Advanced Search

On The Conditions For Connection To The Electricity Grid

Original Language Title: o podmínkách připojení k elektrizační soustavě

Subscribe to a Global-Regulation Premium Membership Today!

Key Benefits:

Subscribe Now for only USD$40 per month.
51/2006 Sb.



DECREE



of 17 May. February 2006



on the conditions for connection to the electricity grid



81/2010: Sb.



82/2011: Sb.



The Energy Regulatory Office shall, pursuant to section 98 para. 7 of law No.

458/2000 Coll., on conditions for business and the public administration in

energy sectors and on amendments to certain acts (the Energy Act),

as amended by Act No. 670/2004 Coll., to implement section 17 para. 7 (b). (d)), and (h))

Energy Bill:



§ 1



The subject of the edit



This Decree lays down the conditions for production of electricity,

distribution system operators and offtake points customers to the electricity

system and method for determining the share of the costs associated with the connection and the

by ensuring that the required input power.



§ 2



Basic provisions



For the purposes of this Ordinance, means the



and a reserved power)



1. the value of the electric power transmission system in the hub site

MW in the basic engagement negotiated with the transmission system operator to

the basis of the desired wattage and the technical parameters of the transmission device

system in the delivery place, or



2. the value of the electrical input of the negotiated with the provider of the distribution

system based on the desired wattage for the place of consumption or

submission site in kW on the surface very high or high voltage

or equal to the nominal value of main circuit breaker in the electricity meter and

on the surface, low-voltage,



(b)) reserved the exercise of



1. the value of the additional electricity production performance in the delivery place

the transmission system in the MW in the basic involvement reduced by value custom

electricity consumption in the production of electricity or electricity and

heat,



2. the value of the additional electricity production performance in the delivery place

the distribution system in kW, less the value of own consumption of electricity

the production of electricity, or



3. performance value in MW, negotiated with the transmission system operator for

submission site distribution system or negotiated with the operator

the distribution system for a forward place, other distribution system,



c) site-a place in the transmission or distribution system, in

where the device is connected, directly, through the House

install or through the connections and plumbing,



d) equipment-production of electricity, the distribution system, or sampling

the electrical equipment,



(e)) by the applicant-the natural or legal person who asks about the connection

device to a transmission or distribution system or to increase

reserved input power or the performance of existing equipment, and that is

authorized to use the device on the basis of ownership or other right; for

the applicant shall also be regarded as a natural or legal person who, in the

the territory intends to make the construction of the device.



§ 3



The conditions of the applicant's device connection to the transmission system or

distribution system



(1) the conditions of connection of the device to the transmission system or the applicant

distribution system are



and request a connection),



(b) presentation of a study) connectivity under the conditions pursuant to Section 4a,



(c)) the conclusion of contracts on connection between the applicant and the operator

the transmission system operator or distribution system operator or change the

existing connection agreements ^ 1).



(2) the applicant is making an application for the conclusion of the contract only for the connection or

change an existing connection agreements, if there is no change

technical conditions of connection when



and the licensee of the operating changes) equipment without interruption

production of electricity connection to the transmission system or distribution

system, or



(b) replace or modify the plant) of electricity, when there is no crossing

existing negotiated the amount of the reserved performance while maintaining the standard

conditions or transmission or distribution of electricity.



(3) when the first change of electricity supplier, in the conclusion of the Treaty on the

connection progresses according to the electricity market rules ^ 2), which

lay down the terms and procedure for change of the supplier of electricity.



(4) the payment of the share of the costs associated with the connection and to ensuring the

the required input or output (hereinafter referred to as "qualifying share

the cost ") shall not apply in the cases referred to in paragraph 2 or 3, or

If the share of the eligible costs already paid another natural or

a legal person. This does not apply, if the elapse of the time booking power input

pursuant to § 7 para. 7 to 9.



(5) where the applicant is a connection with simultaneous license holder

on the distribution of electricity and the production of electricity, it is considered that the requesting

connect distribution system, if the technical documentation

proves that the connected device is in the production of electricity.

If the device is a participant of the electricity market, which is the parallel

holds the licences for the distribution of electricity and the production of electricity, already

connected to the transmission system or distribution system, it is considered that,

that is connected to the distribution system, if the technical documentation

It proves that the connected device is in the production of electricity.



(6) the making of the electricity, it is also possible to connect at the point of use. About

connection of electricity production in the point of asking the customer. When

connecting electricity production to other plants in a pass-through

electricity is the procedure as in the case of connection of electricity production in

point of use.



(7) where the connection to the transmission system or distribution system

an applicant who is licensed to distribute electricity or

the license for the production of electricity, is reserved for a forward place

reserved power double performance.



§ 4



Request for connecting the device to the transmission system or distribution

System



(1) an application shall be filed for each sampling or forward instead of separately.

