16/2016 Coll.
DECREE


Dated 13 January 2016

On conditions for connection to the electricity grid

Energy Regulatory Office (the "Office") pursuant to § 98a paragraph.
2 point. g) of the Act no. 458/2000 Coll., on business conditions and
state administration in the energy sectors and amending certain laws
(Energy Act), as amended by Act no. 211/2011 Coll., to implement § 23
paragraph. Point 1. a) § 24 para. 10 point. a) § 25 par. 10 point. a) and § 28 paragraph
. Point 1. a) Energy Act:

§ 1
Subject Matter


This Decree stipulates

A) conditions for the connection of power plants, distribution systems and supply points
customers to the electricity grid

B) the method of determining the proportion of costs associated with the connection and the
bringing the required power or the performance of electricity and

C) rules for assessing concurrent connection requests.

§ 2
Basic provisions


For the purposes of this Decree

A) reserved input

First value of the electric power in the connection point to the transmission system
MW in basic wiring agreed with the TSO
based on the required input and technical parameters
transmission system at the point of connection to the transmission system, or

Second value of the electric power agreed with the distribution
system based on the desired power at the point of connection to the MW
level very high or high voltage or equal
nominal current of the main circuit breaker before the electrometer A at
connection to low voltage

B) reserved performance

First Performance value of the connected electricity generating plant at the site agreed
connected to the transmission system in MW

Second Performance value of the connected electricity generating plant at the site agreed
connected to the grid in MW, or

Third power in MW negotiated with the TSO for
place grid connection or agreed with the operator
distribution system connection point for other distribution system

C) connection point in the transmission or distribution system, in which
device is connected, either directly, through a plumbing
or through connections and plumbing,

D) an electricity generating plant, distribution system or sampling
electrical equipment

E) mikrozdrojem power source and all related equipment
for electricity production, designed for parallel operation with the distribution system
low voltage is rated AC current up to 16 A per phase
including a total maximum installed power up to 10 kW
including

F) the applicant is a natural or legal person who applies to join
facility to the transmission or distribution system or to change
reserved capacity or performance of an existing installation or connection
mikrozdroje to the grid or to change the character
subscription or a change in the type of electricity generating plant or the plant's installed capacity
electricity, which is authorized to use the device on the basis
property or other rights; for applicants is also considered
natural or legal person in the territory intends to proceed with construction of facilities
a natural or legal person who requests a connection agreement or
modify

G) the installed capacity of electricity generating plant
sum of the rated capacity of the generators; in the case of plants using solar panels
total nominal value of all installed solar panels.

Terms connect the device to the electricity grid

§ 3

(1) The conditions of connection facilities of the applicant to the transmission system or distribution system are


A) connection request

B) connectivity study under the conditions of § 6 and 7

C) a contract of connection between the applicant and the transmission
system operator or distribution system or change existing connection agreements
^ 1).

(2) Paragraph 1 shall not apply and the condition of connecting devices to the applicant
transmission system or distribution system is the only treaty
connection between the applicant and the transmission system or distribution system operator
if it does not
to change the technical conditions in connection


A) change the licensee operating the device without interruption
connecting electricity generating plant (hereinafter referred to as "factory")
to the transmission system or distribution system

B) replacing or modifying the factory, where there is no existing
exceeding the agreed amount of reserved power or to change the type of plant or
to increase installed capacity, while maintaining the standard
conditions, transmission or distribution of electricity || |
C) change in the natural or legal person who is entitled to use
sampling electrical equipment

D) reduction of the reserved power or input device

E) changing customer identification data, or

F) connecting mikrozdrojů under § 16th

(3) A reserved power at the point of connection of the plant
directly connected to the electricity grid or in place of s connection, to which it is attached
factory or the place of connection of the plant to
whose equipment is connected other production may be in the contract agreed maximum
connection as 1.2 times the installed capacity of electricity generating
connected locally connected.

§ 4

(1) An application for connection shall be submitted for each connection separately.
Connection request through the machine

A) before the construction or connecting a new device, except
mikrozdrojů connected to the distribution system, the procedure under § 16

B) before changing the reserved capacity or performance of existing
connected device, except in cases under § 3 para. 2

C) before changing the nature of consumption in accordance with Annex no. 9 hereto,

D) in the case of the change in production,

E) in the case of change of connection to the transmission system or distribution system
,

F) in the case of an increase in installed capacity connected to the grid
.

(2) In the case of plant with an installed capacity of 0.5 MW is further
part of the application for connection of the plant construction schedule preparation
plant. Timetable for the preparation of construction plant lists
decisions, opinions and statements of public authorities and
anticipated dates of their issue, in particular as regards
binding opinion on the impact assessment of the project on the environment,
location of the building, integrated permit, building permit and occupancy permit
agreement, which are necessary for the construction of electricity generating plant.

(3) Requirements for application for connecting different types of devices are
given in Annexes Nos. 1 to 6 hereto.

