552/2006 Coll.
DECREE


Dated 11 December 2006

Amending Decree no. 541/2005 Coll., On Market Rules
electricity pricing principles for activities of the electricity market operator
and execution of certain other provisions of the Energy Act

Energy Regulatory Office (the "Office"), pursuant to § 98 paragraph. 7
Act no. 458/2000 Coll., On business conditions and public administration
in the energy sectors and amending certain laws (
energy Act), as amended by Act no. 670/2004 Coll., and pursuant to Article. II, section 18 of Act No.
. 670/2004 Coll., Amending Act no. 458/2000 Coll., On conditions
business and state administration in energy sectors and amending certain laws
(Energy Act), as amended, to | || implementation of § 17 para. 7 point. e), h) and k) and § 27 para. 7 of the Energy Act
:
Article I


Decree no. 541/2005 Coll., On Electricity Market Rules and principles of pricing
Market Operator, electricity and execution
certain other provisions of the Energy Act, is amended as follows:

First In § 2 para. 1, at the end of the text of letter i) the words "for the territory
entire state and thirty regional average daily temperatures for each
business days for the region of typical".

Second In § 2 para. 1, at the end of the text of the letter), the words "for the territory
entire state and regional average daily temperatures for each
business days for the region of typical".

Third In § 4, at the end of paragraph 2 sentence "At the request
communicate to the transmission or distribution system market participant with electricity
its registration number.".

Fourth In § 5, paragraph 4 reads:

"(4) In the event that the supplier provides electricity supply to final customers through
contract under § 7 para. 1 point. D) closes
DSO at the supplier with the supplier framework
The distribution agreement. ".

Fifth In § 5, after paragraph 4 the following paragraph 5 is added:

"(5) In the event that the distribution system operator and supplier
contract pursuant to paragraph 4, the distribution system allows suppliers
e-invoicing.".

The former paragraphs 5 to 16 shall be renumbered 6 to 17

6th In § 5, at the end of paragraph 8 of the text, the words "except as provided in paragraph
12".

7th In § 5 para. 9, first sentence reads: "Payment for electricity transmission and
payment for the electricity distribution consists of payments for the use of networks
payment for reserved capacity and in the case of distribution of electricity as well as a payment for
exceeding booked capacity. ".

8th In § 5, at the end of paragraph 10, the sentence "If there is a change
connection agreement in part on the value of the main belay
element upstream from the electricity distribution system operator
immediately inform the electricity supplier." .

9th In § 5, paragraph 11, the following paragraph 12 is added:

"(12) of the customer, who is one of the voltage levels
very high or high voltage one DSOs
connecting multiple supply points with continuous metering type A or B, whose consumption is
connected to its own power grid and which are
powered electric traction vehicles, down
distribution system operator booked capacity for each voltage level
separately from the sum of maximum capacities measured at sampling sites in
time when this the sum of the highest in the month. ".

Former paragraphs 12-17 are renumbered as paragraphs 13 to 18

10th In § 5, paragraph 17 reads:

"(17) electricity market participants off electricity in the withdrawal or
delivery point to the value of the lagging power factor from 0.95 to 1.00 when
distribution system operator agree otherwise.".

11th In § 7 para. 1, letter c) reads:

"C) contracts for operational electricity supply from abroad and abroad, which is entered


as the first contract for the operational electricity supplies from abroad to compensate
system imbalance, which the Parties such contracts are
TSO on one side and the contractor supplying electricity
after a previous agreement with the foreign operator
transmission system itself or foreign TSO

On the other; This contract can be concluded in time after closure
bilateral trades,

Second agreement on operational electricity supply abroad when
Contracting Parties of such contracts are cleared entity supplying
after a previous agreement with the TSO electricity abroad
on one side and the operator of the foreign transmission system or trader after
previous agreement with the foreign transmission system
on the other; This contract can be concluded in time after
roadblock bilateral transactions. "

12th in § 7 para. 4, the second sentence is replaced by the phrase"
Party to this Agreement may only be a subject of settlement or a registered market participant
with the consent of the subject of settlement, for which he took responsibility for deviation
.. "

13th in § 8 paragraph 1 reads:

" (1) responsibility for the derogation relating to each individual
offtake point or summary of the final customer delivery points every
individual electricity generating plant or bouquet delivery points for each individual
defined area DSOs can be transferred at a time
1 cleared entity, either directly or through another
registered electricity market participant.
At the request of the electricity market participant registers operator
distribution system instead of connecting the device to the distribution
system in which it is carried out supply and consumption, particularly for delivery
electricity and especially for electricity, taking responsibility
registered for such transfer points can be transferred to two different entities
settlement. ".

14th in § 12 para. 2, the number" 3 "is replaced by" 2 ".
| || 15th § 14 including the title reads:

"§ 14

Balancing market with regulating energy

(1) The balancing market with the regulating energy is realized after closure
bilateral trading and after closure
organized short-term electricity market. Registered market participants participating in balancing
market with regulating energy with the consent of the subject of settlement, which took
responsibility for their imbalances. At the conclusion of
access to the balancing market with regulating energy demonstrates a registered market participant
electricity market operator settlement agreement subject to participation
this market.

