82/2011 Sb.



DECREE



of 17 May. March 2011



for the measurement of electricity and how the determination of damages against unauthorized

subscription delivery, unauthorized, unauthorized transfer or unauthorized

distribution of electricity



476/2012: Sb.



The Ministry of industry and trade shall be determined according to section 98, para. 1 (b). and)

Act No. 458/2000 Coll., on conditions for business and public administration

in the energy sectors and on amendments to certain acts (the energy

Act), as amended by Act No. 158/2009 Coll.:



§ 1



Ways to measure electricity



(1) ensuring the electricity metering installation, operation, service,

inspection and maintenance of measuring devices, including devices of mass

remote control, reading, processing, transmission and storage of data

measurement.



(2) for the measurement of electricity and the evaluation of the data is used



and measurement of the type A,) which is a continuous measurement with remote transmission of the day

data, and continuous recording of medium power values for measuring interval

measuring equipment, directly or



(b) type B) measurement, which is continuous measurement with remote other than

the daily transfer of information, and continuous recording of medium power values for

the measuring interval is conducted directly by the measuring equipment; If it is not possible

to make the remote transmission of data due to technical reasons, it is possible to transfer

perform data in any other way, or



c) measurement type, which is the measurement with remote data transfer

It is not the measurement type, and even the measurement of type B; If it is not possible to make

remote transmission of data due to technical reasons, it is possible to transfer data

do this in a different way, or



d) measurement of type C, which is the other measurement.



(3) measurement of electricity is broken down into



and) direct measurement, when the meter goes through all of the measured electricity and

instrument transformers are not used,



(b)), when indirect measurement is the meter used in connection with measuring

current transformers, which passes through all the measured electricity, and

possibly even with measuring voltage transformers; According to the parties

the transformer, to which they are connected, the measuring transformers

measurements divided into primary (on the side of higher voltage) or secondary

(on the side of lower voltage) measurement.



§ 2



The location of the measurement devices



(1) the measurement type and must be measured using the electricity in the



and pass-through between) transmission system and foreign

systems,



(b)) between the forward transmission grid and distribution

system with a voltage higher than 1 kV,



(c)) with the collection of customer sampling locations of electricity from the transmission

system,



d) transfer between locations with grids

voltage higher than 1 kV,



e) forward places electricity generation facilities with voltage higher than 1 kV

directly connected to the transmission system or distribution system,



(f) sampling points with the customer) collection of the electricity from the distribution

system with a voltage higher than 52 kV,



(g)) of the sampling locations of customers with the procurement of electricity from the distribution

system voltage between 1 kV up to 52 kV inclusive and with reserved input

over 250 kW,



h) sampling locations of customers with the procurement of electricity from the distribution

system voltage between 1 kV up to 52 kV inclusive and with reserved input

over 400 kW.



(2) at least by measuring type B must be measured using the electricity in the



and transfer points between) distribution systems with

voltage up to 1 kV with indirect measurements,



(b) the transfer of electricity generating stations locations) with the voltage up to 1 kV direct

connected to a distribution system,



(c)) with the collection of customer sampling locations of electricity from the distribution

system voltage between 1 kV up to 52 kV inclusive and reserved up to

250 kW including,



(d)) with the collection of customer sampling locations of electricity from the distribution

system with the voltage up to 1 kV with indirect measurements,



(e)) with the collection of customer locations, collecting electricity from the distribution

system voltage between 1 kV up to 52 kV inclusive and reserved up to

400 kW including,



(f) sampling points with the customer) collection of the electricity from the distribution

system with the voltage up to 1 kV with a reserved power of 100 kW or with

the main element of a net shall stream from 200, and, from the first

changes to the electricity supplier,



g) plants of electricity or for each of the sources of electricity

the production plants of electricity connected to the transmission system or distribution

system through other production plants of electricity.



(3) electricity in forward locations and sampling sites according to

paragraph 2 can be measured by measuring the type and.



(4) the measurement type, with electricity can be measured in sampling locations

customers with the procurement of electricity from the grid with a voltage up to 1 kV.



