Print
The Vermont Statutes Online
Title
09
:
Commerce and Trade
Chapter
102
:
CONSTRUCTION CONTRACTS
§
4003. Contractor's and subcontractor's payment obligations
(a) Performance
by a subcontractor in accordance with the provisions of its contract shall
entitle it to payment from the party with which it contracts.
(b)
Notwithstanding any contrary agreement, a contractor or subcontractor shall
disclose to a subcontractor, before a subcontract is entered, the due date for
receipt of payments from the owner. Notwithstanding any other provision of this
chapter, if a contractor or subcontractor fails to accurately disclose the due
date to a subcontractor, the contractor or subcontractor shall be obligated to
pay the subcontractor as though the 20-day due dates in subsection 4002(c) of
this title were met by the owner.
(c)
Notwithstanding any contrary agreement, when a subcontractor has performed in
accordance with the provisions of its contract, a contractor shall pay to the
subcontractor, and each subcontractor shall in turn pay to its subcontractors,
the full or proportional amount received for each such subcontractor's work and
materials based on work completed or service provided under the subcontract,
seven days after receipt of each progress or final payment or seven days after
receipt of the subcontractor's invoice, whichever is later.
(d) Notwithstanding
any contrary agreement, if any progress or final payment to a subcontractor is
delayed beyond the due date established in subsections (b) or (c) of this
section, the contractor or subcontractor shall pay its subcontractor interest,
beginning on the next day, at an interest rate equal to that established by 12
V.S.A. § 2903(b), on such unpaid balance as may be due. (Added 1991, No. 74, §
1, eff. Jan. 1, 1992.)