Chapter I General

In order to strengthen the construction of engineering price management, it is reasonable to determine and effectively control construction works and to preserve the legitimate rights and interests of the parties in construction works, and to develop this approach in line with the People's Republic of China Building Act and relevant laws, regulations and regulations.

Article 2

Article III of this approach refers to the construction of construction projects from one to the completion of construction projects and, in accordance with the relevant provisions of the State and the province, to the cost of installation of works, equipment and engineering equipment for construction projects investments, other fees for engineering construction, preparatory fees, related tax fees and interest earned during construction.

Article IV.

(i) Preparation and review of investment estimates, preliminary design estimates, construction map budgets, engineering checklists, tendering, tendering control and tendering;

(ii) To agree and adjust the contract price;

(iii) Implementation of engineering measures and payment of engineering prices;

(iv) The processing of engineering claims and changes of visas, engineering settlement and accounts;

(v) Processing the construction of engineering price disputes and the establishment of engineering pricing recognition;

(vi) Other activities related to the establishment and control of construction works.

Article 5

More than communal housing and urban-rural-building administrative authorities are responsible for the management of construction works within the current administration.

All levels of construction work-making authority are required to carry out their duties under the law and are guaranteed by the same fiscal sector in accordance with the relevant provisions of the State and the province.

Within their respective responsibilities, the professional construction engineering administrative authorities at all levels are responsible for the supervision of professional construction works in the current administration area.

Article 6. The financial sector is responsible for the budget of the Finance Fund Investment Project, the completion of the work plan (in summary) for evaluation and review.

Article 7

Chapter II

Article 8

(i) Estimates, estimates;

(ii) Purchase, one-time replenishment, cost-setting and criteria;

(iii) Levels of work and labour;

(iv) Consolidated prices of manual, material (assistance) and one-time supplementary material prices and construction machines;

(v) Constraints for the inventory value of the works;

(vi) Purchase information and settlement documents published at all levels by the construction of the engineering price management structure;

(vii) Other basis provided by the State and the province.

Article 9

(i) Approval of indicators, budget estimates, calculations, costs, duration of work, labour customization, engineering inventory price specifications, engineering standard norms and engineering value-added information, etc., by provincial construction pricing management, based on national engineering standards, standards and market price information development and adjustments, and the publication of provincial housing and urban-rural construction administrative authorities;

(ii) A one-time replenishment of construction works, measured by the housing and urban-rural construction administrative authorities in each city (State) and confirmed, issued by the provincial housing and urban-rural construction authorities;

(iii) Construction of a one-time supplementary material price for construction, which is developed by the housing and urban-rural-building administrative authorities in municipalities;

(iv) Price information, such as manuals, materials, construction machines, etc. in the administrative areas of the municipalities (States), is collected, calculated, summarized and published on a regular basis by the provincial housing and urban-rural construction administrative authorities.

Article 10. The contractor shall hold a certificate of fees for the construction of a social insurance for the construction of the enterprise in the Province of Glin, which shall be charged to the lender at the rate approved by the provincial housing and rural and urban construction authorities for the year.

Article 11. The cost of quality safety in construction works is collected and measured by the housing and urban-rural construction administrative authorities in the municipalities (States) and urban areas, in accordance with the type of construction structure divided by provincial housing and urban-rural construction authorities, and the provincial housing and urban-rural construction administrative authorities have confirmed that social disclosure is made within the prescribed time frame.

Chapter III

Article 12

(i) Building units prepare investment estimates based on scale-building, construction standards, process technology standards, estimating indicators, engineering prices based on and taking into account factors such as price, interest rate change during construction;

(ii) The construction unit, the relevant design units or the construction of the construction of the engineering price consulting firm to prepare, within the context of the investment estimates, the proposed budget indicators or estimates, market prices;

(iii) The construction unit or the construction consulting firm shall, within the approved design estimates, prepare the construction map budget based on factors such as the audited construction map, construction programme, market prices;

(iv) The completion of the work is governed by the contractor within the framework of the construction map budget, in conjunction with the construction contract agreed construction contract price and the adjustments to the contract agreement.

The full use of State-owned funding investments or construction projects with State-owned funding investments must be used to meet the inventory value.

The list of works shall be prepared by a solicitor with the capacity to prepare or by a construction engineering consulting firm with the corresponding qualifications.

Article 14.

Article 15. The construction project for the application of the inventory value of the works shall be based on the calculations provided by the State and the province and the relevant provisions to produce the tendering control price in accordance with the design, construction map paper.

The solicitation control price was prepared by the solicitor and the bidder did not have the capacity to prepare and should be entrusted with the development of a construction engineering consulting firm with the corresponding qualifications.