The applicant's application for connecting the device to the transmission system or

the distribution system is administered



and before the construction or connecting) a new device,



(b)) before increasing the wattage or performance of the existing reserved

a connected device,



(c)) before changing the nature of the sampling according to annex No. 7 to this Decree,



(d) in the case of changes to the yarn) production of electricity,



e) in the case of a change of the production plants of electricity connection to the transmission

system or distribution system.



(2) the requirements for an application to connect electricity production plants or part thereof to

the transmission system or distribution system are listed in the annex.

1 to this notice.



(3) the application for connection of electricity production, the consent of the owner of the

real estate with the placement of production plants of electricity in its real estate and later in

the case of the production of electricity with installed power



and) from 30 kW to 5 MW, including spatial planning information on the conditions

issue of zoning and planning decision, from which it is clear that the construction of the plant

electricity in accordance with spatial planning documentation,



(b)) over 5MWpřipojované to the distribution system and production of electricity

connected to the transmission system planning information about

conditions of release planning,



c) above 0.5 MW schedule of preparation of construction production of electricity.



(4) the timetable for the preparation of the construction of a plant producing electricity contains a list of

decisions, opinions and observations of the public authorities and

the expected dates of their issue, in particular as regards the conclusions of the

the discovery of the procedure for the assessment of effects on the environment, the location of the

construction of the integrated permit, authorisation, construction and occupancy,

which are necessary to implement the construction of a plant producing electricity.



(5) the requirements for an application on the device connection to the distribution system,

the transmission system or distribution system are listed in the annex.

2 to this Decree.



(6) the requirements for an application for connection to the electrical equipment of the sampling

the transmission system or distribution system from voltage levels especially

high voltage, high voltage and high voltage are listed in

Annex No. 3 to this notice.



(7) the requirements for an application for connection to the electrical equipment of the sampling

the distribution system of low-voltage voltage levels are listed in

Annex No 4 to this notice.



Section 4a



Study of connectivity



(1) the operator of a transmission system operator or distribution

system may request from the applicant processing study of connectivity,



and) If, having regard to all the circumstances, clearly, that the equipment to which the

the connection applicant applied, will affect the reliability of the transmission

system or distribution system, or



(b)) asks if the device connection to the high voltage and voltage level

higher.



(2) if the applicant Asks about the connection to the transmission grid

system or to increase the input power or the performance of the booked in delivery

place between distribution and transmission system, are responsible for processing

study of connectivity along the transmission system operator and

the distribution system operator.



(3) subject to the study of electricity production or consumption of the connectivity

the electrical equipment is the assessment of expected impacts device connection

the reliable operation of the Czech transmission system or distribution system.

Subject of studies the distribution system to the transmission connectivity


system or distribution system to a different distribution system is hereinafter

the assessment of the possible variations of the desired connection in terms of their

costs.



(4) the transmission system operator or the owner of the distribution

the system may require the processing of study within 30 days of connectivity

request a connection. At the same time must define the desired range

study of connectivity.



(5) if the applicant so requests, the transmission system operator or

distribution system operator about the documents for study

connectivity not later than 30 days after receipt of the application for

processing, the transmission system operator or the operator

distribution system operator shall provide the applicant documentation required for processing

study of connectivity within 15 days of their request. Unless

the applicant a transmission system operator or distribution

system of documentation for processing study of connectivity within 30 days after

receipt of the application for processing, the transmission system operator

or the distribution system operator request is examined.



(6) unless otherwise requested by a transmission system operator or the operator

study of the processing distribution system connectivity within the time limit referred to in

paragraph 4, or if the applicant does not provide the documentation required for processing

study of connectivity, it is considered that the processing of study

connectivity is not required.



(7) an applicant for the device connection to the distribution system passes

the distribution system operator connectivity study within 90 days of

the date when the distribution system operator shall forward the documents to the applicant

necessary for the processing of the study. If the applicant asks about the connection of the device to the

the transmission system, transmission system operators shall transmit to the applicant

study on connectivity to 180 days from the date on which the operator of a transmission

the system gave the applicant the documentation required for processing studies, if

the applicant with the transmission system operator concerned agree otherwise.



(8) if there is no connectivity studies prepared in the range defined by the

the transmission system operator, or the operator of a distribution

system, the transmission system operator or the operator

distribution system to request its addition or extension. The operator

the transmission system operator or distribution system operator may request

additions or extensions to connectivity studies no later than 30 days from the

transmission study of connectivity.



(9) if the transmission system operator shall complement or extend

the study, the applicant shall forward the complete with connectivity or advanced study

connectivity within 90 days from the date of the receipt of the request of the operator

the transmission system operator, unless otherwise. For the processing and transfer of

a new study by connectivity, paragraph 7 shall apply mutatis mutandis.



(10) if the distribution system operator shall supplement or

the extension of the study, the applicant shall forward the complete with connectivity or

extended connectivity study within 30 days of the date on which it received the

request a distribution system operator. For the processing and transfer of

a new study by connectivity, paragraph 7 shall apply mutatis mutandis.



