Wuhan High Pressure Natural Gas Pipeline Facilities Protection

Original Language Title: 武汉市天然气高压管道设施保护办法

Subscribe to a Global-Regulation Premium Membership Today!

Key Benefits:

Subscribe Now for only USD$20 per month, or Get a Day Pass for only USD$4.99.
(July 5, 2005 30th meeting consideration of the people's Government of Wuhan municipality on July 21, 2005, 163th promulgated by the people's Government of Wuhan municipality as of August 20, 2005) article in order to strengthen the protection of high pressure natural gas pipeline facilities, maintenance of public security, in accordance with relevant rules and regulations on the management of Wuhan City gas, these measures are formulated.
    Second this approach applies to the city high pressure natural gas pipelines (hereinafter referred to as high pressure pipeline) facilities related to the protection and management activities.
    Before natural gas receiving station in this city's long-lost high pressure natural gas pipeline facilities and gas enterprises, protection of users within high-pressure gas pipeline facilities, in accordance with the provisions of the relevant laws, rules and regulations.
    Third article this approach by said high pressure pipeline facilities is refers to: (a) conveying gas of high pressure pipeline; (ii) high pressure pipeline anti-corrosion protection facilities, including cathode protection station, and cathode protection test pile, and Yang polar bed and miscellaneous bulk current row flow station,; (three) gas accept door station, and adjustable pressure station (room), and valve (room), and poly wells (room), and wastewater pool, high pressure pipeline subsidiary structures and compensation device, and bleeding tube, related equipment; (four) logo pile, and test pile, and mileage pile, and warning brand, high pressure pipeline facilities security recognition logo;
    (E) the Canal levee, Canal Bridge, the half-tribe and other associated with high-pressure pipeline fixtures.
    Fourth municipal and District Administrative Department for gas in accordance with mandated functions, is responsible for the supervision and management of high-pressure pipeline facilities protection work and organize the implementation of the present measures.
    Safety, quality supervision, public security, planning, construction, transportation and other sectors in accordance with their respective responsibilities, and protection of high-pressure pipeline facilities related to the supervision and administration.
    Fifth article high pressure pipeline facilities run enterprise (following referred to high pressure pipeline enterprise) should comply with following provides: (a) according to construction developed of town gas buried to steel quality pipeline corrosion control technology procedures of provides, on high pressure pipeline topical anti-corrosion insulation layer, set cathode protection device; (ii) according to gas design specification, set high pressure pipeline facilities permanent security warning logo, and guarantee its intact; (three) on easy was forces collision of high pressure pipeline facilities take corresponding protection measures, and set security warning logo;
    (Four) according to construction developed of town gas facilities run, and maintenance and repair security technology procedures, security management provides, increased technology input, on high pressure pipeline facilities regularly inspections and maintenance maintenance, found security hidden timely excluded; (five) developed high pressure pipeline facilities accident disposal plans, and submitted gas administrative competent sector and police, and safety, and quality prison sector and high pressure pipeline along of district people Government prepared save; (six) will high pressure pipeline facilities of completed information according to provides submitted about sector prepared save;
    (VII) against high pressure pipeline safety act to dissuade, deter, dissuade or stop is not valid, timely gas administrative departments, public security, safety and quality supervision departments report; (VIII) to assist the Government and the relevant departments to high pressure along the pipeline unit and individual high pressure piping safety publicity and education.
    Article citizens, legal persons and other organizations have an obligation to protect the high pressure pipeline facility; for acts in violation of administrative provisions on protection of high-pressure pipeline facilities have the right to stop it.
    The seventh article in accordance with the national fuel gas code for design, underground pressure pipes within the wall horizontal spacing of 6.5 meters on both sides of the region, for high pressure piping safety protection in wall horizontal spacing of 6.5 meters to 50 meters on both sides within the region, for high pressure piping safety control.
    Along the River, across the River, the river wear, wear di high-pressure pipeline facilities, their security protection and security control, by the competent departments for gas water supplies, rivers, waterways, and other relevant departments according to the relevant provisions of the State.
    Eighth article in high pressure pipeline facilities security protection range within, except high pressure pipeline Enterprise strictly according to about provides for related job outside, ban following behavior: (a) built buildings, and structures and set poles, facilities; (ii) mining, and take soil; (three) stacked weights or grind pressure; (four) placed flammable easy burst real or dumping, and emissions corrosion sex items; (five) planting tree, and bamboo, deep root plant; (six) mobile, and cover, and altered, and demolition, and damaged high pressure pipeline facilities and security protection logo;
    (VII) on the high-pressure pipeline facilities about wire, rope or drying clothes; (VIII) welding, baking, blasting and other operations.
    Nineth high pressure pipeline safety control within the prohibition of the blasting operation.
    Tenth article in high pressure pipeline facilities security control range within laying pipeline, engaged in piling mining, job, or built buildings or structures,, units should with construction units according to construction engineering safety management Ordinance (State No. 393, makes) of provides, proposed high pressure pipeline facilities special protection programme, by and high pressure pipeline Enterprise consultations consistent rear can implementation; on programme produced dispute of, by gas administrative competent sector organization experts argument Hou coordination solution.
