51/2006 Sb.
DECREE
of 17 May. February 2006
on the conditions for connection to the electricity grid
81/2010: Sb.
82/2011: Sb.
The Energy Regulatory Office shall, pursuant to section 98 para. 7 of law No.
458/2000 Coll., on conditions for business and the public administration in
energy sectors and on amendments to certain acts (the Energy Act),
as amended by Act No. 670/2004 Coll., to implement section 17 para. 7 (b). (d)), and (h))
Energy Bill:
§ 1
The subject of the edit
This Decree lays down the conditions for production of electricity,
distribution system operators and offtake points customers to the electricity
system and method for determining the share of the costs associated with the connection and the
by ensuring that the required input power.
§ 2
Basic provisions
For the purposes of this Ordinance, means the
and a reserved power)
1. the value of the electric power transmission system in the hub site
MW in the basic engagement negotiated with the transmission system operator to
the basis of the desired wattage and the technical parameters of the transmission device
system in the delivery place, or
2. the value of the electrical input of the negotiated with the provider of the distribution
system based on the desired wattage for the place of consumption or
submission site in kW on the surface very high or high voltage
or equal to the nominal value of main circuit breaker in the electricity meter and
on the surface, low-voltage,
(b)) reserved the exercise of
1. the value of the additional electricity production performance in the delivery place
the transmission system in the MW in the basic involvement reduced by value custom
electricity consumption in the production of electricity or electricity and
heat,
2. the value of the additional electricity production performance in the delivery place
the distribution system in kW, less the value of own consumption of electricity
the production of electricity, or
3. performance value in MW, negotiated with the transmission system operator for
submission site distribution system or negotiated with the operator
the distribution system for a forward place, other distribution system,
c) site-a place in the transmission or distribution system, in
where the device is connected, directly, through the House
install or through the connections and plumbing,
d) equipment-production of electricity, the distribution system, or sampling
the electrical equipment,
(e)) by the applicant-the natural or legal person who asks about the connection
device to a transmission or distribution system or to increase
reserved input power or the performance of existing equipment, and that is
authorized to use the device on the basis of ownership or other right; for
the applicant shall also be regarded as a natural or legal person who, in the
the territory intends to make the construction of the device.
§ 3
The conditions of the applicant's device connection to the transmission system or
distribution system
(1) the conditions of connection of the device to the transmission system or the applicant
distribution system are
and request a connection),
(b) presentation of a study) connectivity under the conditions pursuant to Section 4a,
(c)) the conclusion of contracts on connection between the applicant and the operator
the transmission system operator or distribution system operator or change the
existing connection agreements ^ 1).
(2) the applicant is making an application for the conclusion of the contract only for the connection or
change an existing connection agreements, if there is no change
technical conditions of connection when
and the licensee of the operating changes) equipment without interruption
production of electricity connection to the transmission system or distribution
system, or
(b) replace or modify the plant) of electricity, when there is no crossing
existing negotiated the amount of the reserved performance while maintaining the standard
conditions or transmission or distribution of electricity.
(3) when the first change of electricity supplier, in the conclusion of the Treaty on the
connection progresses according to the electricity market rules ^ 2), which
lay down the terms and procedure for change of the supplier of electricity.
(4) the payment of the share of the costs associated with the connection and to ensuring the
the required input or output (hereinafter referred to as "qualifying share
the cost ") shall not apply in the cases referred to in paragraph 2 or 3, or
If the share of the eligible costs already paid another natural or
a legal person. This does not apply, if the elapse of the time booking power input
pursuant to § 7 para. 7 to 9.
(5) where the applicant is a connection with simultaneous license holder
on the distribution of electricity and the production of electricity, it is considered that the requesting
connect distribution system, if the technical documentation
proves that the connected device is in the production of electricity.
If the device is a participant of the electricity market, which is the parallel
holds the licences for the distribution of electricity and the production of electricity, already
connected to the transmission system or distribution system, it is considered that,
that is connected to the distribution system, if the technical documentation
It proves that the connected device is in the production of electricity.
(6) the making of the electricity, it is also possible to connect at the point of use. About
connection of electricity production in the point of asking the customer. When
connecting electricity production to other plants in a pass-through
electricity is the procedure as in the case of connection of electricity production in
point of use.
(7) where the connection to the transmission system or distribution system
an applicant who is licensed to distribute electricity or
the license for the production of electricity, is reserved for a forward place
reserved power double performance.
§ 4
Request for connecting the device to the transmission system or distribution
System
(1) an application shall be filed for each sampling or forward instead of separately.
The applicant's application for connecting the device to the transmission system or
the distribution system is administered
and before the construction or connecting) a new device,
(b)) before increasing the wattage or performance of the existing reserved
a connected device,
(c)) before changing the nature of the sampling according to annex No. 7 to this Decree,
(d) in the case of changes to the yarn) production of electricity,
e) in the case of a change of the production plants of electricity connection to the transmission
system or distribution system.