(5) at least the measurement type (C), unless the electricity consumption by the

paragraph 6 shall be measured using the electricity in the



and the sampling locations of customers with) the procurement of electricity from the distribution

system, which are not referred to in paragraphs 1 to 4,



(b)) with the collection of customer sampling locations of electricity from the distribution

system, pass-through between the distribution systems and

transfer locations connected to the producers of electricity distribution

system, or to load the customer or into a pass-through space

other production plants of electricity where it is not technically and economically possible

install the measurements referred to in paragraphs 1 to 4.



(6) in the event that the connection is in the contract established electricity consumption

without measuring equipment, the customer may subscribe to electricity without measuring

the device, but not to the reserved input 1 kW in a single sampling

the spot; alarms and security devices of railway

the path may have a higher power consumption. the booked



(7) For the application of the support of electricity from renewable energy sources or

of secondary energy sources in the form of the annual green bonus

provided by the manufacturer of electricity for the plant's electricity with installed power

up to 5 kW, including separate measurement of electricity produced at least by measuring

type C in the case of the application of the per-hour green bonus ensures

electricity metering the electricity produced by the measurement type (B).



§ 3



Electricity metering



(1) for the measurement of type and is



Basic measuring interval) 1 if; for the first quarter is

the beginning of the set on time and end on time 00:00:00 00:15:00,



(b)) the basic evaluation interval is 1 hour; in the first hour of the beginning of the

set on time and end on time 00:00:00 01:00:00 calendar day,



(c)) the basic interval for processing and transmission of measured data in the context

the measuring device 1 calendar day.



(2) for the measurement of type B is



Basic measuring interval) 1 if; for the first quarter is

the beginning of the set on time and end on time 00:00:00 00:15:00,



(b)) the basic evaluation interval is 1 hour; in the first hour of the beginning of the

set on time and end on time 00:00:00 01:00:00 calendar day,



(c)) the basic interval for processing and transmission of measured data in the context

measuring equipment for 1 month.



(3) the measurement of type is the base period for processing and transmission of

the measuring device measured data for 1 month.



(4) for the measurement of type C is the processing and transmission of data is carried out at least

Once a year.



Details of electricity metering



§ 4



(1) data from the measurement of electricity market participants with electricity to be transmitted in

kWh, kW, kVAr, kVArh or in MWh, MVArh MW, MVAr, broken down by

tariffs.



(2) Data from the measurement of electricity are



and) data recorded by the measuring device, where applicable, calculated on the basis of

data from the measuring device,



b) information forwarded to the customer or producer of electricity operator

the transmission system operator or distribution system operator, if the amount of

consumption or supply of electricity at a given point or hub

the site corresponds to the nature of consumption or supply of electricity and over

the consumption of the previous period (hereinafter referred to as "samoodečty"),



(c) data obtained by calculation), an estimated or mutual

by consenting to the transmission system operator or the operator

the distribution system with the customer by the manufacturer or

other distribution system operator.



(3) the calculation of spare or consumption data electricity supply and

the progress demonstrable failure of the measuring device, when you repair

bad or missing values makes the operator

the transmission system operator or distribution system operator on the basis of

authorized service or log messages about the failure of the measuring device

According to the amount of electricity consumption in the previous comparable period when

the comparable nature of electricity, electricity consumption was

properly measured, or additionally according to the amount of consumption, or supply of electricity

recorded on the basis of the control of reading in the following period.



(4) the Replacement or consumption data electricity supply when the unavailability of

the data recorded by the measuring device provides for the operator of a transmission

system operator or distribution system operator an estimated on the basis of

data obtained from measurements in the previous comparable period, or from

samoodečtu or additionally according to the amount of consumption, or supply of electricity


identified in the following for the same period on the basis of the inspection

of reading.



(5) for the estimation of electricity consumption for the measurement of type C uses the assigned

equivalents of the type of delivery, the number of evaluated diagram

calendar days and the amount of the most recent annual consumption of electricity. Maximum

number of estimates for the Bill collection or supply of electricity are 2

successive estimates.



(6) Samoodečty and estimates of consumption of electricity for billing can be done

a maximum of three times in a row.