§ 5

(1) asks if a connection applicant who co-operates
distribution systems and production, it is considered that the requests connection
distribution system, if the technical documentation proves that the connected
the device has the character of production. If the subscriber market
electricity, which is parallel distribution license holder
electricity and electricity, already connected to the transmission system or distribution system
, it is considered that it is connected to the distribution || | system, if the technical documentation proves that the connected device has the character
plant.
Condition to prove the character of the connected device are contained in Annex no. 11 hereto.

(2) asks if the applicant connection that runs parallel sampling
electrical equipment and manufacturing, it is considered that the connection is
factory, if the technical documentation proves that the connected || | sampling device has the character of electrical equipment. Conditions
demonstrate the nature of the connected equipment are included in the Appendix.
11 hereto.

(3) asks if a connection to the transmission system or distribution system
applicant who is licensed to distribute electricity or
holds a license for electricity production, reserves a place for connection to the grid reserved
power and reserved power. If the production
applicant also connected to the transmission and distribution system
reserves are aloof and reserved power consumption for each
connection.

(4) Production can be connected to the customer's supply point, or
delivery point other factories. The connection of the plant to the electricity offtake
site asks a connection agreement concluded by the customer. when connecting

Plant to a delivery point other electricity generating plant proceed as in the case
connection of the plant at the supply point that the application is made and
connection agreement concluded manufacturer, whose production is directly connected to the transmission
or distribution system.

§ 6

(1) The transmission system operator or distribution system
may ask an applicant processing connectivity study,

A) if having regard to all the circumstances clear that the device on which the applicant is applying
connections will affect the operation of the transmission system or distribution system
or

B) asks if the device is connected to a voltage level of high voltage
higher.

(2) Study of connectivity is not required in the case of a reduction
reserved input or output.

(3) If the applicant applies for grid connection to the transmission system
or increasing the reserved input or output in the place
grid connection to the transmission system, providing
processing connectivity study jointly the transmission | || system and distribution system operator.

(4) The object of connectivity study plant or sampling
electrical equipment, assessment of expected impacts
connect devices to operate the transmission system or distribution system.
Subject connectivity study of the distribution system to the transmission system or distribution system
other distribution system further assessment
possible variants of the connection in terms of their cost.

(5) The transmission system operator or distribution system may require
processing connectivity study within 30 days of submission of the
connection. It must also define the desired range
connectivity study.

(6) If the applicant TSO or DSOs
a basis for the study
connectivity within 30 days after receipt of the request for its
processing, transmission system operator or operator || | distribution system, provide the applicant with the information required for processing
connectivity study within 15 days of their request.
Requests if the applicant transmission system operator or the distribution system
of documents for processing connectivity study within 30 days after receipt of the request
its processing
TSO or DSO connection request is examined in .

(7) Unless otherwise requested by the transmission system operator or distribution system operator
processing connectivity study within
pursuant to paragraph 5 or does not give the applicant the documents necessary for processing
connectivity study, it is considered that, that the study
connectivity required.

(8) The applicant for connecting devices to the grid passes
DSOs connectivity study within 90 days
day when the distribution system operator, to the applicant
documents necessary to prepare the study. If the applicant applies for connecting devices to
transmission system passes applicant TSO
study of connectivity within 180 days from the date when the transmission system
gave the applicant the documents necessary to prepare the study, if the
applicant with the transmission system operator agree otherwise.

§ 7

(1) Unless connectivity study prepared within the scope defined
by the transmission system operator or distribution
system, the operator of the transmission system or distribution system operator
require the addition or expansion.
Transmission system operator or distribution system operator may request
complement or extend connectivity study within 30 days from the handover
connectivity study. Unless otherwise requested by the transmission system operator or
distribution system complementing or supplementing
connectivity study in this period, it is considered that the addition or expansion
connectivity study required.

(2) When the TSO complementing or supplementing
connectivity study, transmit applicant supplemented or extended study
connectivity within 90 days of receiving the request
operator of the transmission system, unless otherwise. Processing and transmission

New connectivity study to § 6 par. 8 shall apply mutatis mutandis.

(3) When the DSO complementing or supplementing
connectivity study, the applicant shall supplemented or extended study
connectivity within 30 days of receiving the request
distribution system operator. Processing and transfer to a new study
connectivity with § 6 para. 8 shall apply mutatis mutandis.

§ 8

(1) The transmission system operator or distribution system
considers the request to connect the device with respect to

A) the place and method of the desired connection,

B) the size of the required reserved input or output and
time course load,

C) the reliability of the electricity supply

D) the nature of the reverse action of the equipment of the applicant to the transmission or distribution system
,

E) planned development system

F) order of applications received

G) limits attachable power to the electricity grid set
TSO,

H) the size of installed capacity, and

I) the obligation to preferentially connect an electricity generating plant from aided
power to the transmission or distribution system under the Act on supported energy sources
^ 2).

(2) If it is necessary for a proper assessment of the connection request prompts
TSO or DSO
applicant within 15 days of receipt of the request to supplement the information provided in
needed scope and fix reasonable
period. Simultaneously notifies the applicant that if underfill data
desired range within a specified period the application will not be considered.

(3) If the applicant is requested to supplement the information provided under paragraph 2
and the applicant has not done so, the TSO or DSO
request is examined. This fact
shall notify the applicant without undue delay.