The solicitation control price shall be made public at the time of the solicitation and shall not be adjusted or buoyed. The bidder shall send the solicitation control price to the construction of the project site for the preparation of the work-making authority.

Article 16 Investments in State funds or construction projects with State-owned funding investments shall be subject to approval by the solicitation approval of the approval department for the approval of the solicitation control price estimates when they exceed the approved estimates.

The financial investment project portfolio, the solicitation control price and the completion of the works are vested in the financial sector or in the financial sector for the preparation and review of the construction work-building consulting firm. No matter of review shall be used as a basis for the settlement of the construction price.

Article 17

Article 18

The following Article 19 expenditures shall not be used as competitive costs for tendering:

(i) Security protection, civilization construction measures expenditure;

(ii) Exclusive expenditure on work;

(iii) Old-age insurance expenditure;

(iv) Unemployment insurance expenditure;

(v) Health insurance expenditures;

(vi) Housing pools;

(vii) Expenditure on maternity insurance;

(viii) Expenditures for accidental injury to hazardous operations;

(ix) Industrial injury insurance expenditures;

(x) Tax payments;

(xi) Other expenditures provided by the State and the province.

Article 20 The construction of the construction of the engineering consignee and the contractor shall agree on the following matters relating to the construction price:

(i) Scope, quality standards and contract price;

(ii) The amount of the advance payment, the time and the manner in which it is paid;

(iii) Modalities, amounts and time for engineering measurements and payment of progress payments;

(iv) Adjustment factors, methods, procedures, payment modalities and time for the engineering price;

(v) The procedures for the identification and payment of claims with respect to the ground visa;

(vi) The content, scope and approach to risk-taking beyond the agreed content;

(vii) The settlement of the construction and reconciliation, manner and time for the completion of the work price;

(viii) Methods and time for settlement of disputes in the amount of work;

(ix) The amount, prefabrication and timing of the work quality security cost assurance and the quality assurance (insurance);

(x) Requirements for work period adjustments;

(xi) Other matters relating to payment of royalties.

Article 21, where the construction price is required, the contractor shall, within 14 days of the contract agreement, communicate the adjustment, the amount in writing to the lender, after confirming the adjustment as an additional contractual provision, pay the same period as the construction progress. The author was not confirmed within 14 days after the written notice of the contractor was received by the contractor and was considered to be in agreement with the adjustment. The licensor may also decide, within 14 days of the contract agreement adjustment, to adjust the cost of the work and to notify the contractor in writing that the contractor does not recognize it within 14 days after the written notice has been received.

Article 22 introduces a pre-payment engineering and payment rate system.

Article 23

(i) The advance works of the Package works are charged in accordance with the contract agreement and, in principle, less than 10 per cent of the contract price and less than 30 per cent of the contract price;

(ii) Major engineering projects, which are prepaid under the annual engineering plan;

(iii) The application of the inventory value, which should be agreed on the proportion of pre-payments for physical consumption, non-physical consumption.

Article 24. Progress in the payment of works shall be in accordance with the following provisions:

(i) Within 14 days of the determination of the results of the engineering measurement, the licensor shall pay the contractor with a payment of the progress of the works by 80 per cent of the non-performance of the engineering price;

(ii) In accordance with the agreement of the contractor with the agreement on the progress of the extension of work, the parties have failed to conclude the extension payment agreement and, in accordance with the original contract, the lender shall pay the work in advance, and, if not paid at the time, the licensor pays the interest in the same period from the date of default to the date of the payment of the payment.

Article 25 provides for the full use of State-owned funding investments or construction projects that are dominated by State-owned funds, and no contractor shall be required to carry out construction.

Article 26 Producers and contractors shall be subject to the following provisions:

(i) The contractor shall prepare, within a specified time frame, the completion of the completion of the work settlement document and submit the contractor with the contractor's receipt of the completion of the completion of the work settlement document, and shall receive the receipt of the contract, the contractor may not deliver the completed works;

(ii) The licensor shall receive the completion of the work settlement document submitted by the contractor and shall, within a specified time frame, review the completion of the work settlement documents and document the completion of the work completed;

(iii) The contractor's objection to the completion of the work of the lender's clearance documents should be questioned on the basis of and detailed calculations to reciprocize the sender. Clear observations should be made after the reciprocation of the lender;

(iv) Abductor shall settle the works with the contractor within 15 days of confirmation that the completed work settlement document is no objection.

Article 27 provides that the licensor can only entrust a construction engineering consulting firm with the review of the completed engineering settlement documents submitted by the contractor within the prescribed time frame.