(2) the requirements for an application to connect electricity production plants or part thereof to
the transmission system or distribution system are listed in the annex.
1 to this notice.
(3) the application for connection of electricity production, the consent of the owner of the
real estate with the placement of production plants of electricity in its real estate and later in
the case of the production of electricity with installed power
and) from 30 kW to 5 MW, including spatial planning information on the conditions
issue of zoning and planning decision, from which it is clear that the construction of the plant
electricity in accordance with spatial planning documentation,
(b)) over 5MWpřipojované to the distribution system and production of electricity
connected to the transmission system planning information about
conditions of release planning,
c) above 0.5 MW schedule of preparation of construction production of electricity.
(4) the timetable for the preparation of the construction of a plant producing electricity contains a list of
decisions, opinions and observations of the public authorities and
the expected dates of their issue, in particular as regards the conclusions of the
the discovery of the procedure for the assessment of effects on the environment, the location of the
construction of the integrated permit, authorisation, construction and occupancy,
which are necessary to implement the construction of a plant producing electricity.
(5) the requirements for an application on the device connection to the distribution system,
the transmission system or distribution system are listed in the annex.
2 to this Decree.
(6) the requirements for an application for connection to the electrical equipment of the sampling
the transmission system or distribution system from voltage levels especially
high voltage, high voltage and high voltage are listed in
Annex No. 3 to this notice.
(7) the requirements for an application for connection to the electrical equipment of the sampling
the distribution system of low-voltage voltage levels are listed in
Annex No 4 to this notice.
Section 4a
Study of connectivity
(1) the operator of a transmission system operator or distribution
system may request from the applicant processing study of connectivity,
and) If, having regard to all the circumstances, clearly, that the equipment to which the
the connection applicant applied, will affect the reliability of the transmission
system or distribution system, or
(b)) asks if the device connection to the high voltage and voltage level
higher.
(2) if the applicant Asks about the connection to the transmission grid
system or to increase the input power or the performance of the booked in delivery
place between distribution and transmission system, are responsible for processing
study of connectivity along the transmission system operator and
the distribution system operator.
(3) subject to the study of electricity production or consumption of the connectivity
the electrical equipment is the assessment of expected impacts device connection
the reliable operation of the Czech transmission system or distribution system.
Subject of studies the distribution system to the transmission connectivity
system or distribution system to a different distribution system is hereinafter
the assessment of the possible variations of the desired connection in terms of their
costs.
(4) the transmission system operator or the owner of the distribution
the system may require the processing of study within 30 days of connectivity
request a connection. At the same time must define the desired range
study of connectivity.
(5) if the applicant so requests, the transmission system operator or
distribution system operator about the documents for study
connectivity not later than 30 days after receipt of the application for
processing, the transmission system operator or the operator
distribution system operator shall provide the applicant documentation required for processing
study of connectivity within 15 days of their request. Unless
the applicant a transmission system operator or distribution
system of documentation for processing study of connectivity within 30 days after
receipt of the application for processing, the transmission system operator
or the distribution system operator request is examined.
(6) unless otherwise requested by a transmission system operator or the operator
study of the processing distribution system connectivity within the time limit referred to in
paragraph 4, or if the applicant does not provide the documentation required for processing
study of connectivity, it is considered that the processing of study
connectivity is not required.
(7) an applicant for the device connection to the distribution system passes
the distribution system operator connectivity study within 90 days of
the date when the distribution system operator shall forward the documents to the applicant
necessary for the processing of the study. If the applicant asks about the connection of the device to the
the transmission system, transmission system operators shall transmit to the applicant
study on connectivity to 180 days from the date on which the operator of a transmission
the system gave the applicant the documentation required for processing studies, if
the applicant with the transmission system operator concerned agree otherwise.
(8) if there is no connectivity studies prepared in the range defined by the
the transmission system operator, or the operator of a distribution
system, the transmission system operator or the operator
distribution system to request its addition or extension. The operator
the transmission system operator or distribution system operator may request
additions or extensions to connectivity studies no later than 30 days from the
transmission study of connectivity.
(9) if the transmission system operator shall complement or extend
the study, the applicant shall forward the complete with connectivity or advanced study
connectivity within 90 days from the date of the receipt of the request of the operator
the transmission system operator, unless otherwise. For the processing and transfer of
a new study by connectivity, paragraph 7 shall apply mutatis mutandis.
(10) if the distribution system operator shall supplement or
the extension of the study, the applicant shall forward the complete with connectivity or
extended connectivity study within 30 days of the date on which it received the
request a distribution system operator. For the processing and transfer of
a new study by connectivity, paragraph 7 shall apply mutatis mutandis.
