81/2010 Sb.



The DECREE



of 23 December 2003. March 2010,



amending Decree No 51/2006 Coll., on conditions for the connection to the

the electricity grid



The Energy Regulatory Office shall determine under section 98a of paragraph 1. 2 (a). g) of the Act

No. 458/2000 Coll., on conditions for business and the public administration in

energy sectors and on the amendment of certain laws (Energy Act),

as amended by law No 158/2009, code:



Article. (I)



Amendment to Decree No 51/2006 Coll., on conditions for connection to the power

System



Decree No 51/2006 Coll., on conditions for connection to the power

system, shall be amended as follows:



1. the heading of section 1, including:



"section 1



The subject of the edit



This Decree lays down the conditions for production of electricity,

distribution systems and offtake points customers to the electricity

system and method for determining the share of the costs associated with the connection and the

by ensuring the desired wattage. ".



2. In section 2 (a). and the comma, point 1), after the word "involvement" is deleted.



3. In section 2 (a). and (2)) for the word "sampling", the words "instead of

or a pass-through ".



4. In section 2 (b)):



"(b)) reserved performance



1. the value of the additional power production plants of electricity in the delivery place

the transmission system in the MW in the basic involvement reduced by value custom

electricity consumption in the production of electricity or for the electricity and

heat,



2. the value of the additional power production plants of electricity in the delivery place

the distribution system in kW, less the value of own consumption of electricity

for the production of electricity, or



3. the value of the power (in MW) negotiated with the transmission system operator for

pass-through space distribution system or with the operator negotiated

the distribution system for the transmission, distribution system, instead of the other. "



5. In article 2, points (c)) and (e)) including footnote 1 shall be deleted.



Existing subparagraph (d)) shall become point (c)) and the letters f) and (g))

renumbered as subparagraph (d)), and (e)).



6. In section 2 (a). (d)) for the word "sampling" is inserted after the word "electric".



7. In section 2 (a). e), the words "or other production plants of electricity ' shall be deleted.



8. sections 3 and 4, including headings and footnotes 1 and 2:



"section 3



The conditions of the device connection to the transmission system or the applicant

distribution system



(1) the conditions of connection device to the transmission system or the applicant

distribution system are



and request a connection),



(b) presentation of a study for the connectivity) conditions pursuant to Section 4a,



(c)) the conclusion of the Treaty on the connection between the applicant and the operator

the transmission system operator or distribution system operator or change the

existing connection agreements ^ 1).



(2) the applicant shall only request for the conclusion of a Treaty on the connection or

change the existing connection agreements, if there is no change in the

technical conditions of connection when



and a change of the holder) operating equipment without interruption

the production plants of electricity connection to the transmission system or distribution

system, or



(b) replace or modify the Bootmaker) electricity, when there is no crossing

existing negotiated the amount of the reserved performance while maintaining the standard

the conditions of the transmission or distribution of electricity.



(3) when the first change of electricity supplier in the conclusion of the Treaty on

connection progresses according to the electricity market rules ^ 2), which

lay down the terms and procedure for change of the supplier of electricity.



(4) the payment of the share of the costs associated with connecting and securing

the required input or output (hereinafter referred to as "qualifying share

the cost ") shall not apply in the cases referred to in paragraph 2 or 3, or

If the market share of the eligible costs already paid another natural or

a legal person. This does not apply, if the elapse of the time booking power

According to § 7 (2). 7 to 9.



(5) where the applicant for connection, which is the simultaneous holder of licenses

on the distribution of electricity and the production of electricity, it is considered that the requesting

connect distribution system, if the technical documentation

It proves that the simplest device has the character of the production plants of electricity.

If the device is a participant of the electricity market, which is the parallel

holds the licences for the distribution of electricity and the production of electricity, already

connected to the transmission system or distribution system, it is considered that,

that is connected to the distribution system, if the technical documentation

It proves that the connected device has the character of the production plants of electricity.



(6) Manufacture of electricity is also possible to connect in the sampling site. About

the production plants of electricity connections in the sampling site asks a customer. When

connecting the production plants of electricity into a pass-through space other production plants

electricity, as in the case of connection of electricity production plants in

the sampling location.



(7) where the connection to the transmission system or distribution system

an applicant who is licensed to distribute electricity or

the license for the production of electricity, is reserved for the submission site

booked double power performance.



§ 4



The application for the device connection to the transmission system or distribution

System



(1) the request shall be filed for each sampling or pass-through space separately.

The application for the device connection to the transmission system or the applicant

distribution system serving



and before the construction or connection) new equipment,



(b)) before the increase reserved power or performance of an existing

the connected device,



(c)) before the change the nature of the sampling according to annex No. 7 of this Decree,



(d) in the case of changes), the production plants of electricity,



(e) in the case of a change of destination) connection to the production plants of electricity transmission

system or distribution system.