(7) the determination of the electricity consumption data for the measurement of type C to date changes

regulated electricity prices performs



and) the distribution system operator



1. on the basis of the previous known state of reading of the measuring device and

during the consumption of electricity according to an assigned type diagram supply,

or



2. evenly over the part proportional to the length of the period from the date of the previous

billing meter reading until 31 December 2006. December and from 1. January to the date of the next

billing meter reading, or



b) electricity market samoodečtem.



(8) when you change electricity suppliers, the distribution system operator,

responsibilities, a producer of electricity, or customer, when you change the tariff plan

and when the change made on the measuring device must be always carried out

processing of data from the measurement of electricity.



§ 5



(1) the direction of the flow of electricity to the appropriate sampling or a pass-through space

the investigational electricity market participant is considered to be positive. The direction of the

the flow of electricity from the sampling or a pass-through space

the investigational electricity market participant is considered to be negative.



(2) when an asymmetric flow in three-phase power system

evaluate directions of energy flow in the various stages of the newly established

or reconstructed offtake points.



(3) the Reactive energy is identified as positive, as for the phase angle between the

current and voltage applies 08 < j < 1808. Reactive energy is marked as

negative, while for the phase angle between current and voltage applies 1808 < j <

3608.



(4) the measurement and transmission of the actual and the replacement values shall be carried out in

winter or summer time. On the last day when you change to winter time on the

summer is 23hodinový day, the first day when changing daylight saving time to winter is

25hodinový day.



(5) the tolerance headquartered between odečtovou and real time is

a maximum of +/-5 seconds.



(6) for the type and the measurement is between the measuring device and the odečtovou headquarters

allowed deviation of up to +/-5 seconds.



(7) for the measurement of type B is between the measuring device and the odečtovou headquarters

allowed deviation of up to +/-1 minute.



(8) for the measurement of type S is between the measuring device and the odečtovou headquarters

allowed deviation of +/-3 minutes.



(9) for the measurement of type C with tolerance limits.



§ 6



The conditions for electricity metering



(1) part of the measuring device, which is mounted at the measuring point,

located in the point of the customer or in the production of electricity or for

distribution system operator as close as possible to the point of předávacímu

the transmission system operator or distribution

the system. For new or reconstructed offtake points or

forward places the location of the measuring equipment, the competent

the system operator. For reconstruction for this purpose shall be deemed to

replacing the elektroměrového Cabinet or exchange of the power supply lead.



(2) in the event of differences in the location of a pass-through space and measuring space

for details of the measurement readings shall be considered a reduced or increased by

the values specified in the contract or in the contract about connection, about the distribution of

electricity. If the subscription or the supply of electricity measured on

the secondary side of the power transformer and the connection agreement is not

or a contract for the distribution of electricity unless otherwise specified, the data from the

measurements considered measured data in case of elevated or reduced

in the case of the supply of electricity on the basis of the appropriate values of the price

the decision of the Energy Regulatory Office.



(3) the continuous measurement is measured and reactive electricity delivered subscriptions.

For continuous measurement in forward locations between the distribution system and

manufacturer of electricity is measured and reactive electricity supplied and subscriptions in

Depending on the direction of the flow of electricity to operate.



(4) in the case of use of the meter with multiple tariffs for their switching

switching element used or the internal time base of the meter.



(5) on application by the manufacturer or the customer, and if it

measurement allows the transmission system operator shall provide or

the distribution system operator electricity producer or customer

Pulse outputs from the 24-hour measurement directly in the delivery location or in the

point of use. Provision of measured values by the operator

distribution system using other communication interfaces of the meter

It is not electricity producers, or to a customer without the consent of the operator

the transmission system operator or distribution system operator.



(6) in the delivery of electricity production site with a voltage up to 1 kV connected to

the distribution system with the newly installed or the changing of the measurement

evaluates the flow direction of electricity devices in various stages.



§ 7



The installation of the measuring equipment



(1) installation, removal or replacement of a part of the measuring device on the delivery

site or at the point of use, which does not own the operator of a transmission

system operator or distribution system operator must be in advance

agreed to by the transmission system operator or the operator

the distribution system.