§ 5
Examining a request for connection to the transmission system or device
distribution system
(1) the operator of a transmission system operator or distribution
the system assesses the application for connection of the device with regard to the
and the way of the desired) place and connect,
(b) the amount of required reserved input) or performance and time
the progress of the load,
(c) the reliability of electricity supply,)
(d) the nature of the reaction device) of the applicant on the transmission or
distribution system,
(e) the planned development system)
(f)) and the order of the lodgment of applications
g) limits the performance of the power system trimmer set
the transmission system operator.
(2) if it is necessary for a proper examination of the application, it shall invite the
the transmission system operator or distribution system operator
the applicant no later than within 15 days from the date of receipt of the request to add
the data provided to the extent necessary and stipulate the appropriate
the time limit. At the same time notify the applicant, in the case of nedoplnění data in
to the extent required by the deadline will not be considered in the application.
(3) if the applicant will be asked to supplement the information provided in accordance with paragraph
2 and the applicant to do so, the transmission system operator or
the distribution system operator application is not examined. This fact
shall inform the applicant without undue delay.
(4) if they are not determined by the Energy Act, for which the
the applicant cannot be a device to the transmission system or distribution system
connect to ^ 3), the distribution system operator shall provide to the applicant within 30
days, or in the case of a device connected to the high voltage levels
or very high voltage within 60 days of the submission of a complete application for
connection or from the date of transfer, if the connectivity studies
processing study of connectivity required design connection agreements
or the draft Treaty on the future of the connection. In the case of devices
connected to the transmission system, the time limit for the submission of the proposal
connection agreements or contracts of intent on connecting 90 days
from the submission of a complete application for connection or from the date of transmission of the study
connectivity, if the processing of a study requested by the connectivity.
The transmission system operator or distribution system operator
be determined in the preliminary draft Treaty about the connection or the Treaty on
the connection time limit for the adoption of the draft Treaty of 30 days, if it is
to connect the device to power low voltage level, or 60 days,
If this is about connecting the device to the surface voltage of high voltage
or higher.
(5) If you cannot connect the device of the applicant for the reasons set out
the Energy Act ^ 3), the transmission system operator or
the distribution system operator shall notify this fact to the
to the applicant within 30 days from the submission of a complete application for connection or from the date of
transmission study of connectivity if it has been processing studies
connectivity to require. The transmission system operator or
at the same time the distribution system operator shall state the specific reasons for the
You cannot connect to the device of the applicant. However, if the device can be
applicant attach under different conditions and of the content of the application or of the
the circumstances in which the application was made, it can be assumed that the applicant
such a connection will have an interest in, the transmission system operator
or distribution system operator in writing of such fact
the applicant shall communicate, together with the reasons for which cannot be under the required device
conditions, the applicant shall submit to the mount, and the draft Treaty referred to in paragraph 4.
(6) the preliminary agreement on the connection shall be concluded as a rule, if the
If you connect a device of the applicant requires the construction and technical measures
in the transmission system or distribution system, whose implementation
requires a decision on the location of the building or territorial consent pursuant to
the building Act.
(7) if the examination of the application on the connection necessary to measure
or the system voltage 110 kV validation of network operation, the term
referred to in paragraph 4 or 5 of the time required for measurement or verification operation
the network, a maximum of 30 days. On the necessity of a measurement or verification
network operation and extension of time shall inform the operator of a transmission
system operator or distribution system operator the applicant not later than
15 days from the date of receipt of the request.
(8) the transmission system operator or the owner of the distribution
the system suggests the connection of the device, so that the technical implementation
connection of the device was based on the planned development system when you
also taking account of the applicant's interest to minimize the cost of
the device connects to the transmission system or distribution system.
(9) the transmission system operator or the owner of the distribution
the system reserves the applicant required power or power from the moment
submission of the draft of the Treaty referred to in paragraph 4.
(10) if the applicant does not accept the proposal of the contract within 30 days for a connection to the
low voltage or voltage level within 60 days for a connection to the power
the surface of the high voltage and higher performance or booking, reservation
input ceases to exist.
§ 6
The short connection to the distribution system
(1) Short-term connection means the connection of the provisional devices
According to the Czech technical standards ^ 4) to a distribution system for a fixed period.
(2) in the case of short-term connection serves the applicant request for short term
the connection to the distribution system, separately for each sampling or pass-through
instead. Request of the applicant for short-term connection are listed
in annex 5 to this Decree.
(3) on the short-term connection shall apply mutatis mutandis to section 4 to 5 and § 7. Place
priority specifies the connection, so that was the need for the cost
distribution system operator with the connection.
(4) where the distribution system operator costs related
arrange short-term device connection of the applicant, the applicant shall pay
short connection to the distribution system, the costs associated with
connection including the cost of placing space attaching after their subscription
to its original state in full. Share of the eligible costs under section
10A is not reimbursable.