(2) the requirements for an application for connection electricity production plants or part thereof to the

the transmission system or distribution system are listed in the annex.

1 to this notice.



(3) a part of the production plants of electricity connection request the consent of the owner of the

real estate with the placement of production plants of electricity on his property and in

the case of the production plants of electricity with an installed power



and from 30 kW) to 5 MW, including the planning information on the conditions

the issue of land-use decisions, from which it is clear that the construction of production plants

electricity in accordance with territorial planning documentation



(b)) over 5MWpřipojované to the distribution system and production plants of electricity

to connect to the transmission system planning information

conditions of release planning,



c) above 0.5 MW schedule for preparation of the construction of a plant producing electricity.



(4) the timetable for the preparation of the construction of a plant producing electricity contains a list of

the decision, of the opinions and comments of the public authorities and

the dates of their issue, in particular as regards the conclusions of the

the discovery of the procedure for the assessment of effects on the environment, the location of the

the construction of the integrated permit, authorisation, construction and occupancy,

which are necessary for the realization of the construction of a plant producing electricity.



(5) the requirements for an application for the device connection to the distribution system,

the transmission system or distribution system are listed in the annex.

2 to this Decree.



(6) the requirements for an application for connection to the electrical equipment of the sampling

the transmission system or distribution system from voltage levels especially

high voltage, high voltage and high voltage are listed in the

Annex No. 3 to this notice.



(7) the requirements for an application for connection to the electrical equipment of the sampling

the distribution system of low-voltage voltage levels are listed in

Annex No 4 to this notice.



1) § 50 paragraph. 3 the Energy Act.



2) Decree No. 541/2005 Coll., on the electricity market rules, the principles of

pricing for electricity market operator's activities and the implementation of

some of the other provisions of the Energy Act, as amended

regulations. ".



9. in section 4, the following new Section 4a, which including the title:



' Section 4a



A study of connectivity



(1) the operator of a transmission system operator or distribution

system may request from the applicant processing study of connectivity,



and) if having regard to all the circumstances of the obvious, that the equipment to which the

the connection applicant, will have an impact on the reliability of the transmission

system operator or distribution system operator, or



(b)) asks if the device connection to the high voltage and voltage level

higher.



(2) if the applicant Asks about the connection to the distribution system, the transmission

system or to increase the power or the performance of the booked in delivery

place between distribution and transmission system, processing

study together connectivity, the transmission system operator and

the distribution system operator.



(3) the subject of a study of the production plants of electricity or connectivity, sampling

electrical equipment is the assessment of the expected environmental effects of the device connection

the reliable operation of the Czech transmission system or distribution system.

Subject of studies the distribution system to the transmission connectivity

system or distribution system to the distribution system is hereinafter

the assessment of the possible variations of the desired connection in terms of their

costs.



(4) the operator of a transmission system operator or distribution

the system may require the processing of study connectivity within 30 days from the
applying for the connection. At the same time must define the scope of the

a study of connectivity.



(5) if the applicant so requests, the transmission system operator or

distribution system operator of the supporting documents for the processing of study

connectivity, not later than 30 days after receipt of the application for

processing, the transmission system operator or the operator

the distribution system will provide the applicant with the supporting documents necessary for processing

a study of connectivity within 15 days of their request. Thereafter, if

the applicant a transmission system operator or distribution

system of documentation for processing study of connectivity, within 30 days after the

receipt of the application for processing, the transmission system operator

or the distribution system operator request is examined.



(6) unless otherwise requested by a transmission system operator or the operator

study of the processing distribution system connectivity, within the time limit referred to in

paragraph 4, or if the applicant does not provide the documentation required for processing

a study of connectivity, it is considered that processing studies

connectivity is not required.



(7) an applicant for the device connection to the distribution system shall transmit to the

the distribution system operator study, connectivity, within 90 days from the

the date when the distribution system operator shall forward the documents to the applicant

necessary for the processing of the study. If the applicant asks about the connection of the device to the

the transmission system, transmission system operators shall transmit to the applicant

study on connectivity to 180 days from the date when the operator of a transmission

the system forward to the applicant documents necessary for processing the studies, if

the applicant, with the transmission system operator concerned agree otherwise.



(8) if it is not processed in the range of connectivity, the study defined

transmission system operator or distribution

system, the transmission system operator or the operator

distribution system to request its addition or extension. The operator

the transmission system operator or distribution system operator may request

addition or extension studies connectivity, not later than 30 days from the

transmission study of connectivity.



(9) if the transmission system operator of the tween, or extension

the study, together with the applicant passes the connectivity or advanced study

connectivity within 90 days of the date on which it received the request of the operator

the transmission system operator, unless agreed otherwise. For the processing and transfer of

the new study, connectivity, paragraph 7 shall apply mutatis mutandis.



