Advanced Search

Nanning Municipal People's Government On The Revision Of The Decisions Of The Management Of Construction Cost In Nanning City

Original Language Title: 南宁市人民政府关于修改《南宁市建设工程造价管理办法》的决定

Subscribe to a Global-Regulation Premium Membership Today!

Key Benefits:

Subscribe Now for only USD$40 per month.

In order to advance the reform of the administrative approval system and the transformation of government functions in accordance with the law, the promotion and security of government management is shifted to ex post facto regulation by ex-recruit approval, further stimulated market dynamism, development momentum and social creativity, and, at the request of the State and self-government zones, I had established a basis for administrative approval, limited non-public economic development provisions and pre-entry clearance. After cleaning, it is now decided to amend the construction of construction works in Southen City as follows:

i. Delete the “Establishmental advisory contract” in article 5, paragraph 1.

Delete article 13, paragraph 3.

Delete article 26.

Delete the “providing, merging, ending operations and changing names, addresses, statutory representatives” in article 27 shall be registered from 15 days from the date of the change.”

In addition, individual language changes were made and adjustments were made in the order of the relevant provisions.

This decision is implemented since the date of publication.

The Southen City Construction Purchase Management Approach is re-published in accordance with this decision.

Modalities for construction in the Southen City

(Act No. 5 of 21 March 2007 of the People's Government Order No. 5 of 21 March 2007, amended by the Decision of the Government of the South Innin on 17 February 2015 on the revision of the scheme of construction of construction in the Southen City)

Article 1 promotes the health development of the construction market, in accordance with the relevant legal regulations, in order to regulate the operation of the construction price, to determine and effectively control the construction of works, to preserve the legitimate rights and interests of the parties involved in construction.

Article 2 engages in construction of housing buildings and municipal infrastructure within this city's administration and applies this approach.

The management of professional works such as transport, water, electricity, etc., provides that the State provides otherwise.

Article III of this approach refers to the construction of construction works as described in this approach, which refers to the full engineering costs required for construction work from the construction to the completion of the process.

This approach refers to construction work-making activities, including investment estimates preparation, clearance and project economic evaluation; design of budget estimates, construction map budgets, completed work settlement, tendering, control prices, tender preparation and clearance of tenders; adjustments in construction of construction contract prices; creation of price visas and price claims; construction of work price controls at all stages; construction of price-based budgeting and supervision of construction work-based industries.

Article IV. Construction of work-making activities should be guided by the principles of equity, justice, legitimacy and good credit.

Article 5

(i) Preparation, revision and interpretation of the basis for construction works in the city;

(ii) The establishment and refinement of the construction of the engineering price database and the publication of information on construction works;

(iii) The construction contract and the preparation of the price outcome document;

(iv) Oversight management of the qualifications of the construction of engineering consulting enterprises, the qualifications of the construction of engineering-based professionals and professional activities;

(v) Disputes relating to construction.

The municipal construction work-making authority is responsible for the construction of specific work on the construction of engineering price management, as set out in this approach.

The establishment of administrative authorities in the district is responsible for the management of construction of engineering prices.

The sectors such as development and reform, finance, audit, are governed by the law, within their respective responsibilities.

Article 6.

Article 7

(i) The construction of engineering estimates indicators, the proposed budget indicators, the estimated budget levels, the amount of consumption, the amount of expenditure, the amount of work, the length of work, the unit valuation form, the engineering value table;

(ii) A list of price and related provisions for construction works;

(iii) Market reference price and engineering technology economic indicators, price indexes, etc. issued by the municipal construction engineering construction work-making authority;

(iv) Adjustment indices for the element of the construction price and their provision for adjustments in the prices;

(v) Other provisions of laws, regulations.

Article 8.

Article 9

Article 10

Article 11. Fully use of State-owned funding investments or construction projects with State-owned funding investments, tenders should be used in the form of value-added projects; and other construction projects encourage the introduction of a list of works.

The application of the engineering inventory price should be subject to the provisions of the national, self-government and the market for the inventory value.

Article 12. The construction of a list of engineering costs and the introduction of a single price contract, the accuracy and integrity of inventory projects and work volumes are vested with the solicitor, the obligation not validated in the bidder's tenders; the accuracy of the single price and the cobalt is vested with the bidder, the price of the single price is inconsistent with the price and the unconfirmed when the construction contract is concluded, and the liquidation shall be not conducive to the interpretation of the bidder.

