(May 26, 2003 Shandong provincial people's Government, the 6th Executive meeting on June 14, 2003 Shandong provincial people's Government, the 159th published) first in order to strengthen the management of seismic active fault survey, for the preparation of urban planning and site selection provide the scientific basis for major construction projects, protect against and mitigating earthquake disasters, according to relevant laws and regulations, combined with the facts of the province, these provisions are formulated.
    Article in the province engaged in seismic active fault investigation activities in the administrative area, shall comply with this regulation. Article the competent administrative departments are responsible for the investigation on seismic active faults in the administrative area, supervision and management of the work.
    People's Governments above the county level responsible for the management of earthquake seismic active faults within the administrative areas of work of the Department in charge of the supervision and management of the investigation.
    Governments at all levels of planning, construction, land and resources, transportation, water conservancy and other relevant departments shall, in accordance with the Division of responsibilities, work closely together to do active fault and earthquake research work related to the.
    Fourth people's Governments above the county level shall strengthen leadership of the investigation on seismic active faults, seismic active fault survey work in earthquake prevention and disaster mitigation planning and overall urban planning, based on practical needs, invest the necessary funding.
    V people's Governments at various levels shall take measures to encourage and support scientific research in seismic active fault investigation as well as the outcome of the application.
    Article sixth of seismically active fault investigation units, seismic safety evaluation or investigation must be legally obtained qualification certificates.
    Seismic active fault survey article should be open, fair, fair competition principle, shall be determined by tendering unit; the investigation shall strictly implement relevant technical specifications and standards of the State.
    Article eighth of seismically active fault investigation units, distribution and trends of fault, obliquity, crushing width, developmental history, current events, sports properties, rupture and displacement, sliding velocity, seismic events, such as investigations and obtain the appropriate technical specifications.
    Article Nineth seismic active fault investigation unit after the end of the investigation, seismic active fault investigation report shall be compiled.
    Seismic active fault investigation report should include the topic description, fault distribution maps, geophysical and geochemical detection section, borehole data such as earthquake risk and hazard assessment.
    Article tenth of seismically active fault investigation units, seismic active fault investigation report should be submitted to the competent administrative Department of the validation.
    Competent administrative departments shall from the date of receipt of the investigation report on the seismic active faults in the 15th to complete validation.
    11th certified seismic active fault survey reports, and informed in writing and by the competent administrative Department of the province people's Government is responsible for the Administrative Department for seismic work, and copy to the provincial Department of construction, land resources and Planning Department.
    12th certified seismic active fault survey reports, is the preparation of urban planning and the basis for a major site of the construction project.
    Investigation report on the seismic active faults that are not audited, and municipal people's Governments and their relevant authorities shall not as a basis for preparation of urban planning; construction unit shall not be used as a major basis of the site of the construction project.
    13th span seismic active faults in highway, railway (MTR), oil (gas) pipelines, communications (electrical) cable and long distance transfer (transmission) of major construction projects such as water pipelines, should be in accordance with the relevant provisions of the State take the appropriate precautionary measures.
    14th in 10,000 years from now has active faults along the national works within the scope of avoidance under construction, shall be executed in accordance with State regulations.
    In 10,000 to 100,000 years have been active faults along and within the limits of national provisions to avoid, not serious secondary disasters in construction of major projects, engineering, nuclear power plants and nuclear facilities for other projects, reference to the provisions of the third paragraph of this article.
    In 100,000 years ago along the faults of the previous activities, construction without collision, but must at the time of Foundation treatment in accordance with the relevant provisions of appropriate measures can be taken to prevent faults caused by uneven ground.
    15th before the implementation of these provisions has built projects did not avoid seismic active faults, shall take appropriate measures to reinforce or relocation.
    16th due to seismic active fault survey in urban planning and its requirements by the city people's Government commitment to due to major seismic active fault survey site of the construction project, its requirements are borne by the construction unit, and included in the total investment budget of construction projects.
    Seismic active faults in investigation costs standards, in accordance with the relevant provisions of the State and province.
    17th a violation of this provision, preparation of urban planning according to the certified seismic active fault survey reports, by the higher people's Governments shall be ordered to correct.
    Violation of these provisions, before the major construction project site is not seismically active fault survey or not based on certified seismic active fault survey site, above the county level shall be responsible for the Administrative Department for seismic work shall order rectification fails, punishable by fines of less than 10,000 yuan and 30,000 yuan.
    18th party refuses to accept the decision on administrative penalty may apply for administrative reconsideration or bring an administrative lawsuit in accordance with law.
    19th national staff in seismic active fault investigation supervision work, abuse of power, negligence, malpractice, and constitutes a crime, criminal responsibility shall be investigated according to law; do not constitute a crime, administrative sanctions according to law.
                                                  20th article of the regulations come into force on August 1, 2003.