Changchun mobile communication base station management

    (January 13, 2011, Changchun City people's Government, the 35th Executive meeting on January 13, 2011, Changchun Municipal People's Government promulgated as of May 1, 2011, 21st) first to strengthen the management of mobile communication base stations, maintenance of mobile communication users, mobile service operators and the public interest, protect the healthy development of mobile communications, in accordance with relevant provisions of laws and regulations, combined with the city's actual, these measures are formulated.

    Second mobile communications base stations in these measures (hereinafter referred to as the base), is a construction of mobile communication operators in certain radio coverage in the region, through an exchange of mobile communication device and mobile communication terminal for information transfer between radio stations (stations), including an outdoor base station (with Repeater) and indoor coverage systems.

    Mobile communication operators in these measures (hereinafter referred to as operators) is allowed by law in the construction of mobile communication network in the city, and providing mobile users with mobile voice, data, and other business units.

    Mobile communication systems in these measures, including public cellular mobile communications systems, PHS wireless access systems, trunking systems, and other wireless communication system with mobility.

    Indoor distributed system is mentioned in these measures is determined by the signal source and the indoor antenna distribution system (hereinafter referred to as the indoor distributed system).

    Radio licenses in these measures refers to the operator in accordance with the provisions issued by the People's Republic of China radio station license, is a legal set of operators, to use base station's legal credentials.

    This approach applies to this article, within the administrative area of the base station set up, use, and management activities.

    Fourth, radios, base stations, departments are responsible for the Setup, use, management.

    Planning, environmental protection, development and reform, premises, land, public safety, sanitation, and other relevant departments shall, in accordance with their respective responsibilities, to do base station management related work in accordance with law.

    Fifth of municipal radio competent departments shall, jointly with relevant departments in accordance with urban planning and the development needs of the city's mobile communication, upholding the principle of sharing resources, rational layout, preparation of the development planning of mobile communication base station (hereinafter referred to as the base station for development planning), reported to the municipal people's Government for approval organization.

    Sixth operator should be in an annual base station planning cycle began two months ago, according to the layout and siting requirements, annual demand for base stations, radio authority. Radio, competent authorities should be based on the development of base station planning and operators have reported annual demand for base station settings, in conjunction with the departments concerned to develop annual base station settings program.

    Operators have reported annual demand for base station settings in the layout or site duplicates, coordinated by the Radio Authority arrangements.

    Annual base station planning cycle, determined and published by the radio authority.

    Seventh government investment construction of buildings (structures) on buildings or other facilities (internal) intends to set up your base station, its property units, or management units should be provided and the required auxiliary facilities such as piping, the engine room space and electricity.

    Eighth to encourage and support the operation through consultations on an equal footing, reasonable share base station resources. Operator cannot be reached an agreement on sharing, either party may apply to the Radio Department in charge of coordination. Coordinated agreement cannot be reached, City radio departments should organize experts or qualified institutions to share the required technical condition evaluation and justification.

    Evaluation and justification to the shared conditions, possession of the operators of the site resource should be shared with the requirements operators enter into a sharing agreement refusal to enter into a sharing agreement, may not be in the same area within five years prior building base stations.

    Nineth bearing of base station antenna tower (hereinafter referred to as the Eiffel Tower) should be open and sharing. Does not have the conditions for sharing of existing Tower should take technological transformation, expansion means such as sharing. New Tower in both towers in the same area is prohibited.

    Due to special reasons, need new towers in the same region, should be agreed by the radio authority. New towers should be sharing.

    The operator shall notify the other of the proposed new tower operator; other operators are not sharing needs may not be in the same area, the new Tower.

    Other than the tower base station equipped supporting facilities should be open to share.

    Tenth new construction, renovation or expansion of large buildings (structures), construction of subways, tunnels and so should be designing indoor coverage systems of pipes and the engine room, and in accordance with the standard road-building indoor distribution system.

    11th new outdoor base station operators shall comply with the following requirements: (A) the location of residential areas, priority should be set up and attached to the non-residential building (structures) on the matter.

    Needed settings or additional living structures, should ask the one-second per cent of the owners ' consent; (B) location to avoid historic preservation buildings.

    Is really necessary to set, miniaturization, concealment of building programmes should be adopted;

    (C) the antenna direction and layout with buildings (structures) coordination structures and the surrounding environment, use of miniaturization, beautiful building programmes;

    (D) related to Setup and installation shall not endanger the building (structure)-safety;

    (E) you will not interfere with other radio communication systems.

    Outdoor base stations do not meet the above requirements, should gradually be modified.

    12th must set an outdoor base stations, shall apply to the Radio Department in charge of location, and submit the following materials:

    (A) the base station location form

    (B) the legally qualified engineering base station settings the programme prepared by the unit;

    (C) the base station settings in the annual plan of landscape requirements, should also be submitted to the landscape plan. City radio departments location applications received in the 20th, and make a decision on whether to approve it.

    Eligible, to the base station location report; do not meet the conditions, notify the applicant in writing and state the reasons.

    Set outdoor base station other approval shall handle the related formalities to the relevant departments.

    Before the 13th outdoor base station into operation, the applicant shall apply for acceptance to departments of radio, and the following materials:

    (A) the base station configuration files and frequency information;

    (B) technical data base station equipment;

    (C) the equipment issued by a legally qualified testing Agency inspection reports;

    (D) good faith commitment of electromagnetic exposure in line with national standards related to environmental protection;

    (E) signed with the owner of room and ancillary facilities associated with the base station settings the usage agreement. Are received by the Radio Authority, upon acceptance of the application, shall, together with the completion of work within the relevant sector in the 20th.