(2) The balancing market with regulating energy traded positive and negative regulatory
energy in a minimum amount of one MWh.
Bids on the balancing market with regulating energy administered registered participants
market later than 30 minutes before the start of trading hours, when the supply
be positive or negative regulating energy
the transmission system as a single inquirer, used to
protection system deviations. TSO evaluate the offer received
regulatory power as the deliveries of balancing energy and passes it
market operator settlement.

(3) Bids Received supply positive and negative regulating energy
balancing market with regulating energy for the trading hours include
market operator in the system of evaluation and settlement of imbalances. ".

16th In § 18 par. 1 at the end of the text in subparagraph d) the words "and
electricity procured from abroad."

17th in § 18, the following paragraph 14 is added:
|| | "(14) The distribution system transmits information to the market operator
pursuant to paragraph 2. b) 1 point only in the event that he is the supplier
which supplies electricity to such final customer, provide the desired format
every working day no later than 10:30 am.. "

18th in § 19 paragraph. 12, the words "based on" the words
'categorization of end customers pursuant to Annex no. 4a. "

19. In § 19 para. 14, the word" published "is replaced by"
exposes electricity market participants in a manner allowing remote access via the information system
electricity market operator. "

20th in § 19 para. 18 of the words" under § 18 par. 8 point. c) "are replaced
words" in the term pursuant to § 32 para. 4 ".

21st § 22 including the title reads:

" § 22

Rounding actual values ​​when calculating deviations

(1) Deviations of clearing entities are evaluated in MWh with a resolution of 1
decimal place.

(2) The actual value of the undertaking cleared entity
remove electricity from the electricity system shall be rounded to tenths MWh

Follows:

A) is in second place after the decimal point (hundredths MWh)
numbers greater than or equal to 5, then the figure in the first place after the decimal point adds 1
and digits on the second and subsequent decimal place
comma is removed

B) in other cases, all the numbers in the second and another point behind
decimal point removed.

(3) The difference totals of actual daily values ​​for the electricity supply
needs assessment and clearing imbalances in a given month and the actual value
monthly supply of electricity to bill payments for transmission or distribution of electricity
may vary for supply or transfer points
equipped with metering type A maximum of 15 kWh per calendar month, with
supply or transfer points equipped with type B metering maximum of 1
kWh per month.

(4) If supply or consumption of electricity measured on the secondary side of the transformer
, it is understood that the actual values ​​are measured
values ​​increased in the case of collection or reduced in the event of supply of electricity
values ​​established Office's price decision. Such modified
value passes the distribution system operator to the market operator for
evaluation and settlement of imbalances and billing of electricity or subscribe
.. "

22nd § 24 including the title reads:
| || '§ 24

Electricity purchased is TSO

(1) In order to address imbalances in between contracted and actual realization
supply and consumption of electricity in the electricity grid
procures electricity transmission system operator, for
each trading hour.

(2) The TSO procures electricity

A) as regulating energy by activating support services

B) the balancing market with regulating energy, or

C) from abroad on the basis of a contract under § 7 para. 1 point. c) point 1.

(3) Electricity prices under paragraph 2 is used to determine the settlement price
according to § 25 par. 2 and are included in the evaluation system and clearing
deviations.

(4) The TSO provides the overall costs associated with the solution
state of imbalance between contracted and actually implemented
supply and consumption of electricity for each trading hour
amount of electricity as referred to in paragraph 2 and in MWh their prices
CZK / MWh and shall forward this information to the market operator by 11.00 pm on the first working day following
after scoring trading day.
Data are transmitted in the form of quantities and prices of positive and negative energy regulatory
broken down by individual blocks of power plants in case
it is a regulatory energy generated by activation of ancillary services, or
by registered market participants if it is a
electricity provided from abroad. In the case of regulating energy
secured on the balancing market data are transferred by the hour buffet
accepted the sum of energy on the balancing market and the total payment for each
registered market participants.

(5) of electricity pursuant to paragraph 2 shall settle the market operator, and it

A) providers of support services under a contract for the supply of energy or regulatory
agreement on access to the balancing market with regulating energy
,

B) registered market participants on the basis of an agreement on access to the
balancing market with regulating energy

C) the transmission system operator for electricity procured from abroad
under contract according to § 25 paragraph. 4th

(6) The transmission system operator in a manner allowing remote access
quantities of electricity prices broken down by paragraph 2
each trading hour. ".

23rd § 25 including the title and notes footnote no. 20a reads:

"§ 25

Clearing and financial settlement of imbalances

(1) Clearing and financial settlement of imbalances conducted by the market operator
provide the electricity market participants, payment of electricity, which was
delivered to the grid or removed from the power system
beyond the agreed amount, or not
delivered to the electricity system or been removed from the electricity grid, despite being in
contracts negotiated.

(2) Settlement prices for individual trading hours provides market operator
based on electricity prices according to § 24 paragraph. 2. The method of account creation

Prices is given in Annex no. 5 hereto.