(10) if the distribution system operator shall supplement or

the extension of the study, the applicant supplemented by connectivity, transmit or

an extended study of the connectivity within 30 days of the date on which it received the

request a distribution system operator. For the processing and transfer of

the new study, connectivity, paragraph 7 shall apply mutatis mutandis. ";"



10. section 5, including the title and a footnote 3 is added:



"§ 5



The assessment of the applications for connection to the transmission system or device

distribution system



(1) the operator of a transmission system operator or distribution

the system assesses the application for the connection of the device with regard to the



and the place and the way required) connection,



(b) to the desired size of the reserved power) or the performance of, and the time

the progress of the load,



(c) the reliability of electricity supply)



(d) the nature of the reaction device) of the applicant on the transmission or

distribution system,



(e) the planned development system)



(f)) and the order of the lodgment of applications



g) limits the performance of the electricity system trimmer set

the transmission system operator.



(2) if it is necessary for a proper examination of the application, it shall invite the

the transmission system operator or distribution system operator

the applicant no later than within 15 days from the date of receipt of the application for the supplement

of the data provided to the extent needed and shall lay down to ensure adequate

the time limit. At the same time notify the applicant, in the case of nedoplnění data in

to the extent required by the deadline will not be considered in the application.



(3) if the applicant has been invited to supplement the information provided in accordance with paragraph

2 the applicant not having done so, the transmission system operator or

the distribution system operator request is examined. This fact

shall inform the applicant without undue delay.



(4) if they are not given the reasons set out by the law, for which energy

the applicant cannot be a device to the transmission system or distribution system

connect to ^ 3), the distribution system operator shall provide to the applicant within 30

days, or in the case of devices connecting to voltage levels high

or very high voltage within 60 days of the submission of a complete application for

connection or from the date of transmission of the study, if connectivity

processing study of connectivity required design connection agreements

or a proposal for a Treaty on the future of the connection. In the case of devices

to attach to the transmission system, the time limit for the submission of the proposal

connection agreements or contracts for the future to connect for 90 days

from the submission of a complete application for connection or from the date of transmission of the study

connectivity, if the processing of a study requested by connectivity.

The transmission system operator or distribution system operator

determined in the draft Treaty on the future of the connection or the Treaty on

the connection time limit for the adoption of the draft Treaty of 30 days, if it is

the device connects to the voltage low voltage level, or 60 days,

If this is about the connection of the device to the surface voltage of high voltage

or higher.



(5) If you cannot connect to the device of the applicant for the reasons set out

energy law ^ 3), the transmission system operator or

the distribution system operator shall notify this fact to the

to the applicant within 30 days from the submission of a complete application for connection or from the date of

transmission study of connectivity if it has been processing studies

connectivity, you requested. The transmission system operator or

distribution system operator shall also specify the particular reasons for the

You cannot connect to the device of the applicant. However, if the device can be

applicant attach under different conditions and the content of the application or of the

the circumstances in which the application was made, it can be assumed that the applicant

such connections will have an interest in, the transmission system operator

or distribution system operator in writing of such fact

shall notify the applicant, including the reasons for which cannot be under the required device

conditions to join, and submit the draft contract to the applicant in accordance with paragraph 4.



(6) the Treaty of the Treaty to the future of the connection is closed normally,

If the applicant requires the connection of the device construction technical measures

in the transmission system or distribution system, whose implementation

requires a decision on the location of the building or the territorial agreement referred to in

the building Act.



(7) if the examination of the application on the connection necessary to measure

or network with a voltage of 110 kV network operation verification, the term

referred to in paragraph 4 or 5 of the time required for measurement or verification operation

the network, a maximum of 30 days. On the necessity of implementation of measurement or verification

network operation and the extension shall inform the operator of a transmission

system operator or distribution system operator the applicant not later than

15 days from the date of receipt of the request for a connection.



(8) the operator of a transmission system operator or distribution

the system suggests the connection of the device, so that the technical implementation

connection of the device was based on the planned development of the system during the

considering the interest of the applicant to minimize the costs of

the device connects to the transmission system or distribution system.



(9) the transmission system operator, or the operator of a distribution

the system reserves the the applicant desired power or power from the moment

submission of the draft of the Treaty referred to in paragraph 4.



(10) if the applicant does not accept the proposal of the contract within 30 days for a connection to the

voltage low voltage level, or up to 60 days for the connection to the voltage

the surface of the high voltage and higher performance or booking, reservation

input ceases to exist.



section 24, paragraph 3). 10 (a). and § 25 paragraph). 11 (a). and) energy

of the law. ".



11. In section 6 paragraph 1 including the footnote No. 4:



"(1) Short-term connection means the connection of the provisional devices

According to Czech technical standards ^ 4) to a distribution system for a specified period.



ČSN 33 2000-4)-1. ".



12. In section 6 (1). 3, the words "the issue of requests for opinions" be deleted and the

the words "the provisions of section 5" shall be replaced by the words "§ 4 to 5 and section 7".



