Administrative Examination And Approval Of Construction Projects In Xiamen Focused Approach

Original Language Title: 厦门市建设项目行政审批集中办理办法

Subscribe to a Global-Regulation Premium Membership Today!

Key Benefits:

Subscribe Now for only USD$40 per month.
Administrative examination and approval of construction projects in Xiamen focused approach

    (February 5, 2009, Xiamen City people's Government, the 56th Executive meeting on March 14, 2009, Xiamen City people's Government, the 134th announced as of May 1, 2009) Chapter I General provisions

    First to standardize administrative examination and approval of construction projects, innovation and approval, improve the efficiency in providing services, to create a favorable environment for economic and social development, according to the People's Republic of China on administrative licensing law and other laws and regulations, combined with the city's actual, these measures are formulated.

    Article directly related to construction projects within the administrative area of the city of administrative licensing, non-administrative permits and related registration matters (hereinafter referred to as project approval), centralized processing in accordance with these measures.

    Dealt with in the preceding paragraph, refers to the construction of the project's approval to implement accepted, organization management, serve.

    The third municipal people's Government the establishment of the management services Center (hereinafter referred to as the construction services center) is responsible for the approval of construction projects dealt with, its specific work by the municipal construction administrative departments in charge.

    Building services centre unit established by the municipal people's Government.

    Center for construction Service Center can be set up according to the actual needs, the nearest local construction projects approved dealt with services.

    Article fourth Service Center performs the following duties:

    (A) approval of the creation of a unified service platform construction projects approved dealt with services provided;

    (B) to confirm to enter the building a Service Center for examination and approval, validation and release approval Guide;

    (C) formulation of construction service center work systems and practices, and is responsible for supervision;

    (D) coordination of related construction projects approved dealt with the work of the competent departments;

    (E) regularly report to the municipal people's Government approval of construction projects dealt with work, drew attention to the study of the relevant major issues;

    (F) organize the implementation of construction services center stationed in staff performance appraisal;

    (VII) other responsibilities as determined by the municipal people's Government.

    Chapter II approval processing Article fifth construction of project examination and approval Department (hereinafter referred to as the approval authorities) approval should be set in building a Service Center service platform construction project approval, implementation of construction Service Center System.

    Has entered the building a Service Center for examination and approval matters, not take place outside the building approval service platform received acceptance, receipt of corrected material or service decision.

    List of project examination and approval matters provided in the preceding paragraph, by construction services in accordance with laws and regulations and municipal decisions concerning the reform of the administrative examination and approval system to confirm, and to the public.

    Approval matters related to implementation of the construction project of the same unity in building a Service Center for the system.

    Sixth approval departments shall specify to the head of the Department of construction Service Center approval, be responsible for the relevant approval procedures of coordination, management and related activities.

    Article seventh approval departments shall, in accordance with the law, rules and regulations and construction Service Center system requirements, including approval procedures, the basis, conditions, procedures, deadlines, and need all the material submitted by catalog and model text of the application guide, and building service centres authorized release.

    Guide needs to change in the preceding paragraph, shall be subject to the construction services center after the publication of audited, in order to perform.

    Article eighth service center set up registration window (hereinafter referred to as the registration window), exclusively provided services such as reception, served on the approval of construction projects.

    Nineth entered build service center matters in accordance with the following procedure:

    (A) the registration window to item-by-item register vouchers issued by the registration and application materials;

    (B) approval departments shall, in building a service center to review the application materials on the spot, and sent to the registration window to review information, issued by the registration window to the applicant accepted, inadmissibility decision or the notice of correction;

    (C) review of required corrections in the course material, should be at once put forward rectification opinions of the competent departments, issue a notice of correction to the applicant referred to the registration window;

    (D) the approval authority according to the relevant statutory requirements and procedures to review the application, within the period specified in the decision, and served on the registration window.

    The preceding paragraph (b) prescription approval authority to handle such matters, you can delegate the registration window.

   Article tenth the following project approval, approval departments shall, in building a service center to decide on the spot:

   (A) matters of record;

   (B) the application materials are complete and comply with the statutory format, can be made on the spot approval decision;

    (C) according to the relevant technical standards and norms by a corresponding qualification (qualification) recognized professional bodies can make approval decisions on the spot.

    List of approval provided for in the preceding paragraph, by building a service center in conjunction with the relevant approval authorities confirmed to the public.

    11th Association of construction services center construction project approval and concurrent review likely to divide construction projects, implementation, acceptance and approval phase, the implementation phase of approval at the same time, concurrent review of receipt.

    12th following approval of construction projects by building a service center Organization-related joint-approval processing:

    (A) left over from construction projects involving two or more departments;

    (B) changing the function of the project involves the construction of two or more departments;

    (C) the emergency construction projects;

    (Iv) other requires joint approval for processing.

    13th construction Service Center in the published guide approval time limit, since the date of the acceptance and approval decision until the date of submission of registration window calculation, but application materials supplement during and other statutory deductions are not included in the processing period.

    The third chapter website

    14th building service center establish a unified online approval system of construction project, approval for construction projects online.