Article 13

In accordance with the work of the legal solicitation, the bidder will have to file a request for the establishment of administrative authorities in the subsoil or controlled price, in which the Government's investment works are subject to approval by the financial sector.

Article 14.

(i) The determination of the contract price;

(ii) The scope of the contract;

(iii) Quality standards and duration of work;

(iv) Materials or equipment procured by the solicitor by law;

(v) The method of processing errors, omissions;

(vi) In the event of changes in construction, the methodology for adjustments in the amount of the works, the manner of the claim, the time-bound requirements and the manner in which the amount is paid;

(vii) Scope of risks, ranges;

(viii) Modalities, time and amount allocated to the Engineering Section;

(ix) Procedures and time frames for settlement;

(x) The date of completion, the duration of work and its early or extended awards and penalties;

(xi) The amount, prefabrication and time frame for the quality assurance of work (insurance);

(xii) Liability for default;

(xiii) Other factors affecting the construction of works.

The construction works that are not tendered by law shall be made clear by the contracting parties in construction contracts.

The construction of tenders by law and the construction of the construction contract price should be determined in accordance with the threshold price, and the contracting parties shall not enter into any other agreement that departs from the substantive content of tender documents.

Article 15. The following costs in construction works are included in limiting competition costs, which are implemented at rates established in the self-government area and in the city of South Africa:

(i) Exhumation of work;

(ii) Purchase of work;

(iii) Social security payments;

(iv) Housing pools;

(v) Risk accident insurance;

(vi) Security protection, civilization construction measures.

Article 16 provides that the licensor shall report the contract document to the municipal, district-building administrative authorities within 15 days of the date of the construction of the construction contract.

Post-reviewed construction works contracts are changed by law and the lender shall change the contract reserve within 15 days of the contract change.

Article 17 uses national fund investments or construction projects that are owned by State-owned funding investments, and approved design estimates are the control indicators for the project investment, without approval by the project approval sector, without breakthrough.

Article 18 Changes in engineering design and incremental reductions in engineering shall be strictly in accordance with the agreement on construction contracts and the related provisions for the processing of visas.

The full use of State-owned funding investments or construction projects that are central to State-owned funding investments has resulted in more than specified works for the design of changes or other reasons, and the construction units should send the change programme and the accompanying price documents to the project approval sector, which may be implemented by the relevant departments of the organizations of the former project approval sector.

After the completion of the work, the contractor shall submit to the licensor, within the agreed time frame, the completed settlement report and complete settlement information. The construction contract was not agreed or agreed to be undetermined and should be accompanied by the submission of the completed inspection report and the complete settlement information.

Article 20 shall be subject to a review of the completion report in accordance with the agreed time frame for the construction of the construction contract, which is not agreed or undetermined, and shall be completed or commissioned by the appropriate body to complete the review and make observations as set out below:

(i) The construction project of 500,000 dollars (with $5 million);

(ii) The construction project of 500,000 dollars (including 20000,000 dollars)

(iii) Work projects of €50 million (50 million dollars) for the year 2000, 45 days;

(iv) The construction project of €50 million (US$ 1 billion), 60 days;

(v) More than 100 million works, 90 days.

The construction project includes a number of single works, and the contractor should summarize the completion of the completion of the completion of the final single construction review and send the sender within 15 days of the confirmation of the completion of the completion of the completion review.

Article 21 Once agreed or provided, the licensor did not make observations on the completion of the work settlement report and the settlement of the information, which was considered to be endorsed.

The contractor did not provide complete engineering settlement information within the time frame of agreement or provision, which was not provided or did not provide a clear response within 15 days of the written reminder by the author, and the author was entitled to review the information already available.

Article 2, paragraph 2, provides for mediation by a licensor or contractor who has not completed the completion of the work settlement within the specified period or objected to the settlement outcome document.

Article 23. Upon completion of the construction work, the licensor shall send the complete engineering settlement document to the municipal, district-building administrative authorities when the construction work is completed.

Article 24 encourages the development and application of computer software in construction works.

The municipal construction work-making authority should develop a harmonized e-data regulation for the construction of engineering prices and provide harmonized electronic data standards for the collection, analysis, processing, transmission and reuse of construction information.