13. In section 6 (1). 4, the last sentence shall be replaced by the phrase "Share on

eligible costs under section 10 (a). ".



14. In section 6 paragraph 5 is added:



"(5) after the completion of connection agreements lapse booked input; section 7 of the

paragraph. 7 to 9 shall not apply. ".



15. In section 6, the following paragraph 6 is added:



"(6) If a due to the realization of the short connections to distribution

the need to increase system reserved power in forward locations

between the distribution system, in which to implement the short-term connection

occurred, and a distribution system, proceed in accordance with paragraph 4. ".



16. the title of section 7 including:



"section 7 of the
The device connects to the transmission system or distribution

System



(1) connect the device to the transmission system or distribution

the system is implemented on the basis of the Treaty.



(2) the Treaty concerning the connection of one applicant can include multiple sampling

or transfer jobs, if each of them separately in the contract

stated.



(3) the applicant shall be borne by the advance on the share of the eligible costs referred to in

Annex No 6 to this Decree, in the amount of 50% of the value of the share on the

eligible costs, but not more than 50 0000 0000 Czk. The applicant shall pay

the advance on the market share of the eligible costs within 15 days from the date of the conclusion of the

connection agreements or contracts for the future.



(4) if the applicant does not pay the advance on the share of the eligible costs referred to in

paragraph 3 or in additional reasonable period of time provided by the operator

the transmission system operator or distribution system operator and

the transmission system operator or distribution system operator

for this reason, terminate the contract or a contract on connection contract

the future of connectivity, or reservation booking performance input termination

the contractual relationship ceases to exist.



(5) if the connection does not require the applicant's implementation of construction equipment

technical measures in the transmission system or distribution system,

out the transmission system operator, or the operator of a distribution

system and the applicant, the term connection of electricity production plants using

solar radiation to electricity plant was connected by

180 days from the date of conclusion of the contract about connection, in the case of production plants

electricity using solar radiation with installed power of 30 kW

up to 1 year from the date of conclusion of the contract about connection.



(6) if the applicant within the time limits referred to in paragraph 5 shows that despite all the

the efforts made not in connection to the implementation of the agreed deadlines

the production plants of electricity, for reasons that have occurred or are there regardless of the

his will, the transmission system operator or the operator

distribution system operators shall negotiate with the applicant an extension of the deadline for the connection

as long as necessary.



(7) if the agreed reduction of the value of the main circuit breaker before the measurement

device to a value lower than the reserved power of the place

connection device for longer than 24 months,

the value of the reserved power to this value.



(8) If, after the period of 60 months from the date of the last change of the reserved

input not to the negotiation of reserved capacity of at least 90% of the

reserved input, the value of the reserved power is reduced to

value, which is determined by the maximum agreed size reserved

capacity in the period of 60 months from the last changes of the reserved power.



(9) in the case of termination of the contract for the transmission or distribution of electricity takes

booked for existing connection site for a period of 60 months from the

the date of termination of the contract. If the contract for the transmission or distribution of

electricity has not been concluded within 60 months from the date of the agreed connection

in the Treaty, the reservation for place of consumption or for the

place connection. ".



17. section 8 including title:



"section 8



The costs associated with connecting the device to the transmission system or the

distribution system and by ensuring the desired wattage or performance



(1) If an applicant under this Ordinance shall bear the costs associated with

and ensuring the desired wattage or the performance in full

the amount of the costs can be borne by the applicant to include only the costs referred to in

paragraphs 2 to 4.



(2) the costs associated with the connection and to ensuring the desired wattage

or include essential performance incurred eligible costs

related to the acquisition, construction or modification of transmission system

or distribution system, which were raised in the applicant's request

connection with the place and the way to connect his equipment. The acquisition,

construction or modifications to the transmission system operator or distribution system operator are

provided in the extent strictly necessary to the corresponding value input

or the performance of, the desired by the applicant, and the place and how to connect his

the device.



(3) The costs associated with the connection and to ensuring the desired

the wattage or performance will include the cost of the acquisition project

geodetic documentation, focus, easements and other immediately

the related investment costs and fees for the construction, modification or

the acquisition of the transmission system operator or distribution system operator.



(4) The costs associated with the connection and to ensuring the desired

the wattage or performance do not include costs associated with the acquisition,

the construction or modification of transmission system or distribution system,

that exceed the scope strictly necessary corresponding to the value

input or output, requested by the applicant, and the place and the way

the connection of the device.



(5) the construction and adjustment of the transmission system operator is defined from the point of connection

the device of the applicant to the nearest place in the transmission system, where is

or would poprovedení the necessary adjustments in the system was available

the power or the performance of the booked.



(6) construction and adjustment of the distribution system is defined from the point of

connect the device to the nearest location in the distribution system

to the same voltage level, where it is, or would after the execution of the necessary

adjustments in the system was available the booked or power

performance. ".



18. section 9, including the title.