    Approval authority should be open to online approval system of construction project data interface system, data exchange, implementation documents electronically.

    Has entered the build service center for online approval, online approval system should be unified in construction project management. 15th construction project approval to the application, you can use online reporting.

    Online Declaration, shall submit the electronic application materials materials not suitable for transmission over the network, and should express in the online application and submit through registration, the registration window.

    Approval authority shall verify the online Declaration of electronic materials; need to check or receipt of paper data should be passed before the approval issued by the registration window to check or receipt of paper materials.

    The applicant should be responsible for the authenticity of the substance of the application materials. 16th under the way 11th section simultaneously, parallel review and approval by the registration window, unified inbox and through the construction of project examination and approval system was transferred to the online review of the competent departments.

    Corresponding review comments in the approval authority in accordance with the provisions to be shared.

    17th construction Service Center construction project approval information, achieving approval information sharing.

    Project Declaration of the vetting of applications through the construction of project examination and approval system, provide the same application materials would not be repeated.

    18th construction Service Center Online approval system of construction project should be used to provide Web consulting, approving information and guide, download forms and other services.

    Registration window should be in Center field for the applicant to provide construction services online reporting and application materials electronic services.

    19th construction Service Center and the examination and approval Department shall establish an information network safety responsibility system to ensure network security.

    The fourth chapter coordination services

    20th following by building Service Center Directors meeting decided:

    (A) develop construction service center work systems and practices;

    (B) to confirm to enter the building a Service Center for examination and approval matters;

    (C) the establishment of the Service Center;

    (D) Recognizing the construction services center organizations parallel joint review, approval and approval;

    (E) other significant matters require collective study.

    Building service centres should participate in the meeting of Directors of the Member organization.

    21st the following matters, by building a Service Center held working meetings, conferences on decision or coordination to handle:

    (A) streamline approval processes, reduce approval process;

     (B) validation, revision Guide;

    (C) problems in construction project approval process;

    (D) significant investments early approval of construction projects;

    (E) other matters requiring coordination.

    Approval authorities in building service centres should participate in the working meetings, conferences. 22nd construction services center, conferences, work meetings, thematic coordination meeting for the formation of, approval authority should be implemented.

    Unable to form a resolution or larger differences on implementation of the relevant resolutions of the Conference, decided by the building services submitted to the municipal people's Government.

    23rd construction project approval Guide, application format text produced by the construction services center and released, and provided free of charge.

    Applicant asked for publication details of description, explanation, approval authority should indicate, explain and provide accurate and reliable information.

    24th construction services for major investment projects, Government construction of industrial parks, important social and public construction projects, such as construction materials such as vetting applications for assistance organization agency services.

    25th construction Service Center shall provide service charge to help applicants pay construction costs related to the project in accordance with law.

    The fifth chapter, supervision and inspection

    26th supervisory authorities should strengthen supervision and inspection of construction projects approved dealt with work, construction service center operations implement law enforcement supervision, performance monitoring and approval process.

    27th building service centres construction projects approved dealt with handling system, establishing and approval of electronic supervision system, strengthen the construction of real-time supervision of project approval, urge approval and approval duties according to law.

    28th construction Service Center may take the form of supervision:

    (A) according to prescribed procedures and time limits for approval to handle prompts and warnings;

    (B) real-time verification documents, approval to go through the State;

    (C) verification of acts in violation of construction service center work systems and practices;

    (D) issue handling opinions;

    (E) inform approval processing.

    29th construction Service Center shall do complaints admissible complaints, investigate, verify, process and transfer processing. 30th construction Service Center should be the approval authorities in building service centre staff were honest and diligent assessment and recognition awards to outstanding.

    Construction services center staff assessment results should inform the relevant approval authorities.

    City Department of personnel administration according to relevant regulations, building services separate from the center of the annual appraisal indicators of good grades.

    Sector in building a Service Center for examination and approval work included in the performance appraisal of the Executive category.

    The sixth chapter legal liability

    The 31st under any of the following acts by the supervisory departments or building service center shall be ordered to correct serious by the supervisory departments shall be investigated for criminal responsibility:

    (A) the approval of construction projects in accordance with this approach should be dealt with, and refused to enter the building service centres dealt with;

    (B) has entered the building a Service Center for examination and approval matters and approval service platform construction project outside the Inbox receive, receipt of corrected material or served on the approval decision;

    (C) construction Service Center authorized and unauthorized changes without Guide content;

    (D) violation of construction service center work systems and practices;

    (E) the unjustified refusal to implement resolution I construction services center;

    (Vi) refused to build construction Service Center and online approval platform for data exchange to achieve approval information sharing;

    (G) violations of other acts as provided herein.

    32nd construction of service centre staff in violation of the rules by building service center shall be ordered to correct, as the case may be communicated; adverse social impact, commandments, effectiveness of education warned by his employer, and out of the approval status, or by the Inspection Department shall be investigated for criminal responsibility.

    The seventh chapter by-laws

    33rd district administrative service center set up by the Government to carry out administrative examination and approval of construction projects, in accordance with the measures implemented. 34th article of the rules take effect on May 1, 2009.