    Accepted and issued radio licenses; unqualified acceptance, and notify the applicant for rectification, rectification after passing the examination again.

    14th must set the indoor coverage systems, shall apply to the Radio Authority, for the establishment, and provides the following materials:

    (A) the indoor distributed system settings application form;

    (B) the statutory qualification units of engineering design of multi mode combiner System Setup program;

    (C) signed with the owner of room and ancillary facilities associated with the base station settings the usage agreement. City Radio Department since receiving the application for setting indoor coverage systems in the 20th, and make a decision on whether to approve it.

    Eligible, to indoor coverage systems settings report; do not meet the conditions, and notify the applicant in writing and state the reasons.

    Applicant has not obtained the certificate of indoor coverage systems set up, should not be set for indoor coverage systems. 15th indoor coverage before the system is put into operation, the applicant shall apply for acceptance to departments of municipal radio. Are received by the Radio Authority, upon acceptance of the application shall complete acceptance in the 20th.

    Accepted and issued radio licenses; unqualified acceptance, and notify the applicant for rectification, rectification after passing the examination again.

    16th operations after obtaining a radio licence, shall be in accordance with the approved project, put the base station into operation.

    Base station needs to be changed after the approved project, operators shall provide the original authority for the change procedures.

    17th special communications, tasks such as emergency communications needs to set up a temporary base station, operator shall, before the opening of the base station,, radio authority, to submit a written application and related technical information, can apply for a temporary radio licence.

    In case of threatening the State and people's life and property safety of emergency, temporary use of a set of base stations without approval, but shall promptly report to the City radio departments.

    Article 18th radio licenses are valid for less than three years, temporary station temporary radio licence is valid for no more than six months.

    Radio license has expired, the cease, with the corresponding base station radio licenses should cease immediately.

    19th radio base station remains to be used after the expiry date of the licence, operators shall, one month before the expiry of the Radio Authority, radio licence renewal procedures; base stations or cancel is deactivated, operators shall provide the radio authority for cancellation procedures.

    20th base station using electromagnetic radiation produced in the process shall comply with the relevant provisions of the national environmental protection.

    21st in the process of setting the base station building (structure) damaging buildings, set up the base station operator shall bear the compensation liability. 22nd no units or individuals are not allowed to remove operational base stations and their facilities.

    Special circumstances must be removed, should ask the relevant operators agree, borne by the demolition demolition costs, and compensation for the resulting economic losses.

    Article 23rd public interests need to be removed and supporting facilities of the base station, dismantling should compensation agreements with the operator, shall be subject to compensation.
Article 24th abandoned facilities such as outdoor base stations and Tower, which removed all; shall not be removed, dismantled by the municipal Radio Authority, expenses shall be borne by someone.

    25th Base Station due to natural disasters or other causes damage, resulting in mobile communication network, the relevant Department shall assist the operator to repair to ensure normal operation of base stations. 26th article of any units or individuals engaged in the construction, manufacturing and other activities should not endanger the base stations and their facilities; special situations likely to endanger security for base stations and related infrastructure, shall notify in advance the relevant operators, and engaged in the activities of the unit or individual responsible for taking safety measures.

    Damage of base stations and their facilities, shall be restored or repaired, and compensate for the resulting economic losses.

    27th of municipal radio authorities shall on an annual basis to check the base station's transmitting equipment testing, sampling quantity does not exceed 3% of the year in the total number of base stations.

    28th article violates these rules, arbitrarily set, to use base station, radio, departments may, depending on the circumstances giving warnings, seizure or confiscation, confiscation of equipment in serious cases, may be less than 1000 Yuan and 5,000 yuan fine or revoke the station's license.

    29th article violates these rules, feel free to change radio licenses approved projects, City radio departments may, depending on the circumstances giving warnings, seizure or confiscation, confiscation of equipment in serious cases, may be less than 1000 Yuan and 5,000 yuan fine or revoke the station's license.

    30th City radio departments and their staff in the course of the base station management abuse, negligence, malpractice, by a higher competent authority or unit to which the penalties constitute a crime, criminal responsibility shall be investigated according to law.

    31st article this approach involved in the concept and scope of reference standards are as follows:

    (A) the base station facilities: refers to the base station is equipped with a range of facilities, including towers, masts and other supporting facilities as well as rooms, day, indoor distribution system, transmission line, power, etc.

    (B) the Eiffel Tower: generally refers to more than 10 meters high towers (including Tower subsidiary rooms, facilities such as transport and electricity connection), not including the mast.

    (C) the same region: the base station within the predominantly linear range of 500 meters, non-colony area there are 3 km within the linear range of the base station.

    (D) large buildings: the single-storey building area of more than 3000 square meters of buildings or building height over 24 meters.

    (E) frequency coverage of indoor coverage systems: 800-2500MHz, when there is a special need, supports down to 350MHz.

    (F) indoor distributed system settings area: General settings in the building of indoor distribution system, you can also set when you need to implement a covered outdoor area in the same manner.

    (VII) multimode systems: wireless signal combiner in multiple formats, common set of indoor distribution system, sharing part of the passive antenna part. 32nd article this way come into force May 1, 2011.