Article 28 provides that the licensor shall, in accordance with the following provisions, review the completion of the work settlement document:

(i) The findings of the review within 20 days of the construction of the amount of $5 million (with a $5 million);

(ii) The conclusion of the review within 30 days of the construction of more than 5 million dollars (including 20000,000 dollars);

(iii) The findings of the review within 45 days of the construction price of more than 50 million dollars (with a total of 5,000 dollars);

(iv) In 60 days of the construction price of more than 50 million dollars.

Article 29 provides that the lender and the contractor are incompatible with the understanding that the construction of the construction price is based on the construction of the construction of the construction work area.

After the completion of the work, the licensor shall submit the construction of the engineering price management for the construction of the project site for the completion of the work document.

Chapter IV Oversight management

Article 31, above-ranking housing and urban-rural-building administrative authorities monitor the operation of construction-based consulting enterprises in accordance with the law and implement dynamic management of their qualifications.

The implementation of the Department of State provides for professional engineering pricing advice, which is administered by the relevant administration in accordance with national provisions.

Article 32 Construction of a construction consulting firm shall obtain a certificate of qualifications for the construction of the engineering price and, in the context of its qualification licence, be entrusted with the work-making process.

The construction of engineering-based professionals should be eligible by law and registered in a unit for construction work-making activities.

Article 33 Construction of engineering consulting enterprises and their price professionals should strictly implement the standards, norms and the basis for the construction of the construction of the construction of the works and make the results of the construction of the works.

The construction of the engineering consulting firm shall include in its advisory outcome a chapter of the enterprise name, qualifications, certificate number and be signed by the engineer for the implementation of the consultancy operation, plus the executive log.

Article XXX Construction of a construction consulting firm to undertake construction of a engineering price consulting operation shall enter into a written contract and report on the construction of the construction of the construction of the work-burden management body.

Article 33XV, in the province, of the construction of the construction of engineering consultancy operations, should be based on a certificate of qualifications, business licences, etc., within 30 days of the operation.

Article 36

(i) Provision of false material to deceive corporate qualifications;

(ii) Constraints, alterations, sale, rent, borrower certificates or other forms of unlawful transfer of credit certificates;

(iii) Transfer of the construction work-making process;

(iv) Inadequate competition;

(v) The price base and the method of calculating the price set by the State or the province;

(vi) The scope of the operation that is free of charge or exceeds the licence of the quality of the award and the construction of the construction of the engineering price advisory operation;

(vii) At the same time, the solicitation, tenderer, or more than two bidders are entrusted to the construction work-making process for the same engineering project;

(viii) Excluding the ultra vires of the contract;

(ix) false reports;

(x) Other acts prohibited by law, regulations and regulations.

Article 37

(i) Accreditation by means of fraud;

(ii) Excluding the operational scope of the employing units to engage in the operation;

(iii) Business bribery in the course of the operation;

(iv) Non-registered construction work-making;

(v) Registration at the same time of two units;

(vi) Removal, sale, rent, borrower or other forms of unlawful transfer of registration certificates or rules of operation;

(vii) Carrying out construction of engineering price counselling operations on behalf of individuals;

(viii) To allow others to engage in construction of engineering price counselling operations in their own name;

(ix) The results of the fraudulent construction work-making process;

(x) Other acts prohibited by law, regulations and regulations.

Article 338 The construction of an enterprise branch of the construction of a construction consulting firm shall not take place on behalf of the branch in the construction of a construction consulting operation.

Article 39 of the Producer or contractor contested the outcome document of the construction of a engineering consulting firm, which was organized by experts from the provincial housing and rural-urban construction administrative authorities to validate the outcome document and, as confirmed, the outcome document was in line with the construction of engineering prices, the lender, the contractor should be executed; the lender and the contractor should be based on the identification of the findings as the basis for the construction of the work price activities.

Article 40 establishes a credit file for the construction of a construction consulting firm and business personnel. The construction of administrative authorities in housing and rural areas is regularly evaluated, evaluated and published in society in accordance with the relevant provisions of the State.

Chapter V Legal responsibility

Article 40 consists of one of the following acts, being corrected by the administrative authorities responsible for housing and urban-rural construction, at the district level, and by a fine of over 3,000 dollars.

(i) The non-implementation of tendering on the basis of a list of works;

(ii) No publication of the solicitation control price;

(iii) No cost of quality safety in construction works;

(iv) No construction project settlement at the agreed time;

(v) No tender-control capacity to prepare tenders;

(vi) Entrust the establishment of tender control prices by a construction engineering consulting firm with no corresponding qualifications.

Article 42 provides for the construction of engineering consulting enterprises, the presence of professionals involved in the construction of engineering price counselling operations, which is prohibited under article 36, article 37, and the imposition of sanctions by district-level housing and urban-rural-building administrative authorities in accordance with the relevant laws, regulations.