(3) The market operator determines for each trading hour
additional costs for electricity utilized by the TSO for balancing
system imbalance. These additional costs are defined as the positive difference between the total
electricity costs according to § 24 para. 2 in the respective trading hour
absolute value of the product of system imbalance and settlement
prices. If this difference is negative, the additional costs are zero.

(4) For all hours, when there is a positive difference between the absolute value
product of system imbalance and settlement price and electricity costs
according to § 24 para. 2 is a summary of these differences for a given calendar month || | reclassified market operator TSO
under contract for the settlement of differences arising from the settlement
costs of deviations and electricity costs according to § 24 paragraph.
second subject of this contract is the payment for electricity by § 24 para. 2
point. C).

(5) Differences in paragraph 4 of the Office are included in income from
provision of system services in accordance with a special legal
regulation which establishes the procedures for price regulation in the energy-20a).

(6) Based on the settlement of imbalances conducted for each subject
settlement in each trading hour, the market operator shall determine the amount of payment
cleared entity for deviation positive or negative deviation and the amount
payment for clearing. Payment for settlement is determined by the price per
clearing activity of the market operator. Payment settlement entity for deviation
positive or negative deviation is calculated as the sum

A) payment for electricity set by multiplying the amount of deviation
positive or negative deviation and the settlement price,

B) provided additional costs as a proportion of the additional costs referred to in paragraph 3
amount corresponding to the proportion of the absolute value of the positive deviation or a negative deviation
cleared entity on the sum of the absolute values ​​of deviations
clearing entities.

(7) Every working day to 14.00 hours notify the market operator subject
clearing the manner laid down in the agreement on settlement of imbalances
imbalance evaluation for the previous day, or at all
immediately preceding non-working days. This assessment contains
for every business hour

A) the amount of deviation in MWh

B) clearing price in CZK / MWh,

C) share of the additional costs of the grid in CZK / MWh,

D) payment settlement entity in CZK.

(8) After the end of the billing period, which is 1 calendar month
market operator on the basis of the sum of the payments cleared entity
issue a tax receipt for the entire billing period, if applicable added tax on the value
output market operator or the basis for the tax document
applies if the value added tax on output accounting entity.
Settlement payments is secured by the market operator
least once per calendar month.

(9) In the event that a settlement entity fails to pay debts owed
market operator within their maturity, market operator applies to their
payment of funds from the financial security payments, in the manner specified
agreement on settlement of imbalances. If the entity
showdown is contrary to the agreement on settlement of imbalances, may
market operator to cancel the registration.

(10) Cancellation of registration pursuant to paragraph 9 publishes market operator
manner enabling remote access, while this fact
inform all cleared entities that have reported in the previous trading day
contracted quantity of electricity is subject to clearing,
which was unregistered. The notification of deregistration
is the date when the registration is canceled.
Diagrams agreed amount of electricity, which is on the supply side or subscribe identified
settlement entity with deregistration, the market operator, and accept
not included in the agreed amount of clearing entities.

(11) The financial settlement of imbalances conducted market operator in three stages
:

A) the daily settlement in the form of advance payments

B) monthly settlement, which was made after the end of the calendar month
and which is issued a tax receipt and accounted advances from the daily
settlement

C) of the final monthly settlement, which is carried out for all concerned

Settlement entities after the deadline for submission of complaints by
business conditions of the market operator.

(12) The procedure and the exact dates of the individual stages are listed in business conditions
market operator.

(13) for the financial settlement of imbalances using typical in regions
typical profiles under paragraph 11 point. a)
market operator uses the last current value of planned annual electricity consumption
which the DSO has sent to the market operator by
§ 19 paragraph. 7 and 8. For the financial settlement of imbalances using typical diagrams in
regions typical profiles under paragraph 11 point. b) c)
market operator uses the last current value
planned annual electricity consumption for individual settled business days that
DSO sent to the market operator under § 19 paragraph
. 7 and 8.

(14) for the financial settlement of imbalances in local distribution systems
under paragraph 11 point. a) uses the latest market operator
current value of planned annual electricity consumption, which
local distribution operator sent to the market operator by
§ 20 paragraph. 6 and 7. For the financial settlement of imbalances in local distribution networks
pursuant to paragraph 11 point. b) c)
market operator uses the last current value of planned annual electricity consumption for individual
settled business days that the operator
local distribution system operator sent the market according to § 20 para. 6 and 7
| ||
20a) Decree no. 438/2001 Coll., Laying down
contents of economic data and procedures for price control in the energy sector, as amended
regulations. ".

24th V § 26 paragraph 4 reads:

"(4) in the special mode of settlement for evaluation and settlement of imbalances
are contracted amounts of electricity for the obligation to supply power to the electricity grid and
agreed amount of electricity for the commitment to remove | || electricity from the power system of clearing entities determined in accordance with § 12 paragraph
. 4, including electricity provided by the TSO
according to § 24 para. 2, zero. ".

25th in § 29 paragraph. 1, letter d) reads:

"d) information on complaints raised by participants in the electricity market
to the market operator."

26th in § 29 para. 2 sentence the first words of "use of measures for the prevention
" are deleted.

27th in § 29 para. 3, after the word "customer" the words "category
D".