(4) Unless the reasons set out in the Energy Act, for which the device can not be
applicants to the transmission system or distribution system to connect
^ 3) the distribution system operator shall submit to the applicant within 30 days or
if the device connected to voltage level
high or very high voltage within 60 days from the submission of a complete application for
connection or after delivery of connectivity study, if the processing
connectivity study requested, the draft agreement on the connection
or a draft agreement on a future connection. In the case
device connected to the transmission system, the time limit for submitting a proposal
connection agreement or agreement on a future connection
90 days from the submission of a complete application to connect or after delivery of the study
connectivity if the processing connectivity study requested.

(5) If you can not connect the facilities of the applicant of the reasons set out in the Energy Act
^ 3), TSO or DSO
informed in writing of this fact
applicant when the device connected to the low voltage level
voltage within 30 days or if the device connected to the low voltage
level of high or very high voltage within 60 days from the submission of a complete
connection requests or after delivery of connectivity study, if the processing
connectivity study requested.
The transmission system operator or distribution system while specifying
reasons for which the applicant can not connect the device. However, if the applicant can
devices join other conditions, the transmission
system or distribution system operator in writing of such fact
inform the applicant, including the reasons for which it can not be
under the required conditions to attach, the applicant shall submit the draft agreement pursuant to paragraph 4.


(6) When assessing requests for connections necessary to perform measurements
or verify network operation calculation, extending the deadline pursuant to paragraph 4 or 5
about the time required for measurement or verification of operation of the network, not more than || | of 30 days on the surface of HV and 15 days on the surface of HV and LV. About
need to carry out a measurement or verification of operation of the network and the extension of the deadline
inform the operator of the transmission system operator or distribution system
applicant within 15 days of receipt
connection requests.

§ 9


(1) The transmission system operator or distribution system
suggests connecting the device to a technical design
connect devices based on the planned development of the system during
taking into account the applicant's interest to minimize the cost of connecting
facility to the transmission system or distribution system.

(2) The transmission system operator or distribution system
reserves to the applicant the required power or power from the moment
submission of the draft contract pursuant to § 8. 4th

(3) If the applicant does not accept the draft contract within 30 days for connection to
voltage low voltage level or within 60 days for connection to the voltage
high voltage level and higher from the date of submission of the draft agreement by the transmission
system or distribution system
performance reserve or reserve power expires.

(4) In the case of an application relating to the requirement only on reducing
reserved capacity or performance is the deadline for submission of the draft contract
DSO 15 days from the submission of a complete application
.

§ 10

In the event of termination of the contract to ensure service transmission system or service
secure distribution system takes bookings for power
existing connection point for a period of 48 months from the date of termination.
If an agreement on securing the services of the transmission system or to provide services
distribution system was not for the supply of electrical equipment
concluded within 48 months from the date of connection stipulated in the contract
connection reserve power for supply point or instead of connecting
expires.

Method of determining the share of the eligible costs

§ 11

(1) Where an applicant under this decree shall pay the cost
connectivity and the provision of the required input or output in full
amount to be paid by the applicant costs include only those costs by
paragraphs 2 and 3.

(2) The costs associated with connecting and bringing the required power or power
include the necessary costs incurred eligible
related to the acquisition, construction or reconstruction
transmission system or distribution system, which were triggered by request of the applicant
in connection with the place and way to connect his device. Acquisition, construction or modification
transmission system or distribution system are
provided the necessary extent corresponding value
power or performance requested by the applicant, and the location and method of affixing his
devices.

(3) The costs associated with connecting and securing the required
power or performance shall include the cost of acquiring the project
documentation, geodetic surveys and other directly related
investment costs, including the costs directly related to the acquisition
ministry, and reimbursement of costs associated with the construction, alteration, or
acquisition of the transmission system or distribution system.

(4) The costs associated with connecting and securing the required
power or performance shall not include costs related to the acquisition, construction or reconstruction
transmission system or distribution system
scope of which go beyond what is strictly necessary
corresponding to the power or the power required by the applicant, and the place and method of connection
its facilities.

(5) Construction and modification of the transmission system is defined from the connection
facilities of the applicant to the nearest place in the grid where the
or would after making the necessary adjustments in the system was available
required power reserved or performance.

(6) Construction and modification of the distribution system is defined by the place
connect the device to the nearest place applicants in the distribution system
at the same voltage level where it is, or would after making the necessary adjustments
system was to There requested
reserved power or performance.

§ 12

(1) Payment of share of the costs associated with connecting and securing
required input or output (hereinafter referred to as "share of the eligible costs
") is calculated as the product of the unit share in accordance with Annex no. 8 to || | hereto and requested by the applicant
reserved input or output.

(2) In the case of connecting the plant to the transmission system or distribution system
paid takeoff line to the point of attachment claimant in full.


(3) If simultaneously applied for the reservation of power and performance for a
applicants at one point connections, determine the proportion of the eligible costs
extra power for booking and reservation performance.
Applicant pays the higher of the two specified shares eligible costs. Similarly
proceed when it is requested reservation wattage or performance of your current location
s connection or factories that
if the proportion of the eligible costs set for the newly required power or power
is less than or equal to the share of the eligible costs
which is set for the current input or output according to this decree,
applicant does not pay any interest on the eligible costs. In the event that
share of the newly required power or the performance of a higher value than
share, which is set for existing power or performance by the
decree, the applicant pays the higher of the two specified shares authorized || | costs.

