Hunan Provincial Key Construction Project Management Methods

Original Language Title: 湖南省重点建设项目管理办法

Subscribe to a Global-Regulation Premium Membership Today!

Key Benefits:

Subscribe Now for only USD$40 per month.

(Prelease No. 169 of the Order of the People's Government of the Southern Province of the Lake, 8 May 2003)

Article 1 ensures the smooth conduct of the construction of priority projects in order to regulate project management and develop this approach in line with the relevant laws, regulations.
The management of national focus-building projects and provincial priority-building projects (hereinafter referred to as priority-building projects) in the current province's administration is applicable. The State also provides for the provision.
This approach refers to provincial priority-building projects approved by the Government of the province that have a significant impact on the economic and social development of all provincial nationals.
Article 3. The provincial priority-building office assumes the day-to-day work of the provincial people's management priorities.
The provincial Government's development plans, finance, construction, national land resources, transport, water, forestry, material and environmental protection are governed by priority construction projects within their respective mandates.
People's governments at all levels and their work sectors, relevant units should support the construction of priority-building projects and ensure the smooth conduct of priority-building projects.
Article IV provides a written application for the next annual industry, the priority building projects in the region before the end of October, following a comprehensive balance between the provincial priorities and the provincial government development plans.
The declaration of the national focus on construction projects and the identification of implementation in accordance with the relevant national provisions.
Following approval of the feasibility study on priority-building projects, the investors established project legal persons in accordance with the relevant provisions of the State, with project legal persons responsible for the construction of priority construction projects.
The establishment of a project legal person to apply the provisions of the company law. The list of senior managers, including members of the Board and the overall manager of the project, was sent to the provincial priority-building office within 15 days.
Article VI focuses on construction projects and the survey, design, construction, treasury and procurement of essential equipment, materials, which are made public by project legal persons. In the case of article 16 of the Modification Law of the People's Republic of China, the project legal persons may invite tenders, with the approval of the Government of the Provincial People's Republic of China, and in the case of article 5, paragraph 2, of the Module Law of the People's Republic of China, the project legal persons may, with the approval of the Government of the people of the province, adopt other modalities other than tendering.
The Provincial People's Government Development Plan and other relevant administrative oversight departments perform their supervisory duties with respect to the activities of tendering for priority construction projects under the law, receive complaints and investigate offences committed in the solicitation activities under the law.
Project legal persons who focus on construction projects will present solicitation documents and other related information on the administrative oversight sector, while reproducing the provincial focus-building office.
Article 7. Project legal persons who focus on construction must be entrusted to the institution of the institution for the preparation, construction, renovation of investments, work periods and quality of priority construction projects.
Article 8. Project legal persons with a focus on construction projects, after the completion of surveys, designs, land demolitions, construction and treasury contracts, have reported on start-up work and reported to the Government of the province for approval. National focus-building projects are also provided for by their provisions.
Article 9. Project legal persons, project authorities, the city government of the project area at the project site should be carefully implemented by the Government of the Provincial People's Government's Profile of the Focus Construction Project Mandate, which was completed by the Government of the province in accordance with the objectives of responsibility, and rewarded the units of excellence in the construction of the priority construction project and those who made special contributions.
Article 10 focuses on the construction of land for use by the people of the relevant municipalities, counties (communes, areas) following the approval of the law. The provincial authorities of the Land Resources Administration will work with the relevant municipalities, districts (communes, districts) people's governments to ensure the smooth start-up and normal conduct of priority construction projects, as requested by the Government of the province.
Priority-building projects for land and dismantling should be compensated and placed in accordance with the law, and project legal persons should ensure that compensation, resettlement costs are fully in place in a timely manner.
Article 11. Project legal persons with a focus on construction should prepare the guidance-based construction organization design in accordance with the overall requirements of the Focus Building Project Mandate. The design, construction, treasury and equipment supply units should be implemented in accordance with the Steering Organization design.
Article 12 Project legal persons with a focus on construction shall not be subject to the construction of the engineering amputation package and shall not require the design, construction units to reduce the quality and safety standards of the work, and shall not require the construction units to use material, equipment that does not meet the design requirements.
Project legal persons should perform supervisory duties in accordance with the relevant national regulations.
Units such as survey, design, construction and treasury are responsible for the quality of work and obligations under their respective responsibilities.