(2) removal or replacement of measuring devices is performed on exit

electricity, electricity supply interruption due to unauthorized

subscription or unauthorized distribution of electricity, finding fault in the

measuring equipment, periodic verification of the measuring device, when you change the

plan or when verifying the accuracy of measurement at the request of the participant

of the electricity market.



(3) the removal or exchange of the measuring device must be the affected party

the electricity market is informed. On the exchange of the measuring device for measuring

type C or type with measurement for official verification must be concerned

electricity market participant is informed in advance.



(4) in the case of a measuring device for the measurement of type C or type measurement with

demontovaného to verify the accuracy of the measurement or when the failure of the measuring

the device must be made demonstrable record balances the scales and

made clear and demonstrable identification of the measuring device, and

it within 60 days of exchanges or disassembly of the measuring device.



(5) the fault of the measuring apparatus shall be demonstrated by an authorized

service or Protocol on the failure of the measuring device fashioned

the transmission system operator, or the operator of a distribution

the system.



(6) the transmission system operator or the owner of the distribution

the system shall be based on a written request of the customer or manufacturer

electricity and for their participation of the measuring device and its control

the settings in the supply or delivery location.



§ 8



Transmission of the results of measurement of electricity and their storage



(1) measured data supply and electricity subscriptions for the measurement of type A and measurement

Type B are in the measuring devices in the supply and the delivery location kept

at least 40 days from the date of the dropper.



(2) data from the measurements necessary for the clearing of supplies and electricity subscriptions vek

and the true value of supply and consumption of electricity transmitted to the operator

the market for evaluation of deviations shall keep the transmission system operator

or the distribution system operator, which provides measurement, at least

36 months from the date of the dropper. The ways and terms of the transfer of data from the measurement

necessary for the clearing of supplies and electricity subscriptions and actual values

the supply and consumption of electricity transmitted to the market operator for the evaluation

the derogations provided by other legislation.



(3) the transmission system operator or the owner of the distribution

the system provides free of charge upon request to the authorised applicant, its

the information referred to in paragraph 4, within 6 working days of the following month,

manner allowing remote access. The transmission system operator

or the distribution system operator thus provides data for

the last 12 months.



(4) provided data from the measurement of electricity



and) distribution system operator are



1. for the measurement type, and type B values, the measurement of active power in kW,

reactive power in kVAr of inductive and capacitive reactive power in

kvar for measuring interval



2. to measure the type with values in kWh, energy



(b)) the transmission system operator are to measure the type and value

active power in MW for evaluation, resolution interval values is on 3

decimal places.



§ 9



Method of determining damages against unauthorized collection, delivery,

the transmission and distribution of electricity, or



(1) an unauthorized collection of electricity shall determine the quantity actually

unduly electricity transmission system operator or

the distribution system operator based on the measured or otherwise

identified data on unauthorized sampling the demonstrable effects of electricity.




(2) in cases where the quantities actually unduly could not be determined

electricity referred to in paragraph 1, provides for the operator of a transmission

system operator or distribution system operator the amount unduly

electricity for the determination of the amount of compensation calculated according to the

paragraphs 3 to 8.



(3) in the case of unauthorized sampling of electricity from the network, especially the high voltage,

very high voltage or high voltage to determine the

the electrical input of the it value reserved input agreed in

the contract for the connection; If you cannot use the value of the reserved

wattage, electrical power consumption is the sum of the nominal performances

all transformers used in the point of use.



(4) in the case of unauthorized sampling of electricity from low-voltage networks for

the determination of the value of the electrical input of the technically achievable

nominal voltage 230 V multiplied by the number of phases, from which an unauthorized

electricity consumption took place, and the calculated value is multiplied by the



a) rated current of main circuit breaker electricity meter, or



(b) the fuse rated current) located in the main house fuse

Cabinet or in the main residential wired chassis lowered by one level.

Type series rated current values in the event of unauthorized

the connection before the main circuit breaker or



(c)) the current corresponding to the cross-section of the wires

allowing unauthorized electricity consumption, and only in the case that is not

possible to the electrical input power according to subparagraph (a)), or (b)).