§ 5



Examining a request for connection to the transmission system or device

distribution system



(1) the operator of a transmission system operator or distribution

the system assesses the application for connection of the device with regard to the



and the way of the desired) place and connect,



(b) the amount of required reserved input) or performance and time

the progress of the load,



(c) the reliability of electricity supply,)



(d) the nature of the reaction device) of the applicant on the transmission or

distribution system,



(e) the planned development system)



(f)) and the order of the lodgment of applications



g) limits the performance of the power system trimmer set

the transmission system operator.



(2) if it is necessary for a proper examination of the application, it shall invite the

the transmission system operator or distribution system operator

the applicant no later than within 15 days from the date of receipt of the request to add

the data provided to the extent necessary and stipulate the appropriate

the time limit. At the same time notify the applicant, in the case of nedoplnění data in

to the extent required by the deadline will not be considered in the application.



(3) if the applicant will be asked to supplement the information provided in accordance with paragraph

2 and the applicant to do so, the transmission system operator or

the distribution system operator application is not examined. This fact

shall inform the applicant without undue delay.



(4) if they are not determined by the Energy Act, for which the

the applicant cannot be a device to the transmission system or distribution system

connect to ^ 3), the distribution system operator shall provide to the applicant within 30

days, or in the case of a device connected to the high voltage levels

or very high voltage within 60 days of the submission of a complete application for

connection or from the date of transfer, if the connectivity studies

processing study of connectivity required design connection agreements

or the draft Treaty on the future of the connection. In the case of devices

connected to the transmission system, the time limit for the submission of the proposal

connection agreements or contracts of intent on connecting 90 days

from the submission of a complete application for connection or from the date of transmission of the study

connectivity, if the processing of a study requested by the connectivity.

The transmission system operator or distribution system operator

be determined in the preliminary draft Treaty about the connection or the Treaty on

the connection time limit for the adoption of the draft Treaty of 30 days, if it is

to connect the device to power low voltage level, or 60 days,

If this is about connecting the device to the surface voltage of high voltage

or higher.



(5) If you cannot connect the device of the applicant for the reasons set out

the Energy Act ^ 3), the transmission system operator or

the distribution system operator shall notify this fact to the

to the applicant within 30 days from the submission of a complete application for connection or from the date of

transmission study of connectivity if it has been processing studies

connectivity to require. The transmission system operator or

at the same time the distribution system operator shall state the specific reasons for the

You cannot connect to the device of the applicant. However, if the device can be

applicant attach under different conditions and of the content of the application or of the

the circumstances in which the application was made, it can be assumed that the applicant

such a connection will have an interest in, the transmission system operator

or distribution system operator in writing of such fact

the applicant shall communicate, together with the reasons for which cannot be under the required device

conditions, the applicant shall submit to the mount, and the draft Treaty referred to in paragraph 4.



(6) the preliminary agreement on the connection shall be concluded as a rule, if the

If you connect a device of the applicant requires the construction and technical measures

in the transmission system or distribution system, whose implementation

requires a decision on the location of the building or territorial consent pursuant to

the building Act.



(7) if the examination of the application on the connection necessary to measure

or the system voltage 110 kV validation of network operation, the term

referred to in paragraph 4 or 5 of the time required for measurement or verification operation

the network, a maximum of 30 days. On the necessity of a measurement or verification

network operation and extension of time shall inform the operator of a transmission

system operator or distribution system operator the applicant not later than

15 days from the date of receipt of the request.



(8) the transmission system operator or the owner of the distribution

the system suggests the connection of the device, so that the technical implementation

connection of the device was based on the planned development system when you

also taking account of the applicant's interest to minimize the cost of

the device connects to the transmission system or distribution system.



(9) the transmission system operator or the owner of the distribution

the system reserves the applicant required power or power from the moment

submission of the draft of the Treaty referred to in paragraph 4.



(10) if the applicant does not accept the proposal of the contract within 30 days for a connection to the

low voltage or voltage level within 60 days for a connection to the power

the surface of the high voltage and higher performance or booking, reservation

input ceases to exist.



§ 6



The short connection to the distribution system



(1) Short-term connection means the connection of the provisional devices

According to the Czech technical standards ^ 4) to a distribution system for a fixed period.



(2) in the case of short-term connection serves the applicant request for short term

the connection to the distribution system, separately for each sampling or pass-through

instead. Request of the applicant for short-term connection are listed

in annex 5 to this Decree.



(3) on the short-term connection shall apply mutatis mutandis to section 4 to 5 and § 7. Place

priority specifies the connection, so that was the need for the cost

distribution system operator with the connection.