(5) After the termination of the connection terminates the reserve power consumption; § 7 para.
7 to 9 shall not apply.
(6) If a due to implementation of a short connection to the distribution
system need to increase input in pass-through areas reserved
between the distribution system, in which to implement the short-term connection
occurred, and a distribution system, proceed in accordance with paragraph 4.
§ 7
Device connection of the applicant to the transmission system or distribution
System
(1) the applicant's device Connection to the transmission system or distribution
the system is carried out on the basis of connection agreements.
(2) the Treaty concerning the connection of one applicant can include multiple sampling
or forward sites, as is each of them separately in the contract
stated.
(3) the applicant pays an advance on the costs according to the share of eligible
of annex 6 to this Decree, in the amount of 50% of the value of the share on the
eligible costs, but not more than 50 000 000 CZK. The applicant shall pay
advance on the share of the eligible costs within 15 days from the date of the conclusion of the
connection agreements or contracts of intent about the connection.
(4) if the applicant fails to pay the deposit on a share of the eligible costs referred to in
paragraph 3 or in additional reasonable period of time provided by the operator
the transmission system operator or distribution system operator and
the transmission system operator or distribution system operator
for this reason, the connection terminates the agreement or Treaty Treaty
the future of connectivity, performance or reservation booking input termination
the contractual relationship ceases to exist.
(5) if the connection does not require the applicant's implementation of construction equipment
technical measures in the transmission system or distribution system,
taking out the transmission system operator or the owner of the distribution
system and the applicant, the term connection of electricity production using
solar radiation to electricity production has been attached by
180 days from the date of conclusion of the contract about connection, in the case of the plant
electricity using solar radiation with installed power of 30 kW
within 1 year from the date of conclusion of the contract about the connection.
(6) if the applicant within the time limits referred to in paragraph 5 establishes that despite all
the effort did not occur within the agreed deadlines to implement the connection
production of electricity from the reasons that occur or exist independently of the
his will, the transmission system operator or the operator
distribution system operators shall negotiate with the applicant, an extension of the connection
as long as necessary.
(7) if the agreed reduction of the main circuit breaker before the measurement values
device to a value lower than the reserved input space
connection device for a period longer than 24 months,
the value of the reserved power input to this value.
(8) If, after the period of 60 months from the date of the last change of the reserved
the wattage not for negotiation of reserved capacity of at least 90% of the
reserved the reserved value of power input, power consumption is reduced to
value, which is determined by the highest agreed size reserved
capacity in the period of 60 months from the last changes of the reserved power input.
(9) in the event of termination of the contract of transport or distribution of electricity takes
booking for an existing connection point for a period of 60 months from the
date of termination of the contract. If the contract for the transmission or distribution of
electricity has not been concluded within 60 months from the date of the agreed connection
in the Treaty, the reservation for place of consumption or for the
place the connection terminates.
§ 8
The costs associated with connecting the device to the transmission system or
distribution system and by ensuring the desired wattage or performance
(1) If an applicant under this Ordinance shall bear the costs associated with
connection and to ensuring the desired wattage or the performance in full
the amount of the costs borne by the applicant, include only the costs referred to in
paragraphs 2 to 4.
(2) the costs associated with the connection and to ensuring the desired wattage
or include essential performance incurred eligible costs
related to the acquisition, construction, or alteration of the transmission system
or distribution system that were thrown by the request of the applicant in
connection with the place and the way to connect its devices. Acquisition,
construction or modifications to the transmission system or distribution system are
provided to the extent necessary corresponding value input
or performance required by the applicant, and the place and how to connect it
device.
(3) The costs associated with the connection and to ensuring the desired
the wattage or performance will include the cost of the acquisition project
documentation, geodetic focus, easements and other immediately
investment costs and charges related to the construction, modification or
the acquisition of the Czech transmission system or distribution system.
(4) The costs associated with the connection and to ensuring the desired
the wattage or performance do not include costs associated with the acquisition,
the construction or alteration of the transmission system or distribution system,
that exceed the scope strictly necessary level corresponding to the value
input or output, requested by the applicant, and the place and the way
the connection of the device.
(5) the construction and adjustment of the transmission system is defined from the point of connection
the device of the applicant to the nearest place in the transmission system, where is
or would poprovedení the necessary adjustments in the system was available
the reserved power or performance.
(6) construction and adjustment of the distribution system is defined from the point of
connect the device to the nearest locations in the applicant's distribution system
to the same voltage level, where it is, or would after the necessary
adjustments in the system was available the reserved power or
performance.
§ 9
cancelled
§ 10
The proportion of the applicant for connection to the transmission system or device
distribution system to eligible costs
(1) the applicant's share of the eligible costs shall be calculated as the product of
measuring the proportion referred to in annex 6 to this Ordinance and the applicant
the required input power or the performance of the booked.