28. in § 29, the following paragraph 5 is added:

"(5) the market operator will provide the electricity market participants with the right
access to the market operator's information system data listed in Annexes
. 7 and 8 through the operator's information system
market. ".

29th In § 29, the following paragraph 6 is added:

"(6) The market operator shall provide TSO

a) on the day preceding business day for the purpose of preparing traffic data
about the obligation to supply electricity to the grid and commitment to take electricity from a single system
clearing entities,

b) the day following the trading day for the purpose of evaluating data on individual
deviation clearing entities if this deviation exceeds
in the subject of settlement of 50 MWh in a trading range. ".

30th § 30 including the title and footnotes Nos. 23 and 24 reads:

"§ 30

supplier change the regime of delegated responsibility for deviation

(1) Fundamental changes in suppliers electricity market participant are

a) change of supplier for another supplier ,

b) change the number of suppliers,

c) final customer transition from one supply point to another
supply point in a different distribution system

d) change of supplier last resort for another supplier, or

e) in the case of an electricity market participant in the household or small
customer change over to a supplier of last resort ^ 23).

(2) Prior to the first changing suppliers administered electricity market participant at
respective transmission or distribution system
request for a new contract on connections, not later

a) 8 working days prior to the change of supplier, the case
a change of supplier at the supply point measurement type a or b;
change of supplier takes place the first day of the calendar month

b) 17 days before the change of supplier, the case
a change of supplier at the supply point measurement type C.


(3) Following the conclusion of a new contract for connection in accordance with paragraph 2
arises electricity market participant liable to pay the share of the eligible costs
connection ^ 24).

(4) Paragraph 2 shall not apply to associated delivery points
electricity generating plants. Furthermore, does not apply to customers' supply points, which was
connected to the transmission or distribution system after January 1, 2002.

(5) Prior to switching suppliers, at least in terms pursuant to paragraph 2
administered electricity market participant at the respective operator's transmission and distribution system
request to contract for electricity transmission or distribution of electricity
with appurtenances pursuant to Annex no. 1 or 2
to this decree, and it

A) new supplier if the electricity supply will be realized on the basis
contract under § 7 para. 1 point. d) or under § 7 para. 1 point. a) point
2

B) another electricity market participant, if the electricity supply
implemented under other contracts.

(6) Request for contracts for electricity transmission or distribution of electricity
referred to in paragraph 5 is not served if such a contract between the parties concerned
electricity market is already closed.

(7) In the case of the first change suppliers already connected with the transfer
place of electricity generating plant or point of an end customer, which
was connected to the transmission or distribution system after January 1, 2002, and the final customer
already has an offtake agreement concluded instead of
electricity transmission or distribution of electricity, given market participant
relevant electricity transmission or distribution system
application for registration of transfer or supply points
later than the deadlines by paragraph 2.

(8) Prior to the first change of supplier, but not later than 3 working days from the date of delivery
request to conclude a connection agreement under paragraph 2
contract for transmission or distribution of electricity in accordance with paragraph 5, or complete
application for registration of supply point under paragraph 7
registers the transmission or distribution system operator with
market supply points of the electricity market participant.

(9) The transmission or distribution system enters into a
electricity transmission or distribution of electricity within 3 working
days of receipt of a complete application under paragraph 5.

(10) Prior to switching suppliers, at least four working days after the deadlines
pursuant to paragraph 2 shall conclude the electricity market participant a new supplier
electricity supply contract. By the same date given by the new supplier
market operator the request of any modifications to the supplier, which contains the following information from
contract:

A) the identification and registration number of the new supplier,

B) the type of contract for the supply of electricity, the date from which the supply is effected
(the "effective date of the change of supplier") and duration
contract

C) the supplier's obligation to assume responsibility for Deviations participant
electricity market or consent cleared entity responsible for
difference as supply points for which the delivery was made,

D) list and identification of supply points.

(11) No later than one business day after the request under paragraph 10
forward market operator request for execution of supplier change
operator of the transmission system operators or relevant
distribution systems, which are supply points market participant
electricity connected. The market operator simultaneously transmit data from the contract in the range
under paragraph 10.

(12) If the data transmitted pursuant to paragraph 11 are complete, the operator may
transmission or distribution system supplier change
refuse.

(13) Refusal pursuant to paragraph 12, including the reasons report
system operator of the relevant market operator and market operator then
existing suppliers and contractors who demanded change, and it
within 2 working days after handover request for change of supplier
market operator respective system operator.

(14) within 2 working days of the request for change of supplier
respective system operator registers the transmission
or distribution system to which the supply point is market participant
electricity is connected, change supplier, it assigning supply point
participant of the electricity market to new suppliers with an effective date changes

Contractor pursuant to paragraph 15. Within two working days after receipt of the request
to switch suppliers report the transmission or distribution system
registered supplier change to the market operator and market operator
then the previous and the new supplier. Registering
changes in the number of suppliers with the effective date in accordance with paragraph 15 report, the market operator
also the subject of settlement, which took over the supply point
responsibility for imbalance.

