Responsibility Subject And The Bad Records Of Construction Project Quality Management Procedures (Trial Implementation)

Original Language Title: 建设工程质量责任主体和有关机构不良记录管理办法(试行)

Subscribe to a Global-Regulation Premium Membership Today!

Key Benefits:

Subscribe Now for only USD$40 per month.
  First to standardize construction project quality responsibility and relevant agencies engaged in construction activities, strengthening the construction of Administrative Department of supervision of the fulfilment of their responsibility for the quality, these measures in accordance with the relevant laws and regulations.
Second article this approach by said of construction engineering quality responsibility subject and about institutions bad records, is refers to on engaged in new, and expansion, and alterations housing building engineering and municipal based facilities engineering construction activities of units, and survey units, and design units, and construction units and construction figure review institutions, and engineering quality detection institutions, and supervision units violation legal, and regulations, and regulations by provides of quality responsibility and obligations of behavior, and survey, and design file and engineering entity quality not meet engineering construction mandatory technology standard of situation of records.
By the construction administrative departments administrative penalties, according to the Ministry of construction on accelerating the establishment of construction market-related business and professional credit file notice (the city [2002]155) be included in the credit file, do not belong to these measures and publish as well.
Article review of survey, design, construction, construction drawings, engineering quality inspection and supervision unit's poor record as a construction Administrative Department to carry out inspection and an important basis for qualification review.
Fourth unit the following should be recorded: 1, construction drawing design documents should be examined without approval, unauthorized construction design file in the process of construction of major design changes, did not change after construction to repay the original construction drawing Inspection Agency for review and approval, the unauthorized construction.
2, purchase of building materials, fittings and equipment not in conformity with the design documentation and contract requirements; construction unit of express or implied the use of substandard building materials, fittings and equipment.
3, express or implied survey and design unit violates the engineering construction compulsory standard, reduced quality of the project.
4, involving changes in the main building and the load-bearing structure of the renovation works, without the original designer or design unit designs with the appropriate qualifications, unauthorized construction.
5, other violation affected the quality of construction projects.
Article fifth survey and design units should be recorded: 1 approval requirements that are not in accordance with the relevant government departments to survey and design.
2, the design of the unit is not designed according to the investigation file.
3, did not follow the engineering construction compulsory standard inspection, design.
4, used in the survey and design may affect quality and safety, and there are no national standards for new technologies, new processes and new materials, according to stipulations of the validation.
5, survey, design files are not responsibility for signature or signatures is not complete.
6, the survey records are not in accordance with the provisions of the record or the record is not complete.
7, survey and design document before the construction drawing examination and approval after examination found quality problems, these changes at a time.
8, investigation, review of design documents and construction drawings have not been approved.
9, the reconnaissance unit does not participate in the inspection of construction.
10, at the time of acceptance is not according to the quality assessment of the project.
11, design units to the examination and approval of construction drawing design documents, denied construction units to deliver the design before construction; refused to participate in the construction project quality accident analysis.
12, the possible influence of other violations of engineering survey and design quality.
Sixth construction units the following should be recorded: 1, in accordance with the documentation review and approval of construction plans and construction technical standards.
2, according to stipulations on construction materials, concrete construction fittings, equipment and goods for inspection or test failed, unauthorized use.
3, was not in accordance with the regulations on concealed works of quality checks and records.
4, usage not in accordance with the regulations relating to the structural safety of the blocks, specimens and related materials for on-site sampling, detection is not transmitted to the engineering quality inspection institutions.
5, without a supervising engineer's signature, go to the next step of construction.
6, construction personnel are not required to receive education and training, appraisal, or having not passed training, assessment, duty without authorization.
7, during construction, was ordered shut down for quality reasons.
8, other violations that could affect construction quality.
Seventh construction plans should be recorded the following review bodies: 1, without approval by the Administrative Department for the record-building, without authorization, construction drawing review of operational activities.
2, beyond the approved level and scope review of operational activities.
3, review of review content that is not provided for by the State, there is mistake of the trial, missing.
4, other violations that may affect the quality review.
Article eighth engineering quality inspection should be recorded the following institutions: 1, without approval to engage in operational activities of the engineering quality inspection.
2, beyond the approved scope of business engaged in engineering quality inspection business activity was detected.
3 provide a false report and detection report data and conclusions and the measured data does not meet the.
4, other violations that could affect quality.
Nineth supervision unit to the following should be recorded: 1 according to regulations, failure to appoint a qualified Chief supervision engineer and engineer stationed in the construction site.
2, supervising engineers and Chief supervision engineer does not sign by Convention.
3, supervising engineer does not take stand, inspections and parallel testing and other forms of supervision.
4, not according to the relevant laws, regulations, and technical standards and quality supervision of construction project contract.
5, not according to the examination and approval of construction drawing design documents, as well as the examination and approval of construction drawing design document of construction quality supervision.
6, when it is completed not according to engineering quality assessment report.
7, other violations that could affect quality.
Tenth construction drawing review, and engineering quality inspection agencies, the engineer shall record found in the construction, survey, design, construction of the record, in accordance with the administrative permissions of the projects involved, to the appropriate administrative authorities or its authorized engineering quality supervision institutions to submit.
Construction administrative department or its designee to verify the situation of engineering quality supervision institutions to submit.
11th construction of local people's Governments at or above the county level administrative departments or its authorized engineering quality supervision institutions to respond to quality inspection, quality supervision, accident management and quality complaint handling process within their respective administrative areas found in construction, survey, design, construction, construction drawing review, quality inspection, supervision and other units of the record is responsible for recording and verifying.
12th local people's Governments at or above the county level shall construction administrative department or its authorized engineering quality supervision institutions to have been verified by adverse record totals, and construction to the superior administrative departments or its engineering quality supervision institutions commissioned by the record.
13th construction project quality and relevant bodies of the registered location is not in the administrative regions of the province, provinces, autonomous regions and municipalities directly under the construction administrative departments should submit the construction administrative departments under the State Council for the record at the same time, the unit notifies the place where its register of bad record of provinces, autonomous regions and municipalities directly under the construction Administrative Department. 14th of provinces, autonomous regions and municipalities directly under the construction administrative departments should be established in the construction market supervision and management information system engineering construction quality management information system.
Record record through the system, the data transmission should be sent through the Internet as possible, to ensure real-time records.
Construction administrative department or its authorized engineering quality supervision institutions should be verified by adverse record input appropriate information systems.
15th relevant records organizations and personnel responsible for the authenticity and completeness of the record.
() The local people's Governments at or above the construction administration department or its delegate the quality oversight body accountable to the poor record of accuracy within their respective administrative areas.
16th construction administrative departments of provinces, autonomous regions and municipalities, should be published in the media on a regular basis within the administrative area of the record.
() The construction administrative departments can also be published in the media on a regular basis within the administrative area of the record.
17th construction engineering quality supervision of the competent authority or its authorized body, bad record should be involved in building housing and quality status of municipal infrastructure projects to the public.
18th bad records released through the relevant construction information network, announced the retention time of not less than 6 months need to undo records released shall be published by the original organ. 19th local construction administrative departments to attach great importance to poor records management, clear leaders and contractors, staff and responsibilities.
The dereliction of duty, should be investigated and appropriate sanctions.
20th of provinces, autonomous regions and municipalities directly under the construction Administrative Department in accordance with the measures, formulate detailed rules for the implementation. 21st article this way come into force on July 1, 2003.