(4) Share of eligible costs shall be applied in cases under § 3
paragraph. Second, unless it expired reserve power according to § 10

(5) Based on the contract deposit paid by the applicant to the share of the eligible costs under Annex
no. 8 hereto, amounting to 50% of the value
share of eligible costs, up to a maximum 50,000,000 CZK.
The applicant shall pay an advance on the share of the eligible costs within 15 days from the date of conclusion of the contract
connection or an agreement of intent on
connection.

Terms connect the device to the electricity grid beyond the standard connection


§ 13

(1) If the applicant applies for connecting devices beyond the standard
connection, especially when asking for a specific method of construction and technical design
device is connected to the transmission system or distribution system
, paid by the applicant justified
costs associated with the implementation of the above standard connection or the specific construction and technical design
connection in full.

(2) Reserved power or power to low voltage, it is possible to transfer
within one or more adjacent real estate property
only if it is technically possible and implementation of transfer of reserved
power or power does not cause additional costs related to the acquisition, construction or reconstruction
distribution system. Similarly proceed with the transfer
reserved capacity at the level of high or very high voltage
within a nodal region of the appropriate voltage level.

(3) If the applicant applies for connecting the device to a different voltage level than
to which it is connected, and the required change
connection is not enforced change of technical conditions for connection, the applicant pays the costs associated with
this change in full. In this case, up to the original
reserved capacity or performance share
reimbursed eligible costs under § § 12. Article 10 does not apply.

§ 14

If you connect a transmission system operator or distribution system operator
sampling electrical equipment customers, which
been reduced or interrupted electricity supply due to unauthorized
collection, transmission or distribution of electricity, the customer pays the share || | eligible costs amounting

A) 1,500 CZK when connected to a voltage level low voltage

B) 3,500 CZK when connected to a voltage level of high voltage or high
.

§ 15

(1) Short-term connection means connecting temporary equipment
according to Czech technical standards; 4) the distribution system for a specified period.
Short term can not connect to the grid and factory mikrozdroj.

(2) In the case of short connections applicant submitted an application for a short-term
connect to the grid separately for each supply or transfer
place. Particulars of the application of the applicant for short-term connection
are listed in Annex no. 7 to this Decree.

(3) The short-term connection shall apply mutatis mutandis § 4 to 10 Location
connection is preferably determined so as not to cause the need for cost
DSOs connectivity.

(4) If the distribution system operator
costs associated with providing short-term connectivity facilities of the applicant, the applicant shall pay
a short-term grid connection costs associated with

Connection including the cost of putting access points after the completion of the donation
reinstate the full amount. Share of eligible costs according to §
12 will be reimbursed.

(5) Upon termination of the connection terminates reserve power; § 10
apply.

(6) If due to the implementation of short-term connection to the distribution system
need for additional reserved capacity at delivery points
between the distribution system in which to implement short-term connections
occurred, and another distribution system, proceed in accordance with paragraph 4.

§ 16

Terms mikrozdroje simplified connection to the grid

(1) The simplified connectivity mikrozdroj can be connected to low voltage
.

(2) The applicant mikrozdroje connection to the grid are


A) the measured impedance value at the point of connection to the grid
which is greater than the limit impedance in accordance with paragraph 3,

B) mikrozdroje technical solution that prevents electricity supply
distribution system connection point, with the exception of short overflows
electricity into the grid, which is used for the reaction
limiting device, but that does not increase the voltage a connection point

C) applying for contracts for the connection or to change existing
connection agreements, according to Annex no. 10 hereto and

D) the conclusion of a connection between the applicant for connection mikrozdroje
and distribution system operator or the modification of existing contracts for connection
^ 1), the reserved power is zero.

(3) The applicant shall ensure that measuring impedance of the current loop at the point of connection to the grid
according to Czech technical standards ^ 5) persons with professional qualifications
^ 6). The value limit impedance for power up to 16 A per phase
0.47 Ohm and resources to 10 A per phase 0.75 Ohm. In the event that the
measured impedance value is greater than or equal to limit impedance
applicant may attach mikrozdroj at the supply point only under the conditions
under § 3 para. 1st

(4) The application for the conclusion of a connection or to change existing
connection agreements submitted by the applicant DSOs,
with whom it has entered into an agreement to connect. Particulars of a contract
connection simplified scheme are set out in Annex
no. 10 hereto. Part of the application is the property owner's consent
placement mikrozdroje on his property.

(5) The distribution system operator shall assess the completeness of the information contained in
application pursuant to paragraph 4 within 15 days of application.
If the data are complete and in accordance with the requirements of paragraph 2. a) to
c) the distribution system operator prompts the applicant within 15
days of receipt of the request to supplement the information provided in the required
range and set a reasonable time period. At the same applicant notifies
that when replenishing the data to the required extent by the deadline
application will not be considered. Otherwise send the applicant a draft
connection agreement within 20 days of receipt of the complete application for
conclusion of the connection.