(15) registered supplier change takes effect

A) the first trading hour of the first day of the month for market participants
electricity offtake points with measurement type A or B in the case of changes
suppliers mentioned in paragraph 1. a) and b)

B) the date of change in the request for a change of supplier, which is determined
10 working days after registration of the change of supplier
market participants electricity supply points with type C metering, where the
changes in vendor referred to in paragraph 1. a)
electricity market participants with type C metering can occur once every half
year, except for changing the supplier of last resort for another
supplier in case pursuant to § 12a Par. 6 Energy Act or
changes over to a supplier of last resort.

(16) The effective date of the change of supplier performs the transmission or distribution system
reading under a special law, which
down details of electricity metering and technical data
^ 1), in the case of supply points type C metering provides state
measuring device as described in paragraphs 17 and recorded data then sends
market operator. The market operator such data without undue delay transmit
previous suppliers to re-calculate and settlement of obligations. After
effectivities vendor market operator passes the new
supplier of data on the actual quantities of electricity under a special legal regulation
^ 1). In the case of transfer points of power plants with
under this paragraph shall proceed accordingly.

(17) Determination of the status of the measuring device for measuring the supply points with type C
performed the DSO reading on the effective date
supplier change or estimate the state of the measuring device on the effective date
change suppliers based on the assigned recalculated
chart type and the last current projected annual electricity consumption or on the basis of mutually agreed
readings made by new supplier or
electricity market participant on the effective date of the change of supplier.
Thus determined value passes DSO
market operator within 10 working days from the effective date of the change
supplier.

(18) In the event that this is the first change of electricity supplier
final customers whose equipment is connected to the distribution system
registers simultaneously
operator of the respective distribution system and delivery points or the aggregate of delivery points all plants
electricity connected to the distribution system.

(19) sending a request for execution of supplier change, the data required for registration
point of use, registration of end customers
takes place in the form of electronic messages in a communications environment defined
market operator. Messages are relevant actor in the electricity market
sent in the format defined by the market operator.

23) § 12a Par. 1 of the Energy Act.

24) § 28 par. 2 point. i) of the Energy Act. ".

31. Under § 31 the following § 31a, including the heading reads:

" § 31a

The first delivery of electricity to the newly established supply point

(1) Not later than 30 calendar days prior to the requested date of commencement
transmission or distribution of electricity shall electricity market participant,
which has a contract for connection to the appropriate operator
transmission or distribution system a request for
electricity transmission or distribution of electricity under § 5 para. 2,

A) the supplier if the electricity supply realized on the basis
contract under § 7 para. 1 point. d) or under § 7 para. 1 point. a) point
2

B) other participant in the electricity market, where supply of electricity
held under a contract; while the market participant
inform the operator of the electricity transmission or distribution system
which vendor will supply the newly established outlet.


(2) In the event that new supply point will deliver supplier
which is not part of a vertically integrated company whose
part of the distribution system operator, to which the new
supply point is connected, register
transmission or distribution system supply point for the market operator within 10 working
days of receipt of a complete application pursuant to paragraph 1

(3) Not later than four working days prior to the transmission or distribution of electricity
closes the electricity market participant and supplier
contract for electricity supply.

(4) In the event that new supply point will deliver supplier
which is not part of a vertically integrated company whose
part of the distribution system operator, to which the new
supply point is connected, served supplier no later than four working days before the start
transmission or distribution of electricity market operator
request for initiation of deliveries to the supply point (hereinafter referred to as "start
deliveries"), which contains the following data from the concluded agreement: | ||
A) the identification and registration number of the supplier,

B) the type of contract for the supply of electricity, the date from which the supply is
take place, and duration of the contract,

C) the supplier's obligation to assume responsibility for Deviations participant
electricity market or the consent of the subject of settlement with
taking over responsibility for deviation for supply points for which delivery will be carried
,

D) identification outlet.

(5) Not later than one business day after the request under paragraph 4 passes
market operator request for initiation of delivery to the transmission system or the relevant
DSOs to
which will supply points electricity market participant attached.
Market operator simultaneously transmit data from the contract to the extent specified in paragraph 4.


(6) If the data transmitted pursuant to paragraph 5 is complete, the operator may
transmission or distribution system launch supplies
refuse. Including the reasons for the rejection report
operator of the respective system operator and market operator then market suppliers, and
it within 2 working days of the request to initiate the delivery
market operator respective system operator.

(7) Within two working days of the request to initiate deliveries under paragraph 4
respective system operator registers
operator of the transmission or distribution system to which the supply point
electricity market participant is connected, contractors and this assignment
supply point electricity market participant to suppliers with the date of effectiveness
initiating deliveries under paragraph 8. Within two working days after receipt of the request
to initiate deliveries under paragraph 4
report the transmission or distribution system
start of supply to the market operator and market operator suppliers and then also subject
settlement, which took over the supply point of responsibility for imbalance.

(8) Registering initiating deliveries under paragraph 7
becomes effective on the date of commencement of transmission or distribution.

(9) Requests for initiating deliveries under paragraph 4, the data required for registration
supply points are sent via electronic messaging
communication environment defined by the market operator.
Messages are relevant actor in the electricity market
sent in a format defined by the market operator. ".

