of zip/postal code, street and house number,
where applicable, the registration number (to be completed by the applicant-legal person).
Place of business in the breakdown: the State, the County, municipality, with POSTAL CODE, street and number
where applicable, the registration number of the descriptive (to be completed by the applicant natural person-
doing business).
5. the name and surname of the person, which is a statutory body, or all of the
persons who are members of the statutory body (to be completed by the applicant-
a legal person).
6. connection-phone, e-mail.
7. The address for service.
8. Information about the data, if the mailbox has been established.
9. Identification number of the
10. Tax identification number
Part (B)
-the data on the device
1. The term connection
2. Basic data for connection to the transmission system or distribution
system:
2.1. submission site,
2.2. the highest voltage level,
2.3. the fit scheme,
2.4. the cadastral map of the territory with the placement of a pass-through space.
3. data collection:
3.1. the requested value of the reserved power and reserved performance,
3.2. the current value of the reserved power and reserved performance,
3.3. nature of sampling,
3.4. the time course load,
3.5. the power factor and the compensation
3.6. the scheduled subscription of energy per year.
4. the requirements on the reliability of supply (maximum period of interruption
delivery).
5. reverse Options affecting the supply network.
The applicant declares and confirms the accuracy of his signature and the truth
all of the above data.
"The annex No. 3 to Decree No 51/2006 Sb.
REQUEST FOR CONNECTION TO THE ELECTRICAL EQUIPMENT OF THE SAMPLING
A TRANSMISSION OR DISTRIBUTION SYSTEM FROM VOLTAGE LEVELS ESPECIALLY HIGH
VOLTAGE, A VERY HIGH VOLTAGE AND HIGH VOLTAGE
Part And
-information on the applicant
1. Business name (applicant-registered in the commercial entrepreneur
the register).
2. the data on the registration in the commercial register, including the file tags
(to be completed by the applicant-entrepreneur registered in the commercial register).
3. The name or the name and surname of the applicant (unregistered in business
the register).
4. Date of birth (to be completed by the applicant-natural person).
5. Registered Office: the State, the County, municipality, with POSTAL CODE, street and house number,
where applicable, the registration number (to be completed by the applicant-legal person).
Place of business in the breakdown: the State, the County, municipality, with POSTAL CODE, street and number
where applicable, the registration number of the descriptive (to be completed by the applicant natural person-
doing business).
6. the name and surname of the person, which is a statutory body, or all of the
persons who are members of the statutory body (to be completed by the applicant-
a legal person).
7. The address of the place of stay in the breakdown: the State, the County, municipality, with POSTAL CODE, street and number
descriptive, or registration number (to be completed by the applicant natural person-
the nonentrepreneurial).
8. connection-phone, e-mail.
9. The address for service.
10. information on the data, if the mailbox was furnished.
11. The identification number, if one has been assigned.
12. Tax identification number, if one has been assigned.
Part (B)
-information on the applicant's equipment
1. The term of the connection.
2. Basic data for the involvement of the applicant's facilities to transmission systems
or distribution system:
2.1. the sampling/pass-through space,
2.2. the highest voltage level of consumption of the electrical equipment,
2.3. the fit scheme,
2.4. the cadastral map of the territory with the location of the sampling points.
3. data collection:
3.1. the requested value of the reserved power,
3.2. the current value of the reserved power,
3.3. nature of sampling,
3.4. the type and subscription of the connected appliances (in particular the number and performance
engines, electric furnaces and heating, electric welding equipment, drives
etc.),
3.5. the time course load,
3.6. the power factor and the compensation
3.7. information about whether the sampling place installed a backup
the source and in the positive case, its parameters and the expected way
operation.
4. the requirements on the reliability of supply (maximum period of interruption
delivery).
5. reverse Options affecting the supply network.
6. information on the production and mounting or already connected to sampling
the device.
The applicant declares and confirms the accuracy of his signature and the truth
all of the above data.
"Annex No 4 to Decree No 51/2006 Sb.
REQUEST FOR CONNECTION TO THE ELECTRICAL EQUIPMENT OF THE SAMPLING
DISTRIBUTION SYSTEM FROM VOLTAGE LEVELS LOW VOLTAGE
Part And
-information on the applicant
1. Business name (applicant-registered in the commercial entrepreneur
the register).
2. the data on the registration in the commercial register, including the file tags
(to be completed by the applicant-entrepreneur registered in the commercial register).
3. The name or the name and surname of the applicant (unregistered in business
the register).
