Building Fire Protection Management In Shandong Province (Amended 2004)

Original Language Title: 山东省建筑工程消防监督管理办法(2004年修正本)

Subscribe to a Global-Regulation Premium Membership Today!

Key Benefits:

Subscribe Now for only USD$20 per month, or Get a Day Pass for only USD$4.99.
(May 23, 2000, Shandong provincial people's Government, the 111th published according to 172th amendment of July 15, 2004, Shandong province) Chapter I General provisions article in order to strengthen the management of building fire protection, to reduce and prevent fire hazard, according to the People's Republic of China fire protection law, the Shandong provincial fire regulations and other laws and regulations, combined with the province, these measures are formulated.
    Second within the administrative area of the province building, rebuilding, expansion, renovation and change of use of industrial and civil construction works (hereinafter construction work) design, construction supervision and inspection and facility construction, supervision, and fire products, these measures shall apply.
    Article fire services of public security organs and the people's Governments above the county level responsible for fire supervision and management of construction work.
    Chapter II article fourth designer to design the fire protection design, must be implementing national fire protection technical standard provisions relating to fire protection design and construction standards, and design of building fire protection design projects they have undertaken is responsible for the quality. Fifth executive engaged in fire-fighting equipment should be designed to hold nation-building fire facility specialized design qualification certificate issued by the authorities.
    Prohibit access to fire fighting facilities design qualification certificate or beyond the level of qualification in design of fire control facilities.
    Sixth construction project feasibility study report prepared by construction units should be based on national technical standards, fire equipment set a schedule.
    Article seventh preliminary design design units to carry out building works shall be determined in accordance with national and provincial methods and valuation standards, to include requirements for the fire-fighting facilities project budget.
    For the national and provincial key projects, high-rise buildings, underground and other settings of automatic fire-fighting equipment construction works, design units should be preparing documentation special design at the preliminary design stage. Eighth article construction fire design of main content including: (a) total plane layout and plane layout in the involved fire security of fire spacing, and fire Lane, and fire water; (ii) building of fire risk category and refractory grade; (three) building fire anti-smoke partition and structure; (four) security evacuation channel and fire elevator; (five) fire water and automatically fire system; (six) anti-smoke, and row smoke and ventilation, and air conditioning system of fire design; (seven) fire power and distribution; (eight) fire emergency lighting, and emergency wide
    Sowing and evacuation signs; (IX) automatic fire alarm systems and fire control room, (10) fire protection design of interior decoration of buildings, (11) building fire extinguisher (12) risk of explosion of the a and b class plant explosion-proof design (13) national engineering construction standard in other design-related content.
    Nineth must fire control design of construction projects, the construction unit to fire before the construction project for the design drawings and relevant information reported to the public security fire control institutions audited, unaudited or audited is not qualified, the construction Administrative Department is not issuing construction permits, construction of building and construction units shall not.
    Tenth public security fire control institutions to declare the design of building fire protection shall be in accordance with the following terms of audit, compliance, issuance of building fire protection design review comments does not meet the provisions of the proposed amendments in writing: (a) general building 10th; (b) the preparation of fire-fighting design of special construction 20th; (c) organize expert building 30th.
    Fire protection design for national fire protection technical standard has not yet been provided content and new material, new technology, new process issues related to fire safety, the provincial public security fire control institutions shall organize relevant experts to prove proposed building fire safety assessments, as a basis for design review.
    Chapter III supervision article 11th building and construction units must be by public security fire control institutions approved design drawings, and shall not be changed without authorization; fire design drawings really necessary changes shall be made by the original design changes, approved by the public security fire control institutions.
    12th fire facilities construction, supervision and fire product procurement bidding system should be made.
    13th construction units shall be entrusted with the appropriate competent supervision of construction supervision unit for fire service installations.
    Article 14th construction unit and fire fighting facilities installation, supervision and testing fire equipment installation, supervision and inspection contracts signed, record and report to the public security fire control institutions.
    15th construction units shall establish and improve construction site fire safety rules and regulations, are equipped with (and) professional fire safety personnel, implement the fire safety measures.
    16th construction and construction units should be selected national and provincial quality and technical supervision departments identified qualified fire protection products, building components, building materials and decoration materials.
    Public security fire control institutions in the implementation of construction when fire fighting supervision and inspection, depending on the circumstances, you can fire products, building components, building materials and decoration materials of fire performance implementing random sampling check or send the statutory quality inspection bodies and inspection authorities shall cooperate.
    The fourth chapter acceptance article 17th fire equipment construction supervising units shall, before completion, construction supervision evaluation issued by the employer fire service installations.
    Article 18th construction works for the installation of automatic fire-fighting equipment, inspection system must be tested by the statutory agencies function without testing or test failed, no acceptance of public security fire control institutions.
    Article 19th after the completion of the construction, the construction unit shall apply to the public security fire control institutions fire inspection, without acceptance or fire unqualified acceptance of public security fire control institutions, the construction unit shall not be delivered, employer or manager shall not receive.
    Fire engineering acceptance of integrated project completion acceptance, not individually.
    20th fire fighting facilities installation unit should be established in accordance with the provisions of the fire safety facilities of construction technical file, record and report to the public security fire control institutions.
    Article 21st after acceptance of the installation of automatic fire-fighting equipment construction project, its management or use the unit should fire facilities management system, implementation of operator, and at the expiration of the warranty period and with fire-fighting equipment maintenance conditions of the maintenance contract units, regular maintenance to ensure normal operation of fire-fighting facilities.
    Fifth chapter legal responsibility 22nd article violation this approach, has following behavior one of of, by police fire institutions ordered stop violations, deadline corrected; late not corrected of, ordered stop construction or stop using, and at 10,000 yuan above 100,000 yuan following fine: (a) construction fire design without audit or audit not qualified unauthorized construction of; (ii) construction without fire acceptance or acceptance not qualified input using of;
    (C) used without national and provincial quality and technical supervision and management departments identify qualified fire protection products, building components, materials of construction and decoration materials.
    23rd article violation this approach, has following behavior one of, led to fire facilities cannot normal opened run of, by police fire institutions ordered deadline corrected; late not corrected of, at 3000 Yuan above 30,000 yuan following fine: (a) fire facilities construction quality poor of; (ii) supervision, and detection, and maintenance maintenance units fraud or not perform duties of; (three) fire facilities management or using units not by provides maintenance maintenance fire facilities of.
    24th article violates this way, unauthorized change of building fire protection design and construction, rectification by public security fire control institutions; it fails, fines of between 30,000 yuan.
    25th in violation of the provisions of article 15th, rectification by public security fire control institutions; it fails, a warning or be ordered to stop construction.
    Section 26th unit in violation of these regulations, in addition to the punishment according to law, directly responsible to the person in charge and other direct liable shall be warned or fined a maximum of 500 Yuan more than 5000 Yuan.
    27th public security fire control institutions and their functionaries, malpractice, negligence, causes losses to the State and the interests of the people, does not constitute a crime, administrative sanctions according to law constitutes a crime, criminal responsibility shall be investigated according to law. Sixth chapter supplementary articles article 28th these measures shall take effect on June 1, 2000.