32. In § 32 at the end of paragraph 2 sentence" Bill
supply or distribution of electricity final customers whose electricity consumption is carried out
voltage to low voltage and the supply point
is equipped with type C metering is carried out at least once a year. ".

33rd in § 32 paragraph 3 reads:

"(3) the distribution system operator sends via
market after the end of the calendar month to 18.00
fifth working day of the following month, the electricity market participants for their
customers who used the the right to change supplier and whose offtake
places are equipped with metering type a or type B metering, except
supply points with type B metering connected to the low voltage
, the data needed for settlement of payments under paragraph 1 or 2. From
first April 2007 sent to the DSO such data and
for customers who have exercised the right to change supplier and whose offtake

Site is equipped with type B metering and connected to the low voltage level.
Method of data transmission shall be negotiated in the contract on the transfer of technical data
^ 4). Data required for settlement of payments under paragraph 1 or 2
are listed in the business conditions of the market operator. ".

34th in § 32 paragraph 7 reads:

" (7) In the event the electricity market participant who has concluded a framework agreement
under § 5 para. 4, sends the bill before receiving
supplies including date of 31 December to the distribution system
customers own readings on 31 December, the DSO
approves sent to customers own readings or communicate electricity market participants
reasons for their rejection within 30 calendar days after they are sent.
Reconciled customers own readings are used for billing electricity distribution
.. "

35th in § 32 paragraph 8 reads:

" (8) In the event that the customer is in category D
recognized advance payments for distribution and supply of electricity, the total amount may be
greater than 100% of the payments corresponding to the consumption of the previous billing period comparable
assuming preserving the value of reserved capacity
or nominal current of the main belay
element before the meter, unless the parties agree otherwise. This provision does not apply to customers
electricity consuming mode
supplier of last resort. ".

36th in § 32, paragraphs 9-12 deleted.

37th in § 33 paragraph. 1, the word "twentieth" is replaced by "the fifteenth."

38th in Annex no. 3 at the end of paragraph 2 sentence "
the average consumption of electricity provided by the Office, which applies throughout the
calendar year, the market operator in a manner allowing remote access
later than three calendar months prior to the first business day of the calendar year
.. "

39th Annex no. 4 reads:

"Annex no. 4 to Decree no. 541/2005.

Classes typical supply


----------------------------------------------- ------------------------------------------
Class Type Solid Features sampling distribution prices
according to the final price
customer decision Office
-------------------------------------------- ---------------------------------------------
1 Customer - consumption of electricity without heat recovery - C01D, C02d, C03d
Category C
--------------------------------------------- --------------------------------------------
2 Customer - sampling with storage appliance - C25D, C26d, C35d
Category C - taking a hybrid heating
---------------------------------------- ------------------------------------------------- | 3 || Customer - taking a direct electric heating system - C45d, C55d, C56d
Category C - taking heat pump
---------------------------------------- ------------------------------------------------- | 4 || Customer - consumption of electricity without heat recovery - D01d, D02d, D61d
Category D
--------------------------------------------- -------------------------------------------- 5
Customer - sampling with storage appliance - D25D, D26d
Category D
--------------------------------------------- -------------------------------------------- 6
Customer - collection of hybrid heating - D35d
Category D
--------------------------------------------- --------------------------------------------
7 Customer - taking a direct electric heating system - D45d, D55d, D56d
Category D - taking the heat pump
---------------------------------------- ------------------------------------------------- | 8 || Customer - consumption for public lighting - C62d
Category C
--------------------------------------------- --------------------------------------------

Assigning a class diagram type to the existing supply points
performed the DSO under the current tariff and the
Annex. ".

40th after Annex no. 4 the following new Annex no. 4 which reads:

"Annex no. 4 to Decree no. 541/2005.

Categorization of end customers

For the purposes of the organization of the electricity market to end customers
divided into the following categories:

A) Category A purchaser - customer whose supply point is connected to the transmission system
or customer whose supply point is connected to
distribution system with voltage between phases greater than 52 kV,


B) the buyer category B - customer whose supply point is connected
to the grid with voltage between phases from 1 kV up to 52 kV,

C) category C customer - the customer that the customer does not
category A, B or D

D) category D customer - an individual whose supply point is
connected to the grid with voltage between phases up to 1 kV and that
off electricity to meet her personal needs related to housing or
personal needs of members of his household;
per subscriber category D is regarded as a natural or legal person within the scope of the collection
electricity only for the management and operation of the building's common areas
used jointly by the owners or users of flats
.. "|| |
41st Annex no. 5 reads:

"Annex no. 5 to Decree no. 541/2005.

Method for determining the settlement price

(1) Price delivered a positive control for energy suppliers regulatory
power down mode and offer prices is equal to the offer price
positive regulating energy supplied to the blocks providing support services or
provided on the balancing market with regulating energy.

(2) The price for negative regulating energy supplied to the supplier
regulatory power down mode and offer prices is equal to the offer price
negative regulating energy supplied to the blocks providing support services or
provided on the balancing market with regulating energy.

(3) Rate positive and negative regulating energy supplied by units that had
in the business class only secondary control activated, down
Office's price decision.