(4) where the distribution system operator costs related

arrange short-term device connection of the applicant, the applicant shall pay

short connection to the distribution system, the costs associated with


connection including the cost of placing space attaching after their subscription

to its original state in full. Share of the eligible costs under section

10A is not reimbursable.



(5) After the termination of the connection terminates the reserve power consumption; § 7 para.

7 to 9 shall not apply.



(6) If a due to implementation of a short connection to the distribution

system need to increase input in pass-through areas reserved

between the distribution system, in which to implement the short-term connection

occurred, and a distribution system, proceed in accordance with paragraph 4.



§ 7



Device connection of the applicant to the transmission system or distribution

System



(1) the applicant's device Connection to the transmission system or distribution

the system is carried out on the basis of connection agreements.



(2) the Treaty concerning the connection of one applicant can include multiple sampling

or forward sites, as is each of them separately in the contract

stated.



(3) the applicant pays an advance on the costs according to the share of eligible

of annex 6 to this Decree, in the amount of 50% of the value of the share on the

eligible costs, but not more than 50 000 000 CZK. The applicant shall pay

advance on the share of the eligible costs within 15 days from the date of the conclusion of the

connection agreements or contracts of intent about the connection.



(4) if the applicant fails to pay the deposit on a share of the eligible costs referred to in

paragraph 3 or in additional reasonable period of time provided by the operator

the transmission system operator or distribution system operator and

the transmission system operator or distribution system operator

for this reason, the connection terminates the agreement or Treaty Treaty

the future of connectivity, performance or reservation booking input termination

the contractual relationship ceases to exist.



(5) if the connection does not require the applicant's implementation of construction equipment

technical measures in the transmission system or distribution system,

taking out the transmission system operator or the owner of the distribution

system and the applicant, the term connection of electricity production using

solar radiation to electricity production has been attached by

180 days from the date of conclusion of the contract about connection, in the case of the plant

electricity using solar radiation with installed power of 30 kW

within 1 year from the date of conclusion of the contract about the connection.



(6) if the applicant within the time limits referred to in paragraph 5 establishes that despite all

the effort did not occur within the agreed deadlines to implement the connection

production of electricity from the reasons that occur or exist independently of the

his will, the transmission system operator or the operator

distribution system operators shall negotiate with the applicant, an extension of the connection

as long as necessary.



(7) if the agreed reduction of the main circuit breaker before the measurement values

device to a value lower than the reserved input space

connection device for a period longer than 24 months,

the value of the reserved power input to this value.



(8) If, after the period of 60 months from the date of the last change of the reserved

the wattage not for negotiation of reserved capacity of at least 90% of the

reserved the reserved value of power input, power consumption is reduced to

value, which is determined by the highest agreed size reserved

capacity in the period of 60 months from the last changes of the reserved power input.



(9) in the event of termination of the contract of transport or distribution of electricity takes

booking for an existing connection point for a period of 60 months from the

date of termination of the contract. If the contract for the transmission or distribution of

electricity has not been concluded within 60 months from the date of the agreed connection

in the Treaty, the reservation for place of consumption or for the

place the connection terminates.



§ 8



The costs associated with connecting the device to the transmission system or

distribution system and by ensuring the desired wattage or performance



(1) If an applicant under this Ordinance shall bear the costs associated with

connection and to ensuring the desired wattage or the performance in full

the amount of the costs borne by the applicant, include only the costs referred to in

paragraphs 2 to 4.



(2) the costs associated with the connection and to ensuring the desired wattage

or include essential performance incurred eligible costs

related to the acquisition, construction, or alteration of the transmission system

or distribution system that were thrown by the request of the applicant in

connection with the place and the way to connect its devices. Acquisition,

construction or modifications to the transmission system or distribution system are

provided to the extent necessary corresponding value input

or performance required by the applicant, and the place and how to connect it

device.



(3) The costs associated with the connection and to ensuring the desired

the wattage or performance will include the cost of the acquisition project

documentation, geodetic focus, easements and other immediately

investment costs and charges related to the construction, modification or

the acquisition of the Czech transmission system or distribution system.



(4) The costs associated with the connection and to ensuring the desired

the wattage or performance do not include costs associated with the acquisition,

the construction or alteration of the transmission system or distribution system,

that exceed the scope strictly necessary level corresponding to the value

input or output, requested by the applicant, and the place and the way

the connection of the device.



(5) the construction and adjustment of the transmission system is defined from the point of connection

the device of the applicant to the nearest place in the transmission system, where is

or would poprovedení the necessary adjustments in the system was available

the reserved power or performance.



(6) construction and adjustment of the distribution system is defined from the point of

connect the device to the nearest locations in the applicant's distribution system

to the same voltage level, where it is, or would after the necessary

adjustments in the system was available the reserved power or

performance.



§ 9



cancelled



§ 10



The proportion of the applicant for connection to the transmission system or device

distribution system to eligible costs



(1) the applicant's share of the eligible costs shall be calculated as the product of

measuring the proportion referred to in annex 6 to this Ordinance and the applicant

the required input power or the performance of the booked.