(5) the amount of technically achievable electricity consumption per day in

unauthorized collection of electricity is calculated so that the amount of electrical

power consumption as calculated under paragraph 3 or 4 shall be multiplied by the time the use of 24

hours and uses the value of the power factor is equal to one.



(6) the value of the technically achievable electricity consumption for the duration of the

unauthorized subscription shall be fixed so that the amount of technically achievable

consumption of electricity per day, as calculated under paragraph 5, shall be multiplied by the

the number of days after which an unauthorized receiving electricity, he insisted. If

the transmission system operator or distribution system operator

does not detect the duration of unauthorized sampling of electricity, it is considered that the

unauthorized consumption of electricity insisted



and from the penultimate regular deduction) carried out for the purpose of

the clearing of the electricity consumption, with a maximum of 24 months subscription

low-voltage electricity from the network; automatic consumption of electricity is not in

that case considered the regular reading,



(b)) 24 months in the case of electricity networks, especially the high voltage, very

high voltage or high voltage.



(7) in the event that an unauthorized interference with the meter, from the

consumption of electricity calculated in accordance with paragraph 6, subtracts consumption

the measured electricity transmission system operator or

distribution system operator.



(8) the amount of electricity consumed illegally for the purposes of calculating the refund

damages for unauthorized subscription will be calculated as the difference between the value of

technically achievable electricity consumption for the period of unauthorized

electricity fixed pursuant to paragraph 6 and the value determined in accordance with

paragraph 7 in the case of unauthorized interference with the meter multiplied by the



and the coefficient of 0.2 for subscriptions) of electricity from low-voltage networks,



(b)) by a factor of 0.5 for electricity from the network particularly high

voltage, high voltage or high voltage.



(9) the amount of compensation shall be the valuation amount unduly

of electricity established pursuant to paragraph 1 or calculated in accordance with

paragraph 8 of the decision according to the prices of the price of the energy regulatory

the Office of the force at the time the finding of unauthorized sampling of electricity, and

the price of electricity consumed illegally is composed of



and energy prices) electricity that is appreciated by the fixed price

for clearing shipping variances positive regulating energy,



(b)) the price for the distribution of electricity; low voltage network at a rate of C 02d

or (D) according to the category electricity 02d,



c) prices for system services



(d)) prices on support for electricity from renewable sources, combined production

electricity and heat sources,



(e)) prices for clearing the market operator's activities,



(f)) of value added tax and electricity tax.



(10) the amount of damages for the unauthorized consumption of electricity can also be

establish a written agreement between the transmission system operator or

distribution system operator and a customer, or a person

should illegal electricity off benefit, or to such

the benefit involved. The compensation provided for in this way must not be

higher than the refund calculated in accordance with the preceding paragraphs.



(11) for the determination of the amount of damages in wrongful supply of electricity

the electricity system, unauthorized transmission of electricity or when

unauthorized distribution of electricity shall apply the provisions of paragraphs 1 to 9

by analogy. In the case of unauthorized supply of electricity for awards prizes for the

power electricity it's fixed price for the supply of a negative regulatory

energy.



(12) part of the damages incurred by the transmission system operator

or the distribution system operator is entitled to the reimbursement of

demonstrable necessary costs incurred to detect

unauthorized collection of electricity, unauthorized supply of electricity,

unauthorized transmission of electricity or the unauthorized distribution of electricity,

they interrupt and checking of the measuring device and any expert

opinions that are not included in the regulated electricity prices

or for the distribution of electricity.



§ 10



Minimum requirements for electricity meters and metering accuracy classes

Transformers



Minimum requirements for electricity meters and metering accuracy classes

Transformers are listed in annex 1 to this notice.