(2) in the case of connecting electricity production plants to the transmission system or
the distribution system shall be borne by the management to the point of connection, leaded by the applicant in
the full amount.
(3) if the reserved power and performance simultaneously one applicant in one
the connection point, the share of eligible costs separately for
reservation to reserve the wattage and performance. The applicant shall be paid by the higher of the two
set out the eligible costs of the shares.
section 10a
Reconnect the device to the transmission system or distribution
System
If the transmission system operator or the operator
sampling distribution system, the electrical equipment of the customer that
was limited or interrupted the supply of electricity due to unauthorized
collection, transmission or distribution of electricity, shall be borne by the customer market share
of eligible costs in the amount of
and $1 500) when you connect the low voltage level, voltage
(b) Eur 3 500) when you connect the high voltage or voltage level
higher.
§ 11
The specific requirements of the applicant of the device connection to the transmission system
or distribution system
(1) if the applicant Asks about the connection beyond the standard connection
device, or where a specific method of construction or technical
design the device connects to the transmission system or distribution
the system shall be borne by the applicant justified the costs associated with the implementation of
above-standard connection or a specific building or technical
make connections in full.
(2) booked on the surface of low-voltage power consumption can be converted in
one or more adjacent real estate property, only if the
technically possible and realization of transfer of a reserved power input does not throw
additional costs related to the acquisition, construction or alteration
the distribution system. Similarly when you transfer the reserved
the wattage on the surface of a high or very high voltage in a single
nodal areas appropriate voltage levels.
(3) if the applicant Asks about the connection of the device to a different voltage level than the
to which the device is connected, and required change connection is not
enforced by changing the technical conditions of connection shall be borne by the applicant costs
on the legitimate costs associated with this change in full. In such a
If the amount of the original booked the wattage or performance will not refund
share of the eligible costs under section 10. The provisions of § 7 para. 7 to 9
do not apply.
§ 12
Electrical connection for the supply of electricity
(1) the length of the electrical connections means the length of the shortest construction and
technically feasible routes connections to the ground plan of the projected between
place turn from the distribution system and the main fuse
or the main entrance cable housings.
(2) the length of the electrical connections are not included in part led by
vertically.
(3) for the assessment of whether the electrical connection of the built
or outside the built-up areas in accordance with the building Act ^ 5), it is critical
the location of the connected property.
the title launched
section 13 of the
cancelled
§ 14
cancelled
§ 15
cancelled
section 16 of the
The conditions of the power supply in case of disturbances on sampling and measurement
equipment and in the case of a refusal of access to measurement device
(1)
cancelled
(2) if under the influence of a failure in the supply of equipment or disorders caused by
end customer on the measuring device to limit or interruption
the transmission or distribution of electricity, restores the operator of a transmission or
distribution system on the basis of the notification of the final customer
removal of fault on sampling or measuring device or transfer
distribution of electricity within the time limit under special legislation ^ 7).
The costs associated with restoring the transmission or distribution of electricity shall be borne by
the final customer.
§ 17
Transitional provisions
If the applicant so requests on the basis of the opinion of the operator of a transmission or
distribution system issued under the existing legislation on
conclusion of the contract about connection, the operator of a transmission or distribution
system connection before concluding the contract, reexamine the released
opinion within 30 days from the date of receipt of the request, so that it was in accordance with the
This Decree. In fixing the amount of the applicant's share of the cost
associated with connecting and to ensuring the desired wattage or performance
proceed under the law more favourable to the applicant. At the same time with
the operator thus reflected revised opinion of the transmission or
the applicant of the distribution system, the draft Treaty on the connection. The initial period of
binding opinions in accordance with the existing legislation is extended
about the time that a re-examination of the opinion was based on the previous
the sentence.
section 18
Regulation (EEC)
Shall be repealed:
1. Decree No. 297/2001 Coll. laying down the conditions and
electricity supply to the protected customers.
2. Decree No. 18/2002 Coll., on conditions of connection and transport of electricity
in the electricity grid.
3. Decree No. 300/2003 Coll., amending Decree No. 18/2002 Coll.
conditions of connection and transport of electricity in the electricity grid.
§ 19
The effectiveness of the
This Decree shall enter into force on 1 January 2000. March 2006.
President:
Ing. The firt in r.
Annex 1
REQUIREMENTS FOR AN APPLICATION TO CONNECT TO THE TRANSMISSION OR ELECTRICITY PRODUCTION
DISTRIBUTION SYSTEM
Part And
-information on the applicant
1. the business name of the applicant (to be completed-entrepreneur business
Register).
2. the data on the registration in the commercial register, including the file tags
(to be completed by the applicant-entrepreneur in the commercial register).
3. the name or the name and surname of the applicant (unregistered in business
Register).
4. Date of birth (to be completed by the applicant-natural person).
5. the registered office of the broken down: State, County, municipality of zip/postal code, street and house number,
where applicable, the registration number (to be completed by the applicant-a legal entity).