(2) in the case of connecting electricity production plants to the transmission system or

the distribution system shall be borne by the management to the point of connection, leaded by the applicant in

the full amount.



(3) if the reserved power and performance simultaneously one applicant in one

the connection point, the share of eligible costs separately for

reservation to reserve the wattage and performance. The applicant shall be paid by the higher of the two

set out the eligible costs of the shares.



section 10a



Reconnect the device to the transmission system or distribution

System



If the transmission system operator or the operator

sampling distribution system, the electrical equipment of the customer that

was limited or interrupted the supply of electricity due to unauthorized

collection, transmission or distribution of electricity, shall be borne by the customer market share

of eligible costs in the amount of



and $1 500) when you connect the low voltage level, voltage



(b) Eur 3 500) when you connect the high voltage or voltage level

higher.



§ 11



The specific requirements of the applicant of the device connection to the transmission system

or distribution system



(1) if the applicant Asks about the connection beyond the standard connection

device, or where a specific method of construction or technical

design the device connects to the transmission system or distribution

the system shall be borne by the applicant justified the costs associated with the implementation of

above-standard connection or a specific building or technical

make connections in full.



(2) booked on the surface of low-voltage power consumption can be converted in

one or more adjacent real estate property, only if the

technically possible and realization of transfer of a reserved power input does not throw

additional costs related to the acquisition, construction or alteration

the distribution system. Similarly when you transfer the reserved

the wattage on the surface of a high or very high voltage in a single

nodal areas appropriate voltage levels.



(3) if the applicant Asks about the connection of the device to a different voltage level than the

to which the device is connected, and required change connection is not

enforced by changing the technical conditions of connection shall be borne by the applicant costs

on the legitimate costs associated with this change in full. In such a

If the amount of the original booked the wattage or performance will not refund

share of the eligible costs under section 10. The provisions of § 7 para. 7 to 9

do not apply.



§ 12



Electrical connection for the supply of electricity



(1) the length of the electrical connections means the length of the shortest construction and

technically feasible routes connections to the ground plan of the projected between

place turn from the distribution system and the main fuse

or the main entrance cable housings.



(2) the length of the electrical connections are not included in part led by

vertically.




(3) for the assessment of whether the electrical connection of the built

or outside the built-up areas in accordance with the building Act ^ 5), it is critical

the location of the connected property.



the title launched



section 13 of the



cancelled



§ 14



cancelled



§ 15



cancelled



section 16 of the



The conditions of the power supply in case of disturbances on sampling and measurement

equipment and in the case of a refusal of access to measurement device



(1)



cancelled



(2) if under the influence of a failure in the supply of equipment or disorders caused by

end customer on the measuring device to limit or interruption

the transmission or distribution of electricity, restores the operator of a transmission or

distribution system on the basis of the notification of the final customer

removal of fault on sampling or measuring device or transfer

distribution of electricity within the time limit under special legislation ^ 7).

The costs associated with restoring the transmission or distribution of electricity shall be borne by

the final customer.



§ 17



Transitional provisions



If the applicant so requests on the basis of the opinion of the operator of a transmission or

distribution system issued under the existing legislation on

conclusion of the contract about connection, the operator of a transmission or distribution

system connection before concluding the contract, reexamine the released

opinion within 30 days from the date of receipt of the request, so that it was in accordance with the

This Decree. In fixing the amount of the applicant's share of the cost

associated with connecting and to ensuring the desired wattage or performance

proceed under the law more favourable to the applicant. At the same time with

the operator thus reflected revised opinion of the transmission or

the applicant of the distribution system, the draft Treaty on the connection. The initial period of

binding opinions in accordance with the existing legislation is extended

about the time that a re-examination of the opinion was based on the previous

the sentence.



section 18



Regulation (EEC)



Shall be repealed:



1. Decree No. 297/2001 Coll. laying down the conditions and

electricity supply to the protected customers.



2. Decree No. 18/2002 Coll., on conditions of connection and transport of electricity

in the electricity grid.



3. Decree No. 300/2003 Coll., amending Decree No. 18/2002 Coll.

conditions of connection and transport of electricity in the electricity grid.



§ 19



The effectiveness of the



This Decree shall enter into force on 1 January 2000. March 2006.



President:



Ing. The firt in r.



Annex 1



REQUIREMENTS FOR AN APPLICATION TO CONNECT TO THE TRANSMISSION OR ELECTRICITY PRODUCTION

DISTRIBUTION SYSTEM



Part And

-information on the applicant



1. the business name of the applicant (to be completed-entrepreneur business

Register).



2. the data on the registration in the commercial register, including the file tags

(to be completed by the applicant-entrepreneur in the commercial register).



3. the name or the name and surname of the applicant (unregistered in business

Register).



