4761.2600 EMERGENCY PROJECT NOTICE.


§
Subpart 1.

Notice requirement.


§
A.

Except as otherwise provided in this part, an emergency project must be reported to the commissioner according to part 4761.2580.


§
B.

For an emergency project that begins between 8:00 a.m. and 4:30 p.m. on the days the Department of Health is open, the commissioner must receive from the certified lead firm, lead supervisor, or property owner a completed notice before the project begins. The notice must be mailed, faxed, delivered, or submitted electronically.


§
C.

For an emergency project that begins at a time other than that specified in item B, the commissioner must receive from the certified lead firm, lead supervisor, or property owner a completed notice as soon as possible, but no later than 4:30 p.m. the next day that the department is open. The notice must be mailed, faxed, delivered, or submitted electronically.



§
Subp. 2.

Amending emergency project notices.

Amendments to an emergency project notice must be made according to part 4761.2590, items B to D.