Environmental Impact Assessment Regulations 2010 _Eng V2_
C
T
ENVIRONMENTAL IMPACT
ASSESSMENT REGULATIONS 2010
Environmental Impact Assessment Regulations
2010 Arrangement of Regulations
to
Page 3
C
T
ENVIRONMENTAL IMPACT ASSESSMENT
REGULATIONS 2010
Arrangement of Regulations
Regulation
PART I - PRELIMINARY 5
1 Short Title .................................................................................................... 5
2 Interpretation ................................................................................................ 5
3 Forms and Fees .......................................................................................... 5
PART II - ENVIRONMENTAL IMPACT ASSESSMENT
PROCEDURES 6
4 Application for environment impact assessment ....... ....................................... 6
5 Assessment to be appropriate.................................................................... 6
6 Process established ........................................................................................... 6
7 Assessments to be written .......................................................................... 6
8 Notification ................................................................................................... 6
9 Form 1 of Schedule 1 to be used ....................................................................... 6
10 Additional Information Required ................................................................. 7
11 Project to proceed if no environmental impact assessm nt advised ...................... 7
12 Consideration .............................................................................................. 7
13 Secretariat advice may be sought .............................................................. 8
14 Secretariat guidelines to be used for minor projects .............................................. 8
15 Major Project Assessment process to be thorough ................................................ 8
16 Form 3 and environmental study to be used for Major Pr ject assessment ........... 8
17 Secretariat’s guidance shall be sought ....................................................... 9
18 Certification of environmental study ............................................................ 9
19 Secretariat’s guidelines to be used for major projects ........................................... 9
20 Committee to review and recommend ............................................................ 9
21 Structure of recommendation ............................................................................ 9
22 Adoption by quorum .................................................................................. 10
Arrangement of Sections
Environmental Impact Assessment Regulations
2010
Page 4
to
23 Report by Committee ................................................................................ 10
24 Copies of Committee report to be free of charge ................................................. 10
25 Certification of approval ............................................................................ 10
26 Information to be correct ................................................................................. 10
27 Change in circumstances .......................................................................... 10
28 Minister may impose further conditions ........................................................ 11
29 Committee may cancel certification ............................................................. 11
30 Proponent to re-submit application ................................................................... 11
SCHEDULE 1 12
FORM 1: DETERMINATION OF CATEGORY OF ASSESSMENT 12
FORM 2:MINOR ENVIRONMENTAL IMPACT ASSESSMENT 13
FORM 3: MAJOR ENVIRONMENTAL IMPACT ASSESSMENT 14
FORM 4: COMMITTEE RECOMMENDATIONS 15
SCHEDULE 2 16
FEES AND CHARGES 16
Environmental Impact Assessment Regulations 2010 Regulation 1
to
Page 5
C
T
ENVIRONMENTAL IMPACT ASSESSMENT
REGULATIONS 2010
ENVIRONMENTAL IMPACT ASSESSMENT ACT 2003
IN EXERCISE of the powers conferred by section 24 of the Environmental
Impact Assessment Act 2003, the Minister of Environment with the consent of
Cabinet makes the following Regulations —
PART I - PRELIMINARY
1 Short Title
These Regulations may be cited as the Environmental Impact Assessment
Regulations 2010.
2 Interpretation
(1) In these Regulations -
“Act” means the Environmental Impact Assessment Act 2003; and
“Secretariat” means the Secretariat of the Environmental Assessm nt
Committee.
(2) The terms and phrases defined in the Act shall be given the same meaning in
these Regulations, unless the context requires otherwise.
3 Forms and Fees
(1) The forms set out in Schedule 1, are hereby prescribed for the purposes of the
Act and these Regulations.
(2) The fees set out in Schedule 2, are hereby prescrib d for the purposes of the
Act and these Regulations.
Regulation 4 Environmental Impact Assessment Regulations 2010
Page 6
to
(3) Where the Act or these Regulations require a development application to be
referred to a Determining Authority, the Minister, considering the advice of
the Secretariat, may require additional copies of the development application,
the environmental impact assessment, and any supporting documents to be
lodged so that reference can be made.
PART II - ENVIRONMENTAL IMPACT ASSESSMENT
PROCEDURES
4 Application for environment impact assessment
The process of environmental impact assessment shall be pplied to all major
projects so classified under Part III of the Act.