4. Date of birth (to be completed by the applicant-natural person).



5. the registered office of the broken down: State, County, municipality of zip/postal code, street and house number,

where applicable, the registration number (to be completed by the applicant-a legal entity).



Place of business in the breakdown: the State, the County, municipality of zip/postal code, street and number

where applicable, the registration number of the descriptive (to be completed by the applicant-natural person

doing business).



6. the first name and surname of the person who is the statutory body, or all of the

persons who are members of the statutory body (to be completed by the applicant-

a legal entity).



7. The address of the place of stay in the breakdown: the State, County, municipality of zip/postal code, street and number

descriptive, or registration number (to be completed by the applicant-natural person

the nonentrepreneurial).



8. Connection-telephone, e-mail.



9. The address for service.



10. Information on data, if the mailbox has been established.



11. The identification number, if one has been assigned.



12. Tax identification number, if one has been assigned.



Part (B)

-device details



1. The location of the production plants of electricity-County, village, cadastral, land

the numbers of the land on which it is located, the number of electricity production

descriptive, or registration number.



2. the type of electricity production.



3. the character of the production of electricity.



4. The dates of the connection.



5. General information about the production of electricity:



5.1. connection of electricity production plants to the transmission system or distribution

System (dielectric layer, the presumed location of the connection,

fit the scheme, territorial connection of individual variants variants)



5.2. Description of the production plants of electricity [total installed capacity power plants,

efficiency of the power plant, the performance of individual blocks, electric

scheme of the blocks, the block type (coal, steam, water, other), a kind of resource

(top, base), the energy produced per year, nominal power factor,

the estimated reliability of the block],



5.3. Description of the block transformer (type, installed power, rated

voltage, voltage short, engaging, conversion, winding turns, range

loss of short and open circuit, short-circuit resistance loss, etc.)



5.4. Description of the generator (type, installed power the apparent and active,

rated voltage, the wiring, the type, the switch drivers, dynamic

constants, as are spare, the reactance time constants, constants

of inertia)



5.5. Description of own consumption (total installed power, rated

voltage, power factor, the starting current).



6. the required reliability of the outlet of the performance.



The applicant shall declare and signature confirms the accuracy and truthfulness of the

all of the above data.



Annex 2



REQUIREMENTS FOR AN APPLICATION ON THE DEVICE CONNECTION TO THE DISTRIBUTION SYSTEM,

A TRANSMISSION OR DISTRIBUTION SYSTEM



Part And

-information on the applicant



1. the business name of the applicant (to be completed-entrepreneur business

Register).



2. the data on the registration in the commercial register, including the file tags

(to be completed by the applicant-entrepreneur in the commercial register).



3. the name or the name and surname of the applicant (unregistered in business

Register).



4. the registered office of the broken down: State, County, municipality of zip/postal code, street and house number,

where applicable, the registration number (to be completed by the applicant-a legal entity).



Place of business in the breakdown: the State, the County, municipality of zip/postal code, street and number

where applicable, the registration number of the descriptive (to be completed by the applicant-natural person

doing business).



5. First and last name of the person who is the statutory body, or all of the

persons who are members of the statutory body (to be completed by the applicant-

a legal entity).



6. Connection-telephone, e-mail.



7. Address for service.



8. Information on data, if the mailbox has been established.



9. Identification number of the



10. Tax identification number



Part (B)

-device details



1. The term connection



2. Basic data for connection to the transmission system or distribution

system:



2.1. submission site,



2.2. the highest dielectric layer,



2.3. single-pole diagram,



2.4. the cadastral map of the territory with the placement of a pass-through space.



3. information about the subscription:



3.1. the requested value of the booked reserved performance, power consumption and



3.2. the current value of the reserved power consumption and reserved performance,



3.3. nature of sampling,



3.4. the time course load,



3.5. power factor and compensation,



3.6. the projected energy consumption for the year.



4. the requirements on the reliability of the delivery (maximum period of interruption

delivery).



5. reverse Options affecting the supply network.



The applicant shall declare and signature confirms the accuracy and truthfulness of the

all of the above data.



Annex 3



REQUIREMENTS FOR AN APPLICATION FOR CONNECTION TO THE ELECTRICAL EQUIPMENT OF THE SAMPLING

A TRANSMISSION OR DISTRIBUTION SYSTEM OF EXTRA-HIGH VOLTAGE LEVELS

VOLTAGE, HIGH VOLTAGE AND HIGH VOLTAGE



Part And

-information on the applicant



1. the business name of the applicant (to be completed-entrepreneur business

Register).



2. the data on the registration in the commercial register, including the file tags

(to be completed by the applicant-entrepreneur in the commercial register).



3. the name or the name and surname of the applicant (unregistered in business

Register).



4. Date of birth (to be completed by the applicant-natural person).



5. the registered office of the broken down: State, County, municipality of zip/postal code, street and house number,

where applicable, the registration number (to be completed by the applicant-a legal entity).