§ 17
Common provisions


(1) the length of the electrical connections means the length of the shortest construction and
technically feasible route connections between projected in the plan
turning point of the grid and the house's main fuse or the main house
cable boxes.

(2) The length of the electrical connections shall not be part of it led
vertically.

§ 18


Transitional provisions
Connection request, the request for the conclusion of a connection or a request for a change
connection agreement filed before the effectiveness of this Decree
assessed under the existing legislation.

§ 19
Repealing provisions


Repealed:

First Decree no. 51/2006 Coll., On conditions of connection to the electricity grid
.

Second Decree no. 81/2010 Coll., Amending Decree no. 51/2006 Coll., On
conditions for connection to the electricity grid.

§ 20
Efficiency


This Decree shall enter into force on 1 February 2016.

Chair:

Ing. Vitásková vr
Appendix 1


TERMS connection requests to the electricity generating plant to the transmission or distribution system


Part A - information about the applicant


First Business Name (completed by the applicant - an entrepreneur registered in the Commercial Register
).

Second Data on commercial registration, including the file number
(completed by the applicant - an entrepreneur registered in the Commercial Register).

Third Name or name and surname (completed by the applicant not entered in the Commercial Register
).

Fourth Date of birth (completed by the applicant - individual).

Fifth Head of division: state, county, municipality with a ZIP code, street and number, registration number or
(completed by the applicant - legal entity).

Place of business in the following categories: state, county, municipality with a ZIP code, street and number
descriptive or registration number (completed by the applicant - natural person
business).

6th Name and surname of the person who is the statutory body or all
persons who are members of the statutory body (completed by the applicant -
legal entity).

7th Address of residence in the following categories: state, county, municipality with a ZIP code, street and number
descriptive or registration number (completed by the applicant - natural person
non-entrepreneurs).

8th Connections - telephone, e-mail.

9th Postal address.

10th Information about the data box, when it was established.

11th Identification number, if assigned.

12th Tax identification number, if assigned.

Part B - information about equipment

First Plant location - county, municipality, cadastral territory, plot numbers
land on which the factory is located, house number or registration number
.

Second Agreement with the property owner by placing the plant on its property


Third For plant with an installed capacity of 0.5 MW to be attached to
distribution or transmission system
schedule preparations for the construction industry.

Fourth Kind of plant.

Fifth Features of electricity.

6th Required term connection.

06.01 Required aloof performance.

9th Basic data on the factory:

07.01 involvement plant to the transmission system or distribution system
(voltage level, the predicted habitat connectivity
unipolar scheme, spatial variations of connection variants)

07.02 Describe the production (total installed capacity of power plants, achievable
power plant, the performance of individual blocks, electrical diagram blocks
block type (coal, steam gas, water, other), type of resource (peak, basic
), produced energy per year, nominal power factor, estimated
reliability block)

07.03 a description of the block transformer (type, installed capacity,
nominal voltage, short circuit voltage, winding connections, transfer, tapping range, short
losses and load losses, short circuit resistance, etc.)

07.04 Description Generator (type, installed capacity of apparent and active,
nominal voltage wiring, the type of driver, switch, dynamic
constants, such as spare reactance, time constants, constants
inertia)

07.05 description of own consumption (total power installed
rated voltage, power factor, inrush current).

8th Required reliability power output.

Affirms and his signature or a facsimile signature confirms
accuracy and truthfulness of all the data.
Appendix 2


Requirements for applications for connection of the plant or parts thereof, to the distribution system through
supply point

Part A - information about the applicant

First Business Name (completed by the applicant - an entrepreneur registered in the Commercial Register
).

Second Data on commercial registration (completed by the applicant - entrepreneur
Incorporated).

Third Name or name and surname (completed by the applicant not entered in the Commercial Register
).

Fourth Head of division: state, county, municipality with a ZIP code, street and number, registration number or
(completed by the applicant - legal entity).
Place of business in the following categories: state, county, municipality with a ZIP code, street and number, registration number or
(completed by the applicant - natural person
business).

Fifth Name and surname of the person who is the statutory body or all
persons who are members of the statutory body (completed by the applicant -
legal entity).

6th Connections - telephone, e-mail.

7th Postal address.

8th Information about the data box, when it was established.

9th Identification number.

10th Tax identification number.

Part B - information about equipment

First Required term connection.

Second Agreement with the property owner by placing the plant on its
Property


Third For plant with an installed capacity of 0.5 MW to be attached to the grid
schedule of preparations for the construction industry.

Fourth Basic data for connection to the grid:

04.01 transfer point,

04.02 the highest voltage level,

04.03 cadastral map with the location of the handover místa-

Fifth Basic information about the involvement of manufacturing supply points:

05.01 single-line diagram, wiring factory supply points, including decay
place

05.02 cadastral map of the area with the location of the place of connection of the plant.

6th Information about the collection and manufacture:

06.01 setpoint reserved input and reserved performance

06.02 the current value of the reserved capacity and reserved performance

06.03 value installed capacity

06.04 character collection,

06.05 timing of collection and manufacturing

06.06 and power factor compensation

07.06 projected consumption and production of energy per year.

