Revised project plan required, when.

227.556. 1. If, prior to the letting date of the construction project,

the commission's project plan is changed so that additional or different

utility relocation work is found necessary, the commission shall furnish a

revised project plan under section 227.554, and the owner shall provide the

commission with a revised relocation plan under section 227.555, except that

the time allowed for the owner to submit the revised relocation plan after

receipt of the revised project plan shall not exceed sixty days.



2. If, after the letting date of the highway construction project,

additional utility relocation work is found necessary which was not indicated

on the original project plan, the commission shall provide the owner with a

revised project plan within fifteen days and the commission and the owner

shall agree on a reasonable schedule for completion of the additional utility

location.



(L. 2005 H.B. 209 § 227.246)