    Construction administrative departments on safety control of high pressure pipeline facilities construction project in the context of examining and issuing construction permits, shall, in accordance with the provisions of the regulations on work safety of construction projects, the review of construction projects for security measures, no security measures, will not be issued the construction permit.
    With the approval of high pressure piping safety engineering or other operations within the control, may affect the safety of high pressure pipeline facilities, high-pressure pipeline enterprises shall assign special technical personnel to the scene to provide security guidance.
    11th high pressure pipeline facilities outside the control of blasting operations to the area within 500 meters, operating units should take protective measures, upon approval by the relevant authorities, in the high-pressure pipeline companies under the supervision of specialized technical personnel to the scene.
    12th prohibits driving on the sidewalk dedicated to inspection of high-pressure pipeline facilities of motor vehicles.
    13th River, across the River, wearing River, wearing the high-pressure pipeline facilities within the scope of protection of the dyke, in addition to protection under the condition of high pressure piping safety and dredging operations for flood control or navigation, but against the anchor or drag anchor, dig sand, dredged or endanger the safety of high pressure plumbing job. 14th new construction, renovation or expansion projects of high pressure pipeline facilities absolutely necessary to migrate unit prior to the application for planning permit of construction engineering, shall, in accordance with relevant regulations of the State, approved by the competent administrative Department for gas, and handle the relevant procedures after approval, construction of the unit or units shall, together with the high pressure pipeline companies take appropriate remedial measures.
    Transport costs borne by the employer.
    15th departments and units in the development of flood control measures, building the dam, should be taken to protect the safety of high pressure pipeline facilities; when really necessary in the high pressure pipeline regional flood through, waste discharge and discharge time shall promptly be notified high-pressure pipeline companies.
    16th municipal gas Administrative Department shall, in conjunction with the municipal public security Department and high pressure plumbing disaster accident emergency plan, submitted to the municipal people's Government for approval.
    High pressure pipeline accident, high-pressure pipeline enterprises shall, in accordance with the management plan, immediately take the appropriate security measures, for constant repair, rescue operations, until the completion of repairs, emergency rescue, and at the same time to the competent administrative Department for gas and safety, firefighting, quality supervision departments and the district people's Government report.
    Gas administrative departments and safety, firefighting, quality supervision departments and the district people's Government shall, in accordance with their respective responsibilities to strengthen supervision and inspection of high pressure piping safety, found high pressure pipeline accident or after receiving the high pressure pipeline enterprises report on the accident shall immediately activate high pressure plumbing disaster emergency plans, organizing rescue, relief work.
    17th high pressure pipeline companies during high pressure plumbing repair, rescue, relevant units and individuals shall give the necessary assistance, shall not be obstructed, hindering repair, rescue operations for any reason.
    High pressure pipeline companies to repair and rescue operations, that does damage to the legitimate interests of entities or persons, shall be subject to compensation.
    18th gas administrative departments should be telephone hotlines, to citizens, legal persons or other organizations to report timely investigate and deal with acts in violation of these rules; belong to other departments according to law, shall be transferred in time. 19th article on following violation this approach of behavior, by gas administrative competent sector be processing: (a) violation eighth article, and Nineth article provides of, according to Wuhan gas Management Ordinance of about provides be punishment; (ii) violation tenth article first paragraph provides of, ordered deadline corrected, late not corrected, belongs to non-business sex activities of, sentenced 500 Yuan above 2000 Yuan following fine; belongs to business sex activities of, sentenced 10,000 yuan above 30,000 yuan following fine; (three) violation fifth article, and tenth article third paragraph, and
    The 11th article, correction, and a fine of 5000 Yuan and 30,000 yuan fines; (d) violation of the 14th, 16th, second paragraph, impose a penalty of more than 10,000 yuan to 30,000 yuan.
    20th to tie up high pressure pipeline of buildings or structures, organized by the relevant district people's Government plans, gas Division of responsibilities in accordance with the provisions to be dismantled by the Administrative Department, the costs borne by the illegal construction of the units or individuals.
    21st article violates other provisions of these measures, by the relevant authorities according to the provisions of the relevant laws, rules and regulations to deal with it.
    22nd in violation of these regulations, constitutes a breach of security regulations, shall be subject to punishment by public security organs constitutes a crime, transferred to the judicial organs shall investigate the criminal responsibility cause damage to others shall bear liability.
    23rd parties of relevant administrative organs by specific administrative acts, may apply for reconsideration or bring an action according to law.
    24th the relevant administrative organs and their staff do not perform their duties according to the regulations, resulting in serious consequences, supervisor directly responsible and other persons directly responsible shall be dealt with in accordance with the relevant provisions of administrative fault responsibility investigation constitutes a crime, transferred to judicial organs for criminal responsibility shall be investigated according to law.
                                                                                    25th article this way come into force on August 20, 2005.