Place of business in the breakdown: the State, the County, municipality of zip/postal code, street and number
where applicable, the registration number of the descriptive (to be completed by the applicant-natural person
doing business).
6. the first name and surname of the person who is the statutory body, or all of the
persons who are members of the statutory body (to be completed by the applicant-
a legal entity).
7. The address of the place of stay in the breakdown: the State, County, municipality of zip/postal code, street and number
descriptive, or registration number (to be completed by the applicant-natural person
the nonentrepreneurial).
8. Connection-telephone, e-mail.
9. The address for service.
10. Information on data, if the mailbox has been established.
11. The identification number, if one has been assigned.
12. Tax identification number, if one has been assigned.
Part (B)
-device details
1. The location of the production plants of electricity-County, village, cadastral, land
the numbers of the land on which it is located, the number of electricity production
descriptive, or registration number.
2. the type of electricity production.
3. the character of the production of electricity.
4. The dates of the connection.
5. General information about the production of electricity:
5.1. connection of electricity production plants to the transmission system or distribution
System (dielectric layer, the presumed location of the connection,
fit the scheme, territorial connection of individual variants variants)
5.2. Description of the production plants of electricity [total installed capacity power plants,
efficiency of the power plant, the performance of individual blocks, electric
scheme of the blocks, the block type (coal, steam, water, other), a kind of resource
(top, base), the energy produced per year, nominal power factor,
the estimated reliability of the block],
5.3. Description of the block transformer (type, installed power, rated
voltage, voltage short, engaging, conversion, winding turns, range
loss of short and open circuit, short-circuit resistance loss, etc.)
5.4. Description of the generator (type, installed power the apparent and active,
rated voltage, the wiring, the type, the switch drivers, dynamic
constants, as are spare, the reactance time constants, constants
of inertia)
5.5. Description of own consumption (total installed power, rated
voltage, power factor, the starting current).
6. the required reliability of the outlet of the performance.
The applicant shall declare and signature confirms the accuracy and truthfulness of the
all of the above data.
Annex 2
REQUIREMENTS FOR AN APPLICATION ON THE DEVICE CONNECTION TO THE DISTRIBUTION SYSTEM,
A TRANSMISSION OR DISTRIBUTION SYSTEM
Part And
-information on the applicant
1. the business name of the applicant (to be completed-entrepreneur business
Register).
2. the data on the registration in the commercial register, including the file tags
(to be completed by the applicant-entrepreneur in the commercial register).
3. the name or the name and surname of the applicant (unregistered in business
Register).
4. the registered office of the broken down: State, County, municipality of zip/postal code, street and house number,
where applicable, the registration number (to be completed by the applicant-a legal entity).
Place of business in the breakdown: the State, the County, municipality of zip/postal code, street and number
where applicable, the registration number of the descriptive (to be completed by the applicant-natural person
doing business).
5. First and last name of the person who is the statutory body, or all of the
persons who are members of the statutory body (to be completed by the applicant-
a legal entity).
6. Connection-telephone, e-mail.
7. Address for service.
8. Information on data, if the mailbox has been established.
9. Identification number of the
10. Tax identification number
Part (B)
-device details
1. The term connection
2. Basic data for connection to the transmission system or distribution
system:
2.1. submission site,
2.2. the highest dielectric layer,
2.3. single-pole diagram,
2.4. the cadastral map of the territory with the placement of a pass-through space.
3. information about the subscription:
3.1. the requested value of the booked reserved performance, power consumption and
3.2. the current value of the reserved power consumption and reserved performance,
3.3. nature of sampling,
3.4. the time course load,
3.5. power factor and compensation,
3.6. the projected energy consumption for the year.
4. the requirements on the reliability of the delivery (maximum period of interruption
delivery).
5. reverse Options affecting the supply network.
The applicant shall declare and signature confirms the accuracy and truthfulness of the
all of the above data.
Annex 3
REQUIREMENTS FOR AN APPLICATION FOR CONNECTION TO THE ELECTRICAL EQUIPMENT OF THE SAMPLING
A TRANSMISSION OR DISTRIBUTION SYSTEM OF EXTRA-HIGH VOLTAGE LEVELS
VOLTAGE, HIGH VOLTAGE AND HIGH VOLTAGE
Part And
-information on the applicant
1. the business name of the applicant (to be completed-entrepreneur business
Register).
2. the data on the registration in the commercial register, including the file tags
(to be completed by the applicant-entrepreneur in the commercial register).
3. the name or the name and surname of the applicant (unregistered in business
Register).
4. Date of birth (to be completed by the applicant-natural person).
5. the registered office of the broken down: State, County, municipality of zip/postal code, street and house number,
where applicable, the registration number (to be completed by the applicant-a legal entity).