units such as survey, design, construction, treasury and equipment supplies may not be transferred to the engineering projects covered by the package. Some non-partisan and non-critical work would be required to be subcontracted to others and should be made clear in the solicitation documents and accompanied by specific subcontracting programmes; and no subcontracted as indicated in the tender documents.
Article 14 provides for the quality of the work performed by the legal representative and the relevant responsibilities of the project manager and the survey, design, construction, treasury, etc., with a focus on the construction of the project, and shall not be exempted for the reasons for the work of the parties or changes in their functions, retirement or reclassification.
Article 15. Project legal persons with a focus on construction should establish sound priority-building project construction archives, in accordance with national and provincial provisions on the construction of archives management, to ensure the integrity and integrity of archival information.
Article 16 Emphasis-building project-building parties should ensure that priority-building project progresses, the sound security production system, the design of safe production organizations, the adoption of safety-technical measures to avoid security accidents.
Project legal persons with a focus on construction should raise funds in line with the project's annual investment plan to ensure that funds are fully in place in a timely manner. National investment-led construction projects should strictly implement approved engineering estimates without spearheading.
The survey, design, construction, treasury and equipment supply units focusing on construction projects should be organized in accordance with the contractual agreement, with funding, personnel, equipment and technical forces being involved in project construction.
Article 17 states, districts (communes, districts) that focus on the construction of project sites should be maintained by law in order to put an end to the obstruction of project construction. Public security authorities that focus on the construction of project sites should strengthen the focus on building project policing and combat criminal activities that undermine the construction of priority projects in accordance with the law.
Article 18 units such as electricity, transport, telecommunications, water supply, and gas should perform their duties in accordance with the contractual agreement, giving priority to the need for priority construction projects.
Article 19 concerned sectors should strictly implement national and provincial preferences for priority-building projects, in a timely manner, in accordance with the relevant procedures for priority-building projects.
No unit shall be subjected to hardship, obstruction of the construction of priority projects and shall not be charged with incest charges, incest fines and assessments for priority construction projects.
Article 20, after the completion of the project construction project, is the preliminary receipt of the project's corporate organization. Preliminary tests are eligible and carried out through probationary operations and are completed in accordance with national provisions. National focus-building projects are governed by national provisions.
Article 21, the provincial priority-building office should enhance the scrutiny of priority-building projects. The inspection may take the following:
(i) Hearing reports of project legal persons and survey, design, construction, management, equipment supply units, and participating in relevant meetings on priority construction projects;
(ii) Access to engineering information from project legal persons and survey, design, construction and treasury units;
(iii) Information on funding use and management of priority construction projects to development plans, financial, auditing and banks;
(iv) To guide, promote the recruitment, removal and compensation and resettlement of priority construction projects;
(v) On-site knowledge of tenders, contract performance and quality of work, progress in the period of work, safe production and integrated management of priority construction projects;
(vi) To urge project legal persons or survey, design, construction, supervision, equipment supply units to correct violations;
(vii) Coordinate the relationship between the relevant sectors and the city, the city, the district and the Government of the people with the focus on the construction of the project to address the issue of priority-building projects.
Article 2 imposes a performance record system for the survey, design, construction, treasury and equipment supply units that focus on construction projects, which are regularly published by the Provincial Focus Building Office.
There is no need to participate in tenders for priority-building projects within two years from the date of publication of the performance record, for example, in the survey, design, construction, supervision, equipment supply units with serious violations of the construction of projects.
Article 23 violates the laws, regulations, regulations and regulations, such as tendering, quality of work, and financial management, in accordance with the law of the executive branch concerned; constitutes an offence punishable by law.
Article twenty-four of the State's staff members are subject to administrative disposition by law, one of the following acts in the management of the priority construction project, which constitutes an offence and is criminally liable by law:
(i) Contrary intervention to focus on building tenders for projects;
(ii) The receipt, request for priority-building project investors, project legal persons or surveys, design, construction, treasury, equipment supply units or other illegal interests;
(iii) Constraints, diversions, focus on building blocks, resettlement compensation requirements;
(iv) To deny and delay the processing of priority construction projects to be carried out by law, to focus on construction projects or to build fees, incest fines or assessments;
(v) Participation, organization, manipulating and condoning extortion and resistance to priority construction projects;
(vi) Other serious impediments to priority-building.
Article 25