The scope and timing of the transmission of data to the market operator



section 10a



The transmission system operator, and transmission system operator

distribution system operators shall transmit to the market operator for the

processing and registration information on our sites, electricity, for which the

a future contract on the connection, or the connection agreement

and set your dates and conditions for the connection



and to issue State) authorizing the construction of production plants

the electricity Ministry and



(b)) message processing on future expected consumption of electricity and gas and

How to secure a balance between the supply and demand of electricity and

gas.



section 10b



(1) the operator of a transmission system operator or distribution

the system passes the market operator



and data on the production of electricity) to the extent provided for in annex 2 to this

the decree and the



(b) data on the makers of electricity) to be out of the market operator

evidence to be discarded.



(2) the operator of a transmission system operator or natural gas

distribution system passes the information about production and the market operator electricity

to the extent referred to in annex 3 to this Decree, if electricity production

will be connected to the gas network.



section 10 c



(2) the transmission system operator, and transmission system operator

distribution system operators shall update the data referred to in annex No.

2 and annex No. 3 to this Decree to the last day in the quarter

and forward is the market operator by the 15th. day of the following month.



§ 11



Transitional provision



Liquidated damages for unauthorized collection, supply, transfer or distribution of the

electricity, which occurred before the entry into force of this order, the

be assessed according to the existing legislation.



§ 12



Regulation (EEC)



Shall be deleted:



1. Decree No. 218/2001 Coll. laying down the details of the measurement

electricity and the transmission of technical data.



2. Decree No. 450/2003 Coll., amending Decree No. 218/2001 Coll.

laying down the details of the measurement of electricity and transmission of technical

of the data.



3. Decree No. 326/2005 Coll., amending Decree No. 218/2001 Coll.

laying down the details of the measurement of electricity and transmission of technical

data, as amended by Decree No. 450/2003 Coll.



4. sections 13 to 15, § 16 para. 1 and 3 of Decree No. 51/2006 Coll., on conditions for

connection to the electricity grid.



section 13 of the



The effectiveness of the



1. this Decree shall enter into force on 1 January 2000. April 2011, with the exception of

the provisions of § 2 (2). 1 (b). (g)) (a). 2 (a). (c)), and (d)) and § 5 para. 2,

that will become effective on 1 January 2004. January 2015.



2. the provisions of section 2 (2). 1 (b). (h)), and the provisions of § 2 (2). 2 (a). (e)), and

f) shall expire on 31 December 2007. December 2014.



Minister:



Ing. Sri k v r.



Annex 1



Minimum requirements for electricity meters and metering accuracy classes

Transformers

------------------------------------------------------------- ----------------------------------------------------

Measuring site Measuring transformers Measuring Meter the meter under regulation

current transformers of the Government No. 464/2005 Coll.

voltage

------------------------------------------------------------- ----------------------------------------------------

Voltage up to 1kV active energy active energy


direct measurement of the accuracy class 2-class and

reactive energy

accuracy class 3

------------------------------------------------------------- ----------------------------------------------------

Voltage up to 1kV-active energy active energy

indirect measurements with accuracy class 0.5 1 class B

reactive energy

accuracy class 2

------------------------------------------------------------- ----------------------------------------------------

Voltage active energy active energy

from 1kV up to 52kV 0.5 0.5 with accuracy class 1 class B

indirect measurement of reactive energy

accuracy class 2

------------------------------------------------------------- ----------------------------------------------------

Voltage is higher than the energy illuminating 52kV active energy

0.2 0.2 0.5 with accuracy class class C

reactive energy

přesnoti class 1

------------------------------------------------------------- ----------------------------------------------------



Annex 2



Data on the production of electricity transmitted to the transmission system operator

or provozovatelemelektroenergetické distribution system



Part A-information about the production of electricity



(1) the identification of the production plants of electricity



and the name of the production plants of electricity)



(b) the production of electricity) identification number



(2) data on transmission system operators or the operators of the

the distribution system



and) identification of the transmission system operator or service provider.

the distribution system



(b)) in the database Identification číslovýrobny electricity operator

System



(c)) number of the network to which the connection of electricity production is expected



