DECREE OF December 9, 2002

Outorga to the State Power Company Electrical-CEEE concession for operation of public electric power transmission service, relative to the transmission line by interconnecting Substation President Medici to Pelotas Substation 3, located in the State of Rio Grande do Sul, and other arrangements.

THE VICE PRESIDENT OF THE REPUBLIC, at the exection of the post of President of the Republic, using the assignment that confers you the art. 84, inciso IV, of the Constitution, and in view of the provisions of the Laws n 8,987, of February 13, 1995, and 9,074, of July 7, 1995, and what is contained in Process No 48500.001296 /02-71,

D E C R E T A:

Art. 1º It is awarded to the State Power Company-CEEE grant for public power transmission operation of electric power, for deployment, operation and maintenance of the Transmission Line Chairman Medici-Pelotas 3, at 230 kV, simple circuit, with an estimated extension in 130 km, with origin at Substation President Medici and termination at the Pelotas 3 Substation located in the State of Rio Grande do Sul, and other facilities necessary to the functions of measurement, supervision, protection command, control, telecommunication, administration and support.

Art. 2º The granting of this Decree shall apply for the period of thirty years, counted from the date of signature of the respective Public Power Transmission Public Service Concession Contract.

§ 1º The Contract is to be signed within thirty days, counted from the publication of this Decree, under penalty of ineffectiveness of the concession ora given.

§ 2º The application of the State Energy Company Electrical Electrical-CEEE to the National Energy Agency Electrical-ANEEL, presented up to thirty-six months before the termination of the constant deadline of the chaput of this article, the concession may be extended under the conditions stipulated.

Art. 3º The existing goods and facilities in function of the electric power transmission service shall be linked to the public services granted, vetting its disposal, assignment, transfer or dation in guarantee, without prior and express permission of ANEEL.

Single Paragraph. Upon expiry of the concession period, the goods and facilities bound for the provision of the service granted will revere to the Union, in the manner provided for in law and in the Grant Agreement.

Art. 4º This Decree shall enter into force on the date of its publication.

Brasilia, December 9, 2002 ; 181º of the Independence and 114º of the Republic.

MARCO ANTONIO DE OLIVEIRA MACIEL

Francisco Gomide