Place of business in the breakdown: the State, the County, municipality of zip/postal code, street and number
where applicable, the registration number of the descriptive (to be completed by the applicant-natural person
doing business).
6. the first name and surname of the person who is the statutory body, or all of the
persons who are members of the statutory body (to be completed by the applicant-
a legal entity).
7. The address of the place of stay in the breakdown: the State, County, municipality of zip/postal code, street and number
descriptive, or registration number (to be completed by the applicant-natural person
the nonentrepreneurial).
8. Connection-telephone, e-mail.
9. The address for service.
10. information on the data locker if it was furnished.
11. The identification number, if one has been assigned.
12. Tax identification number, if one has been assigned.
Part (B)
-device information of the applicant
1. The dates of the connection.
2. Basic data for the involvement of the applicant, within the transmission system device
or distribution system:
2.1. the sampling/submission site,
2.2. the highest level of consumption of the voltage of the electrical equipment,
2.3. single-pole diagram,
2.4. the cadastral map of the territory with the location of the sampling points.
3. information about the subscription:
3.1. the requested value of the reserved power input,
3.2. the current value of the reserved power input,
3.3. nature of sampling,
3.4. type and subscription of connecting appliances (in particular the number and performance
motors, electric furnaces and heating, electric welding equipment, drives
etc.),
3.5. the time course load,
3.6. the power factor and compensation,
3.7. information about whether it will be installed in the point of the backup
the source and in the positive case, its parameters and the expected way
operation.
4. the requirements on the reliability of the delivery (maximum period of interruption
delivery).
5. reverse Options affecting the supply network.
6. information on the production and mounting, or no longer connected to the sampling
device.
The applicant shall declare and signature confirms the accuracy and truthfulness of the
all of the above data.
Annex 4
REQUIREMENTS FOR AN APPLICATION FOR CONNECTION TO THE ELECTRICAL EQUIPMENT OF THE SAMPLING
DISTRIBUTION SYSTEM FROM VOLTAGE LEVELS LOW VOLTAGE
Part And
-information on the applicant
1. the business name of the applicant (to be completed-entrepreneur business
Register).
2. the data on the registration in the commercial register, including the file tags
(to be completed by the applicant-entrepreneur in the commercial register).
3. the name or the name and surname of the applicant (unregistered in business
Register).
4. Date of birth (to be completed by the applicant-natural person).
5. the registered office of the broken down: State, County, municipality of zip/postal code, street and house number,
where applicable, the registration number (to be completed by the applicant-a legal entity).
Place of business in the breakdown: the State, the County, municipality of zip/postal code, street and number
where applicable, the registration number of the descriptive (to be completed by the applicant-natural person
doing business).
6. the first name and surname of the person who is the statutory body, or all of the
persons who are members of the statutory body (to be completed by the applicant-
a legal entity).
7. The address of the place of stay in the breakdown: the State, County, municipality of zip/postal code, street and number
descriptive, or registration number (to be completed by the applicant-natural person
the nonentrepreneurial).
8. Connection-telephone, e-mail.
9. The address for service.
10. Information on data, if the mailbox has been established.
11. The identification number, if one has been assigned.
12. Tax identification number, if one has been assigned.
Part B-information about the applicant's equipment
1. The term connection
2. Basic data on the involvement of the applicant's equipment in the distribution system:
2.1. the sampling/submission site (e.g. establishment of a family house, cottage)
2.2. the cadastral map of the territory with the location of the sampling points.
3. information about the subscription:
3.1. the requested value of the reserved power input,
3.2. the current value of the reserved power input,
3.3. nature of sampling,
3.4. type and subscription of the connected appliances (connection of individual
appliances with a nominal power of 5 kW and above, in particular the number and performance
motors, electric furnaces and heating, electric welding equipment, drives
etc.),
3.5. information about whether it will be installed in the point of the backup
the source and in the positive case, its parameters and the expected way
operation,
4. the requirements on the reliability of supply.
5. reverse Options affecting the supply network.
6. Type and performance of heat pumps.
7. information on the production and mounting, or no longer connected to the sampling
device.
The applicant shall declare and signature confirms the accuracy and truthfulness of the
all of the above data.
Annex 5
REQUIREMENTS FOR AN APPLICATION FOR A SHORT-CONNECT THE DEVICE TO THE DISTRIBUTION
SYSTEM
Part And
-information on the applicant
1. the business name of the applicant (to be completed-entrepreneur business
Register).
2. the data on the registration in the commercial register, including the file tags
(to be completed by the applicant-entrepreneur in the commercial register).
3. the name or the name and surname of the applicant (unregistered in business
Register).
4. Date of birth (to be completed by the applicant-natural person).
5. the registered office of the broken down: State, County, municipality of zip/postal code, street and house number,
where applicable, the registration number (to be completed by the applicant-a legal entity).