(4) If in the respective trading hour procuring electricity according to § 24 paragraph.
2 settlement price is determined by the market operator for each trading hour
follows:

A) if the system imbalance is negative or zero, the settlement price
Highest price of electricity according to § 24 para. 2
supplied at this trading hour and paid providers of electricity market operator;
If so determined price lower than the price fixed price decision
Office, then the price set by the

B) if the system imbalance is positive, the highest settlement price
achieved price of electricity according to § 24 para. 2 supplied at this trading
hour to compensate for the positive system imbalance and paid by the operator
market electricity provider ; if so determined price lower than the price fixed
Office's price decision, then the price set by the Office.

(5) In the event that for any trading hour not procure any
electricity according to § 24 para. 2, then the settlement price according to price
Office's decision. ".

42nd Annex no. 6 reads:

"Annex no. 6 to Decree no. 541/2005.
MODEL


Monthly report on production of electricity from renewable sources

Per month / year: the name of the plant ^ 1):

---------------------------- ------------------- -----------

---------------------------- ------------------- -----------

----------------------------------------------- ---------------------------
name and any supplement or business name or manufacturer:

Identification number:
----------------------------------------- ---------------------------------
Address factories ^ 1)
----- -------------------------------------------------- -------------------
license number:
---------------------- -------------------------------------------------- -
Type of renewable resource:
--------------------------------------
------------------------------------ Date of commissioning:
--- -------------------------------------------------- ---------------------
biomass categories: ^ 2)
----------------- -------------------------------------------------- -------

----------------------------------------------- ---------------------------------
item No. name unit per month from the beginning of data
| || ------------------------------------------------ --------------------------------
1 Installed electrical capacity MW X -----------------------------------------
---------------------------------------
2 Clamp electricity generation, 3) ^ 4) MWh
----------------------------------- ---------------------------------------------
3 Technological own consumption MWh
electricity, 3) ^ 5)
--------------------------------------- -----------------------------------------
4 Other private consumption MWh
electricity, 3) ^ 6)

----------------------------------------------- ---------------------------------
5 supply of electricity to the local MWh
or regional distribution
system or to transfer
System mode bonuses ^ 3)
---------------------------------------- ----------------------------------------
6 Supply of electricity to the regional MWh
distribution system
to the transmission system under
purchase prices ^ 3)
------------------------------------------ --------------------------------------
7 The voltage at the delivery point kV
----------------------------------------- ---------------------------------------
8 marking the transfer point
according to the contract to connect -------------------------------------------
-------------------------------------
9 The total amount claimed CZK
(Green bonuses) -------------------------------------------
-------------------------------------
10 Total amount claimed CZK
(Redemption price) -------------------------------------------
-------------------------------------

I declare that all the above information is true and correct.

The day ....... ...... ................................
Name and surname producer /
Name and surname of the person or persons
authorized to act on behalf of the manufacturer

................................
signature



Notes:

1) The name and address of the production of electricity in accordance with the decision
a license to produce electricity.

2) Completion required for energy use pure biomass.
In the case of clean-burning biomass gives all categories of biomass
under Decree no. 502/2005 Coll., On methods for reporting
amount of electricity in co-combustion of biomass and non-renewable resources.

3) In the case of biomass burning more categories in the respective calendar month
states in detail the structure of production, respectively. consumption and supply of
breakdown for each category of biomass under Decree no. 502/2005
Coll., on methods for reporting electricity quantities joint
biomass and non-renewable resources.

4) Total electricity production measured at the generator terminals
installed at the factory.

5) Electricity consumption for electricity generation for electricity production
or electricity and heat in the main production equipment and auxiliary
operations that are directly related to production, including distribution losses,
own consumption and losses step-up transformers for supply to
distribution or transmission system, if the billing metering
installed on their primary side.

6) Electricity from renewable resources, which is subject to a right to payment of green bonus
under § 4 para. 16 of Law no. 180/2005 Coll., On
promotion of electricity from renewable energy sources and amending
some laws (Act on support of renewable resources., and
which is efficiently used by the manufacturer or another natural or legal person
without the use of regional distribution or transmission system
.

43. Appendix no. 6, the following new annexes Nos. 7 and 8 are added:

"Annex no. 7 to Decree no. 541/2005.

data made available by the market operator for each region of load profiles
-----------------------------------------------------------------------------------------------------
NO. Item Role Type Unit of measurement Accessed

--------------------------------- -------------------------------------------------- -
first sum of deliveries in the transfer of electricity supplied in the region A kWh
locations generating electricity load profiles
---------------------- --------------------------------------------------
------------- second sum of deliveries in the transfer of electricity supplied in the region B kWh
locations generating electricity load profiles
----------- -------------------------------------------------- ------------------------
third Sum supplies in the transfer of electricity supplied in the region C kWh
locations generating electricity load profiles
-------------------------------------------------- -----------------------------------
fourth sum withdrawals in the transfer of electricity over the region, A kWh
locations generating electricity load profiles
--------------------------------------- ----------------------------------------------