7th Requirements for reliability of supply (maximum duration of interruption of supply
).

8th Options Reverse affecting the supply network.

Affirms and his signature or a facsimile signature confirms
accuracy and truthfulness of all the data.
Appendix 3


Requirements for applications for connection of the plant or parts thereof
to the distribution or transmission system through any other electricity generating plant

Part A - information about the applicant

First Business Name (completed by the applicant - an entrepreneur registered in the Commercial Register
).

Second Data on commercial registration (completed by the applicant - entrepreneur
Incorporated).

Third Name or name and surname (completed by the applicant not entered in the Commercial Register
).

Fourth Head of division: state, county, municipality with a ZIP code, street and number, registration number or
(completed by the applicant - legal entity).

Place of business in the following categories: state, county, municipality with a ZIP code, street and number
descriptive or registration number (completed by the applicant - natural person
business).

Fifth Name and surname of the person who is the statutory body or all
persons who are members of the statutory body (completed by the applicant -
legal entity).

6th Connections - telephone, e-mail.

7th Postal address.

8th Information about the data box, when it was established.

9th Identification number.

10th Tax identification number.

Part B - information about equipment

First Required term connection.

Second Agreement with the property owner by placing the plant on its property


Third For plant with an installed capacity of 0.5 MW to be attached to
distribution or transmission system
schedule preparations for the construction industry.

Fourth Basic data for connection to the grid:

04.01 transfer point,

04.02 the highest voltage level,

04.03 single-line diagram, wiring plants including decay place

04.04 cadastral map of the area with the location of the transfer point.

Fifth Information about the collection and manufacture:

05.01 setpoint reserved input and reserved performance

05.02 the current value of the reserved capacity and reserved performance

05.03 value installed capacity,

05.04 character collection,

05.05 time course load

06.05 and power factor compensation

07.05 projected energy consumption per year.

6th Requirements for reliability of supply (maximum duration of interruption of supply
).

7th Options Reverse affecting the supply network.

Affirms and his signature or a facsimile signature confirms
accuracy and truthfulness of all the data.
Appendix 4


TERMS requested to plug in the distribution system
transmission or distribution system

Part A - information about the applicant

First Business Name (completed by the applicant - an entrepreneur registered in the Commercial Register
).

Second Data on commercial registration, including the file number
(completed by the applicant - an entrepreneur registered in the Commercial Register).

Third Name or name and surname (completed by the applicant not entered in the Commercial Register
).

Fourth Head of division: state, county, municipality with a ZIP code, street and number, registration number or
(completed by the applicant - legal entity).

Place of business in the following categories: state, county, municipality with a ZIP code, street and number

Descriptive or registration number (completed by the applicant - natural person
business).

Fifth Name and surname of the person who is the statutory body or all
persons who are members of the statutory body (completed by the applicant -
legal entity).

6th Connections - telephone, e-mail.

7th Postal address.

8th Information about the data box, when it was established.

9th Identification number

10th Tax Identification Number

Part B - information about equipment

First Required term connection

Second Basic data for connection to the transmission system or distribution system
:

02.01 transfer point,

02.02 the highest voltage level,

03.02 single-line diagram,

04.02 cadastral map of the area with the location of the transfer point.

Third Subscription data:

03.01 setpoint reserved input and reserved performance

03.02 the current value of the reserved capacity and reserved performance

03.03 character collection,

04.03 time course load

05.03 and power factor compensation

06.03 projected energy consumption per year.

Fourth Requirements for reliability of supply (maximum duration of interruption of supply
).

Fifth Options Reverse affecting the supply network.

Affirms and his signature or a facsimile signature confirms
accuracy and truthfulness of all the data.
Appendix 5


Requirements for applications for s connection
electrical equipment to the transmission or distribution system from the voltage levels are particularly high
VOLTAGE, very high voltage and high voltage

Part A - information about the applicant

First Business Name (completed by the applicant - an entrepreneur registered in the Commercial Register
).

Second Data on commercial registration, including the file number
(completed by the applicant - an entrepreneur registered in the Commercial Register).

Third Name or name and surname (completed by the applicant not entered in the Commercial Register
).

Fourth Date of birth (completed by the applicant - individual).

Fifth Head of division: state, county, municipality with a ZIP code, street and number, registration number or
(completed by the applicant - legal entity).

Place of business in the following categories: state, county, municipality with a ZIP code, street and number
descriptive or registration number (completed by the applicant - natural person
business).

6th Name and surname of the person who is the statutory body or all
persons who are members of the statutory body (completed by the applicant -
legal entity).

7th Address of residence in the following categories: state, county, municipality with a ZIP code, street and number
descriptive or registration number (completed by the applicant - natural person
non-entrepreneurs).

8th Connections - telephone, e-mail.

9th Postal address.

10th Information about the data box if it has been furnished.

11th Identification number, if assigned.

12th Tax identification number, if assigned.

Part B - information about equipment

First Required term connection.

