SECTION .0200 ‑ ELIGIBILITY REQUIREMENTS
15A NCAC 01L .0201 ELIGIBLE PROJECT COSTS
(a) Project costs eligible for a loan under this Subchapter
are limited to:
(1) the actual costs of the works described in
the project application;
(2) contingency costs, not to exceed ten
percent of the estimated eligible construction costs for which a loan award is
made under this Subchapter. Upon receipt of bids, the contingency costs shall
be reduced to not more than five percent of the actual eligible construction costs
as bid.
(b) Eligible costs do not include recurring annual
expenditures for administration, repairs, or operation and maintenance of any
wastewater treatment works, wastewater collection system, water supply system
or water conservation projects. Items not covered or allowed in the definition
of "cost" are also excluded.
History Note: Filed as a Temporary Rule Eff. March 8,
1994, for a period of 180 days or until the permanent rule becomes effective,
whichever is sooner;
Authority S.L. 1998, c. 132, s. 10;
Eff. July 1, 1994.