Quality management provisions for construction projects in North Province

The 11th ordinary meeting of the provincial Government, held on 29 October 2013, discussed the publication, effective 1 January 2014, of Government Order No. 10 of the Northern Province of Mali, of 2 November 2013, of implementation by 1 January 2014.

Article 1 oversees the quality of the construction projects, guarantees the quality of the works, public safety and the life, property security of citizens, and establishes this provision in the light of the relevant national legislation, regulations and regulations.

Article 2

Article III provides for the installation of engineering projects referred to in this Article, which refers to equipment, pipelines, electrical devices, automated industrial construction works and construction of corruption, inequity and industrial stoves.

Article IV. The Ministry of People's Development and Reform and the municipalities, districts (communes, districts) People's Government Development and Reform Departments or other sectors responsible for the quality management of the construction projects established by the Government of the Territory (markets, districts) are the Government of the people at this level to install the quality of engineering construction projects. The quality management of the installation of engineering construction projects could be entrusted with the quality of the engineering construction work monitoring body, with specific implementation of the quality management of the installation of engineering projects.

In accordance with their respective responsibilities, sectors such as housing and rural-urban construction, safe production supervision, quality technical supervision management are governed by the law by the laws.

Article 5 Construction, survey design, construction, treasury and quality testing units should establish a sound quality assurance system and be responsible for the quality of the work in accordance with the law.

The construction units for the installation of engineering projects should be assigned to the survey design, construction, treasury and quality test units with a corresponding level of qualifications, and no post-movable engineering kits shall be released.

The survey design, construction, treasury and quality testing units should be provided with a corresponding hierarchy of qualifications in accordance with the law, and be operational within their qualifications.

Article 7. The construction unit shall, prior to the receipt of a construction licence, process the quality supervision of the installation of works in accordance with the provisions of the construction project.

Article 8. In accordance with the contract agreement that the construction unit is responsible for the acquisition of equipment and material required for the installation of the engineering construction project, the construction unit should ensure that the equipment and materials procured are in compliance with the design requirements and the relevant national standards, without express or implying that the construction units use unqualified equipment and material.

Article 9. The design of the construction project should take advantage of new technologies, new equipment, new materials and new processes promoted by the State, and its design documents should be consistent with the provisions of the relevant laws, regulations and national standards and contractual agreements, which should be accurate, reliable and reasonable, and selection of equipment, materials should indicate their specifications, patterns, and technical indicators and quality requirements.

In addition to specialized equipment and materials with special requirements, the design cell shall not designate the production plants, suppliers.

Article 10. The design units for the installation of construction projects shall be subject to the technical subsection of construction map paper to units such as construction, construction and treasury, with timely participation in the processing of the related issues arising in the construction process, the quality of work at the relevant stages and the evaluation of the quality of the design after completion of the project.

Article 11. Construction units for the installation of engineering projects shall be constructed in accordance with the engineering design map and relevant national standards and shall not be subject to any unauthorized modification of the engineering design.

The construction units have found poor design documents and paper in the construction process and should make observations and recommendations to units such as construction and custodial.

Article 12. The construction unit shall test the equipment and material used in the installation of the engineering construction project, as prescribed, and shall not steal the work or use non-qualified equipment and material.

Article 13. The construction units shall record in a timely, accurate and complete manner the quality, technical control of the construction process and submit complete engineering technical information to the construction units prior to the receipt of the engineering tests.

Article 14.

For important engineering sites and hidden works, the treasury engineer should have uninterrupted wings and retain video material.

Article 15. The construction unit shall not carry out the construction of the order without the signature of the custodial engineers, the equipment and material concerned shall not be used in the installation of the works. Without the signing of the General Architects, construction units are not subject to the payment of engineering funds and are not subject to the inspection of the works.

Article 16 Quality Tests Units for the installation of engineering projects should be conducted in accordance with the law to test operations, to test reports and to be responsible for the findings. The quality test unit should immediately inform units such as construction and custodial.

Article 17 Quality Tests Units should carefully implement the quality test archives management system, harmonize and maintain numbers of construction quality testing contracts, commissioners, original records and testing reports, without drawing of lots and modifications.

Article 18

Article 19 The following measures may be taken in connection with the installation of the quality management of the engineering construction project to perform oversight duties:

(i) Access to construction sites and other workplace inspections by inspection units;

(ii) To request the inspectorate to provide documentation and information relevant to the quality of the installation;

(iii) The responsibility of the inspectorate shall immediately cease violations of the law, regulations, regulations and national standards of quality management and improve quality management.

Article 20, when the quality management of the engineering construction project is installed to perform oversight duties, the inspection units should be synergized, such as providing information and information, and taking timely improvement measures on the quality management of the existence.

Article 21 Staff of the construction project to install the quality management of the works should be kept confidential for the commercial secrets known in the performance of oversight duties.

Article 2: The construction units shall be sent within 15 days of the date on which the engineering construction project is installed for the quality management of the works to be installed in the inspection reports and related materials.

Article 23

Article 24, in violation of articles 7, 8, 9, paragraph 2, 11, paragraph 1, and 12 of the present article, is criticized by the responsibility of the management responsible for the installation of the quality of the construction project and punished in accordance with the provisions of the State Department's Regulations on the Quality of Engineering.

Article 25, in violation of article 14 of the present article, is changing by the responsibility of the management responsible for the installation of the quality of the works by the chemical construction project and criticized it.