19. section 10 including title:



"§ 10



Market share of the applicant for connection to the transmission system or device

distribution system on legitimate costs



(1) the applicant's share of the eligible costs shall be calculated as the product of

measuring the proportion referred to in annex 6 to this Decree and by the applicant

the required power or the performance of the booked.



(2) in the case of connecting production plants of electricity to the transmission system or the

the distribution system shall be borne by the pin connection to the places the applicant in

full.



(3) if the performance of the parallel input and checked out one applicant in one

a place to connect, the share of the eligible costs, especially for

reservation and booking of performance power. The applicant pays the higher of the two

set out the eligible shares the costs. ".



20. in article 10 the following new section 10a, including title:



"§ 10a



Reconnect the device to the transmission system or distribution

System



Connects to the transmission system operator or the operator

the sampling distribution system, the electrical equipment of the customer

was limited or interrupted the supply of electricity due to unauthorized

collection, transmission or distribution of electricity, shall be borne by the customer market share

of eligible costs in the amount of



1 500 Czk) when connecting to a voltage level low voltage,



(b)) 3 500 Czk in connection to the high voltage or voltage level

higher. ".



21. section 11 including the title:



"section 11



The specific requirements of the applicant for the device connection to the transmission system

or distribution system



(1) if the applicant Requests a connection beyond standard connection

the device or if a specific method of construction or technical

implementation of the device connection to the transmission system or distribution

the system shall be borne by the applicant justified the costs associated with the implementation of

above-standard connection or a specific building or technical

make connections in full.



(2) booked on the surface of low-voltage power can be transferred in the

one or more adjacent real estate property, only if the

It's technically possible and realization of transfer of a reserved power does not raise the

additional costs related to the acquisition, construction or modifications

the distribution system. Similarly, when the transfer of the reserved

power on the surface of a high or very high voltage in one

the nodal region of the appropriate voltage levels.



(3) if the applicant Asks about the connection of the device to a different voltage level than the

to which the device is connected, and the required change of the connection is not

enforced by changing the technical conditions of connection shall be borne by the applicant costs

on the legitimate costs associated with this amendment in full. In such a

If the amount of the original booked the wattage or performance shall stipulate

share of the eligible costs under section 10. The provisions of section 7 (1). 7 to 9

shall not be used. ".



22. In the heading of section 12, the word "households" is deleted.



23. In section 12, the following paragraph 3, including footnote 5.

added:



"(3) for the assessment of whether there is an electrical connection in a built-up

or outside the built-up territory pursuant to the building Act ^ 5), it is critical

the location of the link property.



5) § 2 (2). 1 (a). (d)), the building Act. ".



24. Annexes 1 to 6 are added:



"The annex No. 1 to Decree No 51/2006 Sb.



REQUEST FOR CONNECTION TO THE TRANSMISSION OR PRODUCTION PLANTS OF ELECTRICITY

DISTRIBUTION SYSTEM



Part And

-information on the applicant



1. Business name (applicant-registered in the commercial entrepreneur

the register).



2. the data on the registration in the commercial register, including the file tags
(to be completed by the applicant-entrepreneur registered in the commercial register).



3. The name or the name and surname of the applicant (unregistered in business

the register).



4. Date of birth (to be completed by the applicant-natural person).



5. Registered Office: the State, the County, municipality, with POSTAL CODE, street and house number,

where applicable, the registration number (to be completed by the applicant-legal person).



Place of business in the breakdown: the State, the County, municipality, with POSTAL CODE, street and number

where applicable, the registration number of the descriptive (to be completed by the applicant natural person-

doing business).



6. the name and surname of the person, which is a statutory body, or all of the

persons who are members of the statutory body (to be completed by the applicant-

a legal person).



7. The address of the place of stay in the breakdown: the State, the County, municipality, with POSTAL CODE, street and number

descriptive, or registration number (to be completed by the applicant natural person-

the nonentrepreneurial).



8. connection-phone, e-mail.



9. The address for service.



10. information on the data, if the mailbox has been established.



11. The identification number, if one has been assigned.



12. Tax identification number, if one has been assigned.



Part (B)

-the data on the device



1. The location of the production plants of electricity-region, municipality, cadastral, land

the numbers of the land on which the plant is located, the number of electricity

descriptive, or registration number.



2. the type of electricity production plants.



3. the character of the production of electricity.



4. The term of the connection.



5. basic data on the production of electricity:



5.1. the involvement of the production plants of electricity to the transmission system or distribution

System (insulation level, estimated the site connection,

fit the scheme, territorial connection variants variants of each)



5.2. Description of the production plants of electricity [total installed capacity of the power plant,

achievable performance power, the performance of the individual blocks, electric

scheme of the blocks, block type (coal, water, another paroplynový), a kind of resource

(top, base), the energy produced per year, the rated power factor,

the estimated reliability of the block],



5.3. Description of the block transformer (type, installed power, nominal

the tension, the tension of the short, winding, conversion, a range of branches,

loss of short and loss, short-circuit resistance, etc.)