Article 25. The construction of engineering consulting enterprises shall obtain a certificate of qualifications for the construction of administrative authorities in the State or in the self-government area, and undertake construction work-making activities within the scope of the award.

Article 26

Article 27 practitioners involved in construction of construction works must obtain professional qualifications certificates from national, self-governing administrative authorities and take advantage of construction work-making operations within the professional scope of registered units and qualification certificates.

Article 28 provides units such as construction of engineering surveys, design, construction, treasury, price counselling, solicitation, price management and priority-building projects, real estate development, and the construction of agents, which should be equipped with registered engineering engineers.

The construction engineering design estimates, the construction map budget, the completion of the work settlement documents should be signed by the registered engineers and incorporated into the exclusive chapter of the Gégué administration, and the units of the non-registered engineer may be signed and added to the governing body; the tendering or engineering budget control price, the list of works, tendering, engineering clearance and engineering value identification documents, and shall be signed by the registered engineer and incorporated into the governing body.

The preparation units and the registration of price engineers, construction agents assume legal responsibility for the results of the construction price.

Article 29

Any unit or person has the right to report or lodge a complaint in violation of the provisions relating to construction of construction.

Article 33

(i) Removal, sale, rent, borrower certificate, or unlawful transfer of credit certificates;

(ii) Excluding the scope of the work-making process;

(iii) At the same time, the solicitation and tenderer or more tenderer are accepted to consult the work-making process for the same engineering project;

(iv) Inadequate competition, for example, for the granting of repayments and for malicious pressure;

(v) The construction consultancy operation for the pipeline;

(vi) Other acts prohibited by law, regulations.

Article 33

(i) borrowing, transferring, selling, adapting professional qualifications, professional printing, manuals for the operation or allowing others to engage in price-making activities in their own name;

(ii) Registration and operation at the same time in two or more units;

(iii) Work construction activities on behalf of individuals;

(iv) Disadvantages, malicious collation, leading, or a clear preference for a party when the engineering price dispute is identified;

(v) The use of the work to obtain, receive gifts or other property other than the award contract agreement;

(vi) Non-controversarial or doubt in the construction price management process in accordance with the provisions and procedures of the construction price management;

(vii) Other acts prohibited by law, regulations.

In accordance with article 32, the preparation of the enterprise, the preparation of the document shall ensure the accuracy of the outcome document of the construction price. The preparation of the proposed budget, the construction map budget document would not exceed 10 per cent; the preparation of tenders, control prices, and completion of the work settlement documents would not exceed 3 per cent.

Article 33 provides for the full use of State-owned funding investments or construction units with State-owned funding investments, in violation of this approach, one of the following cases is administratively disposed of by the relevant management against the direct responsibilities and supervisors; the construction project is yet to be corrected and corrective by the project approval sector.

(i) Without approval by the Project Approval Unit, changes in construction content, scale-building, and improvement of construction standards, resulting in higher construction costs than approval of the approved design budget;

(ii) Resistance in business activities related to construction costs, such as engineering changes and visas, and do not carry out their duties.

Article 34, the construction consulting firm violates article 33, which is documented by the municipal, district-building administrative authorities, is correct and fined by more than 300,000 dollars; in exceptional circumstances, it may be brought to a lower or write-off of their qualifications by the competent authority.

Article 33 fractures in construction works are converted by administrative authorities in urban, district and district construction and fines of up to $50 million in 20000; in exceptional circumstances, they may be brought to the competent management to write their qualifications.

Article 36 Developments of enterprises, preparers in violation of article 33, deliberately or resulting from major negligence, resulting in excess of the discount rate, with the suspension of their participation in tendering activities in tangible construction markets for three months by municipal, district-building administrative authorities; in exceptional circumstances, prohibiting their participation in tendering activities in tangible construction markets and imposing a fine of up to 5,000 dollars for the preparation of enterprises.

Article 37 builds the administrative authorities and the staff of the construction of the construction of the engineering price management body, pays administrative disposal by their superior organs or authorities in the event of the construction of price management.

Article 338 of this approach provides for the floor of tendering, the control of prices, construction contracts, settlement-based billing documents, which apply to the full use of State-owned fund investments or construction works with State-owned funds, as well as construction works with other construction costs of $300,000.

Article 39 of this approach was implemented effective 1 May 2007.