(3) for more information about the production of electricity



and the performance of electricity production) booked



b) Fuel



(c)) number, in which the cadastral territory assumes realization

production of electricity



d) Numbers of the parcels on which the implementation of electricity production



e) information about the switching station transmission system or distribution system, to

that assumes the upbringing of the electricity production performance



f) in the case of photovoltaic power stations for the production location information

roof construction or on open space



g) sampling and pass-through space EAN



(4) the anticipated dates in the preparation and implementation of electricity production



the date of signature of the Treaty) on future contract about connection



(b) the date of signature of the Treaty) of the connection



(c)), the term first parallel connection to the electricity grid



(d) the planned closure Date), if known



e) Dates of interruption and recovery operation, if known



(f)) in stations with an installed output of 30 kW release date of territorial

planning information on the conditions of issue of zoning and planning decision



g) in stations with installed power of 0.5 MW



1. The term opinion to EIA



2. the term of the grant of a State authorization for the construction of electricity production



3. The term of issue of zoning and planning decision



4. The term of issue of the integrated permit



5. term of building permit



6. Start of construction



7. Start trial operation



8. term of issue of the certificate of occupancy



Part B-information about the investor electricity production



(1) personally identifiable information



and investor Type)-a natural person or a natural person-non-entrepreneur

doing business or legal person



(b)) identification number in case that is a natural person

doing business or legal entity



(c)) date of birth in case that is a natural person



(d)) business firmav the case that this is a legal person



e) name and surname in the case that is a natural person

nonentrepreneurial natural person-entrepreneur



(f)) statutory authority in the case that this is a legal person



(2) the registered office or the address of the place of stay



and)



(b)) the municipality



(c)) Street



(d) the number and number) of the Guide



e) ZIP CODE



(3) the address for service



and Municipality)



(b)) Street



(c) the number and number) of the Guide



d) postal code



e) Email



f) phone



g) data mailbox



Part C-information about the network construction sites related with the connection factory

electricity to the electricity grid



(1) information about the construction



and network building identification)



(b)) name of the network construction



(c) a description of the network building)



(2) Implied terms in the preparation and implementation of network structures



and release) the term spatial planning information on the conditions of release

zoning and planning decision



(b)) the term opinion to EIA



(c)), the term release planning



(d) the building permit)



e) start of construction



(f)), the term connection of electricity production for test operation



g) start trial operation



h) Release Date of occupancy



Annex 3



Data on the production of electricity transmitted to the transmission system operator

or operator of the gas distribution system



Part A-information about the production of electricity



(1) details of the transmission system operator or operators

distribution system and gas consumption data



and) identification of the transmission system operator or service provider.

the distribution system



(b) the production of electricity) identification number in the database operator

the transmission system operator or distribution system operator



(c)) the number of the network to which the connection of electricity production is expected



(d)) the planned natural gas consumption



(2) terms in the preparation and implementation of electricity production



the date of signature of the Treaty) on future contract for connection to natural gas

System



(b) the date of signature of the Treaty) be connected to the gas system



c) expected date of connection to the gas network



Part B-information about the network construction sites related with the connection factory

electricity to the gas network



(1) information about the construction



and network building identification)



(b)) name of the network construction



(c) a description of the network building)



(2) Implied terms in the preparation and implementation of network structures



and release) the term spatial planning information on the conditions of release

zoning and planning decision



(b) the grant of a State) the term authorization of selected gas devices



(c)) the term opinion to EIA



(d)), the term release planning



(e) the building permit)



(f)) start of construction



(g)), the term connection of electricity production for test operation



h) start trial operation



I) Release Date of occupancy.



Selected provisions of the novel



Article. (II) Decree No. 476/2012 Coll.



Transitional provision



(1) a producer of electricity, the electricity production was put into operation

until 31 December 2006. December 2012, the making of the electricity measurement of electricity in accordance with

§ 2 (2). 2 (a). g) until 31 December 2006. March 2013.



(2) the transmission system operator and distribution system operators

system operators in the electricity sector for the first time the market operator shall send the data referred to in

section 10b, para. 1 on the status as at 31 December. December 2012 at the latest by 15. January 1, 2013.



(3) the transmission system operator and distribution system operators

systems in the gas industry for the first time the market operator shall transmit the information referred to in section

10B, para. 2 on the status as at 31 December. December 2012 at the latest by 15. January 1, 2013.