5.4. Description of the generator (type, installed power the apparent and active,

nominal voltage, the wiring, the type, the switch drivers, dynamic

constants, as are spare, the reactance time constants, constants

of inertia)



5.5. Description of own consumption (total installed power, nominal

voltage, power factor, the starting current).



6. the required reliability of the power outlet.



The applicant declares and confirms the accuracy of his signature and the truth

all of the above data.



"Annex No. 2 to the Decree No 51/2006 Sb.



THE ELEMENTS OF THE REQUEST FOR THE DEVICE CONNECTION TO THE DISTRIBUTION SYSTEM,

A TRANSMISSION OR DISTRIBUTION SYSTEM



Part And

-information on the applicant



1. Business name (applicant-registered in the commercial entrepreneur

the register).



2. the data on the registration in the commercial register, including the file tags

(to be completed by the applicant-entrepreneur registered in the commercial register).



3. The name or the name and surname of the applicant (unregistered in business

the register).



4. Registered Office: the State, in the region, the municipality of zip/postal code, street and house number,

where applicable, the registration number (to be completed by the applicant-legal person).



Place of business in the breakdown: the State, the County, municipality, with POSTAL CODE, street and number

where applicable, the registration number of the descriptive (to be completed by the applicant natural person-

doing business).



5. the name and surname of the person, which is a statutory body, or all of the

persons who are members of the statutory body (to be completed by the applicant-

a legal person).



6. connection-phone, e-mail.



7. The address for service.



8. Information about the data, if the mailbox has been established.



9. Identification number of the



10. Tax identification number



Part (B)

-the data on the device



1. The term connection



2. Basic data for connection to the transmission system or distribution

system:



2.1. submission site,



2.2. the highest voltage level,



2.3. the fit scheme,



2.4. the cadastral map of the territory with the placement of a pass-through space.



3. data collection:



3.1. the requested value of the reserved power and reserved performance,



3.2. the current value of the reserved power and reserved performance,



3.3. nature of sampling,



3.4. the time course load,



3.5. the power factor and the compensation



3.6. the scheduled subscription of energy per year.



4. the requirements on the reliability of supply (maximum period of interruption

delivery).



5. reverse Options affecting the supply network.



The applicant declares and confirms the accuracy of his signature and the truth

all of the above data.



"The annex No. 3 to Decree No 51/2006 Sb.



REQUEST FOR CONNECTION TO THE ELECTRICAL EQUIPMENT OF THE SAMPLING

A TRANSMISSION OR DISTRIBUTION SYSTEM FROM VOLTAGE LEVELS ESPECIALLY HIGH

VOLTAGE, A VERY HIGH VOLTAGE AND HIGH VOLTAGE



Part And

-information on the applicant



1. Business name (applicant-registered in the commercial entrepreneur

the register).



2. the data on the registration in the commercial register, including the file tags

(to be completed by the applicant-entrepreneur registered in the commercial register).



3. The name or the name and surname of the applicant (unregistered in business

the register).



4. Date of birth (to be completed by the applicant-natural person).



5. Registered Office: the State, the County, municipality, with POSTAL CODE, street and house number,

where applicable, the registration number (to be completed by the applicant-legal person).



Place of business in the breakdown: the State, the County, municipality, with POSTAL CODE, street and number

where applicable, the registration number of the descriptive (to be completed by the applicant natural person-

doing business).



6. the name and surname of the person, which is a statutory body, or all of the

persons who are members of the statutory body (to be completed by the applicant-

a legal person).



7. The address of the place of stay in the breakdown: the State, the County, municipality, with POSTAL CODE, street and number

descriptive, or registration number (to be completed by the applicant natural person-

the nonentrepreneurial).



8. connection-phone, e-mail.



9. The address for service.



10. information on the data, if the mailbox was furnished.



11. The identification number, if one has been assigned.



12. Tax identification number, if one has been assigned.



Part (B)

-information on the applicant's equipment



1. The term of the connection.



2. Basic data for the involvement of the applicant's facilities to transmission systems

or distribution system:



2.1. the sampling/pass-through space,



2.2. the highest voltage level of consumption of the electrical equipment,



2.3. the fit scheme,



2.4. the cadastral map of the territory with the location of the sampling points.



3. data collection:



3.1. the requested value of the reserved power,



3.2. the current value of the reserved power,



3.3. nature of sampling,



3.4. the type and subscription of the connected appliances (in particular the number and performance

engines, electric furnaces and heating, electric welding equipment, drives

etc.),



3.5. the time course load,



3.6. the power factor and the compensation



3.7. information about whether the sampling place installed a backup

the source and in the positive case, its parameters and the expected way

operation.



4. the requirements on the reliability of supply (maximum period of interruption

delivery).



