(a) A disinfection system must include a backup power
system capable of providing sufficient power to operate continuously
during all power outages in accordance with the requirements of §217.36
of this title (relating to Emergency Power Requirements), including
outages that are longer than outage predicted based on the power reliability
determination required in §217.36(e) of this title.
(b) A backup power system must automatically restart
the disinfection system during a power outage.
(c) A backup power system must meet the requirements
of §217.36 of this title.


Source Note: The provisions of this §217.37 adopted to be effective August 28, 2008, 33 TexReg 6843; amended to be effective December 4, 2015, 40 TexReg 8254