5 Assessment to be appropriate
The process of assessment shall be appropriate for the activity taking into account
the scale and intensity of the proposed activity and its anticipated environmental
impacts.
6 Process established
All Major Project assessment shall follow a process of notification, environmental
impact assessment, review, final decision with or without conditions.
7 Assessments to be written
All assessments of environmental impact shall be undertaken by the proponent and
shall be submitted to the Minister in written form together with a copy of the form
for development application.
8 Notification
All development activities proposed shall be notified to the Minister or, in the case
of a license issued by another Determining Authority, to that Authority for referral,
as necessary, to the Minister, prior to any project-r lated work or activity
commencing, or any decision being made to approve such an activity.
9 Form 1 of Schedule 1 to be used
Notification shall be in accordance with Form 1 of the Schedule 1 and include such
information as is necessary for the Minister, acting upon the advice of the
Secretariat, to determine whether any environmental impact assessment is necessary
under the Act.
Environmental Impact Assessment Regulations 2010 Regulation 10
to
Page 7
10 Additional Information Required
The Minister shall, within 30 working days of receipt of notification of a
development application, and after consideration of advice from the Secretariat and
any other agency relevant to the proposal, by notice in writing to the proponent,
notify the proponent, and the Determining Authority, where it applies, of the
requirement to conduct environmental impact assessmnt or the need to furnish
additional information in relation to the proposed development, being information
which is, in the Minister’s view, essential to the d termination of the proposal under
section 8(2) of the Act.
11 Project to proceed if no environmental impact as sessment advised
Where the Minister has not advised the proponent, and the Determining Authority in
writing within 30 working days of receipt of notice that an environmental impact
assessment is required, or has not indicated to the proponent that an extension of
time for further consideration of the development application applies, then the
Proponent may assume that no environmental impact assessment is required and,
subject to gaining all other necessary approvals, the activity may commence.
12 Consideration
The factors to be taken into account by the Minister and the Secretariat when
considering the likely impact of an activity upon the environment shall include
whether that activity may cause:
(a) any environmental impact upon a community;
(b) any transformation of a locality;
(c) any environmental impact upon the ecosystems of a c mmunity;
(d) any diminution of the aesthetic, recreational, scientific or other environmental
quality or value of a locality;
(e) any effect upon a locality, place or building having aesthetic, archaeological,
architectural, cultural, historical, scientific, social significance or any other
special value for present or future generations;
(f) any endangering of any species of flora or fauna;
(g) any long-term effects upon the environment;
(h) any degradation of the quality of the environmet;
(i) any risk to the safety of the environment;
(j) any curtailing of the beneficial uses of the environment;
(k) any pollution of the environment;
(l) any environmental problems associated with the disposal of waste;
Regulation 13 Environmental Impact Assessment Regulations 2010
Page 8
to
(m) any increased demands upon resources, natural or otherwise, which are, or
likely to become, in short supply;
(n) any effect upon the supply of electricity, water, waste collection services,
telephone or other services;
(o) any increase in the amount or duration of traffic generated by either the
construction of the development or by its consequent se; and
(p) any cumulative effect with any other existing or likely future activities.
13 Secretariat advice may be sought
(1) In completing the impact assessment, the Proponent may seek the assistance
of the Secretariat in determining what degree of asses ment shall be
undertaken.
(2) The Minister’s written advice in such matters shall be final.
14 Secretariat guidelines to be used for minor proj ects
Where the Secretariat has prepared guidelines for minor projects assessment, these
shall be used to complement matters outlined in the Schedule 1.
15 Major Project Assessment process to be thorough
A Major Project assessment shall involve a thorough assessment of environmental
impacts and be determined by the appropriate Determining Authority taking into
account environmental recommendations of the Committee.