5. reverse Options affecting the supply network.



6. information on the production and mounting or already connected to sampling

the device.



The applicant declares and confirms the accuracy of his signature and the truth

all of the above data.



"Annex No 4 to Decree No 51/2006 Sb.



REQUEST FOR CONNECTION TO THE ELECTRICAL EQUIPMENT OF THE SAMPLING

DISTRIBUTION SYSTEM FROM VOLTAGE LEVELS LOW VOLTAGE



Part And

-information on the applicant



1. Business name (applicant-registered in the commercial entrepreneur

the register).



2. the data on the registration in the commercial register, including the file tags

(to be completed by the applicant-entrepreneur registered in the commercial register).



3. The name or the name and surname of the applicant (unregistered in business

the register).



4. Date of birth (to be completed by the applicant-natural person).



5. Registered Office: the State, the County, municipality, with POSTAL CODE, street and house number,

where applicable, the registration number (to be completed by the applicant-legal person).



Place of business in the breakdown: the State, the County, municipality, with POSTAL CODE, street and number

where applicable, the registration number of the descriptive (to be completed by the applicant natural person-

doing business).



6. the name and surname of the person, which is a statutory body, or all of the

persons who are members of the statutory body (to be completed by the applicant-

a legal person).



7. The address of the place of stay in the breakdown: the State, the County, municipality, with POSTAL CODE, street and number

descriptive, or registration number (to be completed by the applicant natural person-

the nonentrepreneurial).



8. connection-phone, e-mail.



9. The address for service.



10. information on the data, if the mailbox has been established.



11. The identification number, if one has been assigned.



12. Tax identification number, if one has been assigned.



Part B-information about the applicant's equipment



1. The term connection



2. Basic data on the involvement of the applicant's equipment in the distribution system:



2.1. the sampling/submission site (e.g. the establishment, rod House, cottage)



2.2. the cadastral map of the territory with the location of the sampling points.



3. data collection:



3.1. the requested value of the reserved power,



3.2. the current value of the reserved power,
3.3. nature of sampling,



3.4. the type and subscription of the connected appliances (connection of individual

appliances with a nominal input of 5 kW and above, in particular the number and performance

engines, electric furnaces and heating, electric welding equipment, drives

etc.),



3.5. information about whether the sampling place installed a backup

the source and in the positive case, its parameters and the expected way

the operation,



4. the requirements on the reliability of supply.



5. reverse Options affecting the supply network.



6. Type and performance of heat pumps.



7. information on the production and mounting or already connected to sampling

the device.



The applicant declares and confirms the accuracy of his signature and the truth

all of the above data.



"Annex No. 5 to Decree No 51/2006 Sb.



REQUIREMENTS FOR AN APPLICATION FOR A SHORT-CONNECT THE DEVICE TO THE DISTRIBUTION

SYSTEM



Part And

-information on the applicant



1. Business name (applicant-registered in the commercial entrepreneur

the register).



2. the data on the registration in the commercial register, including the file tags

(to be completed by the applicant-entrepreneur registered in the commercial register).



3. The name or the name and surname of the applicant (unregistered in business

the register).



4. Date of birth (to be completed by the applicant-natural person).



5. Registered Office: the State, the County, municipality, with POSTAL CODE, street and house number,

where applicable, the registration number (to be completed by the applicant-legal person).



Place of business in the breakdown: the State, the County, municipality, with POSTAL CODE, street and number

where applicable, the registration number of the descriptive (to be completed by the applicant natural person-

doing business).



6. the name and surname of the person, which is a statutory body, or all of the

persons who are members of the statutory body (to be completed by the applicant-

a legal person).



7. The address of the place of stay in the breakdown: the State, the County, municipality, with POSTAL CODE, street and number

descriptive, or registration number (to be completed by the applicant natural person-

the nonentrepreneurial).



8. connection-phone, e-mail.



9. The address for service.



10. information on the data, if the mailbox has been established.



11. The identification number, if one has been assigned.



12. Tax identification number, if one has been assigned.



Part (B)

-information on the applicant's equipment



1. The date and the duration of the connection.



2. Basic data on the involvement of the applicant's equipment in the distribution system.



3. The sampling/submission site.



4. the Location of the sampling of the electrical equipment.



5. Information about the subscription:



5.1. the required size of the reserved value input/main

circuit breakers,



5.2. nature of sampling.



The applicant declares and confirms the accuracy of his signature and the truth

all of the above data.



"Annex No 6 to Decree No 51/2006 Sb.