4. Date of birth (to be completed by the applicant-natural person).
5. Registered Office: the State, the County, municipality, with POSTAL CODE, street and house number,
where applicable, the registration number (to be completed by the applicant-legal person).
Place of business in the breakdown: the State, the County, municipality, with POSTAL CODE, street and number
where applicable, the registration number of the descriptive (to be completed by the applicant natural person-
doing business).
6. the name and surname of the person, which is a statutory body, or all of the
persons who are members of the statutory body (to be completed by the applicant-
a legal person).
7. The address of the place of stay in the breakdown: the State, the County, municipality, with POSTAL CODE, street and number
descriptive, or registration number (to be completed by the applicant natural person-
the nonentrepreneurial).
8. connection-phone, e-mail.
9. The address for service.
10. information on the data, if the mailbox has been established.
11. The identification number, if one has been assigned.
12. Tax identification number, if one has been assigned.
Part B-information about the applicant's equipment
1. The term connection
2. Basic data on the involvement of the applicant's equipment in the distribution system:
2.1. the sampling/submission site (e.g. the establishment, rod House, cottage)
2.2. the cadastral map of the territory with the location of the sampling points.
3. data collection:
3.1. the requested value of the reserved power,
3.2. the current value of the reserved power,
3.3. nature of sampling,
3.4. the type and subscription of the connected appliances (connection of individual
appliances with a nominal input of 5 kW and above, in particular the number and performance
engines, electric furnaces and heating, electric welding equipment, drives
etc.),
3.5. information about whether the sampling place installed a backup
the source and in the positive case, its parameters and the expected way
the operation,
4. the requirements on the reliability of supply.
5. reverse Options affecting the supply network.
6. Type and performance of heat pumps.
7. information on the production and mounting or already connected to sampling
the device.
The applicant declares and confirms the accuracy of his signature and the truth
all of the above data.
"Annex No. 5 to Decree No 51/2006 Sb.
REQUIREMENTS FOR AN APPLICATION FOR A SHORT-CONNECT THE DEVICE TO THE DISTRIBUTION
SYSTEM
Part And
-information on the applicant
1. Business name (applicant-registered in the commercial entrepreneur
the register).
2. the data on the registration in the commercial register, including the file tags
(to be completed by the applicant-entrepreneur registered in the commercial register).
3. The name or the name and surname of the applicant (unregistered in business
the register).
4. Date of birth (to be completed by the applicant-natural person).
5. Registered Office: the State, the County, municipality, with POSTAL CODE, street and house number,
where applicable, the registration number (to be completed by the applicant-legal person).
Place of business in the breakdown: the State, the County, municipality, with POSTAL CODE, street and number
where applicable, the registration number of the descriptive (to be completed by the applicant natural person-
doing business).
6. the name and surname of the person, which is a statutory body, or all of the
persons who are members of the statutory body (to be completed by the applicant-
a legal person).
7. The address of the place of stay in the breakdown: the State, the County, municipality, with POSTAL CODE, street and number
descriptive, or registration number (to be completed by the applicant natural person-
the nonentrepreneurial).
8. connection-phone, e-mail.
9. The address for service.
10. information on the data, if the mailbox has been established.
11. The identification number, if one has been assigned.
12. Tax identification number, if one has been assigned.
Part (B)
-information on the applicant's equipment
1. The date and the duration of the connection.
2. Basic data on the involvement of the applicant's equipment in the distribution system.
3. The sampling/submission site.
4. the Location of the sampling of the electrical equipment.
5. Information about the subscription:
5.1. the required size of the reserved value input/main
circuit breakers,
5.2. nature of sampling.
The applicant declares and confirms the accuracy of his signature and the truth
all of the above data.
"Annex No 6 to Decree No 51/2006 Sb.