Place of business in the breakdown: the State, the County, municipality of zip/postal code, street and number
where applicable, the registration number of the descriptive (to be completed by the applicant-natural person
doing business).
6. the first name and surname of the person who is the statutory body, or all of the
persons who are members of the statutory body (to be completed by the applicant-
a legal entity).
7. The address of the place of stay in the breakdown: the State, County, municipality of zip/postal code, street and number
descriptive, or registration number (to be completed by the applicant-natural person
the nonentrepreneurial).
8. Connection-telephone, e-mail.
9. The address for service.
10. Information on data, if the mailbox has been established.
11. The identification number, if one has been assigned.
12. Tax identification number, if one has been assigned.
Part (B)
-device information of the applicant
1. The date and the duration of the connection.
2. Basic data on the involvement of the applicant's equipment in the distribution system.
3. The sampling/submission site.
4. the Location of the sampling of the electrical equipment.
5. Information about the subscription:
5.1. the required size of the reserved value input/main
circuit breakers,
5.2. nature of sampling.
The applicant shall declare and signature confirms the accuracy and truthfulness of the
all of the above data.
Annex 6
THE SPECIFIC CONTRIBUTION OF THE APPLICANT FOR CONNECTION TO LEGITIMATE COSTS ASSOCIATED WITH
CONNECTION AND SECURING OF THE REQUIRED POWER CONSUMPTION AND PERFORMANCE
FOR BOOKING INPUT
------------------------------------------------------ -------------------------
Instead the connection to the voltage level of the specific contribution of the applicant connection method
------------------------------------------------------ -------------------------
transmission system 200 EUR/MW
HIGH VOLTAGE distribution system and Type 600 EUR/MW
HIGH VOLTAGE distribution system of type B 150 EUR/MW
the distribution system of INDOOR type and 800 EUR/MW
the distribution system of HV type B1 200 EUR/MW
distribution system NN 3 phase connection 500 Kč/A
distribution system NN 1 phase 200 CZK/connection and
------------------------------------------------------ -------------------------
PERFORMANCE FOR A RESERVATION
------------------------------------------------------ -------------------------
Instead the connection to the voltage level of the specific contribution of the applicant connection method
------------------------------------------------------ -------------------------
the transmission system at the connection point
in the opinion of 500 EUR/MW
the operator
the transmission system
HIGH VOLTAGE distribution system type and 1 200 000 Eur/MW
HIGH VOLTAGE distribution system of type B 150 EUR/MW
the distribution system of INDOOR type and 640 000 CZK/MW
the distribution system of HV type B 150 EUR/MW
distribution system NN 3 phase connection 500 Kč/A
distribution system NN 1 phase 200 CZK/connection and
------------------------------------------------------ -------------------------
A Type Of Connection And
This is where the distribution system operator shall extend
distribution system up to a pass-through space, eg.
transformer station or substation of the applicant for connection.
A Type Of Connection (B)
such a connection that does not meet the conditions of the connection.
Connection Type B1
such a connection is not needed when construction of the new dungeons and busbars and
they are only necessary adjustments of a technical nature (e.g. replenishment armament
the Dungeon)
In the case of a connection request, or raise the reserved input
or performance in the objects already connected is to determine the proportion of
eligible costs the determining existing connection method.
Annex 7
CHARACTER COLLECTION
1. the place of consumption of "T1"-supply point with electrical equipment
standard appliances to 16 and that they have the mark of conformity within the meaning of
Act No. 22/1997 Coll.-lighting and electric appliances connected to the
divorce corded (the sockets) or securely attached, with
power consumption of any appliances does not exceed 3.5 kVA.
2. the place of consumption of the type "T2"-supply point with electrical equipment as
for the type "T1", where the water is used for heating, electrical energy (excluding
flow heaters).
3. the place of consumption of "T3"-supply point with electrical equipment as
for the type "T1" or "T2", where cooking and baking using electric
appliances with input above 3.5 kVA.
4. the place of consumption of the type "T4"-supply point with electrical equipment as
for the type "T1", "T2" or "T3", for heating (accumulation,
direct heating, heat pump) or air conditioning use electric
appliances whose consumption is measured for each customer.
5. the place of consumption of "T5" – a place of consumption with electric equipment such as
of a type of "T3" or "T4", which are equipped with additional electrical
appliances that may affect the operation of the network.
1) § 50 para. 3 the Energy Act.
2) § 50 para. 3 the Energy Act.
1) § 50 para. 3 the Energy Act.
3) § 24 para. 10 (a). and) and § 25 para. 11 (a). and) energy
the law.
4) Din 33 2000-1.
5) § 2 (2). 1 (b). (d)) to the building Act.
6) Act 505/1990 Coll., on metrology, as amended.
7) Decree No. 540/2005 Coll., on the quality of electricity supply and
related services in the electricity sector.