Second Basic data for connecting the device to the applicant's transmission system or distribution system
:

02.01 offtake / delivery points,

02.02 the highest voltage level the consumption of electrical devices

03.02 single-line diagram,

04.02 cadastral map of the area with the location of the sampling sites.

Third Subscription data:

03.01 setpoint reserved input,

03.02 the current value of reserved capacity,

03.03 character collection,

04.03 type and consumption of connected appliances (especially the number and performance
engines, electric furnaces and heating, electric welding equipment, drives
etc.)

05.03 time course load

06.03 and power factor compensation

07.03 Information on whether the supply point will be installed
backup source and, if so, its characteristics and intended
operation.

Fourth Requirements for reliability of supply (maximum duration of interruption of supply
).

Fifth Options Reverse affecting the supply network.

6th Information about the production or the accessory is already connected to the sampling device
.

Affirms and his signature or a facsimile signature confirms
accuracy and truthfulness of all the data.
Annex 6


Requirements for applications for s connection
electrical equipment to the distribution system from the voltage level LOW VOLTAGE

Part A - information about the applicant


First Business Name (completed by the applicant - an entrepreneur registered in the Commercial Register
).

Second Data on commercial registration, including the file number
(completed by the applicant - an entrepreneur registered in the Commercial Register).

Third Name or name and surname (completed by the applicant not entered in the Commercial Register
).

Fourth Date of birth (completed by the applicant - individual).

Fifth Head of division: state, county, municipality with a ZIP code, street and number, registration number or
(completed by the applicant - legal entity).

Place of business in the following categories: state, county, municipality with a ZIP code, street and number
descriptive or registration number (completed by the applicant - natural person
business).

6th Name and surname of the person who is the statutory body or all
persons who are members of the statutory body (completed by the applicant -
legal entity).

7th Address of residence in the following categories: state, county, municipality with a ZIP code, street and number
descriptive or registration number (completed by the applicant - natural person
non-entrepreneurs).

8th Connections - telephone, e-mail.

9th Postal address.

10th Information about the data box, when it was established.

11th Identification number, if assigned.

12th Tax identification number, if assigned.

Part B - information about equipment

First Required term connection

Second Basic data on the device is connected to the applicant's distribution system:

02.01 offtake / delivery points (eg. business, genus. house, cottage)

02.02 cadastral map of the area with the location of the sampling sites.

Third Subscription data:

03.01 setpoint reserved input,

03.02 the current value of reserved capacity,

03.03 character collection,

04.03 type and consumption of connected appliances (
connect individual appliances with power inputs of 5 kW and higher, in particular the number and performance
engines, electric furnaces and heating, electric welding equipment, drives
etc.)

05.03 Information on whether the supply point will be installed
backup source and, if so, its characteristics and intended
operation.

Fourth Requirements for reliability of supply.

Fifth Options Reverse affecting the supply network.

6th The type and capacity of heat pumps.

7th Information about the production or the accessory is already connected to the sampling device
.

Affirms and his signature or a facsimile signature confirms
accuracy and truthfulness of all the data.
Annex 7


Requirements for applications for short-term connection EQUIPMENT FOR DISTRIBUTION SYSTEM The


Part A - information about the applicant

First Business Name (completed by the applicant - an entrepreneur registered in the Commercial Register
).

Second Data on commercial registration, including the file number
(completed by the applicant - an entrepreneur registered in the Commercial Register).

Third Name or name and surname (completed by the applicant not entered in the Commercial Register
).

Fourth Date of birth (completed by the applicant - individual).

Fifth Head of division: state, county, municipality with a ZIP code, street and number, registration number or
(completed by the applicant - legal entity).

Place of business in the following categories: state, county, municipality with a ZIP code, street and number
descriptive or registration number (completed by the applicant - natural person
business).

6th Name and surname of the person who is the statutory body or all
persons who are members of the statutory body (completed by the applicant -
legal entity).

7th Address of residence in the following categories: state, county, municipality with a ZIP code, street and number
descriptive or registration number (completed by the applicant - natural person
non-entrepreneurs).

8th Connections - telephone, e-mail.

9th Postal address.

10th Information about the data box, when it was established.

11th Identification number, if assigned.

12th Tax identification number, if assigned.

Part B - information about equipment

First Requested date and duration of the connection.

Second Basic data on the device is connected to the applicant's distribution system.

Third Sampling / delivery point.

Fourth Location offtake of electrical equipment.

Fifth Subscription data:

05.01 Setpoint reserved input /
size of the main circuit breaker

05.02 character collection.

Affirms and his signature or a facsimile signature confirms
accuracy and truthfulness of all the data.