Place of business in the breakdown: the State, the County, municipality of zip/postal code, street and number

where applicable, the registration number of the descriptive (to be completed by the applicant-natural person

doing business).



6. the first name and surname of the person who is the statutory body, or all of the

persons who are members of the statutory body (to be completed by the applicant-

a legal entity).



7. The address of the place of stay in the breakdown: the State, County, municipality of zip/postal code, street and number

descriptive, or registration number (to be completed by the applicant-natural person

the nonentrepreneurial).



8. Connection-telephone, e-mail.



9. The address for service.



10. information on the data locker if it was furnished.



11. The identification number, if one has been assigned.



12. Tax identification number, if one has been assigned.



Part (B)

-device information of the applicant



1. The dates of the connection.



2. Basic data for the involvement of the applicant, within the transmission system device

or distribution system:



2.1. the sampling/submission site,



2.2. the highest level of consumption of the voltage of the electrical equipment,



2.3. single-pole diagram,



2.4. the cadastral map of the territory with the location of the sampling points.



3. information about the subscription:



3.1. the requested value of the reserved power input,




3.2. the current value of the reserved power input,



3.3. nature of sampling,



3.4. type and subscription of connecting appliances (in particular the number and performance

motors, electric furnaces and heating, electric welding equipment, drives

etc.),



3.5. the time course load,



3.6. the power factor and compensation,



3.7. information about whether it will be installed in the point of the backup

the source and in the positive case, its parameters and the expected way

operation.



4. the requirements on the reliability of the delivery (maximum period of interruption

delivery).



5. reverse Options affecting the supply network.



6. information on the production and mounting, or no longer connected to the sampling

device.



The applicant shall declare and signature confirms the accuracy and truthfulness of the

all of the above data.



Annex 4



REQUIREMENTS FOR AN APPLICATION FOR CONNECTION TO THE ELECTRICAL EQUIPMENT OF THE SAMPLING

DISTRIBUTION SYSTEM FROM VOLTAGE LEVELS LOW VOLTAGE



Part And

-information on the applicant



1. the business name of the applicant (to be completed-entrepreneur business

Register).



2. the data on the registration in the commercial register, including the file tags

(to be completed by the applicant-entrepreneur in the commercial register).



3. the name or the name and surname of the applicant (unregistered in business

Register).



4. Date of birth (to be completed by the applicant-natural person).



5. the registered office of the broken down: State, County, municipality of zip/postal code, street and house number,

where applicable, the registration number (to be completed by the applicant-a legal entity).



Place of business in the breakdown: the State, the County, municipality of zip/postal code, street and number

where applicable, the registration number of the descriptive (to be completed by the applicant-natural person

doing business).



6. the first name and surname of the person who is the statutory body, or all of the

persons who are members of the statutory body (to be completed by the applicant-

a legal entity).



7. The address of the place of stay in the breakdown: the State, County, municipality of zip/postal code, street and number

descriptive, or registration number (to be completed by the applicant-natural person

the nonentrepreneurial).



8. Connection-telephone, e-mail.



9. The address for service.



10. Information on data, if the mailbox has been established.



11. The identification number, if one has been assigned.



12. Tax identification number, if one has been assigned.



Part B-information about the applicant's equipment



1. The term connection



2. Basic data on the involvement of the applicant's equipment in the distribution system:



2.1. the sampling/submission site (e.g. establishment of a family house, cottage)



2.2. the cadastral map of the territory with the location of the sampling points.



3. information about the subscription:



3.1. the requested value of the reserved power input,



3.2. the current value of the reserved power input,



3.3. nature of sampling,



3.4. type and subscription of the connected appliances (connection of individual

appliances with a nominal power of 5 kW and above, in particular the number and performance

motors, electric furnaces and heating, electric welding equipment, drives

etc.),



3.5. information about whether it will be installed in the point of the backup

the source and in the positive case, its parameters and the expected way

operation,



4. the requirements on the reliability of supply.



5. reverse Options affecting the supply network.



6. Type and performance of heat pumps.



7. information on the production and mounting, or no longer connected to the sampling

device.



The applicant shall declare and signature confirms the accuracy and truthfulness of the

all of the above data.



Annex 5



REQUIREMENTS FOR AN APPLICATION FOR A SHORT-CONNECT THE DEVICE TO THE DISTRIBUTION

SYSTEM



Part And

-information on the applicant



1. the business name of the applicant (to be completed-entrepreneur business

Register).



2. the data on the registration in the commercial register, including the file tags

(to be completed by the applicant-entrepreneur in the commercial register).



3. the name or the name and surname of the applicant (unregistered in business

Register).



4. Date of birth (to be completed by the applicant-natural person).



5. the registered office of the broken down: State, County, municipality of zip/postal code, street and house number,

where applicable, the registration number (to be completed by the applicant-a legal entity).