THE SPECIFIC CONTRIBUTION OF THE APPLICANT FOR CONNECTION TO THE LEGITIMATE COSTS ASSOCIATED WITH
CONNECTION AND SECURING OF THE REQUIRED POWER AND PERFORMANCE
FOR BOOKING INPUT
------------------------------------------------------ -------------------------
Instead the connection to the voltage level of the specific contribution of the applicant connection method
------------------------------------------------------ -------------------------
transmission system 200 USD/MW
HIGH VOLTAGE distribution system and Type 600 USD/MW
HIGH VOLTAGE distribution system Type (B) 150 USD/MW
the distribution system of HV Type and 800 USD/MW
the distribution system of HV Type B1 200 USD/MW
distribution system NN 3 phase connection 500 Kč/A
distribution system NN 1 phase connection of 200 Czk/A
------------------------------------------------------ -------------------------
FOR BOOKING THE PERFORMANCE
------------------------------------------------------ -------------------------
Instead the connection to the voltage level of the specific contribution of the applicant connection method
------------------------------------------------------ -------------------------
the transmission system at the point of connection
According to the opinions of 500 USD/MW
the operator
the transmission system
HIGH VOLTAGE distribution system and Type 1 200 0000 CZK/MW
HIGH VOLTAGE distribution system Type (B) 150 USD/MW
the distribution system of HV type 640 USD/MW
the distribution system of HV type B 150 USD/MW
distribution system NN 3 phase connection 500 Kč/A
distribution system NN 1 phase connection of 200 Czk/A
------------------------------------------------------ -------------------------
Connection Type And
is such a connection, where the distribution system operator shall extend the
the distribution system up to the pickup points.
transformer station or substation of the applicant for connection.
Connection Type (B)
is such a connection that does not meet the conditions for the connection type and.
Connection Type B1
is such a connection when it is not necessary to the construction of the new dungeons and Busbar and
they are only necessary adjustments of a technical nature (e.g. replenishment of armament
the Dungeon)
In the case of a connection request, or an increase of the reserved power
or the performance of the objects already connected is to determine the amount of the share of the
eligible costs the determining existing connection method. ".
25. the following Annex No. 7:
"Appendix No. 7 to Decree No 51/2006 Sb.
CHARACTER COLLECTION
1. the place of consumption of the type "T1"-the place of consumption with electric equipment
standard appliance to 16 and that they have the mark of conformity in the sense of
Act No. 22/1997 Coll.-lighting and electrical appliances to connect to the
divorce, moving supply (wall outlet) or securely attached, with
input any appliances does not exceed 3.5 kVA.
2. The sampling place type "T2"-the place of consumption with electric equipment such as
for the type "T1", where the water is used for heating of the electric power (outside of the
flow heaters).
3. The sampling place type "T3"-the place of consumption with electric equipment such as
for the type "T1" or "T2", where cooking and baking using electric
the appliance of over 3.5 kVA.
4. The sampling place type "T4"-the place of consumption with electric equipment such as
for the type "T1", "T2" or "T3", where the heating (accumulator,
direct heating, heat pump) or air conditioning used electrical
appliances whose consumption is measured for each customer.
5. The sampling place type "T5" – place of consumption with electric equipment such as
for the type "T3" or "T4", which are equipped with additional electrical
the appliance which may affect the operation of the network. ".
Article. (II)
Transitional provisions
1. the period of binding opinions to connection requests issued under the
Decree No. 51/2006 Coll. cannot be extended.
2. Where the applicant, before the date of entry into force of this Decree on the
the conclusion of the contract about connection and the deadline for the conclusion of the contract about connection
has not expired before the date of entry into force of this Decree, the operator
the transmission system shall provide the applicant within 60 days or the operator
distribution system within 30 days of the draft Treaty on the future of
connection, or the connection agreement in accordance with this Decree and
the opinion to the connection requests issued pursuant to Decree No 51/2006 Sb.
3. If the applicant so requests at the time of binding opinions on the applications for connection
the devices after the date of entry into force of this Decree concerning the conclusion of the Treaty on
connection, the transmission system operator shall submit to the applicant within 60 days
or the distribution system operator within 30 days, a draft Treaty on the
future of the connection, or the connection agreement in accordance with
This Decree and the opinion to connection requests issued by
Decree No. 51/2006 Sb.
4. If the extension of the binding opinions on the applications for
connection according to § 5 (3). 5 of the Decree, as amended by the effective to date of the acquisition
the effectiveness of this Decree and extended time binding opinion takes
for the effectiveness of this order, the applicant so requests at the time of binding,
not later than 3 months after the entry into force of this order, the
the conclusion of the Treaty of the Treaty to the future of the connection or the draft Treaty on the
connection in accordance with this Decree. The transmission system operator
the applicant shall submit, within 60 days, or the distribution system operator to
30 days, a draft Treaty on the future of the connection or the draft Treaty on the
connection in accordance with this Decree and the opinion on the application of
According to a decree issued by a connection No 51/2006 Coll. does not ask if the applicant for
the conclusion of the contract in accordance with this provision, booked the wattage or
performance shall lapse.
Article. (III)
The effectiveness of the
This Decree shall take effect on 1 January 2005. April 2010.
Chairman:
Ing. The firt in r.