16 Form 3 and environmental study to be used for Ma jor Project
assessment
The environmental impact assessment for projects which require Major Project
assessment under sections 7 and 9 of the Act shall be in general accordance with
Form 3 of the Schedule 1 and shall comprise a written Environmental Study which
will:
(a) fully describe the proposed development activity;
(b) fully describe the existing environment that is likely to be affected by the
proposed development;
(c) present a justification of the proposed development activity in terms of
environmental, economic, cultural and social considerations;
(d) identify, describe and analyse the potential direct and indirect physical,
biological, social, cultural and economic impacts of the development activity
for both construction and operational phases of the development;
Environmental Impact Assessment Regulations 2010 Regulation 17
to
Page 9
(e) detail any measures to be taken to protect the environment and to avoid,
reduce or otherwise mitigate any potential adverse ffects of the development;
(f) evaluate and describe any feasible alternative activities, including locations,
for achieving the objectives of the development;
(g) evaluate and describe the implications and consequences of not undertaking
the proposed development;
(h) identify, describe and analyse the possible cumulative effects upon
components of the environment with other existing or likely future
development activities; and,
(i) assess the way in which the project accords with the current Government of
Tonga Development Plan, declared Government of Tonga environmental
policy, and any international environmental policies, agreements, conventions
or treaties to which the Government of Tonga is, or is considering becoming,
a signatory.
17 Secretariat’s guidance shall be sought
(1) In completing the Environmental Study, the Proponent shall seek the guidance
of the Secretariat in determining how much assessment shall be undertaken.
(2) The Director's advice in such matters shall be final.
18 Certification of environmental study
An Environmental Study that is submitted for environmental impact assessment
review shall bear a certificate by the person preparing the study to the effect that it
has been prepared in accordance with regulations 16 and 17.
19 Secretariat’s guidelines to be used for major pr ojects
Where the Secretariat has prepared guidelines for Major Project assessment these
shall be used to complement matters outlined in the Schedule 1.
20 Committee to review and recommend
The Committee shall review the application, environme tal assessments, Secretariat
report, and any additional relevant reports provided to it before making its
recommendations to the appropriate Determining Authority.
21 Structure of recommendation
The recommendation to the appropriate Determining Authority shall state:
(a) whether to approve, reject, defer or modify the development application;
Regulation 22 Environmental Impact Assessment Regulations 2010
Page 10
to
(b) the reasons for that recommendation; and
(c) any conditions that shall be attached to any approval.
22 Adoption by quorum
The recommendations shall be formally adopted by a majority of the Committee
present.
23 Report by Committee
The Committee, in relation to any Major Development Project, shall prepare an
Assessment Review Report of its examination and consideration of the
environmental study, as required under section 14 of the Act.
24 Copies of Committee report to be free of charge
Individual copies of the Committee Assessment Review Report shall be furnished
free of charge to the proponent and the Determining Authority.
25 Certification of approval
Written advice from the Minister to the proponent or the Determining Authority
shall constitute certification of completion of the environmental impact assessment
process for a development activity under section 16 of the Act.
26 Information to be correct
An applicant or proponent for any development activity shall not make any
application or furnish any document in respect of any development activity under
the terms of these regulations knowing:
(a) it is false in any material particular; or
(b) that it contains information that is materially misleading in the form or context
in which it appears.
27 Change in circumstances
Any change in circumstances which has the effect of rendering any such information
false, incomplete or misleading shall be notified immediately to the Minister who
shall refer the matter to the Committee.
Environmental Impact Assessment Regulations 2010 Regulation 28
to
Page 11
28 Minister may impose further conditions
Where a matter is referred to the Committee pursuant to regulation 27, the
Committee may recommend that the Minister imposes such further conditions as are
appropriate, and the procedures outlined in regulations 5 to 26 shall apply as if this
was the original application.
29 Committee may cancel certification
Where the information notified pursuant to regulation 8 is of such ecological
significance that, were it known at the time, the project would not have been
approved, the Committee shall determine whether the certification under regulation
25 should be cancelled and whether the development activity should cease while a
new application under the terms of the Act is prepad and considered, or whether
the approval for the activity should be cancelled by the Determining Authority and
environmental restoration undertaken at the cost of the proponent.
30 Proponent to re-submit application
If a development activity is subject to cessation of w rk under regulation 29, the
activity shall not proceed to continue until it has met the requirements of the Act as
if it were a new development activity.
Made at Nuku’alofa this 20th day of October 2010.
Minister of Environment
SCHEDULE 1 Environmental Impact Assessment Regulations 2010
Page 12
to
SCHEDULE 1
FORM 1: DETERMINATION OF CATEGORY OF ASSESSMENT
Name:
Address:
Contact Officers of the Proponent:
Proponent Company:
(Official Use Only)
Project ID No.:
Requirement: Minor Assessment (Form 2) Major Assessment (Form 3)
The following information is to be included in the proposal to be submitted for assessment:
1. full description of the proposed activity/development and its costs.