Place of business in the breakdown: the State, the County, municipality of zip/postal code, street and number

where applicable, the registration number of the descriptive (to be completed by the applicant-natural person

doing business).



6. the first name and surname of the person who is the statutory body, or all of the

persons who are members of the statutory body (to be completed by the applicant-

a legal entity).



7. The address of the place of stay in the breakdown: the State, County, municipality of zip/postal code, street and number

descriptive, or registration number (to be completed by the applicant-natural person

the nonentrepreneurial).



8. Connection-telephone, e-mail.



9. The address for service.



10. Information on data, if the mailbox has been established.



11. The identification number, if one has been assigned.



12. Tax identification number, if one has been assigned.



Part (B)

-device information of the applicant



1. The date and the duration of the connection.



2. Basic data on the involvement of the applicant's equipment in the distribution system.



3. The sampling/submission site.



4. the Location of the sampling of the electrical equipment.



5. Information about the subscription:



5.1. the required size of the reserved value input/main

circuit breakers,



5.2. nature of sampling.



The applicant shall declare and signature confirms the accuracy and truthfulness of the

all of the above data.



Annex 6



THE SPECIFIC CONTRIBUTION OF THE APPLICANT FOR CONNECTION TO LEGITIMATE COSTS ASSOCIATED WITH

CONNECTION AND SECURING OF THE REQUIRED POWER CONSUMPTION AND PERFORMANCE



FOR BOOKING INPUT



------------------------------------------------------ -------------------------

Instead the connection to the voltage level of the specific contribution of the applicant connection method

------------------------------------------------------ -------------------------

transmission system 200 EUR/MW

HIGH VOLTAGE distribution system and Type 600 EUR/MW

HIGH VOLTAGE distribution system of type B 150 EUR/MW

the distribution system of INDOOR type and 800 EUR/MW

the distribution system of HV type B1 200 EUR/MW

distribution system NN 3 phase connection 500 Kč/A

distribution system NN 1 phase 200 CZK/connection and

------------------------------------------------------ -------------------------



PERFORMANCE FOR A RESERVATION



------------------------------------------------------ -------------------------

Instead the connection to the voltage level of the specific contribution of the applicant connection method

------------------------------------------------------ -------------------------

the transmission system at the connection point

in the opinion of 500 EUR/MW

the operator

the transmission system

HIGH VOLTAGE distribution system type and 1 200 000 Eur/MW

HIGH VOLTAGE distribution system of type B 150 EUR/MW

the distribution system of INDOOR type and 640 000 CZK/MW

the distribution system of HV type B 150 EUR/MW

distribution system NN 3 phase connection 500 Kč/A

distribution system NN 1 phase 200 CZK/connection and

------------------------------------------------------ -------------------------



A Type Of Connection And

This is where the distribution system operator shall extend

distribution system up to a pass-through space, eg.

transformer station or substation of the applicant for connection.



A Type Of Connection (B)

such a connection that does not meet the conditions of the connection.



Connection Type B1

such a connection is not needed when construction of the new dungeons and busbars and

they are only necessary adjustments of a technical nature (e.g. replenishment armament

the Dungeon)



In the case of a connection request, or raise the reserved input

or performance in the objects already connected is to determine the proportion of

eligible costs the determining existing connection method.



Annex 7



CHARACTER COLLECTION



1. the place of consumption of "T1"-supply point with electrical equipment

standard appliances to 16 and that they have the mark of conformity within the meaning of

Act No. 22/1997 Coll.-lighting and electric appliances connected to the

divorce corded (the sockets) or securely attached, with

power consumption of any appliances does not exceed 3.5 kVA.



2. the place of consumption of the type "T2"-supply point with electrical equipment as

for the type "T1", where the water is used for heating, electrical energy (excluding

flow heaters).



3. the place of consumption of "T3"-supply point with electrical equipment as

for the type "T1" or "T2", where cooking and baking using electric

appliances with input above 3.5 kVA.



4. the place of consumption of the type "T4"-supply point with electrical equipment as

for the type "T1", "T2" or "T3", for heating (accumulation,

direct heating, heat pump) or air conditioning use electric

appliances whose consumption is measured for each customer.



5. the place of consumption of "T5" – a place of consumption with electric equipment such as

of a type of "T3" or "T4", which are equipped with additional electrical

appliances that may affect the operation of the network.



1) § 50 para. 3 the Energy Act.



2) § 50 para. 3 the Energy Act.



1) § 50 para. 3 the Energy Act.



3) § 24 para. 10 (a). and) and § 25 para. 11 (a). and) energy

the law.



4) Din 33 2000-1.



5) § 2 (2). 1 (b). (d)) to the building Act.



6) Act 505/1990 Coll., on metrology, as amended.




7) Decree No. 540/2005 Coll., on the quality of electricity supply and

related services in the electricity sector.