Annex 8


Applicant's unit share CONNECTION TO ELIGIBLE costs associated with
connection and providing the required Input and output




Wattage per booking ----------------------------------------- -----------------------------------------------
instead of connecting to a voltage level connection unit share of
------------------------------------- -------------------------------------------------- -
transmission system CZK 200,000 / MW
distribution system HV Type A 600 000 CZK / MW
distribution system HV Type B 150 000 CZK / MW
distribution system VN 800 000 CZK / MW || | HV distribution system type B1 200 000 CZK / MW
distribution system LV three-phase connections 500 CZK / A
distribution system NN 1 phase connection CZK 200 / A ----------
-------------------------------------------------- ----------------------------


PERFORMANCE FOR RESERVATION ----------------------------------------- -----------------------------------------------
instead of connecting to a voltage level connection unit share of
------------------------------------- -------------------------------------------------- -
transmission system at the connection
in the opinion of CZK 500 000 / MW
operator
transmission system
distribution system HV Type A 1 200 000 CZK / MW
distribution system HV Type B 150 000 CZK / MW
distribution system VN Type A 640 000 CZK / MW
distribution system VN Type B CZK 150,000 / MW
distribution system LV three-phase connections 500 CZK / A
distribution system NN 1 phase connection CZK 200 / A ----------------
-------------------------------------------------- ----------------------


A type is a connection, the operator of the distribution system expands
distribution system up to the transfer point, which is, for example.
Transformer substation or the applicant for connection.


B type connection is a connection that does not meet the conditions of connection type A.

Connection Type B1
such a connection when the applicant connects directly to the substation
DSOs and is not necessary for building new cells and
busbars and are only necessary technical amendments (eg.
supplementing armed dungeon)

In case of request for connection or increase
reserved capacity or performance in buildings already connected for determining the amount of shares eligible costs
critical current connection method.
Appendix 9


Nature of consumption

First The sampling instead of "T1" - consumption instead of electrical equipment
standard appliances up to 16 A, which are labeled in conformity sense
Act no. 22/1997 Coll., As amended - lighting and electrical
appliances to be attached to divorce a flexible cord (on
sockets) or firmly attached, the power of any appliance
does not exceed 3.5 kVA.

Second The sampling instead of "T2" - sampling site with electrical equipment such
by a "T1", where the water heater uses electrical energy (excluding
instantaneous water heater).

Third The sampling instead of "T3" - sampling site with electrical equipment such
by a "T1" and "T2", where the cooking and use electrical appliances
wattage than 3.5 kVA.

Fourth The sampling instead of "T4" - sampling site with electrical equipment such
by a "T1", "T2" and "T3", where heating (accumulator,
direct heating, heat pump) or cooling use electric | || consumers whose consumption is measured by individual buyers.

Fifth Extraction point type "T5" - sampling site with electrical equipment such
with a "T3" or "T4", which are equipped with other electrical appliances
that may affect the operation of the network.
Annex 10


TERMS OF APPLICATION FOR CONTRACT TO JOIN OR A CHANGE
EXISTING CONTRACTS TO JOIN IN CONNECTION WITH THE CONNECTION TO MIKROZDROJE
distribution system

Part A - information about the applicant

First Identification of the customer (business name, VAT number or name, and
date of birth, place of residence).

Second EAN outlet.

Part B - data mikrozdroji

First Required term connection.

Second Data on mikrozdroji:


02.01 installed capacity mikrozdroje,

02.02 the existence of devices for storing electrical energy (battery) and
its capacity in Ah.

Part C - mandatory appendices to the application

First Simple documentation of the mikrozdroje comprising:

01.01 Technical Report

1.1.1. Description of equipment - the kind mikrozdroje

1.1.2. For PVP type and number of unit power kW photovoltaic panels

1.1.3. The type, number and label generator parameters (inverters for photovoltaic plants)
active power, apparent power, power factor, number of phases, manufacturer

1.1.4. Possibility of island operation

1.1.5. Types, parameters and setting values ​​of its manufacturing,

1.1.6. Involvement in storage (batteries) if installed

02.01 Drawing documentation

1.2.1 Single-line diagram mikrozdroje including involvement
supply point showing the decay point

03.01 Report on initial revision of electrical equipment containing
requirements according to CSN including:

1.3.1 Readings fault loop impedance at the connection
(the house's main fuse box or cable)

Affirms and his signature or a facsimile signature confirms
accuracy and truthfulness of all the data.
Annex 11


CONDITIONS OF PROOF OF CHARACTER connected device ACCORDING TO TECHNICAL DOCUMENTATION


To determine the nature of the connected device is an essential criterion
involvement factory, or the location of production sites in decay
relation to the involvement of the connected equipment.

If a factory involved so that its location allows decay
traffic island connected device or at least part thereof, it is understood that
it is the connection of the plant to the distribution system diagram in Fig. 1 .

If manufactory connected so that it does not decay instead island
operation of connected equipment, or at least part thereof, it is understood that
is a sampling device connected to the grid, chart
Fig. 2.




1) § 50 par. 3 of Law no. 458/2000 Coll., On business conditions and
state administration in the energy sectors and amending certain
acts (Energy Act), as amended.

2) § 7 para. 1 of Act no. 165/2012 Coll., On supported energy sources
and amending certain laws, as amended.

3) § 24 para. 10 point. a) and § 25 par. 10 point. a)
Energy Act.

4) CSN 33 2000-1 ED.2. Electrical low-voltage installations - Part 1: Basic
perspective, determine the basic characteristics definition.

5) CSN 33 1500 Electrical regulations.
Revision of electrical devices.

6) § 9 of Decree no. 50/1978 Coll., On professional competence in electrical engineering
, as amended.