Fifth Purse donations in the transfer of electricity over the region B kWh
locations of power plants type diagrams
------------------------------------------ -------------------------------------------
6th Purse donations in the transfer of electricity over the region C kWh
locations of power plants type diagrams
------------------------------------------ -------------------------------------------
7th The sum of deliveries in the transfer of electricity supplied in the region A kWh
locations of base load profiles
------------------------------------------ -------------------------------------------
8th The sum of deliveries in the transfer of electricity supplied in the region B kWh
locations of base load profiles
------------------------------------------ -------------------------------------------
9th The sum of deliveries in the transfer of electricity supplied in the region in terms of kWh C
locations of base load profiles identical
----------------------------------------- -------------------------------------------- with deadlines for
10th Purse donations in the transfer of electricity over the region, A kWh settlement
points between systems of typical deviations
----------------------------------------- -------------------------------------------- according to § 25 || | 11th Purse donations in the transfer of electricity over the region B kWh paragraph. 110
locations of base load profiles
------------------------------------------ -------------------------------------------
12th Purse donations in the transfer of electricity over the region C kWh
locations of base load profiles
------------------------------------------ -------------------------------------------
13th Sum withdrawals in the sampling
locations including the sum withdrawals News / kWh electricity consumption A
at delivery points manufactories
electricity (ie. including 4th)
--------------------------------------- ----------------------------------------------
14 . Sum withdrawals in the sampling
locations including the sum withdrawals News / kWh electricity consumption B
at delivery points manufactories
electricity (ie. including the fifth)
--------------------------------------- ----------------------------------------------
15 . Sum withdrawals in the sampling
locations including the sum withdrawals News / kWh electricity consumption C
at delivery points manufactories
electricity (ie. including the 6th)
--------------------------------------- ----------------------------------------------
16 . Purse positive balancing electricity supply kWh
Energy
---------------------------------------------- ---------------------------------------
17th Sum of negative regulating electricity consumption kWh
Energy
---------------------------------------------- ---------------------------------------
18th losses kWh
-----------------------------------------------------------------------------------------------------



Annex no. 8 of Decree no. 541/2005.

Data made available by the market operator for each local distribution system

-----------------------------------------------------------------------------------------------------
NO. Item Role Type Unit Accessed
measurement
-----------------------------------------------------------------------------------------------------
First The sum of deliveries in the transfer of electricity supplied to the local A kWh
locations of power plants distribution system
without the regulatory power
-------------------------------------------- -----------------------------------------
second The sum of deliveries in the transfer of electricity supplied to the local B kWh
locations of power plants distribution system
------------------------------------------ -------------------------------------------
third The sum of deliveries in the transfer of electricity supplied to the local C kWh
locations of power plants distribution system
------------------------------------------ -------------------------------------------
fourth Purse donations at delivery Electricity collected from the local A kWh
locations of power plants distribution system
------------------------------------------ -------------------------------------------
fifth Purse donations at delivery Electricity collected from the local B kWh
locations of power plants distribution system
------------------------------------------ -------------------------------------------

6th Purse donations at delivery Electricity collected from the local C kWh
locations of power plants distribution system
------------------------------------------ -------------------------------------------
7th The sum of deliveries in the transfer of electricity supplied to the local A kWh
points between systems distribution system
------------------------------------------ -------------------------------------------
8th The sum of deliveries in the transfer of electricity supplied to the local B kWh
points between systems distribution system
------------------------------------------ -------------------------------------------
9th The sum of deliveries in the transfer of electricity supplied to the local C kWh in terms
points between systems distribution system identical
----------------------------------------- -------------------------------------------- with deadlines for
10th Purse donations at delivery Electricity collected from local kWh A settlement
points between systems distribution system deviations
----------------------------------------- -------------------------------------------- according to § 25 || | 11th Purse donations at delivery Electricity collected from the local B kWh paragraph. 110
points between systems distribution system
------------------------------------------ -------------------------------------------
12th Purse donations at delivery Electricity collected from the local C kWh
points between systems distribution system
------------------------------------------ -------------------------------------------
13th Sum withdrawals in the sampling
locations including the sum withdrawals News / kWh electricity consumption A
at delivery points manufactories
electricity (ie. including 4th)
--------------------------------------- ----------------------------------------------
14 . Sum withdrawals in the sampling
locations including the sum withdrawals News / kWh electricity consumption B
at delivery points manufactories
electricity (ie. including the fifth)
--------------------------------------- ----------------------------------------------
15 . Sum withdrawals in the sampling
locations including the sum withdrawals News / kWh electricity consumption C
at delivery points manufactories
electricity (ie. including the 6th)
--------------------------------------- ----------------------------------------------
16 . Purse positive balancing electricity supply kWh
Energy
---------------------------------------------- ---------------------------------------
17th Sum of negative regulating electricity consumption kWh
Energy
---------------------------------------------- ---------------------------------------
18th Loss or imputation kWh
for local distribution
system "
----------------------------------------------------------------------------------------------------- Article II





Effectiveness This Decree shall take effect on 1 January 2007, except
provisions of Article I, para. 4 and 28, which come into effect
1 July 2007, the provisions of Article I, para. 5, which takes effect on July 1
2008 and the provisions of Article I, para. 13 and 34, which come into effect on the day of its publication
.