2. location of the proposed activity and of any associated developments.
3. full description of the existing environment of the sites and their relationship to existing
adjoining uses or habitation; in particular details of any significant physical, biological,
social or cultural heritage items which may be affected by the proposed development or
activity.
4. timing of design, construction and operation of the development.
5. estimated type, source and volume of any materials to be used in the construction and
operation of the development; and proposed demand for utility services.
6. any plant or animal species to be introduced which are not native to Tonga.
7. any likely solid, liquid or gaseous emissions from the activity/development, whether or not
totally contained upon site.
8. likely noise generated by the development, and assessm nt of likely increases in traffic
flow.
9. employment likely to be generated by the activity/development, and contribution (if any) to
the local or national economy.
10. assessment of anticipated environmental risks and impacts, and measures to be taken by the
proponent to mitigate the same.
Please attach proposal to this form.
Environmental Impact Assessment Regulations 2010 SCHEDULE 1
to
Page 13
FORM 2:MINOR ENVIRONMENTAL IMPACT ASSESSMENT
Project ID No.:
Name of Project:
Contact Person:
Contact Number:
Additional information required:
This is to confirm that all required information has been lodged in accordance to the requirements
of the Act.
Signature:
Print Name:
Determining Authority:
SCHEDULE 1 Environmental Impact Assessment Regulations 2010
Page 14
to
FORM 3: MAJOR ENVIRONMENTAL IMPACT ASSESSMENT
Project ID No.:
Name of Project:
Contact Person:
Contact Number:
The written environmental study shall include the following:
1. Title, abstract and executive summary.
2. Description of the purpose and scope of the proposed development activity:
a) Purpose: What goals and objectives of society are se ved? Why is the project
needed?
b) Direct benefits expected: products, services, jobs, return on investment
c) Location and extent of site boundaries and associated facilities at preferred site
and other feasible sites (please provide map of area)
d) Technology to be used.
e) Local infrastructure required: roads, utilities, etc.
f) Inputs of capital, labour, natural resources.
g) Duration of construction period and operating life.
3. Present a justification of the proposed development activity in terms of environmental,
economic, cultural and social considerations.
4. Identify, describe and analyse the potential direct and indirect physical, biological, social,
cultural and economic impacts of the development activity for both construction and
operational phases of the development.
5. Detail any measures to be taken to protect the enviro ment and to avoid, reduce or
otherwise mitigate any potential adverse effects of the development.
6. Evaluate and describe any feasible alternative activities, including locations, for achieving
the objectives of the development.
7. Evaluate and describe the implications and consequences of not undertaking the proposed
development.
8. Identify, describe and analyse the possible cumulative effects upon components of the
environment with other existing or likely future development activities.
9. Public involvement.
10. Assess the way in which the project accords with the current Government of Tonga
Development Plan, declared Government of Tonga enviro mental policy, and/or any
international environmental policies, agreements, conventions or treaties to which the
Government of Tonga is, or is considering becoming, a signatory.
This is to confirm that all required information has been lodged in accordance to the requirements
of the Act.
Signature:
Print Name:
Determining Authority:
Environmental Impact Assessment Regulations 2010
to
Page 15
FORM 4: COMMITTEE RECOMMENDATIONS
Project ID No.:
Name of Project:
Contact Person:
Contact Number:
Final Environmental Study Not Satisfactory
Satisfactory
Conditions/Recommendations
This is to confirm that all requirements have been met in accordance with the Act.
Signature:
Print Name:
Determining Authority:
SCHEDULE 2 Environmental Impact Assessment Regulations 2010
Page 16
to
SCHEDULE 2
FEES AND CHARGES
The following charges may apply:
1 For all applications, a Registration Fee of $10.00 shall apply, to accompany
lodgement of the application.
2 For all applications requiring major project assessment, including all
applications listed in the Schedule to the Act, an initial application fee of
$250.00 shall accompany the Environmental Study. Upon final scoping of the
proposal the Minister shall require a final fee of 1% of the capital cost of the
proposed activity/development.
3 Where the final fees levied exceed $10,000, and where the proponent
considers this fee to be unreasonable, the proponent may make application to
the Committee for a reduction in the fees to be levied. The proponent shall
meet the cost of any special meeting of the Committee to be held to consider
such an application.