THE SPECIFIC CONTRIBUTION OF THE APPLICANT FOR CONNECTION TO THE LEGITIMATE COSTS ASSOCIATED WITH

CONNECTION AND SECURING OF THE REQUIRED POWER AND PERFORMANCE



FOR BOOKING INPUT



------------------------------------------------------ -------------------------

Instead the connection to the voltage level of the specific contribution of the applicant connection method

------------------------------------------------------ -------------------------

transmission system 200 USD/MW

HIGH VOLTAGE distribution system and Type 600 USD/MW

HIGH VOLTAGE distribution system Type (B) 150 USD/MW

the distribution system of HV Type and 800 USD/MW

the distribution system of HV Type B1 200 USD/MW

distribution system NN 3 phase connection 500 Kč/A

distribution system NN 1 phase connection of 200 Czk/A

------------------------------------------------------ -------------------------



FOR BOOKING THE PERFORMANCE



------------------------------------------------------ -------------------------

Instead the connection to the voltage level of the specific contribution of the applicant connection method

------------------------------------------------------ -------------------------

the transmission system at the point of connection

According to the opinions of 500 USD/MW

the operator

the transmission system

HIGH VOLTAGE distribution system and Type 1 200 0000 CZK/MW

HIGH VOLTAGE distribution system Type (B) 150 USD/MW

the distribution system of HV type 640 USD/MW

the distribution system of HV type B 150 USD/MW

distribution system NN 3 phase connection 500 Kč/A

distribution system NN 1 phase connection of 200 Czk/A

------------------------------------------------------ -------------------------



Connection Type And

is such a connection, where the distribution system operator shall extend the

the distribution system up to the pickup points.

transformer station or substation of the applicant for connection.



Connection Type (B)

is such a connection that does not meet the conditions for the connection type and.



Connection Type B1

is such a connection when it is not necessary to the construction of the new dungeons and Busbar and

they are only necessary adjustments of a technical nature (e.g. replenishment of armament

the Dungeon)



In the case of a connection request, or an increase of the reserved power

or the performance of the objects already connected is to determine the amount of the share of the

eligible costs the determining existing connection method. ".



25. the following Annex No. 7:



"Appendix No. 7 to Decree No 51/2006 Sb.



CHARACTER COLLECTION



1. the place of consumption of the type "T1"-the place of consumption with electric equipment

standard appliance to 16 and that they have the mark of conformity in the sense of

Act No. 22/1997 Coll.-lighting and electrical appliances to connect to the

divorce, moving supply (wall outlet) or securely attached, with

input any appliances does not exceed 3.5 kVA.



2. The sampling place type "T2"-the place of consumption with electric equipment such as

for the type "T1", where the water is used for heating of the electric power (outside of the

flow heaters).



3. The sampling place type "T3"-the place of consumption with electric equipment such as

for the type "T1" or "T2", where cooking and baking using electric

the appliance of over 3.5 kVA.



4. The sampling place type "T4"-the place of consumption with electric equipment such as

for the type "T1", "T2" or "T3", where the heating (accumulator,

direct heating, heat pump) or air conditioning used electrical

appliances whose consumption is measured for each customer.



5. The sampling place type "T5" – place of consumption with electric equipment such as

for the type "T3" or "T4", which are equipped with additional electrical

the appliance which may affect the operation of the network. ".



Article. (II)



Transitional provisions



1. the period of binding opinions to connection requests issued under the

Decree No. 51/2006 Coll. cannot be extended.



2. Where the applicant, before the date of entry into force of this Decree on the

the conclusion of the contract about connection and the deadline for the conclusion of the contract about connection

has not expired before the date of entry into force of this Decree, the operator

the transmission system shall provide the applicant within 60 days or the operator

distribution system within 30 days of the draft Treaty on the future of

connection, or the connection agreement in accordance with this Decree and

the opinion to the connection requests issued pursuant to Decree No 51/2006 Sb.



3. If the applicant so requests at the time of binding opinions on the applications for connection

the devices after the date of entry into force of this Decree concerning the conclusion of the Treaty on

connection, the transmission system operator shall submit to the applicant within 60 days

or the distribution system operator within 30 days, a draft Treaty on the

future of the connection, or the connection agreement in accordance with

This Decree and the opinion to connection requests issued by

Decree No. 51/2006 Sb.



4. If the extension of the binding opinions on the applications for

connection according to § 5 (3). 5 of the Decree, as amended by the effective to date of the acquisition

the effectiveness of this Decree and extended time binding opinion takes

for the effectiveness of this order, the applicant so requests at the time of binding,

not later than 3 months after the entry into force of this order, the

the conclusion of the Treaty of the Treaty to the future of the connection or the draft Treaty on the

connection in accordance with this Decree. The transmission system operator

the applicant shall submit, within 60 days, or the distribution system operator to

30 days, a draft Treaty on the future of the connection or the draft Treaty on the

connection in accordance with this Decree and the opinion on the application of

According to a decree issued by a connection No 51/2006 Coll. does not ask if the applicant for

the conclusion of the contract in accordance with this provision, booked the wattage or

performance shall lapse.



Article. (III)



The effectiveness of the



This Decree shall take effect on 1 January 2005. April 2010.



Chairman:



Ing. The firt in r.